UNITED STATES DISTRICT COURT
9
SOUTHERN DISTRICT OF CALIFORNIA
10
11
12
13
14
15
16
17
18
19
20
ST. PAUL MERCURY INSURANCE
COMPANY,
CASE NO. 15cv1548 JM(BLM)
ORDER DENYING MOTION TO
DISMISS COUNTERCLAIMS
Plaintiff,
v.
MCMILLIN HOMES
CONSTRUCTION, INC.;
MCMILLIN HOMES, INC.;
MCMILLIN MANAGEMENT
SERVICES, LP; SERENO
RESIDENTIAL INVESTORS, LLC;
and IMPERIAL VALLEY
INVESTORS, LLC,
Defendants.
_______________________________
AND RELATED COUNTERCLAIM.
21
22
Plaintiff St. Paul Mercury Insurance Company (“St. Paul”) moves to dismiss the
23 Amended Counterclaim (“ACC”) filed by Defendants McMillin Homes Construction,
24 Inc., McMillin Homes, Inc., McMillin Management Services, LP, Sereno Residential
25 Investors, LLC, and Imperial Valley Investors, LLC (collectively “McMillin”).
26 McMillin opposes the motion. Pursuant to Local Rule 7.1(d)(1), the court finds the
27 matters presented appropriate for decision without oral argument. For the reasons set
28 forth below, the court denies the motion.
-1-
15cv1548
1
BACKGROUND
2 The Complaint
3
On July 13, 2015, St. Paul commenced this diversity action by alleging three
4 claims for relief: declaratory relief, breach of contract, and equitable reimbursement.
5 For the time period from May 19, 2003 to June 30, 2009, St. Paul issued a commercial
6 general liability policy (“Policy”) to Executive Landscape, Inc. McMillin is an
7 additional insured under the Policy. St. Paul’s claims arise from the following
8 generally described allegations.
9
McMillin developed and acted as the general contractor on a project known as
10 “Sereno.” On May 12, 2012, various homeowners in the Sereno development, located
11 in the City of Calexico, California, filed a first amended complaint in the lawsuit
12 entitled Yanez v. Sereno Residential Investors, LLC. The homeowners commenced the
13 action in Imperial County Superior Court, alleging several claims for construction
14 defects. The Yanez action was subsequently consolidated with a related construction
15 defect lawsuit, Vizcarra v. Sereno Residential Investors, LLC (unless otherwise noted,
16 both actions are collectively referred to as the “Yanez Action”).
17
On August 8, 2012, McMillin, through its legal representative Simpson Delmore
18 Greene (“SDG”), tendered the Yanez Action to St. Paul as an additional insured under
19 the Policy. (Compl. ¶16). On December 31, 2012, St. Paul agreed to fully and
20 completely defend McMillin in the Yanez Action as an additional insured under the
21 Policy, subject to a reservation of rights.
22
On June 26, 2013, St. Paul allegedly asserted its contractual right to retain
23 counsel of its choosing and advised McMillin that it had retained the law firm of Clapp,
24 Moroney, Bellagamba, Vucinich, Beeman & Scheley (“Clapp”) to represent and defend
25 McMillin in the Yanez Action. McMillin allegedly refused, and continues to refuse,
26 to accept Clapp as counsel in the Yanez Action.
27
St. Paul seeks a declaration that (1) St. Paul has the right to control the defense
28 in the Yanez action; (2) McMillin is not entitled to the appointment of independent
-2-
15cv1548
1 counsel under Cal. Civil Code §2860; (3) McMillin breached the Policy by refusing to
2 acknowledge St. Paul’s right to control the defense, including the selection of counsel,
3 and (4) St. Paul has no obligation under the Policy to pay any fees or costs incurred by
4 McMillin’s retained counsel. The breach of contract claim is based upon allegations
5 that McMillin refused to accept the counsel provided by St. Paul. Finally, the third
6 claim seeks equitable reimbursement for certain defense fees and costs paid by St. Paul.
7 The Counterclaims
8
On November 12, 2015, McMillin filed the ACC, alleging three claims for relief:
9 (1) declaratory relief; (2) breach of contract; and (3) breach of the implied covenant of
10 good faith and fair dealing. As set forth in the complaint, on August 8, 2012, McMillin
11 tendered the Yanez Action to St. Paul. Nearly four months later, on December 31,
12 2012, St. Paul agreed to defend McMillin in the Yanez Action, subject to a full
13 reservation of rights. (ACC ¶27).
14
Counter-claimants allege that St. Paul paid only a portion of the defense costs
15 incurred by SDG. On June 26, 2013, ten months after McMillin tendered its defense
16 to St. Paul, St. Paul retained Clapp to represent the defense. (ACC ¶31). Shortly
17 thereafter, on July 22, 2013, McMillin provided St. Paul with a Joint Consent to
18 Representation (“Joint Consent”) pursuant to Cal. Civ.Code §2860. When St. Paul did
19 not respond to the Joint Consent, McMillin again provided the Joint Consent to St. Paul
20 on September 4, 2013, and December 13, 2013. On February 24, 2014, St. Paul
21 advised McMillin that it would only pay for defense fees incurred by Clapp, and not
22 SDG.
23
At the heart of the counterclaim is the allegation that St. Paul failed to provide
24 an immediate defense upon tender on August 8, 2012, and to appoint independent
25 counsel. (ACC ¶48). The ACC alleges that St. Paul withdrew from participating in
26 McMillin’s defense once it requested the association of independent counsel, (ACC
27 ¶58), and St. Paul ignored the conflicts of interests that arose as to who had the right
28 to control McMillin’s defense.
McMillin also identifies that it and Executive
-3-
15cv1548
1 Landscape had sufficient adverse interests to warrant the appointment of independent
2 counsel. Furthermore, McMillin alleges that St. Paul placed its own interests ahead of
3 the insured by (1) failing to provide an immediate defense without proper cause, (2)
4 failing to conduct a reasonable investigation, (3) representing that it would provide a
5 complete defense and then failing to provide one, (4) refusing to consent to joint
6 representation, and (5) using McMillin’s request for independent counsel as a pretext
7 for refusing to defend. (ACC ¶64(a) - 64(i)).
8
DISCUSSION
9 Legal Standards
10
Federal Rule of Civil Procedure 12(b)(6) dismissal is proper only in
11 "extraordinary" cases. United States v. Redwood City, 640 F.2d 963, 966 (9th Cir.
12 1981). Courts should grant 12(b)(6) relief only where a plaintiff's complaint lacks a
13 "cognizable legal theory" or sufficient facts to support a cognizable legal theory.
14 Balistreri v. Pacifica Police Dept., 901 F.2d 696, 699 (9th Cir. 1990). Courts should
15 dismiss a complaint for failure to state a claim when the factual allegations are
16 insufficient “to raise a right to relief above the speculative level.” Bell Atlantic Corp.
17 v. Twombly, 550 U.S. 544, 555 (2007) (the complaint’s allegations must “plausibly
18 suggest[]” that the pleader is entitled to relief); Ashcroft v. Iqbal, 556 U.S. 662 (2009)
19 (under Rule 8(a), well-pleaded facts must do more than permit the court to infer the
20 mere possibility of misconduct). “The plausibility standard is not akin to a ‘probability
21 requirement,’ but it asks for more than a sheer possibility that a defendant has acted
22 unlawfully.” Id. at 678. Thus, “threadbare recitals of the elements of a cause of action,
23 supported by mere conclusory statements, do not suffice.” Id. The defect must appear
24 on the face of the complaint itself. Thus, courts may not consider extraneous material
25 in testing its legal adequacy. Levine v. Diamanthuset, Inc., 950 F.2d 1478, 1482
26 (9th Cir. 1991). The courts may, however, consider material properly submitted as part
27 of the complaint. Hal Roach Studios, Inc. v. Richard Feiner and Co., 896 F.2d 1542,
28 1555 n.19 (9th Cir. 1989).
-4-
15cv1548
1
Finally, courts must construe the complaint in the light most favorable to the
2 plaintiff. Concha v. London, 62 F.3d 1493, 1500 (9th Cir. 1995), cert. dismissed,
3 116 S. Ct. 1710 (1996). Accordingly, courts must accept as true all material allegations
4 in the complaint, as well as reasonable inferences to be drawn from them. Holden v.
5 Hagopian, 978 F.2d 1115, 1118 (9th Cir. 1992). However, conclusory allegations of
6 law and unwarranted inferences are insufficient to defeat a Rule 12(b)(6) motion. In
7 Re Syntex Corp. Sec. Litig., 95 F.3d 922, 926 (9th Cir. 1996).
8 The Motion
9
The thrust of McMillin’s counterclaims is that St. Paul breached its duty to
10 defend, and lost the right to control the defense, when it waited four months after
11 tender before agreeing to defend McMillin in the Yanez action. The law is well12 established that an insurer who breaches its duty to defend forfeits its right to control
13 the defense of the action. J.R. Mktg., L.L.C. v. Hartford Casualty Ins. Co., 216
14 Cal.App.4th 1144 (2013). Here, McMillin alleges that it tendered the defense on
15 August 8, 2012, and St. Paul accepted the defense subject to a reservation of rights on
16 December 31, 2012, thereby forfeiting its right to control the defense.1 These
17 allegations, viewed in the best light for McMillin, state a counterclaim for breach of the
18 insurance contract.
19
In response to these allegations, St. Paul comes forward with evidence to show
20 that on August 27, 2012, it acknowledged McMillin’s tender and requested the
21 submission of what it considered necessary information to complete its coverage
22 analysis. (Vandermoore Decl. ¶6). The requested information included the contract
23 between McMillin and Executive Landscape and scope of work matrices. Id. About
24 two and one half months later, on or about November 8, 2012, St. Paul received the
25 requested information and, on December 31, 2012, St. Paul accepted the defense.
26 (Vandermoore Decl. ¶9).
27
28
1
California Code of Regulations, Title 10, Chapter 5, Subchapter 8, §2695.7(b)
provides that an insurer must accept or deny a claim withing 40 days.
-5-
15cv1548
1
The difficulty with St. Paul’s argument is that it is dependent upon evidentiary
2 matters not properly considered on a motion to dismiss. See Levine, 950 F.2d at 1482.
3 Here, whether St. Paul timely and reasonably accepted tender presents a question of
4 fact not properly resolved on a motion to dismiss. Moreover, discovery is required to
5 provide context to the reasonableness of the period of time between tender and
6 providing a defense and whether McMillin suffered any injury as a result. See Cal.
7 Shoppers Inc. v. Royal Globe Ins. Co., 175 Cal.App.3d 1, 38 (1985) (insurer entitled
8 to a reasonable time to investigate claim in order to identify potential coverage). The
9 four-month delay in accepting the defense may, or may not, be reasonable, depending
10 on circumstances arising outside the four corners of the complaint.
11
In sum, the court denies the motion to dismiss the ACC.
12
IT IS SO ORDERED.
13 DATED: March 2, 2016
14
Hon. Jeffrey T. Miller
United States District Judge
15
16
cc:
All parties
17
18
19
20
21
22
23
24
25
26
27
28
-6-
15cv1548
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?