United States of America et al v. County of San Diego
Filing
37
ORDER Granting 32 Defendant's Motion to Dismiss Second Amended Complaint. The Court grants Defendant's motion to dismiss, and dismisses this action in its entirety without prejudice, and with leave to amend. Plaintiff may file a Third Amended Complaint that cures the deficiencies described above on or before 2/1/2018. Signed by Judge Michael M. Anello on 1/11/2018. (rmc)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
SOUTHERN DISTRICT OF CALIFORNIA
10
11
12
UNITED STATES OF AMERICA, ex rel
Michael Durkin
15
16
ORDER GRANTING DEFENDANT'S
MOTION TO DISMISS SECOND
AMENDED COMPLAINT
Plaintiff,
13
14
Case No.: 15cv2674-MMA (WVG)
v.
COUNTY OF SAN DIEGO,
Defendant.
[Doc. No. 32]
17
18
Plaintiff Michael Durkin filed this action under the qui tam provisions of the False
19
Claims Act (“FCA”), 31 U.S.C. § 3729 et seq., on behalf of the United States of America
20
and against Defendant County of San Diego. See Doc. Nos. 1, 17, 31. The United States
21
declined to intervene in this action. See Doc. No. 7. Defendant now moves to dismiss
22
the Second Amended Complaint (“SAC”) pursuant to Federal Rule of Civil Procedure
23
12(b)(6) on the grounds that all causes of action are not pled with the specificity required
24
by Rule 8 and Rule 9(b) of the Federal Rules of Civil Procedure. See Doc. No. 32-1
25
(“MTD”). Plaintiff Durkin filed an opposition [Doc. No. 33 (“Oppo.”)], the United
26
States of America filed a statement of interest [Doc. No. 34], and Defendant filed a reply
27
[Doc. No. 35 (“Reply”)]. The Court found the matter suitable for determination on the
28
1
15cv2674-MMA (WVG)
1
papers and without oral argument pursuant to Civil Local Rule 7.1.d.1. Doc. No. 36. For
2
the reasons set forth below, the Court GRANTS Defendant’s motion.
BACKGROUND1
3
By way of background, Plaintiff2 alleges that in 2014, he was involved in a lawsuit
4
5
in which the owners of two properties—Lots 24 and 25—located near the McClellan-
6
Palomar Airport sued the County of San Diego for inverse condemnation. Doc. No. 31
7
(“SAC”), ¶ 7. The SAC states that Plaintiff was the manager of the two entities that
8
owned those properties. Id. In the course of that litigation, Plaintiff alleges he uncovered
9
the information underlying this action. Id. In the instant case, Plaintiff asserts thirteen
10
claims against Defendant County of San Diego under the FCA, and requests damages and
11
civil penalties. See generally, SAC. Plaintiff alleges Defendant made false statements to
12
the Federal Aviation Administration (“FAA”) in applying for grants for the maintenance
13
and development of the Palomar-McClellan Airport located in Carlsbad, County of San
14
Diego, California. SAC, ¶ 1.
Plaintiff alleges the FAA makes funding “available to improve American airports,”
15
16
and provides funds to recipients “primarily to ensure the safety of airports, the
17
surrounding areas, and the people in or around the airports.” SAC, ¶ 9. In order to obtain
18
federal funds through the FAA, Plaintiff alleges applicants must “make statements and
19
promises, and give assurances regarding, inter alia, how the land surrounding the airport
20
is being controlled by the applicant to protect airport operations from hazards on the
21
ground, and conversely to protect people and property on the ground from hazards
22
inherent to airport operations.” Id. Further, the SAC states that “[u]pon approving a
23
grant, the FAA requires the applicant to make certain statements, assurances, and
24
25
26
27
28
1
Because this matter is before the Court on a motion to dismiss, the Court must accept as true the
allegations set forth in the complaint. See Hosp. Bldg. Co. v. Trs. of Rex Hosp., 425 U.S. 738, 740
(1976).
2
For convenience, “Plaintiff” hereinafter refers to Qui Tam Plaintiff Durkin, as opposed to the United
States.
2
15cv2674-MMA (WVG)
1
promises regarding how the airport and surrounding areas will be operated, maintained,
2
improved, or acquired” for safety purposes. SAC, ¶ 10. Then, Plaintiff alleges, “a
3
grantee is required to file applications for payment to the FAA in the form of receipts or
4
vouchers,” which “impliedly or expressly recertify all the promises, assurances, and
5
statements previously made in the grant applications and agreements.” SAC, ¶ 11.
6
In particular, Plaintiff alleges Defendant applied, was approved, and obtained
7
funding for use in relation to the McClellan-Palomar Airport. SAC, ¶ 13. Plaintiff
8
contends that, in 1995, Defendant knew that certain properties were in the Runway
9
Protection Zone (“RPZ”)3, and obtained federal funds from the FAA in order to acquire
10
those properties. SAC, ¶¶ 20-23. Plaintiff alleges that later in 1995, Defendant
11
reprioritized “its projects because it determined the cost of acquisition was more than it
12
was willing to pay” and “reallocated [the] funds granted by the FAA for such acquisition
13
to other airport improvements.” SAC, ¶ 22. The SAC asserts that the County knew that
14
it was required under federal regulations to “acquire interests in the non-airport owned
15
RPZ property sufficient to prevent or eliminate incompatible development.” SAC, ¶ 23.
16
Plaintiff alleges that, since its 1995 postponement, Defendant has not “taken any step to
17
acquire any interest at all in said lots, much less an interest sufficient to prevent or
18
eliminate incompatible uses in the RPZ.” SAC, ¶ 24. Plaintiff alleges that Defendant
19
“did nothing to prevent the development of Lot 24 with an office building in 2004 . . .
20
and has done nothing since that time to eliminate this office building from the RPZ . . . .”
21
Id. Plaintiff alleges this safety hazard continues to the present time, despite Defendant’s
22
assertions in its grant applications. See id.
23
Specifically, Plaintiff alleges Defendant, on multiple occasions between 2005 and
24
2014, made misrepresentations to the FAA in applying for, entering into agreements for,
25
or making claims for federal funds. See generally, SAC. Each cause of action is based
26
27
28
3
The RPZ is defined as “an area off the end of all airport runways.” SAC, ¶ 15.
3
15cv2674-MMA (WVG)
1
on four or five allegedly false statements contained in thirteen different written FAA
2
grant applications or agreements. See generally, id.
3
4
LEGAL STANDARD
A Rule 12(b)(6) motion to dismiss tests the sufficiency of the complaint. Navarro
5
v. Block, 250 F.3d 729, 732 (9th Cir. 2001). A pleading must contain “a short and plain
6
statement of the claim showing that the pleader is entitled to relief. . . .” Fed. R. Civ. P.
7
8(a)(2). However, plaintiffs must also plead “enough facts to state a claim to relief that is
8
plausible on its face.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007); Fed. R. Civ.
9
P. 12(b)(6). The plausibility standard demands more than “a formulaic recitation of the
10
elements of a cause of action,” or “naked assertions devoid of further factual
11
enhancement.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (internal quotations and
12
alterations omitted). Instead, the complaint “must contain sufficient allegations of
13
underlying facts to give fair notice and to enable the opposing party to defend itself
14
effectively.” Starr v. Baca, 652 F.3d 1202, 1216 (9th Cir. 2011).
15
In reviewing a motion to dismiss under Rule 12(b)(6), courts must assume the truth
16
of all factual allegations and must construe them in the light most favorable to the
17
nonmoving party. Cahill v. Liberty Mut. Ins. Co., 80 F.3d 336, 337-38 (9th Cir. 1996).
18
The court need not take legal conclusions as true merely because they are cast in the form
19
of factual allegations. Roberts v. Corrothers, 812 F.2d 1173, 1177 (9th Cir. 1987).
20
Similarly, “conclusory allegations of law and unwarranted inferences are not sufficient to
21
defeat a motion to dismiss.” Pareto v. FDIC, 139 F.3d 696, 699 (9th Cir. 1998).
22
Under Rule 9(b), when the complaint includes allegations of fraud, a party must
23
“state with particularity the circumstances constituting fraud . . . .” Fed. R. Civ. P. 9(b).
24
“In other words, the complaint must set forth what is false or misleading about a
25
statement, and why it is false.” Rubke v. Capitol Bancorp Ltd, 551 F.3d 1156, 1161 (9th
26
Cir. 2009) (internal quotation marks omitted). The plaintiff’s allegations of fraud must
27
be “specific enough to give defendants notice of the particular misconduct . . . so that
28
they can defend against the charge and not just deny that they have done anything
4
15cv2674-MMA (WVG)
1
wrong.” Vess v. Ciba-Geigy Corp. USA, 317 F.3d 1097, 1106 (9th Cir. 2003) (internal
2
citations and quotation marks omitted). Further, the plaintiff must describe “the who,
3
what, when, where, and how” of the fraudulent misconduct charged. Id. at 1106. In
4
other words, the plaintiff must specify the time, place, and content of the alleged
5
fraudulent or mistaken conduct. In re Glenfed, Inc. Sec. Litig., 42 F.3d 1541, 1547-48
6
(9th Cir. 1994). However, “[m]alice, intent, knowledge, and other conditions of a
7
person’s mind may be alleged generally.” Fed. R. Civ. P. 9(b). Failure to satisfy this
8
heightened pleading requirement can result in dismissal of the claims. Vess, 317 F.3d at
9
1107.
10
11
REQUESTS FOR INCORPORATION BY REFERENCE
As an initial matter, both parties request the Court incorporate by reference some
12
documents into the SAC. See Doc. Nos. 32-2, 33-1. In determining the propriety of a
13
Rule 12(b)(6) dismissal, courts generally may not look beyond the complaint for
14
additional facts. See United States v. Ritchie, 342 F.3d 903, 907-08 (9th Cir. 2003). “A
15
court may, however, consider certain materials—documents attached to the complaint,
16
documents incorporated by reference in the complaint, or matters of judicial notice—
17
without converting the motion to dismiss into a motion for summary judgment.” Id. at
18
908; see also Fed. R. Evid. 201; see also Lee v. City of Los Angeles, 250 F.3d 668, 688
19
(9th Cir. 2001), overruled on other grounds by Galbraith v. Cnty. of Santa Clara, 307
20
F.3d 936, 942 (9th Cir. 2009). A document “may be incorporated by reference into a
21
complaint if the plaintiff refers extensively to the document or the document forms the
22
basis of the plaintiff’s claim.” Ritchie, 342 F.3d at 908 (internal citations omitted). In
23
other words, a court “may consider a document the authenticity of which is not contested,
24
and upon which the plaintiff’s complaint necessarily relies.” Parrino v. FHP, Inc., 146
25
F.3d 699, 706 (9th Cir. 1998), superseded by statute on other grounds in Abrego v. Dow
26
Chem. Co., 443 F.3d 676 (9th Cir. 2006); Swartz v. KPMG LLP, 476 F.3d 756, 763 (9th
27
Cir. 2007); Knievel v. ESPN, 393 F.3d 1068, 1076 (9th Cir. 2005).
28
5
15cv2674-MMA (WVG)
1
Defendant requests the Court incorporate by reference copies of thirteen grant
2
applications and grant agreements underlying Plaintiff’s claims, and the Federal Aviation
3
Administration Advisory Circular4 referenced in the SAC. See Doc. No. 32-2, 32-3,
4
Exhibits 1-27. Plaintiff does not dispute the authenticity of these documents, but opposes
5
Defendant’s request on the grounds that “the exhibits submitted to the Court [by
6
Defendant] are not a full true and correct copy of the document.” Doc. No. 33-3 at 1.
7
Plaintiff specifies that “each grant application and grant agreement omits form sets of
8
assurances which are the basis for certain Plaintiff’s claims herein alleged.” Id. at 2. By
9
way of example, Plaintiff requests the Court incorporate by reference a grant application
10
dated February 1, 2005—which he asserts is the full and complete copy of Defendant’s
11
Exhibit 1— and a grant agreement dated August 9, 2005—which he asserts is the full and
12
complete copy of Defendant’s Exhibit 2. See id., Exhibits 1-2. Defendant does not
13
oppose Plaintiff’s request for incorporation by reference. See Reply. Further, Plaintiff’s
14
claims necessarily rely on each of the exhibits submitted by Defendant and Plaintiff.
Because Defendant does not dispute Plaintiff’s requests for incorporation by
15
16
reference, and Plaintiff’s claims necessarily rely on the exhibits, the Court GRANTS
17
Plaintiff’s requests. In light of incorporating Plaintiff’s exhibits by reference into the
18
SAC and for the purposes of avoiding duplicity, the Court DENIES Defendant’s requests
19
for incorporation by reference with respect to Exhibits 1 and 2. However, Plaintiff does
20
not submit complete copies of Defendant’s remaining exhibits. See id. Accordingly, the
21
Court GRANTS Defendant’s requests to incorporate Exhibits 3 through 27 by reference
22
into the SAC as the applicable grant applications or agreements without the grant
23
assurances.
24
//
25
26
27
28
According to the record, an “Advisory Circular” is a document issued by the United States Department
of Transportation, Federal Aviation Administration, delineating guidelines and standards pertaining to
aviation. See Doc. No. 32-3, Exhibit 27.
4
6
15cv2674-MMA (WVG)
MOTION TO DISMISS
1
2
Defendant moves to dismiss Plaintiff’s False Claims Act (“FCA”) causes of action
3
on the grounds that they “are not pled with the specificity required by Rules 8 and 9(b) of
4
the Federal Rules of Civil Procedure.” MTD at 7. More specifically, Defendant argues
5
that “the SAC fails to adequately allege non-conclusory facts supporting the FCA
6
elements of falsity, materiality, and scienter.” Id. Plaintiff opposes dismissal of any
7
claims. See Oppo. Also, the United States has filed a statement of interest in response to
8
the County’s motion to dismiss, despite that the United States has declined to intervene in
9
this action. Doc. No. 34. The United States requests only that if the Court decides to
10
dismiss any claims in response to the County’s motion, the Court dismiss such claims
11
without prejudice as to the United States. Id. at 2. Otherwise, the United States asserts
12
that it takes no position as to the merits of the pending motion to dismiss. Id. at 6.
13
1.
14
The False Claims Act
“The False Claims Act makes liable anyone who ‘knowingly presents, or causes to
15
be presented, a false or fraudulent claim for [government] payment or approval,’ or
16
‘knowingly makes, uses, or causes to be made or used, a false record or statement
17
material to a false or fraudulent claim’” for government payment. See United States ex
18
rel. Campie v. Gilead Scis., 862 F.3d 890, 898-99 (9th Cir. 2017) (quoting 31 U.S.C.
19
§ 3729(a)(1)(A),(B)). While, “[i]n an archetypal qui tam False Claims action, such as
20
where a private company overcharges under a government contract, the claim for
21
payment is itself literally false or fraudulent,” liability under the FCA “is not limited to
22
such facially false or fraudulent claims for payment.” United States ex rel. Hendow v.
23
Univ. of Phoenix, 461 F.3d 1166, 1170 (9th Cir. 2006). Rather, “the scope of false or
24
fraudulent claims should be broadly construed.” Id. Relevant here, “[t]he principles
25
embodied in this broad construction of a ‘false or fraudulent claim’ have given rise to two
26
doctrines that attach potential False Claims Act liability to claims for payment that are
27
not explicitly and/or independently false: (1) false certification (either express or
28
implied); and (2) promissory fraud.” Id. at 1171.
7
15cv2674-MMA (WVG)
1
In false certification cases, “parties avail themselves of benefits of some type, such
2
as loan guarantees or agricultural supports, through false statements which create
3
eligibility that otherwise would not exist.” See United States ex rel. Hopper v. Anton, 91
4
F.3d 1261, 1266 (9th Cir. 1996) (John T. Boese, Civil False Claims and Qui Tam Actions
5
1-29 to 1-30 (1995)). Mere regulatory violations do not create liability. Id. Rather, “[i]t
6
is the false certification of compliance which creates liability when certification is a
7
prerequisite to obtaining a government benefit.” Id. Similarly, under an implied false
8
certification theory, “‘when a defendant submits a claim, it impliedly certifies compliance
9
with all conditions of payment,” and “if the claim fails to disclose the defendant’s
10
violation of a material statutory, regulatory, or contractual requirement . . . the defendant
11
has made a misrepresentation that renders the claim ‘false or fraudulent’ under
12
§ 3729(a)(1)(A).’” Campie, 862 F.3d at 901 (quoting Universal Health Servs. v. United
13
States ex rel. Escobar, 136 S.Ct. 1989, 1999 (2016)).
14
The theory of promissory fraud is closely related to false certification, and dictates
15
“that liability will attach to each claim submitted to the government under a contract,
16
when the contractor extension of government benefit was originally obtained through
17
false statements or fraudulent conduct.” Hendow, 461 F.3d at 1173. Promissory fraud
18
“sometimes differs from the false certification theory only in a temporal sense.” United
19
States ex rel. Hansen v. Deming Hosp. Corp., 992 F. Supp. 2d 1137, 1154 (D.N.M.
20
2013). For example, “[w]hile the false certification theory alleges that a contractor
21
certified that it did comply with a statute, regulation, or contractual term when it knew at
22
the time that it did not do so, the promissory fraud theory may allege that a contractor
23
originally certified that it would comply with a law, regulation, or term when it knew at
24
the time that it would not do so.” Id.
25
Under either a false certification or promissory fraud theory, “the essential
26
elements of False Claims Act liability remain the same: (1) a false statement or fraudulent
27
course of conduct, (2) made with scienter, (3) that was material, causing (4) the
28
government to pay out money or forfeit moneys due.” Hendow, 461 F.3d at 1174. In
8
15cv2674-MMA (WVG)
1
considering a claim of false certification, there are “two major considerations: ‘(1)
2
whether the false statement is the cause of the Government’s providing the benefit; and
3
(2) whether any relation exists between the subject matter of the false statement and the
4
event triggering Government’s [sic] loss.’” Id. at 1171 (quoting Hopper, 91 F.3d at
5
1266). Under either theory, a false claim or promise must be the “sine qua non of receipt
6
of state funding.” See Ebeid v. Lungwitz, 616 F.3d 993, 998 (9th Cir. 2010). Further,
7
“for promissory fraud to be actionable under the False Claims Act, ‘the promise must be
8
false when made.’” Hendow, 461 F.3d at 1174 (quoting Hopper, 91 F.3d at 1267).
9
“Innocent mistakes, mere negligent misrepresentations and differences in interpretations
10
are not false certifications under the Act.” Hopper, 91 F.3d at 1267.
11
2.
Identification of Defendant’s Statements
12
Defendant first argues that the SAC does not identify the alleged false statements
13
with sufficient particularity. MTD at 10-22. Defendant asserts it had to “guess” which
14
provisions contained the allegedly false statements with respect to false statements one
15
and four. MTD at 10-11, 19-20. Defendant further contends that it could not locate the
16
provisions containing false statements two, three, and five. MTD at 15-18, 21. Plaintiff
17
counters, arguing that “[t]he SAC clearly identifies the time, place, and nature of each
18
fraudulent statement.” Oppo. at 10. Specifically, Plaintiff contends “[e]ach Cause of
19
Action identifies a grant application or grant agreement submitted by the County to the
20
FAA which contains the fraudulent statement, and the date upon which the application
21
was submitted or grant agreement [was] executed.” Id. Further, Plaintiff asserts that
22
“[e]ach false statement is paraphrased.” Id.
23
Rule 9(b) of the Federal Rules of Civil Procedure requires particularized
24
allegations of the circumstances constituting fraud. Fed. R. Civ. P. 9(b). Thus, “[t]he
25
time, place, and content of an alleged misrepresentation may identify the statement or the
26
omission complained of . . . .” In re GlenFed, Inc. Sec. Litig., 42 F.3d at 1547-48.
27
Defendant contends Plaintiff must identify where each statement is specifically located
28
within the grant agreement or grant application. See MTD at 10-20. The Court disagrees
9
15cv2674-MMA (WVG)
1
and finds that Plaintiff has identified the statements with sufficient particularity. Here,
2
Plaintiff has identified the date, document, and paraphrased content of the allegedly false
3
statements. See Oppo. at 10; see also SAC.
4
In the first statement, Plaintiff alleges that in each of the thirteen grant applications,
5
Defendant “certified, represented, and assured the FAA in the above-described
6
applications that it had assured compatible land use in the RPZ by the adoption of the
7
‘Palomar Airport Comprehensive Land Use Plan.’” SAC ¶¶ 30, 78, 126, 174, 222, 258,
8
294, 330, 366, 402, 450, 486, 522. Defendant’s “best guess” is that this certification is
9
contained in Part II—Section C of the grant applications. MTD at 11. The relevant
10
11
12
portion requires the applicant to respond to the following:
The Sponsor hereby represents and certifies as follows:
1. Compatible Land Use. – The Sponsor has taken the following actions to
assure compatible usage of land adjacent to or in the vicinity of the airport:
13
14
See Doc. No. 33-1, Exhibit 2; see also Doc. No. 32-3, Exhibits 3, 5, 7, 9, 11, 13, 15, 17,
15
19, 21, 23, 25. In each application, Defendant responded: “Palomar Airport
16
Comprehensive Land Use Plan.” See Doc. No. 33-1, Exhibit 2; see also Doc. No. 32-3,
17
Exhibits 3, 5, 7, 9, 11, 13, 15, 17, 19, 21, 23, 25. Plaintiff states that this is the correct
18
provision statement one paraphrases. Oppo. at 12.
19
In the fourth statement, Plaintiff alleges Defendant promised in five of the grant
20
agreements “to acquire an interest in properties located within the RPZ sufficient to
21
eliminate existing incompatible uses of land in the RPZ and sufficient to prevent
22
development of further incompatible uses.” SAC, ¶¶ 60, 108, 156, 204, 432. Defendant
23
explains that “it appears” this allegedly false statement is based on the following
24
language in paragraph 15 of the grant agreements:
25
26
27
28
15. RUNWAY PROTECTION ZONES: The Sponsor agrees to take the
following actions to maintain and/or acquire a property interest, satisfactory
to the FAA, in the Runway Protection Zones:
I.
Existing Fee Title Interest in the Runway Protection Zone:
The Sponsor agrees to prevent the erection or creation of any
10
15cv2674-MMA (WVG)
1
structure or place of public assembly in the Runway Protection
Zone, except for NAVAIDS that are fixed by their functional
purposes or any other structure approved by the FAA. Any
existing structures or uses within the Runway Protection Zone
will be cleared or discontinued unless approved by the FAA.
II.
Existing Easement Interest in the Runway Protection Zone:
The Sponsor agrees to take any and all steps necessary to ensure
that the owner of the land within the designated Runway
Protection Zone will not build any structure in the Runway
Protection Zone that is a hazard to air navigation or which might
create glare or misleading lights or lead to the construction of
residences, fuel handling and storage facilities, smoke generating
activities, or places of public assembly, such as churches,
schools, office buildings, shopping centers, and stadiums.
Future Interest in the Runway Protection Zone: The Sponsor agrees
that it will acquire fee title or less-than-fee interest in the Runway
Protection Zones for runways that presently are not under its control
within ten5 years of this Grant Agreement. Said interest shall provide
the protection noted in above Subparagraphs a and b.
2
3
4
5
6
7
8
9
10
11
12
13
14
Doc. No. 32-3, Exhibits 4, 6, 8, 20, 24, 20; Doc. No. 33-1, Exhibit 1. Plaintiff states that
15
paragraph 15 of the grant agreements are the correct provisions being paraphrased in the
16
fourth false statement. Oppo. at 17.
17
In the second statement, Plaintiff alleges that Defendant certified in all of the grant
18
agreements that “it was in compliance with all applicable FAA Advisory Circulars and
19
regulations applicable to AIP6 projects, including compliance with FAA Advisory
20
Circulars AC 150/5300-13 and AC 150/5100, and 49 CFR Part 24.” SAC, ¶¶ 38, 86,
21
134, 182, 230, 266, 302, 338, 374, 410, 458, 494, 530. In the fifth statement, Plaintiff
22
alleges that Defendant promised in all of the grant agreements “that it would be guided in
23
the acquisition of real property by 49 CFR Part 24, subpart B, and that it had complied
24
and would comply with Advisory Circular 150/5300-13, Changes 1 through 5, and
25
26
27
28
Causes of action 1, 3, and 4 state Defendant’s promise would be fulfilled in 10 years, cause of action 2
states 20 years, and cause of action 10 omits the term of years. SAC, ¶¶ 60, 108, 156, 204, 432.
6
AIP refers to “Airport Improvement Program.” See Doc. No. 20, Exhibit 31.
5
11
15cv2674-MMA (WVG)
1
150/5100.” SAC, ¶¶ 72, 120, 168, 216, 252, 288, 324, 360, 396, 444, 480, 516, 552.
2
Defendant contends these certifications are not in the grant agreement, and assumes they
3
are in assurances incorporated into the grant agreements. MTD at 15 n.8. Plaintiff
4
explains that statements two and five “correspond with the Sponsor Certification and
5
Assurance 34 in the Grant Agreements.” Id. at 15. That assurance states:
6
7
8
9
10
11
12
13
14
15
C.
Sponsor Certification. The sponsor hereby assures and certifies, with
respect to this grant that:
1.
General Federal Requirements. It will comply with all
applicable Federal laws, regulations, executive orders, policies,
guidelines, and requirements as they relate to the application,
acceptance and use of Federal funds for this project including but not
limited to the following:
...
34. Policies, Standards, and Specifications. It will carry out the
project in accordance with policies, standards, and specifications
approved by the Secretary including but not limited to the advisory
circulars listed in the Current FAA Advisory Circulars for AIP projects,
dated 7/1/05 and included in this grant, and in accordance with
applicable state policies, standards, and specifications approved by the
Secretary.
16
17
Doc. No. 33-1, Exhibit 1 at 6, 18.
18
In the third statement, Plaintiff alleges that in all thirteen of the grant agreements
19
Defendant “expressly promised the FAA it would take appropriate action, to the extent
20
reasonable, to restrict the use of land adjacent to or in the vicinity of the airport to
21
activities and purposes compatible with normal airport operations, including the take-off
22
and landing of planes.” SAC, ¶¶ 48, 96, 144, 192, 240, 276, 312, 348, 384, 420. 468,
23
504, 540. Plaintiff contends this included promising that Defendant “would ensure
24
compatible land uses in the RPZ in accordance with FAA Circulars 150/5300 and
25
150/5100,” which means “restricting land use in the RPZ to prevent future office
26
development and eliminate existing office development.” SAC, ¶¶ 49, 97, 145, 193, 241,
27
277, 313, 349, 385, 421, 469, 505, 541.
28
12
15cv2674-MMA (WVG)
Defendant contends that “the alleged promise . . . is not contained within the four
1
2
corners of the agreement” and that Defendant is unsure where the statement comes from.
3
See Oppo. at 10; MTD at 18. Plaintiff explains that statement three “refers to assurance
4
21 of the grant agreements.” Oppo. at 16. That assurance provides:
5
C.
Sponsor Certification. The sponsor hereby assures and certifies, with
respect to this grant that:
1.
General Federal Requirements. It will comply with all
applicable Federal laws, regulations, executive orders, policies,
guidelines, and requirements as they relate to the application,
acceptance and use of Federal funds for this project including but not
limited to the following:
...
21. Compatible Land Use. It will take appropriate action, to the
extent reasonable, including the adoption of zoning laws, to restrict the
use of land adjacent to or in the immediate vicinity of the airport to
activities and purposes compatible with normal airport operations,
including landing and takeoff of aircraft. In addition, if the project is
for noise compatibility program implementation, it will not cause or
permit any change in land use, within its jurisdiction, that will reduce
compatibility, with respect to the airport, of the noise compatibility
program measures upon which Federal funds have been expended.
6
7
8
9
10
11
12
13
14
15
16
17
Doc. No. 33-1, Exhibit 1 at 6, 13.
As a result, each allegedly false statement has been identified as paraphrasing a
18
19
specific provision in a grant agreement, application, or the assurances incorporated
20
therein. While Plaintiff’s SAC could have provided more clarity by identifying the
21
specific provisions of the grant agreements, applications, or assurances, Plaintiff was not
22
required to do so. Therefore, the Court finds that the SAC’s claims are sufficiently
23
particular to identify each allegedly false statement because Plaintiff specified the date,
24
document, and paraphrased content of the provisions containing the allegedly false
25
statements.
26
3.
Falsity
27
Defendant argues that Plaintiff failed to sufficiently plead with particularity that
28
the five statements are false. MTD at 10-22. While the time, place, and content of an
13
15cv2674-MMA (WVG)
1
alleged misrepresentation might identify the statement or omission, those circumstances
2
do not constitute fraud. In re GlenFed, Inc. Sec. Litig., 42 F.3d at 1547-48. Thus, the
3
statement must be false in order to be fraudulent. Id. at 1548. To prove falsity, a plaintiff
4
“must set forth what is false or misleading about a statement, and why it is false. In other
5
words, the plaintiff must set forth an explanation as to why the statement or omission
6
complained of was false or misleading.” Id. Ultimately, a complaint “need not identify
7
representative examples of false claims to support every allegation,” but the complaint
8
must still allege the “particular details of a scheme to submit false claims.” See United
9
States ex rel. Swoben v. United Healthcare Ins. Co., 848 F.3d 1161, 1180 (9th Cir. 2016)
10
(internal quotations omitted).
11
A.
12
With respect to the first statement delineated above, Defendant argues its
Statement 1
13
response—“Palomar Airport Comprehensive Land Use Plan”—cannot give rise to FCA
14
liability because the response is not objectively false and does not certify compliance
15
with a statute or regulation. MTD at 11-14. Plaintiff counters that certification of
16
compliance with a statute or regulation is not necessarily required if Defendant made a
17
misrepresentation about compliance with a contractual requirement. Oppo. at 8. Plaintiff
18
is correct that false certification of compliance with a contractual requirement is a
19
misrepresentation that renders the claim false or fraudulent under the FCA. Campie, 862
20
F.3d at 901 (citing Escobar, 136 S.Ct. at 1995).
21
Defendant also argues the response “Palomar Airport Comprehensive Land Use
22
Plan,” is not objectively false. Id. at 12. Defendant contends that Plaintiff’s allegations
23
that this answer “assured compatible land use in the RPZ by the adoption of the ‘Palomar
24
Airport Comprehensive Land Use Plan,’” which “restricted the use of RPZ land sufficient
25
to eliminate existing, and prevent future development of, incompatible uses such as office
26
buildings” are unsupported. Id. at 12-13 (quoting SAC, ¶¶ 30-31). Defendant asserts that
27
28
14
15cv2674-MMA (WVG)
1
the Airport Comprehensive Land Use Plan (“ALCUP”)7 is adopted by the Airport
2
Authority, not Defendant, and that the Airport Authority is responsible for assisting local
3
agencies in ensuring compatible land uses in the vicinity of airports. Id. at 13. As such,
4
Defendant claims that, as a matter of law, its answer cannot be interpreted as a
5
certification that it adopted the plan or certified that all land was compatible and that the
6
only reasonable interpretation is that the answer evinces Defendant looked at the ALCUP
7
to ensure compatibility. Id.
8
As indicated in the Court’s August 3, 2017 Order Granting Defendant’s Motion to
9
Dismiss (“Order”), “‘at this stage, a court does not make factual findings.’” Doc. No. 28
10
(“Order”) at 15 (citing Browne v. McCain, 612 F. Supp. 2d 1125, 1130 (C.D. Cal. 2009)).
11
The Court again declines to determine as a matter of law the scope of Defendant’s
12
authority over land use. See id. Plaintiff alleges that Defendant “assured compatible land
13
use in the RPZ by adoption of the ‘Palomar Airport Comprehensive Land Use Plan,’” and
14
promised to make sure that the RPZ was and would remain free from incompatible land
15
uses, including office buildings. SAC, ¶¶ 30-31, 78-79, 126-27, 174-75, 222-23, 258-59,
16
294-95, 330-31, 366-67, 402-03, 450-51, 486-87, 522-23. Plaintiff further alleges that an
17
office building existed in the RPZ and Lot 25 was zoned and planned for office or
18
industrial use at the time the grant applications were made. SAC, ¶¶ 32, 80, 128, 176,
19
224, 260, 296, 332, 368, 404, 452. Moreover, Plaintiff contends Defendant never took
20
any steps to acquire interest in RPZ lands to prohibit incompatible uses and had no
21
intention of doing so in the future. Id. Because the SAC itself now alleges Defendant’s
22
statement was false for this reason, Plaintiff sufficiently pleads falsity with the specificity
23
required under Rule 9(b). See Order at 15 n.8.
24
25
26
27
28
Defendant explains that Palomar’s Airport Comprehensive Land Use Plan is what is now called an
airport land use compatibility plan (“ALCUP”). MTD at 12. An ALCUP “provides for the orderly
growth of each public airport and the area surrounding the airport . . . and will safeguard the general
welfare of the inhabitants within the vicinity of the airport and the public in general.” Id. (internal
citations and quotation marks omitted).
7
15
15cv2674-MMA (WVG)
1
B.
2
Defendant asserts that the second and fifth allegedly false statements are
3
insufficiently pleaded because Plaintiff failed to identify the portions of the Advisory
4
Circulars (“AC”) and the regulation Defendant allegedly violated. MTD at 15, 21-22.
5
However, Rule 9(b) does not require Plaintiff to identify the specific portion of the ACs
6
and the regulation Defendant allegedly violated; rather Rule 9(b) requires Plaintiff to
7
plead with sufficient particularity the allegedly false statement and why and how that
8
statement is false. See In re GlenFed, Inc. Sec. Litig., 42 F.3d at 1548. In the SAC,
9
Plaintiff identifies the content of the ACs and the regulation and explains how they render
10
11
Statements 2 and 5
Defendant’s statement false.
Specifically, Plaintiff alleges that AC 150/5300 declares that “[t]he RPZ’s function
12
is to enhance the protection of people and property on the ground. This is best achieved
13
through airport owner control over RPZs. Control is preferably exercised through the
14
acquisition of sufficient property interest in the RPZ and includes clearing RPZ areas
15
(and maintaining them clear) of incompatible objects and activities.” SAC, ¶ 16. AC
16
150/5300 also declares that office buildings, and any other use involving an assembly of
17
people are incompatible uses prohibited in the RPZ by specifically stating “[i]t is
18
desirable to clear the entire RPZ of all above-ground objects. Where this is impractical,
19
airport owners, at a minimum, should maintain the RPZ clear of all facilities supporting
20
incompatible activities.” Id.
21
Plaintiff alleges that AC 150/5100 states that “[n]ormally the sponsor will acquire
22
fee title to all land within the airport boundaries and for the [RPZ]. If fee acquisition for
23
the RPZ is not practical then an avigation easement is required. . . . Generally, where less
24
than fee title is proposed to be acquired the property rights acquired shall be sufficient to
25
encumber the remainder real estate with provisions that will ensure full use of the
26
property as needed for airport construction and/or for safe airport operations conforming
27
to FAA requirements.” SAC, ¶ 17. AC 150/5100 recommends “that the RPZ be
28
acquired in fee, however, if this is not practical, an easement must be acquired that
16
15cv2674-MMA (WVG)
1
adequately restricts land use. The easement acquired must . . . restrict current and future
2
use of the land surface to preclude incompatible uses. Incompatible uses within the RPZ
3
include land use for residences and places of public assembly (churches, schools,
4
hospitals, office buildings, shopping centers, and other uses with similar concentrations
5
of persons) and other uses inconsistent with airport operations.” Id.
6
With respect to the federal regulation, Plaintiff alleges the FAA requires airport
7
sponsors to comply with 49 CFR Part 24 requirements, which include that the airport
8
owner: (1) “[m]ake every reasonable effort to acquire the real property expeditiously by
9
negotiation;” (2) “[a]s soon as feasible notify the property owner in writing of the interest
10
in acquiring the real property, and the basic protections provided to the owner by law and
11
under 49 CFR Part 24;” (3) “[c]ause the real property interest to be acquired to be
12
appraised prior to commencement of negotiations;” (4) “[b]efore initiating negotiations,
13
cause an amount which it believes to be just compensation to be established, at not less
14
than the approved appraisal, make a written offer to the property owner in said amount,
15
and include a written statement of the basis for the offer of just compensation;” and (5)
16
[n]ot defer the negotiations, and if the intent is to acquire by eminent domain, not delay
17
so as to make it necessary for the owner to institute legal proceedings to prove the fact of
18
the taking of the real property.” SAC, ¶ 18.
19
Plaintiff alleges Defendant falsely certified it was in compliance with these ACs
20
and federal regulation. SAC, ¶¶ 38, 72, 86, 120, 134, 168, 182, 216, 230, 252, 266, 288,
21
302, 338, 360, 374, 396, 410, 444, 458, 480, 494, 516, 530, 552. Plaintiff alleges this
22
certification was false “because Lot 24 in the RPZ was at that time fully developed and
23
occupied as an office building, and Lot 25 was vacant and zoned and planned for an
24
office/industrial building, and there were no land use restrictions preventing or
25
eliminating such uses, and Defendant . . . had not undertaken and had no intent to
26
undertake an[y] steps to acquire an interest in said Lots sufficient to prevent or eliminate
27
such incompatible uses.” SAC, ¶¶ 38, 86, 134, 182, 230, 266, 302, 360, 338, 374, 410,
28
458, 494, 530; see also SAC, ¶¶ 74, 122, 170, 218, 254, 290, 326, 362, 398, 446, 482,
17
15cv2674-MMA (WVG)
1
518, 554. Plaintiff explains that the ACs required Defendant to acquire either a fee
2
interest or an easement in RPZ property to preclude incompatible uses, but Defendant
3
failed to do so, permitted an office building to be developed, and had no intent to acquire
4
a sufficient property interest to eliminate the incompatible use. Oppo. at 15-16. Plaintiff
5
therefore argues that Defendant could not truthfully certify its compliance with the ACs
6
and the federal regulation because an incompatible use existed in the RPZ and it did not
7
intend to acquire any interest to eliminate or restrict that incompatible use. Id. at 16.
8
9
Based on Plaintiff’s allegations, the falsity of statements two and five are pleaded
with sufficient particularity to survive the instant motion to dismiss. Plaintiff has
10
identified Defendant’s statements, explained the relevant portions of the ACs and federal
11
regulation, indicated that Defendant’s statements were false, and explained how
12
Defendant’s statements were false.
13
C.
14
In the third statement delineated above, Plaintiff alleges that Defendant “promised
Statement 3
15
the FAA it would take appropriate action, to the extent reasonable, to restrict the use of
16
land” within the RPZ. SAC, ¶¶ 48, 96, 144, 192, 240, 276, 312, 348, 420, 468, 504, 540.
17
Plaintiff alleges this is a false promise because at the time Defendant made the promise
18
there was and still is an incompatible use, an office building, within the RPZ and
19
Defendant had not taken any steps to eliminate the incompatible use. SAC, ¶¶ 50, 98,
20
146, 194, 242, 278, 314, 350, 422, 470, 506, 542.
21
Defendant argues that because it only agreed to take “appropriate action, to the
22
extent reasonable” to restrict land use in the RPZ, Defendant cannot be liable under the
23
FCA. MTD at 18. Specifically, Defendant contends Plaintiff’s allegation “ignores the
24
obvious possibility that there was no reasonable and appropriate action available to fulfill
25
the promise.” Id. Again, the Court does not make factual findings in determining the
26
propriety of a Rule 12(b)(6) motion to dismiss, and accordingly, declines to rely on
27
Defendant’s argument that there was no reasonable and appropriate action available to
28
18
15cv2674-MMA (WVG)
1
fulfill the promise. See Order at 16. Accordingly, statement three survives Defendant’s
2
falsity argument.
3
D.
4
With respect to statement four, Defendant argues it cannot give rise to an FCA
Statement 4
5
claim because it is qualified by statements which are not objectively false—“satisfactory
6
to the FAA” and “unless approved by the FAA.” MTD at 15. As explained in this
7
Court’s prior Order, “[w]ithout deciding as a matter of law what was required under the
8
provisions, it appears to the Court that the provisions required sponsors to comply with
9
the subsections in order to ‘maintain and/or acquire a property interest satisfactory to the
10
FAA.’” Order at 14. As such, Defendant had to agree to “prevent the erection or
11
creation,” of incompatible uses in the RPZ, or clear or “discontinue” such uses, “unless
12
approved by the FAA,” and to acquire an interest in the RPZ for runways not presently
13
under Defendant’s control. Doc. No. 32-3, Exhibits 4, 6, 8, 20, 24, 20; Doc. No. 33-1,
14
Exhibit 1. As stated in this Court’s prior Order, “[u]nder Defendant’s interpretation, the
15
subsections would be rendered either permissive, despite that the language indicates that
16
they are mandatory requirements, or superfluous. Sponsors would be left guessing what
17
actions would be ‘satisfactory to the FAA.’” Order at 14-15. Moreover, the fact that
18
Plaintiff does not allege whether the FAA approved of the continuing incompatible use of
19
a lot within the RPZ does not mean Defendant’s statement was not objectively false.
20
Here, Plaintiff alleges Defendant promised to acquire an interest in properties
21
located within the RPZ to eliminate existing incompatible uses and prevent development
22
of future incompatible uses. SAC, ¶¶ 60, 108, 156, 204, 432. Plaintiff alleges an existing
23
incompatible use existed on one lot in the RPZ and another lot in the RPZ was planned
24
for an incompatible use when Defendant promised to eliminate such uses. SAC, ¶¶ 61,
25
109, 157, 205, 433. Further, Plaintiff alleges at the time Defendant made this promise it
26
“had no intent to acquire any interest in the RPZ property.” SAC, ¶¶ 62, 110, 158, 206,
27
434 (emphasis added). Plaintiff supports this allegation by providing the sworn
28
testimony of the County Agent who signed each grant application and agreement on
19
15cv2674-MMA (WVG)
1
behalf of the County. Plaintiff alleges that this agent, Peter Drinkwater, testified under
2
oath that the County did not have any intent to acquire interests in Lots 23, 24, or 25. Id.
3
In further support, Plaintiff alleges Eric Nelson, who was the County Airport Engineer
4
between 2005 and at least August of 2015, testified under oath that Defendant was not
5
aware of “any intent to acquire any interest at all in Lot 24 or 25” and also was not aware
6
of any intent to prevent development of lots 24 and 25 which are incompatible with the
7
airport. Id. As a result, the Court is unconvinced by Defendant’s argument and finds that
8
Plaintiff pleads the falsity of statement four with sufficient particularity.
9
4.
10
Materiality
Defendant contends Plaintiff insufficiently pleads materiality because no relation
11
exists between the false statements and the government’s loss and the allegedly false
12
assurances, promises, or certifications were not prerequisites to obtaining funding from
13
the FAA. MTD at 22-26.
14
In FCA cases, “[t]he materiality standard is demanding.” Escobar, 136 S. Ct. at
15
2003. “A misrepresentation cannot be deemed material merely because the Government
16
designates compliance with a particular statutory, regulatory, or contractual requirement
17
as a condition of payment.” Id. “Nor is it sufficient for a finding of materiality that the
18
Government would have the option to decline to pay if it knew of the defendant’s
19
noncompliance.” Id. “Materiality, in addition, cannot be found where noncompliance is
20
minor or insubstantial.” Id. Further, courts consider whether there is any relationship
21
between the subject matter of the false statement and the provision of the benefit. See
22
Hopper, 91 F.3d at 1266.
23
Defendant argues materiality is not met because no relation exists between the
24
subject matter of the allegedly false statements and the event triggering the government’s
25
loss. MTD at 24-25. Defendant contends the subject matter of the false statements
26
“relates to an office building located in the RPZ” and the event triggering the
27
Government’s loss is “the County’s request for grant fund payments for 13 airport
28
improvement projects.” Reply at 4. This is a skewed understanding of Plaintiff’s SAC.
20
15cv2674-MMA (WVG)
1
See SAC. The false statements all relate to Defendant’s assurances, promises, or
2
certifications that it would eliminate or prevent incompatible land use in the RPZ and the
3
event triggering the Government’s loss is the existence of an ongoing safety hazard to
4
people and property posed by incompatible uses in the RPZ. See id.
5
A relation does exist between the allegedly false statements and the government’s
6
alleged loss. See United States ex rel. Holder v. Special Devices, Inc., 296 F. Supp. 2d
7
1167, 1174 n.2 (C.D. Cal. 2003) (“[I]t is apparent in the instant case that the
8
government’s loss—the pollution—was triggered by [Defendant’s] alleged false warranty
9
and promise to abide by environmental regulations.”); see also Hopper, 91 F.3d at 1266
10
(stating the question is “whether any relation exists between the subject matter of the
11
false statement and the event triggering Government’s loss”) (emphasis added). Here,
12
each and every time Defendant submitted a grant application or signed a grant agreement,
13
it warranted that it would comply with and abide by the FAA’s requirements relating to
14
land use in the RPZ. It is alleged that Defendant’s failure to abide by those regulations
15
led to ongoing safety hazards. The government’s loss is caused by the existence of those
16
safety hazards, which were triggered by Defendant’s false certifications, assurances, and
17
promises that it would abide by land use requirements in the RPZ.
18
Next, Defendant argues that Plaintiff “fails to plead facts sufficient to show any of
19
the five allegedly false statements constituted certifications prerequisite to a condition of
20
payment.” MTD at 23. Defendant points to several allegations in the SAC it contends
21
are conclusory and asserts that Plaintiff “has failed to plead sufficient facts with
22
particularity showing the certifications at issue were prerequisites to obtaining a
23
government benefit.” MTD at 24. Plaintiff counters the certifications and promises were
24
prerequisites. Oppo. at 20. Specifically, Plaintiff alleges that the FAA’s mission is to
25
“provide the safest, most efficient aerospace system in the world” and that the FAA’s
26
highest aviation priority is airport safety. SAC, ¶¶ 8-9. As a result, Plaintiff contends
27
that “[b]ecause the FAA’s very purpose for existence and its highest priority is to ensure
28
the safety of American airports, it follows that the most important statements in the AIP
21
15cv2674-MMA (WVG)
1
grant applications and grant agreements are those which are specifically calculated to
2
enhance the safety of American airports.” Oppo. at 20; see SAC, ¶¶15-17, 9, 21, 23
3
(stating that each of the allegedly false statements are required by the FAA to protect
4
people and property in the RPZ).
5
Plaintiff alleges that the FAA would not have made the grants or disbursed grant
6
funds to Defendant had it known Defendant was not assuring compatible uses in the RPZ
7
because “to do so would have been a breach of the FAA’s duties to the American public
8
to ensure a safe system of airports.” SAC, ¶¶ 36, 46, 57, 69, 84, 94, 105, 117, 132, 142,
9
153, 165, 180, 190, 201, 213, 228, 238, 249, 264, 274, 285, 300, 310, 321, 336, 346, 357,
10
372, 382, 393, 408, 418, 429, 441, 456, 466, 477, 492, 502, 513, 528, 538, 549. Thus,
11
Plaintiff asserts that noncompliance with the assurances, statements, and rules leads to
12
safety risks, which are most likely to influence the FAA’s decision to provide funding.
13
Oppo. at 20; SAC, ¶ 36. Plaintiff also alleges that, for this reason, the FAA would have
14
been obligated to reject funding if Defendant had been truthful. SAC, ¶¶ 58, 70, 106,
15
118, 151, 154, 166, 202, 211, 214, 250, 286, 322, 358, 394, 430, 442, 478, 514, 550.
16
With respect to statement five, Plaintiff merely alleges that “[t]he FAA would not have
17
provided the federal funding for the project had it been aware the foregoing was false.”
18
SAC, ¶¶ 73, 121, 169, 217, 253, 289, 325, 361, 397, 445, 481, 517, 553.
19
Plaintiff also argues the FAA is “required by law to base its decision to approve or
20
disapprove applications for AIP funds on the statements, certifications, and assurances
21
therein.” Oppo. at 21-22. In Hendow, the Ninth Circuit held that materiality is met
22
where funding is “explicitly conditioned” on compliance with certain requirements.
23
Hendow, 461 F.3d at 1175-76. However, after the Supreme Court’s decision in Escobar,
24
a statue or regulation which explicitly conditions compliance is only a non-dispositive
25
factor to consider in the materiality analysis because “statutory, regulatory, and
26
contractual requirements are not automatically material, even if they are labeled
27
conditions of payment” Escobar, 136 S. Ct. at 2001. Accordingly, Plaintiff’s argument
28
22
15cv2674-MMA (WVG)
1
that the FAA is required by law to base its decision on compliance is only a factor to be
2
considered. See id.
Here, Plaintiff asserts the funding is explicitly conditioned in two different ways.8
3
4
See Oppo. at 22. First, 49 U.S.C.S. § 47107(a)(10) provides that “[t]he Secretary of
5
Transportation may approve a project grant application for an airport development
6
project only if the Secretary receives written assurances, satisfactory to the Secretary, that
7
. . . appropriate action . . . has been or will be taken to the extent reasonable to restrict the
8
use of land next to or near the airport to uses that are compatible with normal airport
9
operations.” 49 U.S.C.S. § 47107(a)(10) (emphasis added). Second, 49 U.S.C.S. §
10
47107(g) states that “[t]he Secretary of Transportation may approve an application for a
11
project grant only if the Secretary is satisfied that the requirements prescribed . . . have
12
been or will be met.” 49 U.S.C.S. § 47107(g)(2) (emphasis added). Because both
13
subsections of § 47107 demonstrate that compliance with the required certifications,
14
assurances, or promises within the grant applications and agreements is a necessary
15
condition of the FAA’s disbursement of funds, Plaintiff argues compliance is a
16
“prerequisite” to funding. See 49 U.S.C.S. § 47107 (a)(10), (g)(2).
Defendant argues the subsections of the statute “relate to government approval of
17
18
grant applications, not payment of grant funds,” and therefore, materiality is not met.
19
Reply at 3 (emphasis in original). That is a distinction without difference at this stage in
20
the litigation. If the Court were to find that conditions of grant approval were not
21
conditions of disbursement of grant funds, “there would be no conditions of payment at
22
23
24
25
26
27
28
8
Plaintiff argues 49 U.S.C.S. § 47108 also explicitly conditions compliance because it states an
accepted offer in writing by the sponsor is a binding agreement and the government may pay only after a
grant agreement is signed. Oppo. at 22. This, however, does not explicitly condition compliance, it
merely states an accepted offer is a contract. See 49 U.S.C.S. § 47108(a). “The False Claims Act is not
‘an all-purpose antifraud statute’ or vehicle for punishing garden-variety breaches of contract or
regulatory violations. A misrepresentation cannot be deemed material merely because the Government
designates compliance with a particular statutory, regulatory, or contractual requirement as a condition
of payment.” Escobar, 136 S. Ct. at 2003 (internal citation omitted).
23
15cv2674-MMA (WVG)
1
all.” See Hendow, 461 F.3d at 1176; see also Siebert v. Gene Sec. Network, Inc., 75 F.
2
Supp. 3d 1108, 1120-24 (N.D. Cal. 2014) (stating in a pre-Escobar case that materiality
3
was met where the defendant “was required to certify compliance with . . . accounting
4
regulations . . . and those certifications incorporated the Grants Policy Statement, which
5
provided that compliance was ‘essential to the grant relationship . . . .’”).
“[W]hen evaluating materiality under the False Claims Act, the Government’s
6
7
decision to expressly identify a provision as a condition of payment is relevant, but not
8
automatically dispositive.” Escobar, 136 S.Ct. at 2003. Here, Plaintiff has not alleged
9
with sufficient particularity proof of materiality, which “can include, but is not
10
necessarily limited to, evidence that the defendant knows that the Government
11
consistently refuses to pay claims in the mine run of cases based on noncompliance with
12
the particular statutory, regulatory, or contractual requirement.” See id. In other words,
13
the plaintiff “must allege some facts that show that the government actually does not pay
14
claims if they involve the statutory[, regulatory, or contractual] violations in question.”
15
United States ex rel. Ferris v. Afognak Native Corp., No. 3:15-cv-0150-HRH, 2016 WL
16
9088706, at *3 (D. Alaska Sept. 28, 2016). The materiality allegations in the SAC are
17
still largely conclusory, stating that the FAA would not have disbursed funding had it
18
known Defendant’s assurances, certifications, or promises were false, because the FAA
19
was required by law to assure compliance, and because the FAA’s priority is ensuring
20
safety. See SAC. Ultimately, Plaintiff has not sufficiently alleged that Defendant’s
21
assertions of compliance, or promises to remove the alleged office building in the RPZ
22
were the “sine qua non of receipt of” the government funding received. See Ebeid, 616
23
F.3d at 998.
24
//
25
//
26
//
27
//
28
//
24
15cv2674-MMA (WVG)
1
5.
Scienter
Defendant argues Plaintiff’s scienter allegations are insufficiently pleaded because
2
3
they are vague and conclusory. 9 MTD at 26. In opposition, Plaintiff argues he
4
sufficiently alleged:
5
1) that the grant assurances were binding and required the County to mitigate
hazards to the RPZ; 2) that the FAA requires Sponsors to sufficiently control
RPZ property to prevent incompatible land use in conformance with FAA
Advisory Circulars; 3) that the requirements for controlling and protecting the
RPZ are safety related and based on empirically demonstrated heightened
risks from airport activities; 4) that FAA requirements prohibited office
buildings in the RPZ; 5) that an office building was in fact developed in the
RPZ and that it exists to this day and 6) that the FAA would not grant federal
funding to an airport which was not being operated in compliance with safety
requirements, and if the FAA had known of the incompatible use it would
have either refused to fund the airport or required costly remedial measures
prior to funding
6
7
8
9
10
11
12
13
14
Oppo. at 27. Plaintiff argues scienter is also met because he alleges Defendant covered
15
up the existence of an office building in the RPZ in its submissions to the FAA. Id.
In short, scienter is “the knowing presentation of what is known to be false,” and
16
17
that the false statement or fraudulent conduct must be made with intent to deceive.
18
United States ex rel. Hochman v. Nackman, 145 F.3d 1069, 1073 (9th Cir. 1998);
19
Hendow, 461 F.3d at 1172; see also 31 U.S.C. § 3729(a)(1)(A), (B). Under Rule 9(b),
20
“scienter[] can be alleged generally.” See United States ex rel. Lee v. Corinthian
21
Colleges, 655 F.3d 984, 996 (9th Cir. 2011) (internal quotation marks omitted).
22
23
24
25
26
27
28
9
Defendant also argues that Plaintiff does not mention whether the false statements were material to the
FAA’s decision to pay the grant funds. MTD at 27-28. This is appropriately analyzed under the
materiality element. Ferris, 2016 WL 9088706, at * 2-3 (“The Court explained that ‘[w]hat matters is
not the label the Government attaches to a requirement, but whether the defendant knowingly violated a
requirement that the defendant knows is material to the Government’s payment decision.’ In other
words, ‘a misrepresentation about compliance with a statutory, regulatory, or contractual requirement
must be material to the Government’s payment decision in order to be actionable . . . .’”) (citing
Escobar, 136 S.Ct. at 2002) (emphasis added).
25
15cv2674-MMA (WVG)
1
However, “‘innocent mistakes, mere negligent misrepresentations and differences in
2
interpretations’ will not suffice to create liability.” Id. (citing Hendow, 461 F.3d at
3
1174).
4
Under the FCA, “knowingly” does not require specific intent to defraud. 31
5
U.S.C. § 3729(b)(1)(B). Rather, the FCA defines “knowingly” as actual knowledge,
6
deliberate ignorance of the truth or falsity of the information, or reckless disregard of the
7
truth or falsity of the information. 31 U.S.C. § 3729(b)(1)(A)(i)-(iii). Further, “an
8
inference of scienter must be more than merely plausible or reasonable—it must be
9
cogent and at least as compelling as an opposing inference or nonfraudulent intent.”
10
11
Tellabs, Inc. v. Makor Issues & Rights, Ltd., 551 U.S. 308, 314 (2007).
To show actual knowledge, Plaintiff must allege that Defendant knew its
12
statements were false when made, meaning Defendant knew the statements were “lie[s].”
13
Wang v. FMC Corp., 975 F.2d 1412, 1421 (9th Cir. 1992), overruled on other grounds,
14
United States ex rel. Hartpence v. Kinetic Concepts, Inc., 792 F.3d 1121 (9th Cir. 2015);
15
see also Hendow, 461 F.3d at 1171-72. Plaintiff alleges that Defendant was “acutely
16
aware” of the FAA’s requirement to acquire real property interests in the RPZ sufficient
17
to prevent or eliminate incompatible uses. SAC, ¶ 20. In support of this allegation,
18
Plaintiff alleges a 1995 written application for an AIP grant to the FAA declared that Lots
19
23, 24, and 25 are in the “West RPZ” and that Defendant “budgeted for acquisition” of
20
these lots. SAC, ¶21. Later in 1995, Defendant allegedly postponed its plan to acquire
21
Lots 23, 24, and 25 “because it determined the cost of acquisition was more than it was
22
willing to pay.” SAC, ¶ 22. In 1997, Plaintiff alleges Defendant again “expressly
23
acknowledged that Lots 24 and 25 in the RPZ should be acquired.” SAC, ¶ 23.
24
However, Plaintiff alleges that Defendant “has not at any time since its 1995
25
postponement of the acquisition of said lots taken any step to acquire any interest at all in
26
said lots . . . . even though it is fully aware that [Lot 24] is and has since 2004 been used
27
and occupied continuously as an office building . . . .” SAC, ¶ 24. Plaintiff further
28
26
15cv2674-MMA (WVG)
1
alleges that Defendant “at all relevant times had no intent of performing its grant
2
assurances and promises made to the FAA in connection with the RPZ . . . .” SAC, ¶ 25.
3
Additionally, Plaintiff alleges Defendant knew statements one through four were
4
false when made because Defendant knew Lot 24 in the RPZ was fully developed and
5
occupied as an office building and Lot 25 was zoned and planned for use as an office or
6
industrial building. SAC, ¶¶ 32, 38, 50, 63, 80, 86, 98, 110, 128, 134, 146, 157, 176, 182,
7
194, 205, 224, 230, 242, 260, 266, 278, 296, 302, 314, 332, 338, 350, 368, 374, 386, 404,
8
410, 422, 433, 452, 458, 470, 488, 494, 506, 524, 530, 542. Plaintiff further alleges that
9
Defendant intended to deceive the FAA into believing it had adequately protected the
10
RPZ to satisfy the FAA’s land use requirements, but had no intention at the time of the
11
grant agreements to acquire any sufficient interests in the lots. SAC, ¶¶ 32, 34, 39, 53,
12
65, 82, 87, 90, 101, 113, 130, 135, 138, 149, 158, 161, 178, 183, 186, 197, 206, 209, 226,
13
231, 234, 245, 262, 267, 270, 281, 298, 303, 306, 317, 334, 339, 342, 353, 370, 375, 378,
14
389, 406, 411, 414, 425, 434, 437, 454, 459, 462, 473, 490, 495, 498, 509, 526, 531, 534,
15
545. In support, Plaintiff alleges Defendant submitted a bird’s-eye photograph of the
16
airport from before the office building was built—indicating Defendant was attempting to
17
“hid[e] a critical development from the FAA, a safety hazard in the RPZ.” SAC, ¶¶ 43,
18
91, 102, 150, 162, 187, 198, 235, 246, 271, 282, 307, 318, 343, 354, 379, 415, 426, 438,
19
463, 474, 499, 510, 535, 546. In further support, Plaintiff alleges Mr. Drinkwater
20
testified under oath that the County did not have an intent to acquire any interest in Lots
21
23, 24, or 25 while he was employed as the Director of Airports for the County. SAC, ¶¶
22
39, 62, 87, 110, 135, 158, 183, 206, 231, 267, 303, 339, 375, 411, 434, 459, 495, 531.
23
Similarly, Plaintiff alleges that Mr. Nelson testified under oath that Defendant did not
24
have any intent to acquire any interest in Lots 24 and 25. Id. These allegations
25
sufficiently plead that Defendant did not have an intent to acquire an interest in Lots 23,
26
24, and 25, but they are conclusory with respect to Defendant’s actual knowledge that an
27
office building was in existence in the RPZ and another lot was planned and zoned for an
28
incompatible use at the time the representations were made.
27
15cv2674-MMA (WVG)
Plaintiff’s allegations with respect to the fifth statement are also insufficient to
1
2
establish scienter. Plaintiff merely alleges that Defendant “knew that these certifications,
3
representations, promises and assurances were false and did not intend to comply with
4
federal law and regulations.” SAC, ¶¶ 75, 123, 171, 219, 255, 291, 327, 363, 399, 447,
5
483, 519, 555. These allegations are vague and conclusory and, accordingly, scienter is
6
not met with respect to the fifth allegedly false statement.
7
Even if actual knowledge is not met, Plaintiff argues the SAC adequately alleges
8
that Defendant “acted with deliberate indifference.” Oppo. at 27. As Defendant correctly
9
points out, “the correct statutory standard is ‘deliberate ignorance,’” or reckless disregard.
10
See Reply at 6; see also 31 U.S.C. § 3729(b)(1)(A)(ii)-(iii). Notwithstanding this error,
11
Plaintiff asserts that Defendant “has to be inferred to have some degree of knowledge
12
about how the grants work and what is required to do to be eligible for the grants.” Id. at
13
28. According to Plaintiff, this means it must be inferred that Defendant was familiar
14
with the requirements of eligibility for grant funding, including certifying, promising, or
15
assuring compliance with land use requirements. Id. Further, Plaintiff contends
16
Defendant “would have known, in the absence of deliberate indifference to the fact, that
17
the FAA would deem compliance with safety related requirements to be the most
18
important goals of the grant applications and grant agreements.” Id. Plaintiff’s
19
argument, however, fails to address how Defendant deliberately ignored or recklessly
20
disregarded the truth or falsity of the statements; rather, Plaintiff focuses on Defendant’s
21
deliberate ignorance or reckless disregard for the requirements to obtain funding.
22
Accordingly, Plaintiff has failed to sufficiently allege that Defendant made a false
23
statement with deliberate ignorance or reckless disregard.
24
The allegations discussed herein are vague and conclusory, particularly with
25
respect to Defendant’s knowledge of the falsity of the statements. Therefore, Plaintiff
26
fails to show Defendant had the requisite scienter for FCA liability.
27
//
28
//
28
15cv2674-MMA (WVG)
CONCLUSION
1
2
For the foregoing reasons, Plaintiff does not sufficiently plead causes of action
3
under the FCA. Accordingly, the Court GRANTS Defendant’s motion to dismiss, and
4
DISMISSES this action in its entirety without prejudice, and with leave to amend.
5
Plaintiff may file a Third Amended Complaint that cures the deficiencies described above
6
on or before February 1, 2018. Pursuant to Civil Local Rule 15.1(c), if Plaintiff wishes
7
to file a Third Amended Complaint, Plaintiff must also include “a version of that
8
pleading that shows—through redlining, underlining, strikeouts, or other similarly
9
effective typographic methods—how that pleading differs from the previously dismissed
10
11
12
pleading.” See Civ. LR 15.1(c).
IT IS SO ORDERED.
Dated: January 11, 2018
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
15cv2674-MMA (WVG)