Sun Construction Company, Inc. v. Torix General Contractors, LLC et al
Filing
341
ORDER. Plaintiff, Sun Construction Company, Inc. (Sun), is awarded the amount of $535,216.62 pursuant to Paragraph 39 of the parties subcontract for its reasonable attorney fees incurred in this matter against Defendants, Torix General Contractors, LLC. and St. Andrews/Alliance Joint Venture (the Joint Venture). By Judge Lewis T. Babcock on 8/18/2011. (sah, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
LEWIS T. BABCOCK, JUDGE
Civil Case No. 07-cv-01355-LTB-MJW
UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF SUN CONSTRUCTION
COMPANY, INC., a Colorado corporation;
Plaintiff,
and
FIDELITY AND DEPOSIT COMPANY OF MARYLAND, a Maryland corporation,
Intervenor Plaintiff,
v.
TORIX GENERAL CONTRACTORS, LLC, a Colorado limited liability company f/k/a Alliance
General Contractors, LLC; and ST. ANDREWS/ALLIANCE JOINT VENTURE, a joint
venture,
Defendants and Counterclaimants,
and
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, a Connecticut
corporation;
Defendant.
______________________________________________________________________________
ORDER
______________________________________________________________________________
This matter is before me on the reasonableness of the amount of attorney fees requested
by Plaintiff Sun Construction Company, Inc. (“Sun”). On June 6, 2011, I awarded Sun its
attorney fees in this matter, when ruling on its Motion to Amend Judgment [Doc # 261], but I
reserved the question of the reasonableness of the fees requested. [Doc # 328] Pursuant to my
minute order [Doc # 329], Defendants, Torix General Contractors, LLC. and St. Andrews/
Alliance Joint Venture (the “Joint Venture”), filed a response contesting the reasonableness of
the fees requested [Doc # 337], and Sun has filed a reply [Doc # 338]. After consideration of the
parties arguments, briefs, and exhibits, as well as oral arguments presented to me at the hearing
on August 18, 2011, I award Sun the sum of $535,216.62 for its reasonable attorney fees against
the Joint Venture. I note that while Sun seeks an award of $567,216.62 for its reasonable
attorney fees, the Joint Venture argues that the amount should be reduced to $239,608.00.
I. BACKGROUND
The underlying lawsuit was brought pursuant to the Miller Act, 40 U.S.C. §3131 and
§3133, for damages incurred related to delay and overruns on a construction project. The prime
contractor on the project was the Joint Venture. Under the requirements of the Miller Act, the
prime contractor posted a payment bond issued by Defendant Travelers Casualty and Surety
Company of America. Plaintiff Sun (as a subcontractor) sued Defendants (as the prime
contractor and its surety) for damages it incurred as a result of the delay and, in turn, the Joint
Venture counterclaimed for its damages. In addition, Fidelity and Deposit Company of
Maryland (“F&D”) intervened to defend against the counterclaims as surety, as well as to claim
over and against Plaintiff Sun for assignment/subrogation on any damages awarded to Sun under
the terms of its bond.
The matter went to trial in November of 2010. The jury found that Plaintiff Sun had
proven its breach of contract claim against Defendants and, as such, incurred damages in the
total amount of $4,143,416. The jury also found that $1,300,000 of that amount was due to F&D
on its assignment/subrogation claim. In addition, the jury found that the Joint Venture had not
proven its counterclaims against Sun. As a result, judgment entered in favor of Plaintiff Sun on
2
November 24, 2010. [Doc # 258] The parties have subsequently filed cross-appeals with the
Tenth Circuit Court of Appeals. [Doc # 287 & 296]
II. SUN’s MOTION TO AMEND
On December 21, 2010, Sun filed a Motion to Amend Judgment, pursuant to Fed. R. Civ.
P. 59, asking that I amend the judgment in its favor to include the following: 1) its reasonable
attorney fees; 2) its costs incurred; 3) attorney fees and costs incurred by Intervenor Plaintiff
F&D in this matter; and 4) prejudgment interest. I granted Sun’s Motion to Amend, in part, on
June 6, 2011. In so doing, I awarded Sun its prejudgment interest on its award of damages, its
costs pursuant to Fed. R. Civ. P. 54(d)(1) , and “its reasonable attorney fees, in an amount to be
determined, against Defendants and Counter-claimants Torix General Contractors, LLC, and St.
Andrews/Alliance Joint Venture,” but I denied Sun’s request for an award of attorney fees and
costs it paid to F&D.
[Doc # 328] I now address the reserved question of the amount of
reasonable attorney fees to be awarded to Sun.
III. REASONABLE ATTORNEY FEES
Sun requests an award of $567,216.62 for its reasonable attorney fees, pursuant to
Paragraph 39 of the subcontract which provides that if a controversy thereunder is decided by
court action, “the prevailing party shall be entitled to have included in the judgment an award for
reasonable attorney fees incurred in connection with said action.” Sun has provided an expert
opinion that the fees requested are reasonable under a lodestar analysis and via application of the
reasonableness factors set forth in Colorado Rule of Professional Conduct 1.5(a). Sun further
notes the existence of its contingency fee agreement with its legal counsel that, in turn, lends
reasonability to the fees sought, and also asserts that it has “gone to great lengths to self-reduce
3
the award” by not seeking significant fees incurred in this matter prior to the filing of the
complaint or during post-trial litigation. Finally, Sun notes that the fees requested represent
approximately 5% of the aggregate difference between the amount it claimed, and the amount it
was defending at trial.
In United States ex rel. C.J.C., Inc. v. Western States Mech. Contractors, Inc., 834 F.2d
1533, 1548 (10th Cir. 1987), the Tenth Circuit reviewed an award of attorney fees to a prevailing
subcontractor in a Miller Act case. The court ruled that “[w]hen the agreement between the
contractor and the subcontractor provides for attorneys’ fees, the subcontractor may recover
from the contractor and its Miller Act surety consistent with the terms of that agreement. Id.
(citations omitted); see also U.S. ex rel. Noyes v. Kimberly Const., Inc., 43 Fed.Appx. 283, 288,
2002 WL 1722139, 4 (10th Cir. 2002)(not selected for publication). Discretion of the court in
such cases is “limited such that ‘fees are routinely granted and [contracts] enforced according to
[their] terms.’” Student Marketing Group, Inc. v. College Partnership, Inc., 2007 WL 2269440,
12 (10th Cir. 2007)(unpublished)(citing C.J.C. v. Western States Mech. Contractors, supra, 834
F.2d at 1548).
“This does not mean, however, that the trial court should simply award the full amount
billed by the prevailing party’s attorneys. . . . [c]learly, the trial court has discretion to adjust or
even deny a contractual award of fees if such an award would be inequitable or unreasonable.”
C.J.C. v. Western States Mech. Contractors, supra, 834 F.2d at 1548 (citations omitted). The
Tenth Circuit further noted “[i]n considering whether a fee is unreasonable or excessive, the trial
court need not wholly disregard the familiar factors from the federal cases awarding fees in a
statutory context; [t]he district court may choose to use these factors, not to compute a
4
reasonable fee, but to assist in determining if the fees claimed are unreasonable or inequitable.”
C.J.C. v. Western States Mech. Contractors, supra, 834 F.2d at 1550.
In Westar Energy, Inc. v. Lake, 552 F.3d 1215, 1228 (10th Cir. 2009), the Tenth Circuit
clarified the ruling in C.J.C. v. Western States Mech. Contractors, supra, related to an award of
attorney fees when the contract provision at issue provided for “reasonable” attorney fees – as
here – as opposed to provisions that allow for the recovery of attorney fees without expressly
referencing reasonableness. Id. The Court indicated that when an attorney fee provision is not
limited to “reasonableness,” a fee award is be upheld unless the payor proves they are
unreasonable or inequitable. Id.; see also J.R. Simplot v. Chevron Pipeline Co., 563 F.3d 1102,
1119 (10th Cir. 2009). However, when the contract specifies that the attorney fees must be
reasonable, the burden remains with party seeking the award of attorney fees to prove its
reasonableness. Westar Energy v. Lake, supra, 552 F.3d at 1249.
The Joint Venture does not challenge the stated hourly rates of Sun’s attorneys, nor does
it dispute that this was a complex case. It argues, however, that the fees requested are
unreasonable because Sun has failed to segregate out the attorney fees that are allocable to
claims upon which it did not prevail. The Joint Venture maintains that Sun asserted four claims
for relief against it, but that the jury returned a verdict on only one of those claims for breach of
contract and, thus, Sun is not entitled to collect the fees it incurred related to the three
unsuccessful claims. The Joint Venture also argues that in order to be deemed reasonable, the
amount of attorneys fees requested should be reduced to reflect the “limited degree of success”
in this matter. It maintains that Sun’s received a judgment for only about 50% of the amounts it
originally sought when taking into account its dismissed claim for lost profits, dismissed on
5
summary judgment. Thus, it maintains that a reasonable fee award should be reduced by 50% of
what it claims to reflect the fact that it only prevailed on a single claim for relief, and for only a
portion of the damages originally sought.
I first note that the case law relied upon by the Joint Venture does not support its
assertion that the attorney fees provided for in the provision of their subcontract – Paragraph 39
which provides that if a controversy thereunder is decided by court action, the prevailing party
shall be entitled to an award for reasonable attorney fees – allows only for the fees incurred on
ultimately successful claims. See e.g. LSV, Inc. v. Pinnacle Creek, LLC, 996 P.2d 188, 192
(Colo. App. 1999)(indicating that a literal interpretation of “all attorney fees” as set forth in a
fee-shifting statute “could lead to the absurd result that a party in a multiple-claim suit who
prevails on other unrelated claims would be liable for all attorney fees of the other
party”)(emphasis added).
Moreover, I agree with Sun that their unsuccessful claims seeking lost profits and
bonding capacity were dismissed relatively early in the litigation on summary judgment. To the
extent that Sun withdrew its claim for implied contract (or quantum merit) at the close of trial –
with an agreement that each party was to bear is only costs and attorney fees – I find that this
claim arose out of the same factual circumstances as the breach of contract claim, and, as such,
overlapped in proof.
In addition, I disagree that Sun was only partially successful in this matter because did
not recover the full amount of damages initially sought. Although a district court may reduce a
lodestar calculation on the grounds that a prevailing party has achieved only partial success,
when a lawsuit involves multiple claims based on “a common core of facts or . . . related legal
6
theories,” it is inappropriate for a district court to evaluate the individual claims as though they
were discrete and severable for the purpose of awarding attorney fees. Robinson v. City of
Edmond, 160 F.3d 1275, 1283 (10th Cir. 1998) (assessing statutorily-mandated fees in a civil
rights case)(quoting Hensley v. Eckerhart, 461 U.S. 424, 435, 103 S.Ct. 1933, 76 L.Ed.2d 40
(1983)). “Litigants should be given the breathing room to raise alternative legal grounds without
fear that merely raising an alternative theory will threaten the attorney’s subsequent
compensation. Instead, a court should focus on the significance of the overall relief that the
prevailing party has won.” Id. Although “there is no precise rule or formula for assessing the
plaintiff’s degree of success, a reduced fee award is appropriate if the relief, however significant,
is limited in comparison to the scope of the litigation as a whole.” Flitton v. Primary Residential
Mortg., Inc., 614 F.3d 1173, 1178- 79(10th Cir. 2010)(quoting Hensley v. Eckerhart, supra, 461
U.S. at 440). A “district court must make a qualitative assessment to determine what less-thanperfect results are ‘excellent,’ justifying full recovery, or to what extent plaintiffs ‘limited
success’ should effect a reduction in the lodestar.” Jane L. v. Bangerter, 61 F.3d 1505, 1511
(10th Cir. 1995)(quoting Hensley v. Eckerhart, supra, 461 U.S. at 436).
As argued by Sun, although its possible damages were significantly reduced when its lost
profits and bonding capability was dismissed on summary judgment, it was still substantially
successful. Following dismissal of the lost profits claim, Sun sought approximately $6.5 million
in damages at trial, of which it was awarded over $4.1 million by the jury and was subsequently
awarded prejudgment interest of approximately $737,000 by the Court and, in addition,
successfully defended against the Joint Venture’s counterclaim seeking $4.6 million dollars in
damages. I agree that Sun’s results in this case were sufficiently successful to avoid a reduction
7
of the reasonable amount of fees requested.
The Joint Venture also asserts that Sun’s fees are unreasonable because the amount
requested includes fees for time spent in another lawsuit with its surety, F&D. Specifically, the
Joint Venture claims that approximately $32,000 of the fees sought by Sun were for time
incurred on a separate state court action between Sun and F&D, or for other “general
communication or negotiations with F&D.” In response, Sun maintain that the billings related to
the state court action were usually strategic discussions related to this action and, in many
instances, dealt with the damages claimed by F&D against Sun in F&D’s claim in this matter.
In its briefing, the Joint Venture provides three examples for billing entries in support of
its claim: 1) Time entry for 11/12/2009, $910 (“Meeting with RHM in preparation for meeting
with Vince and Patrick. Meeting with JCC regarding fee agreement. Review pretrial order in
preparation for tomorrow’s pretrial conference in Colorado Springs. Meeting with Vince and
Patrick”); 2) Time entry for December 8, 2008, $468 (“Prepare for meeting with Surety”); 3)
Time entry for March 6, 2008, $182 (“Telephone call with Vince Wegher, JCC and RHM
regarding standstill agreement; inspections, cooperation of surety”). At the hearing on this
matter, counsel for the Joint Venture argued that $32,000 in attorney time appeared to be related
to the state court case, and that the billing records of that time were not meticulously kept in
order to ascertain otherwise.
In response, counsel for Sun argued that the Joint Venture misinterpreted the references
in the billing statements to the state court case which, in reality, consisted of “strategy sessions”
with F&B’s counsel related to this case and that even if the time or billing records somehow
related to the state court matter, they were incurred as a “direct result” of the Joint Venture’s
8
conduct and, as such, were still awardable to Sun.
I conclude, however, that Sun’s argument is too attenuated and, as such, it did not meet
its burden of proving the reasonableness of the fees that the Joint Venture argues were related to
the state court action. See Westar Energy v. Lake, supra, 552 F.3d at 1249 (ruling that when the
contract provides that attorney fees must be “reasonable,” the burden remains with party seeking
the award). As such, I will reduce the amount of the reasonable attorney fees requested by Sun
in the amount of $32,000.
IV. CONCLUSION
I agree with Sun and its expert that the fees requested are reasonable given the
complexity of the case, the number of parties involved, the relationships between those parties,
the time expended, and the hourly rates charged. My review and consideration of the case
record, the billing records and oral arguments of counsel leads me to the conclusion that the
attorney fees sought by Sun in this case are reasonable and equitable. However, I also agree
with the Joint Venture that Sun failed to meet its burden to prove that $32,000 of those fees –
which allegedly appeared to be related to a different lawsuit in state court – were actually
incurred in this matter.
9
ACCORDINGLY, I AWARD Plaintiff, Sun Construction Company, Inc. (“Sun”), the
amount of $535,216.62 – pursuant to Paragraph 39 of the parties’ subcontract – for its
reasonable attorney fees incurred in this matter against Defendants, Torix General Contractors,
LLC. and St. Andrews/Alliance Joint Venture (the “Joint Venture”).
Dated: August
18 , 2011.
BY THE COURT:
s/Lewis T. Babcock
LEWIS T. BABCOCK, JUDGE
10
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?