WildEarth Guardians v. Lamar Utilities Board et al
Filing
196
Reivsed Order Granting Plaintiff Partial Summary Judgment, Denying Plaintiff's Motion to Take Judicial Notice, and Denying Defendants' Renewed Motion for Abstention and Motion for Summary Judgment by Judge David M. Ebel on 03/21/13. (jjhsl, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Civil Action No. 1:09-cv-02974-DME-BNB
WILDEARTH GUARDIANS, a New Mexico non-profit corporation,
Plaintiff,
v.
LAMAR UTILITIES BOARD doing business as LAMAR LIGHT AND POWER, and
ARKANSAS RIVER POWER AUTHORITY,
Defendants.
REVISED ORDER GRANTING PLAINTIFF PARTIAL SUMMARY JUDGMENT,
DENYING PLAINTIFF’S MOTION TO TAKE JUDICIAL NOTICE, AND DENYING
DEFENDANTS’ RENEWED MOTION FOR ABSTENTION AND MOTION FOR
SUMMARY JUDGMENT
This matter comes before the Court on three pending motions. After considering
those motions and relevant briefing, the Court GRANTS Plaintiff Wildearth Guardians’
(“Wildearth’s”) Motion for Partial Summary Judgment (Doc. 77), DENIES Wildearth’s
Motion to Take Judicial Notice of Documents in Support of Their Motion for Partial
Summary Judgment (Doc. 78), and DENIES Defendants Lamar Utilities Board, doing
business as Lamar Light and Power, and Arkansas River Power Authority’s Renewed
Request for Abstention and Motion for Summary Judgment (Doc. 76). In doing so, the
Court concludes that Wildearth’s request for injunctive relief is MOOT, but the
remainder of the case remains justiciable.
I. BACKGROUND
The Court set forth the facts of this case in its Order Granting in Part and
Denying in Part Defendants’ Motion to Dismiss; however, due to their importance to the
Court’s analysis, some facts are worth repeating here. Over the last decade, the
Environmental Protection Agency (“EPA”) has twice changed its position on how coalfired power plants, such as the one at issue here, are regulated under the Clean Air Act
(“CAA”). See generally Wildearth Guardians v. Pub. Serv. Co. of Colo., No. 11-1400,
2012 WL 3243458, at *1-*3 (10th Cir. Aug. 10, 2012) (to be reported at 690 F.3d 1174).
This has created problems for the industry as the governing regulatory requirements
have changed at the same time plants have actively been designed, built, and operated.
That difficulty notwithstanding, it is incumbent on operators, such as Defendants Lamar
Utilities Board and Arkansas River Power Authority (collectively “the Utilities”), to ensure
that their facilities comport with federal law. The Court will first lay out that law and then
briefly sketch the undisputed facts underlying this case.
A. Clean Air Act Section 112(g), the Delisting Rule and CAMR, and New Jersey v.
EPA
Section 112 of the CAA, 42 U.S.C. § 7412, 1 regulates the emission of hazardous
air pollutants into the atmosphere. In 1990, Congress amended § 112 to list more than
one hundred specific hazardous air pollutants, including mercury, that the EPA would be
required to regulate. New Jersey v. EPA, 517 F.3d 574, 578 (D.C. Cir. 2008). These
amendments also required the EPA to conduct a study to determine whether it was
1
This Order will refer to statutory provisions by the Clean Air Act section numbers (e.g.,
“CAA § 112”) rather than the U.S. Code codification (e.g., “42 U.S.C. § 7412”).
2
“appropriate and necessary” to regulate, under § 112, electric utility steam-generating
units (“EGUs”) as sources of hazardous air pollutants. CAA § 112(n)(1)(A). This study,
which the EPA completed in 1998, found “a plausible link” between human-generated
sources of mercury, such as coal- and oil-fired EGUs, and methylmercury in fish, which
poses a significant human health hazard. New Jersey, 517 F.3d at 579.
Based on this report, the EPA determined in 2000 that coal- and oil-fired EGUs
would be regulated under § 112(g), which requires that all new and reconstructed EGUs
meet the “maximum achievable control technology emission limitation” (“MACT”)
standard. CAA § 112(g)(2)(A). Congress had previously directed the EPA to establish
specific MACT standards applicable to various categories of hazardous waste emitters.
See id. § 112(d) These standards “reflect the maximum reduction in emissions which
can be achieved by application of the best available control technology.” Natural Res.
Def. Council v. EPA, 489 F.3d 1364, 1368 (D.C. Cir. 2007) (internal quotation marks,
alteration omitted). In the interim, before the EPA promulgated MACT standards for
EGUs, the relevant state or federal air pollution permitting authority was to determine
whether an EGU met the required MACT standard “on a case-by-case basis.” CAA
§ 112(g)(2). The EPA authorized the State of Colorado to make MACT determinations
for EGUs in this State, see Wildearth Guardians, 2012 WL 3243458, at *1 & n.1, and
the State does so through the Air Pollution Control Division (“APCD”) of Colorado’s
3
Department of Public Health and Environment. 2 In the normal course, MACT
determinations are made prior to the construction or reconstruction of an EGU.
The MACT requirement applies only to EGUs that are a “major source” of
hazardous air pollutants. CAA § 112(g). An EGU is a major source if it “emits or has
the potential to emit considering controls, in the aggregate, 10 tons per year or more of
any hazardous air pollutant or 25 tons per year or more of any combination of
hazardous air pollutants.” Id. § 112(a)(1).
In 2005, the EPA changed course in its approach to regulating EGUs and
determined that it would “de-list” EGUs from § 112 regulation and, instead, regulate
EGUs under § 111. New Jersey, 517 F.3d at 579-80. It did this by issuing two rules:
the Delisting Rule, which removed EGUs from § 112 coverage, and the Clean Air
Mercury Rule (“CAMR”), which, under § 111, set nationwide mercury emission limits
and established a voluntary cap-and-trade system for new and reconstructed EGUs.
New Jersey, 517 F.3d at 577. These rules went into effect in May of 2005. Id. at 580.
A number of states filed suit against the EPA in response, arguing that § 112(c)(9) of
the CAA sets forth specific procedures for delisting sources of hazardous air pollutants
and that the EPA did not follow those procedures when it delisted EGUs. Id. at 581.
2
The EPA adopted specific MACT emissions standards for EGUs, effective April 16,
2012. See 77 Fed. Reg. 9304 (Feb. 16, 2012); see also Wildearth Guardians, 2012 WL
3243458, at *2. No one has suggested that these new MACT standards are relevant
here. Instead, during the time at issue in this case, any required MACT determination
would have been made by Colorado’s APCD on a case-by-case basis.
4
The D.C. Circuit agreed and vacated both the Delisting Rule and the CAMR. 3 Id. at
583-84. Thus, as of the issuance of the mandate by the D.C. Circuit, on March 14,
2008, coal-fired EGUs that are major sources of hazardous air pollutants were once
again required to obtain a MACT determination in order to operate lawfully.
In January of 2009, the EPA Principal Deputy Assistant Administrator sent a
letter to all EPA Regional Administrators addressing the question of “coal- and oil-fired
EGUs that are major sources and that began actual construction or reconstruction
between the March 29, 2005 publication of [the Delisting Rule and CAMR] and the
March 14, 2008 vacatur of the rule[s].” (Doc. 76-12 at 2 (footnote omitted).) In the
EPA’s view, “these EGUs are legally obligated to come into compliance with the
requirements of Section 112(g).” (Id.) In the letter, the EPA acknowledged that
[s]ection 112(g) proceedings ordinarily are concluded before the
commencement of any construction activity, so it is reasonable for the
permitting authority – under these unique and compelling circumstances,
and within the bounds of its discretion under [CAA] Section 112(g) and
EPA’s section 112(g) regulations – to give consideration to the effect of
prior construction, undertaken in reasonable reliance on now-vacated
rules, in making the case-by-case determination of applicable MACT
requirements.
3
The CAA’s citizen suit provision gives federal courts like this one jurisdiction over suits
asserting that specific “major emitting facilities” violate the requirements of the CAA.
CAA § 304(a), (f). But Congress specifically reserved jurisdiction over challenges to the
EPA’s administrative rules and regulations implementing the statute as a whole to the
U.S. Court of Appeals for the D.C. Circuit. Id. § 307(b)(1). Congress’s designation of
the D.C. Circuit as the court with exclusive jurisdiction over challenges to rules such as
the Delisting Rule and other “standard-setting actions by the Administrator . . . ensure[s]
uniformity in decisions concerning issues of more than purely local or regional impact.”
Natural Res. Def. Council, Inc. v. EPA, 512 F.2d 1351, 1357 (D.C. Cir. 1975).
“Consequently, it is clear, and no party contests, that the D.C. Circuit’s vacatur of the
Delisting Rule applies unequivocally throughout all of the Federal Circuits.” Sierra Club,
Inc. v. Sandy Creek Energy Assocs., L.P., 627 F.3d 134, 138 n.6 (5th Cir. 2010), cert.
dismissed, 132 S. Ct. 872 (2011).
5
(Id. at 3 (footnote omitted).) But the letter further urged that, in the process of
evaluating the MACT status of these projects, “permitting authorities should not
consider any MACT options to have been foreclosed simply by the prior issuance of
permits, by the progress of administrative processes, nor by obligation of contract.” (Id.)
Instead, “in considering the effect of prior construction on the applicable MACT
requirements,” the EPA directed “permitting authorities [to] limit such consideration to
actual physical construction only,” and then only to actual construction occurring before
February 8, 2008, when the D.C. Circuit issued its decision vacating the Delisting Rule
and the CAMR. (Id.)
B. The Lamar Repowering Project
This case involves an EGU constructed during the time the application of § 112
to coal-fired EGUs was in a state of flux. In 2004, the Utilities resolved to upgrade an
existing power plant in Lamar, Colorado, and to change it from a natural gas-fired plant
into a coal-fired one, thus increasing its generating capacity. This plan, known as the
Lamar Repowering Project (the “Project”), involved substantial upgrades and changes
to the existing plant. On December 29, 2004, the Utilities applied to Colorado’s APCD
for a construction permit for the Project. The APCD issued that permit to the Utilities on
February 3, 2006. Because at that time the Delisting Rule and CAMR were in effect,
the Utilities did not have to get a MACT determination in order to obtain a permit or
begin construction, and they did not do so. Construction on the Project began in July
2006, and the Project began operating in some capacity in May 2009. The Project,
however, has not yet obtained an operating permit.
6
In July 2009, the EPA notified the Utilities that the D.C. Circuit, in February 2008,
had vacated the Delisting Rule and that the Project was thus required to comply with
CAA § 112(g). The EPA directed the Utilities to contact APCD “as expeditiously as
possible to obtain a new source [MACT] determination and a schedule for coming into
compliance with the requirements of Section 112(g).” (Doc. 76-4 at 15.) The EPA
further informed the Utilities that if they determined that they were not subject to the
requirements of § 112(g), then the Utilities “should maintain a record of [their]
determination and all supporting analyses. The applicability determination and
supporting analyses should contain accurate, detailed information that enables the EPA
and the permitting authority [APCD] to make their own finding regarding” the
applicability of § 112(g) to the Project. (Id. at 16.)
The Utilities contacted APCD, as directed, and sought, not a MACT
determination, but instead a modification of their construction permit to limit the Project’s
emissions in order to qualify the Project as a minor, rather than a major, source of
hazardous air pollutants and, thus, to obviate the need for a MACT determination. After
three years of administrative proceedings before the APCD, that agency, on July 25,
2012, issued the Utilities a modified permit identifying the Project as a “synthetic minor
source of Hazardous Air Pollutants . . . not subject to a MACT 112(g) determination.”
(Doc. 148-1 at 13.)4 A “synthetic minor source” is one that is legally restricted as to its
4
Colorado law requires a construction permit for the construction or substantial
alteration of any source of air pollutants. See Colo. Rev. Stat. § 25-7-114.2. Colorado’s
APCD has thus far issued the Utilities four construction permits for the Project, the initial
permit and three modified permits. These permits require that, within 180 days of
beginning operations, the Project must demonstrate that it is in compliance with the
7
rate of emission, but has “the physical and mechanical potential to emit above a
statutorily specified rate.” United States v. Marine Shale Processors, 81 F.3d 1329,
1352 (5th Cir. 1996); see also United States v. E. Ky. Power Coop., Inc., 498
F. Supp. 2d 995, 1005 n.8 (E. D. Ky. 2007) (noting that “[a] synthetic minor permit keeps
an otherwise regulated source from having to comply with . . . CAA requirements”).
C. Wildearth’s suit
Wildearth Guardians (“Wildearth”) initiated this litigation in December 2009, as a
citizens’ suit under the CAA, see CAA § 304(a), alleging that the Utilities were violating
§ 112(g) by constructing and operating the Project without receiving a MACT
determination. At issue here are the parties’ cross-motions for summary judgment.
The Utilities, in their summary judgment motion, request that this Court abstain,
under Burford v. Sun Oil Co., 319 U.S. 315 (1943), from resolving Wildearth’s CAA
claim because this case presents “difficult questions of state law bearing on policy
problems of substantial public import whose importance transcends the result in the
case,” or because federal consideration of this case “would be disruptive of state efforts
to establish a coherent policy with respect to a matter of substantial public concern,”
New Orleans Pub. Serv., Inc. v. Council of City of New Orleans, 491 U.S. 350, 361
terms of the permit, which among other things limit the Project’s emission of air
pollutants. In this case, the parties agree that the Project began operating in May 2009,
but the Project has had a variety of problems and apparently has not yet established
that it can operate in compliance with all of the conditions established in the
construction permit(s). Eventually, the Project must obtain final approval from the
APCD, after demonstrating compliance with the conditions set forth in the construction
permit(s), and it will then have to obtain a renewable operating permit, see Colo. Rev.
Stat. § 25-7-114.3. The terms of the construction permit “must be incorporated into the
operating permits.” (Doc. 149-2 at 11.)
8
(1989) (internal quotation marks, citations omitted). For the same reasons this Court
previously rejected this abstention argument, the Court again declines to abstain from
considering the merits of Wildearth’s CAA claim.
Further, the Court rejects the Utilities’ argument, made in a recent supplemental
brief, that this CAA action is an impermissible collateral attack on the third modified
permit the APCD issued the Utilities on July 25, 2012, a collateral attack over which this
Court has no jurisdiction. Although there is language in Wildearth’s supplemental briefs
challenging the propriety of the APCD’s decision to issue that most recent modified
permit, this Court does not review here the APCD’s decision to issue that permit.
II. WILDEARTH’S MOTION TO TAKE JUDICIAL NOTICE
As a preliminary matter, Wildearth requested, pursuant to Fed. R. Evid. 201, that
this Court take judicial notice of eighteen documents, Exhibits A through R, which
Wildearth submits in support of its Motion for Partial Summary Judgment. (Doc. 78.)
Wildearth has now withdrawn this request as to Exhibits B, F, L, M, and R. And the
Utilities do not object, and have stipulated, to the Court considering Exhibits A, C, D, E,
G, H, I, J, and O. Therefore Wildearth’s request that this Court take judicial notice is
now limited to Exhibits K, N, P, and Q. But, because the Court does not need to
consider these four documents in order to resolve the parties’ cross-motions for
summary judgment, the Court declines to take judicial notice of them.
III. THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT
Briefly stated here, Wildearth, in its Motion for Partial Summary Judgment, asks
this Court to conclude as a matter of law that the Utilities violated § 112(g) by
9
constructing and operating the Project without the required MACT determination. The
Utilities, on the other hand, in their motion for summary judgment, seek a ruling that,
because the Project is not a major source under the CAA, it was never required to
obtain a MACT determination and, thus, has not violated § 112(g).
A. Standard of Review
Summary judgment is appropriate when “there is no genuine dispute as to any
material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P.
56(a). In deciding whether summary judgment is appropriate, the Court construes all
facts and reasonable inferences drawn from the record in the light most favorable to the
nonmoving party. Atl. Richfield Co. v. Farm Credit Bank, 226 F.3d 1138, 1148 (10th Cir.
2000). Where, as here, the parties file cross-motions for summary judgment, the Court
“assume[s] that no evidence needs to be considered other than that filed by the parties,
but summary judgment is nevertheless inappropriate if disputes remain as to material
facts.” James Barlow Family Ltd. P’ship v. David M. Munson, Inc., 132 F.3d 1316, 1319
(10th Cir. 1997). Therefore, each party as the nonmovant is given “wide berth to prove
a factual controversy exists.” Jeffries v. Kansas, 147 F.3d 1220, 1228 (10th Cir. 1998)
(internal quotation marks omitted), abrogated on other grounds as recognized by
Zisumbo v. McLeanUSA Telecomm. Servs., Inc., 154 F. App’x 715, 728 n.8 (10th Cir.
2005) (unpublished).
10
B. The Project was a major source of hazardous air pollutants from the time the
Utilities first applied for a construction permit, in December 2004, until APCD
issued the third modified permit on July 25, 2012
As previously stated, only an EGU that is a “major source” of hazardous air
pollutants is required to obtain a MACT determination. CAA § 112(g). “The term ‘major
source’ means any stationary source or group of stationary sources located within a
contiguous area and under common control that emits or has the potential to emit
considering controls, in the aggregate, 10 tons per year or more of any hazardous air
pollutant or 25 tons per year or more of any combination of hazardous air pollutants.”
§ 112(a)(1). Under both federal and Colorado law, “potential to emit”
means the maximum capacity of a stationary source to emit a pollutant
under its physical and operational design. Any physical or operational
limitation on the capacity of the stationary source to emit a pollutant,
including air pollution control equipment and restrictions on hours of
operation or on the type or amount of material combusted, stored, or
processed, shall be treated as part of its design if the limitation or the
effect it would have on emissions is federally enforceable.
40 C.F.R. § 63.2; see also Colo. Rev. Stat. § 25-7-114(4) (including limitations that are
enforceable generally and adding that “[s]econdary emissions do not count in
determining the potential to emit of a stationary source”); 5 Colo. Code Regs. 10015:3A.I.B.37 (same, but including only limitations that are state and federally
enforceable).
The CAA deems hydrochloric acid to be a hazardous air pollutant. CAA
§ 112(b). When the Utilities first applied with the APCD for a construction permit for the
Project, the Utilities indicated that the Project would emit 20,591 pounds, or 10.3 tons,
of hydrochloric acid annually. The construction permit the APCD originally issued to the
11
Utilities, in February 2006, incorporated that amount. The first modified permit the
APCD issued the Utilities, eighteen months later, in August 2007, indicated instead that
the Project’s emissions “shall not exceed” 10.5 tons of hydrochloric acid per year.
(Docs. 76-2 at 18; 76-6 ¶ 8.) And, in October 2009, the APCD issued a second
modified permit which continued to mandate that the Project’s emissions “not exceed”
10.5 tons of hydrochloric acid annually. (Doc. 76-3 at 20.)
These permits, then, establish that the Project exceeded the threshold for being
a major source of hazardous air pollutants; that is, a source “that emits or has the
potential to emit considering controls, in the aggregate, 10 tons per year or more of any
hazardous air pollutant,” § 112(a)(1). It was not until July 25, 2012, when the APCD
issued the third modified construction permit, which mandated, instead, that the
Project’s emissions “shall not exceed” eight tons of hydrochloric acid annually, that the
Project no longer met the “major source” threshold. Therefore, from the time the
Utilities applied for and received the initial construction permit through July 25, 2012,
when the Utilities received the third modified permit, the Project was a “major source” of
hazardous air pollutants. See Sierra Club, 627 F.3d at 136.
The parties’ contrary arguments are unavailing. The Utilities contend that the
Project has never been a major source. In support of that assertion, they first argue
that, in issuing the third modified permit, which limited the Project’s annual emission of
hydrochloric acid to eight tons and identified the Project as a synthetic minor source of
hazardous air pollutants, the APCD further determined that the Project “never has been”
a major source. (Doc. 149 at 2, 6, 7, 12, 20.) But the Utilities fail to point to any such
12
APCD determination. Instead, in considering the Utilities’ request for a modification of
their construction permit, the APCD reviewed stack tests conducted while the Project
was operational. After reviewing those tests, the APCD concluded that the Project,
while operating, never actually emitted hydrochloric acid in levels exceeding ten tons
annually. But that does not mean that the Project never had the “potential to emit” more
than ten tons of hydrochloric acid annually. To the contrary, the APCD, in issuing the
third modified permit, identified the Project as a “synthetic minor source” (Doc. 148 at
13), defined as a source that is legally restricted as to its emissions, but which has “the
physical and mechanical potential to emit above a statutorily specified rate,” Marine
Shale Processors, 81 F.3d at 1352. That indicates that the Project has the physical and
mechanical capacity to emit a sufficient amount of hydrochloric acid annually to be
deemed a major source. And that is what the Utilities conveyed to the ACPD when they
first applied for a construction permit, stating that the Project would admit more than ten
tons of hydrochloric acid annually.
The Utilities counter that, when they initially applied for the construction permit,
they made an overly conservative estimate of the Project’s annual emissions of
hydrochloric acid and that, at that time, in light of the Delisting Rule, it did not matter
whether or not the Project was a major source of hazardous air pollutants. But the
Utilities’ assertion of the Project’s annual hydrochloric acid emissions in its application
for the initial construction permit still had meaning. The APCD issued the construction
permit “in reliance upon the accuracy and completeness of information supplied by the
applicant [Utilities] and . . . conditioned . . . upon conduct of the activity, or construction,
13
installation and operation of the source, in accordance with this information and with
representations made by the applicant [Utilities].” (Doc. 76-2 at 9.) And even though, at
the time the APCD issued the Project a construction permit, characterization as a major
source of hazardous air pollutants did not require the Project to obtain a MACT
determination, that characterization, too, was still meaningful. For example, according
to the EPA, “whether a facility is a major or area source of hazardous air pollutants may
affect the applicability of other CAA requirements – such as when or whether the facility
is required to obtain a Title V operating permit.” (Doc. 78-7 at 17.) See 42 U.S.C.
§§ 7661(2), 7661a(a). See generally MacClarence v. U.S. EPA, 596 F.3d 1123, 112526 (9th Cir. 2010) (discussing permitting regulations). Thus, prior to receiving the third
modified permit on July 25, 2012, the Project was a major source of hazardous air
pollutants because it had the potential, legally and physically, to emit more than ten tons
of hydrochloric acid annually.
Wildearth, for its part, argues that, once the Project initially qualified as a major
source of hazardous air pollutants, prior to construction, that source status can never be
undone. It is true that, ordinarily, the determination of whether an EGU is a major
source of hazardous air pollutants must be made prior to construction. And, generally,
once an EGU is deemed a major source of hazardous air pollutants at the time of the
“first compliance date,” the EPA, applying its “once in, always in” policy, precludes
changing the EGU’s status as a major source. (Doc. 78-7 at 21 (“EPA believes that
once a source is required to install controls or take other measures to comply with a
MACT standard, it should not be able to substitute different controls or measures that
14
happen to bring the source below major source levels.”), 24.) One of the reasons
underlying this EPA policy is that,
in many cases, application of MACT will reduce a major emitter’s
emissions to levels substantially below the major thresholds. Without a
once in, always in policy, these facilities could “backslide” from MACT
control levels by obtaining potential-to-emit limits, escaping applicability of
the MACT standard, and increasing emissions to the major-source
threshold (10/25 tons per year).
Thus, the maximum achievable
emissions reductions that Congress mandated for major sources would
not be achieved. A once in, always in policy ensures that MACT
emissions reductions are permanent, and that the health and
environmental protection provided by MACT standards is not undermined.
(Doc. 78-7 at 24.)5
The situation presented here, however, is not the ordinary case because there
was no MACT requirement until after the Utilities began the Project’s reconstruction.
The EPA, in the Administrator’s letter to regional administrators, recognized that these
circumstances were not the usual case:
EPA recognizes that the application of MACT standards to a project
already begun construction may present challenges. . . . Section 112(g)
proceedings ordinarily are concluded before commencement of any
construction activity, so it is reasonable for the permitting authority—under
these unique and compelling circumstances, and within the bounds of its
discretion under Clean Air Act Section 112(g) and EPA’s section 112(g)
regulations—to give consideration to the effect of prior construction,
5
The parties agree that the EPA’s internal “once in, always in” policy may be entitled to
some deference. See Christensen v. Harris Cnty., 529 U.S. 576, 587 (2000) (noting
agency interpretations contained in opinion letters, policy statements and enforcement
guidelines, which do not have the force of law, “are entitled to respect,” to the extent
they are persuasive, under Skidmore v. Swift & Co., 323 U.S. 134, 140 (1944), but are
not entitled to Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467
U.S. 837 (1984), deference); Reno v. Koray, 515 U.S. 50, 61 (1995) (affording “some
deference” to internal agency guideline, even though the guideline had not been
subjected to the “rigors” of the Administrative Procedure Act, including public noticeand-comment requirements, because the guideline represented a permissible
construction of the relevant statute).
15
undertaken in reasonable reliance on now-vacated rules, in making the
case-by-case determination of applicable MACT requirements.
(Doc. 76-12 at 3 (emphasis added; footnote omitted).) 6 And the EPA, in later directing
the Project to comply with § 112(g), gave the Utilities the option of determining instead
that § 112(g) did not apply to the Project. The EPA further directed the Utilities, if they
determined § 112(g) did not apply to the Project, to provide their analysis leading to that
determination to the EPA and permitting authority, support that analysis with “accurate,
detailed information,” and let the APCD determine whether § 112(g) applied to the
Project.
Thus, regardless of the measure of deference this Court should afford the EPA’s
application of its internal “first in, always in” policy in the ordinary case, the EPA itself
decided not to apply that policy under the “unique and compelling circumstances”
presented here. 7 The EPA’s approach is consistent with the purposes of the “once in,
always in” policy, which include preventing a major source from using MACT to reduce
its emissions below “major source” levels in order to then avoid having to comply with
MACT limits on emissions. That circumstance is not presented here because the
Project has not used MACT to reduce its emission limits below the “major source”
threshold.
6
The parties agree that the Court should also give the EPA’s January 7, 2009 letter
some deference.
7
The parties dispute whether the “first in, always in” policy even applies where a MACT
determination is made on a case-by-case basis. The Court need not resolve that
dispute because, assuming that policy applies generally where the MACT determination
is made on a case-by-case basis, the policy does not control the issues presented here.
16
For these reasons, then, the Court concludes that the Project was a major source
of hazardous air pollutants, from the time the Utilities applied for and received a
construction permit, until the APCD issued the Utilities the third modified permit, on July
25, 2012.
C. Violation of § 112(g)
Pursuant to the CAA, “no person may construct or reconstruct any major sources
of hazardous air pollutants, unless the Administrator (or the State) determines that the
maximum achievable control technology emission limitation under this section for new
sources will be met.” CAA § 112(g)(2)(B). Because the Project never had a MACT
determination and was a major new source of hazardous air pollutants, from the time
the Utilities initially applied for a construction permit for the Project (in 2004) until the
APCD modified the Project’s permit (on July 25, 2012), the Court must next decide for
how much of this time, if any, the Utilities were violating § 112(g).
At the time the APCD issued the Utilities the initial construction permit for the
Project, the Delisting Rule and the CAMR were in effect. Thus, the Project, even
though a major source of hazardous air pollutants, was not required to obtain a MACT
determination. That was the case until March 14, 2008, when the D.C. Circuit issued its
mandate in New Jersey v. EPA, vacating the Delisting Rule and the CAMR and
reinstating the requirement for a MACT determination. See Wildearth Guardians, 2012
WL 3243458, at *9. Therefore, the Project was in violation of § 112(g) beginning March
14, 2008, until the APCD modified the Project’s permit on July 25, 2012. See Sierra
Club, 627 F.3d at 136, 140-42.
17
The Utilities’ arguments to the contrary are unavailing. The Utilities first reassert
that they never violated § 112(g) because that provision sets forth only preconstruction
requirements that do not apply to the Utilities because construction was already
underway on the Project when the D.C. Circuit vacated the Delisting Rule. This Court
previously rejected that argument in the Order partially denying the Utilities’ motion to
dismiss:
While the plain text of the statute requires an operator to obtain a MACT
determination before “construct[ing] or reconstruct[ing]” a major source,
nothing in the text indicates that the operator is relieved of the
responsibility of complying with the statute after construction begins.
“[C]onstruct or reconstruct” are active verbs that have force after the
permit is issued and after construction or reconstruction has begun.
(Doc. 75 at 12.) The Fifth Circuit has reached the same conclusion, that § 112(g)
applies to current and ongoing construction, not just the commencement of
construction. See Sierra Club, 627 F.3d at 141 (“[Section] 112(g)(2)(B) prohibits the act
of construction itself and not the commencement thereof.”). And that is the position of
the EPA as well, in the Administrator’s January 7, 2009 letter to the agency’s regional
administrators, indicating that EGUs that began construction while the Delisting Rule
was in effect are, after the D.C. Circuit vacated that Rule, “legally obligated to come into
compliance with the requirements of Section 112(g).” (Doc. 76-12 at 2.) Therefore, the
Utilities began violating § 112(g) as of March 14, 2008, when the D.C. Circuit issued its
mandate in New Jersey.
The Utilities next argue that they should be given a reasonable time after the
D.C. Circuit vacated the Delisting Rule to come into compliance with § 112(g)’s
requirement that a major source obtain a MACT determination. Once the D.C. Circuit
18
issued its opinion in New Jersey, however, the Utilities were put on notice that § 112(g)
applied to EGUs. From that point forward, the continued reconstruction and operation
of the Project without receiving a MACT determination violated § 112(g). See Sierra
Club, 627 F.3d at 141-42. But the Court notes that, in determining the appropriate
remedies to be imposed for the violation of § 112(g), the Court must consider, among
other factors, “the violator’s full compliance history and good faith efforts to comply.” 42
U.S.C. § 7413(e)(1).
For the foregoing reasons, then, the Court concludes that the Project violated
§ 112(g)’s MACT requirement from the date the D.C. Circuit issued its mandate
vacating the Delisting Rule until the APCD issued the Utilities the third modified
construction permit, on July 25, 2012.
IV. REMEDIES/MOOTNESS
Wildearth seeks several remedies available under the CAA for the violation of
§ 112(g). See CAA § 304(g)(1), (d). Wildearth seeks an order enjoining the Utilities
from constructing, reconstructing or operating the Project except in accordance with
CAA § 112(g). Wildearth’s request for such injunctive relief is now moot, however,
because the Utilities are now no longer violating § 112(g), after the APCD issued the
Utilities the third modified permit for the Project, making the Project a synthetic minor,
rather than a major, source of hazardous air pollutants and obviating the need for a
MACT determination. See Wildearth Guardians, 2012 WL 3243458, at *12-*13.
Wildearth also seeks the imposition of civil penalties. In Wildearth Guardians v.
Public Service Co., supra, (“Public Service”), the Tenth Circuit concluded, under
19
circumstances with some similarities to those presented here, that Wildearth’s claims for
a declaratory judgment, civil penalties and attorneys’ fees, as well as an injunction, were
moot after the EGU at issue in that case came into compliance with the CAA. 2012 WL
3243458, at *1. After receiving supplemental briefing from the parties on this
jurisdictional question, id. at *4-*5, the Court concludes that the circumstances
presented here are sufficiently distinguishable from those addressed by the Tenth
Circuit in “Public Service” and that Wildearth’s claims for a declaratory judgment, civil
penalties and attorneys’ fees, therefore, remain justiciable.
In the Tenth Circuit “Pubic Service” case, Public Service constructed a major
source EGU. Id. at *3. Before doing so, Public Service reached an agreement with
several environmental and community groups to install “‘state of the art pollution
controls,’ including mercury controls equal to or exceeding the MACT standards
proposed by the EPA prior to the Delisting Rule.” Id. (citation, internal quotation marks
omitted). Public Service obtained a construction permit which incorporated the terms of
the agreement into its requirements. Id. Public Service also applied with APCD for a
MACT determination, which was at that time required. Id. But the EPA adopted the
Delisting Rule while Public Service’s application for a MACT determination was
pending, and so Public Service never obtained such a determination. Id. When the
D.C. Circuit later vacated the Delisting Rule and reinstated the requirement for a MACT
determination, Public Service worked with the APCD to obtain such a determination but
continued construction while it sought the MACT determination, as the APCD instructed
it to do. Id. at *3-*4, *10. At the same time, Wildearth Guardians sued Public Service,
20
alleging it was violating CAA § 112 by constructing a major course EGU without a
MACT determination. Id. at *1, *4.
The Tenth Circuit acknowledged that, “[i]n most Clean Air Act citizen suits,
mootness is difficult to establish because the plaintiff’s interest in deterring the
defendant from future violations is sufficient to sustain a constitutional case or
controversy between the parties.” Id. at *1; see also id. at *9. And the defendant’s
burden to show mootness resulting from the defendant’s own voluntary cessation of the
offending conduct is “formidable.” Id. at *6 (quoting Friends of the Earth, Inc. v. Laidlaw
Envtl. Servs., Inc., 528 U.S 167, 190 (2000)). Nevertheless, the court concluded that,
under the “unusual” and “rare” circumstances presented in “Public Service,” once Public
Service obtained the necessary MACT determination and came into compliance with
the CAA, Wildearth’s cause of action, including its request for civil penalties and
attorneys’ fees, became moot because there was no longer any remedy that the court
could order that would redress Wildearth’s originally asserted injury, that Public Service
was constructing a major source EGU without a MACT determination. Id. at *1, *9.
“Public Service” required the defendant to establish mootness by showing that “it
is ‘absolutely clear’ that its ‘conduct could not reasonably be expected to recur,’ thereby
negating the potential deterrent value of the suit.” Id. at *9 (quoting Laidlaw, 528 U.S. at
189.) The Tenth Circuit concluded Public Service was able to meet that standard,
under the “unusual” circumstances presented in that case id. at *1, for three reasons:
1) Public Service’s “non-compliance with the [CAA] was precipitated by events entirely
outside its control.” Id. at *9. 2) Public Service “made all reasonable efforts to comply
21
with the Act, and even went above and beyond what was required in attempting to
accommodate environmental interests.” Id. at *9-*10. 3) “[T]he particular violation
alleged, constructing a major source without a case-by-case MACT determination, “is
unlikely to be repeated” because the EPA has now issued specific MACT standards
applicable to EGUs, so “if [Public Service] constructs a new coal plant in the future, it
will no longer be subject to the case-by-case MACT determination provisions that
Wildearth alleges were violated.” Id. at *10.
The Utilities here cannot match the strong showing that Public Service made in
the Tenth Circuit case and cannot meet the “formidable” burden of showing that it is
“absolutely clear that its conduct” challenged here “could not reasonably be expected to
recur.” Id. at *9. Although the Utilities were subject to the same changing regulatory
environment which was beyond the Utilities’ control, the Utilities’ non-compliance with
the CAA here was also due in part to its own initial assertion to the permitting authority
that it was a major source emitter of hydrochloric acid, an assertion the Utilities now
disclaim as erroneous. Only after the requirement of major sources to obtain a case-bycase MACT determination did the Utilities attempt to change their initial estimation of
the Project’s potential to emit hydrochloric acid. The Utilities then continued
constructing the Project, even though the Utilities had not gotten a MACT determination
or a revised construction permit making the project a minor, rather than a major, source
of hazardous air pollutants. Further, while the Project is now characterized as a minor
source of air pollutants based upon the emission limits placed on the Project by the
newly revised permit, it appears that the Project is physically capable of emitting
22
hydrochloric acid at a major emitter level. So, the possibility remains that the Project
could violate the terms of its construction permit and emit hydrochloric acid at major
source levels without ever obtaining a MACT determination. Further, although if the
Utilities chose to construct another EGU in the future, that EGU would not require a
case-by-case MACT determination since the EPA has now promulgated specific MACT
standards that apply to EGUs, the Utilities will still have to represent to the permitting
authority that it is either a major or a minor source of hazardous air pollutants. Under
these circumstances, the Court cannot conclude that it is “absolutely clear” that the
Utilities conduct being challenged here “could not reasonably be expected to recur.” Id.
at *9. Thus, the Utilities cannot negate the potential deterrent value here of Wildearth’s
claims for the imposition of civil penalties. See id. Therefore, Wildearth’s claim for the
imposition of civil penalties is not moot under the circumstances of this case. In
considering that request for civil penalties, the Court must still consider, among other
factors, the Utilities’ compliance history and good faith efforts to comply with CAA
§ 112(g). 8
8
“A penalty may be assessed for each day of violation.” 42 U.S.C. § 7413(e)(2). In
calculating imposition of civil penalties under 42 U.S.C. § 7604(a), 42 U.S.C.
§ 7413(e)(1) requires the court to consider
(in addition to such other factors as justice may require) the size of the
business, the economic impact of the penalty on the business, the
violator’s full compliance history and good faith efforts to comply, the
duration of the violation established by any credible evidence (including
evidence other than the applicable test method), payment by the violator
of penalties previously assessed for the same violation, the economic
benefit of noncompliance, and the seriousness of the violation.
23
Wildearth did not seek summary judgment on the question of these penalties,
acknowledging that a trial to the Court would, instead, be necessary. The Court
therefore directs the parties to contact the Court, within seven days of the date this
Order is issued, to set a date for trial to the Court on the question of whether, and in
what amount, imposition of civil penalties against the Utilities is warranted. The parties
should also set a date for a Final Trial Preparation Conference to precede trial. The
parties are ordered simultaneously to file trial briefs, of no more than twenty pages in
length, on the issue of the possible imposition of civil penalties, no later than thirty days
before the scheduled trial date. The parties may also each file a response brief, no
longer than ten pages in length, due no later than fifteen days after the filing of any trial
brief.
V. CONCLUSION
For the foregoing reasons, therefore, it is ORDERED as follows:
1) Wildearth’s motion to take judicial notice (Doc. 78) is DENIED.
2) Wildearth’s motion for partial summary judgment (Doc.77) is GRANTED.
Id. § 7413(e)(1); see also Pound v. Airosol Co., 498 F.3d 1089, 1094-1100 (10th Cir.
2007) (applying these factors). Weighing these factors and determining the amount of
penalties, if any, to impose, is left to the district court’s discretion. See Pound, 498 F.3d
at 1094. It appears that Wildearth is not entitled to a jury trial on imposition of civil
penalties. See Tull v. United States, 481 U.S. 412, 427 (1987) (holding that jury should
decide liability under the Clean Water Act, but court, rather than jury, should determine
amount of civil penalties, if any); see also Pound, 498 F.3d at 1094 n.2 (noting that
“[t]he penalty provisions of the CAA and the Clean Water Act (CWA) are virtually
identical; thus, CWA cases are instructive in analyzing issues arising from the CAA”);
United States v. Corning Glass Works, No. 3:CV-90-0207, 1991 WL 329759, at *1 (M.D.
Pa. Sept. 16, 1991) (unreported) (applying Tull to CAA action). Even if Wildearth were
entitled to a jury trial on the issue of civil penalties, however, Wildearth never requested
a jury. And the Final Pretrial Order notes that trial will be to the Court.
24
3) The Utilities’ motion for summary judgment (Doc.76) is DENIED.
4) Wildearth’s request for an injunction directing the Utilities to comply with CAA
§ 112(g) is DENIED as MOOT.
5) The parties are directed to contact the Court, within seven days after the date this
Order is issued, to schedule a trial to the Court on the possible imposition of civil
penalties, and to abide by the trial briefing schedule set forth above.
Dated this
21st
day of
March
, 2013.
BY THE COURT:
s/ David M. Ebel
U. S. CIRCUIT COURT JUDGE