Superior Steel Connectors Corporation v. RK Specialties Inc. et al
Filing
27
ORDER Staying Proceedings Pending Arbitraion. Granting in part and denying in part 4 Motion to Dismiss, or Alternatively, to Stay Proceedings. Denying 12 Cross Motion to Stay Arbitration and Demand for Jury Trial. Case shall be administratively closed. Defendants' request for attorneys' fees and costs incurred in connection with the Motion to Dismiss is denied, by Judge Christine M. Arguello on 10/31/11.(gmssl, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Judge Christine M. Arguello
Civil Action No. 11-cv-01488-CMA-MEH
UNITED STATES OF AMERICA, for the use of
SUPERIOR STEEL CONNECTORS CORPORATION,
Plaintiff,
v.
RK SPECIALTIES INC.;
RK MECHANICAL INC.;
GREAT AMERICAN INSURANCE COMPANY,
Defendants.
ORDER STAYING PROCEEDINGS PENDING ARBITRATION
This matter is before the Court on the Motion to Dismiss Pursuant to Fed. R. Civ.
P. 12(b)(1) and (6), or Alternatively, to Stay Proceedings (Doc. # 4) of Defendants RK
Specialities, Inc. (RKS) and RK Mechanical, Inc. (RK Mechanical), and on Plaintiff’s
Cross Motion to Stay Arbitration and Demand for Jury Trial Pursuant to 9 U.S.C. § 4
(Doc. # 12). For the following reasons, Defendants’ Motion is granted in part to the
extent it seeks to stay the proceedings, denied in part to the extent it seeks to dismiss
any or all claims for lack of subject matter jurisdiction, and stayed in part to the extent
it seeks to dismiss on the merits for failure to state a claim. Plaintiff’s Cross Motion is
denied.
I. BACKGROUND
Plaintiff Superior Steel Connectors Corporation (SSC) is a Colorado corporation
in the steel construction business. (Doc. # 1 at 1–2.) Defendants RKS and RK
Mechanical are Colorado corporations. (Id. at 2.) RKS is a corporate subsidiary of RK
Mechanical. (Id. at 5.) Defendant Great American Insurance Company (GAIC) is an
Ohio corporation. (Id. at 2.)
A.
THE UNDERLYING SUBCONTRACT
This action arises from the parties’ dispute concerning a subcontract for a facility
in Boulder undertaken by the National Institute for Standards and Technology (NIST).
(Id. at 1.) NIST hired a prime contractor for the facility that later subcontracted certain
aspects to RK Mechanical. (Doc. # 4 at 3.) GAIC issued a payment bond in connection
with this subcontract between the prime contractor and RK Mechanical. (Doc. # 5 at 1.)
In turn, RK Mechanical hired RKS to fabricate and supply steel, and RKS entered into
a subcontract (the Subcontract) with SSC for SSC to perform the steel construction for
the facility. (Doc. # 1 at 3.)
SSC began the contracted work on November 22, 2010 (Doc. # 1 at 4); however,
RKS terminated the Subcontract by notice on February 21, 2011. (Doc. # 1 at 5.) SSC
and RKS dispute whether SSC complied with specifications of the Subcontract. (Doc.
# 4 at 3.) RKS withheld payment on the belief that SSC was in breach of the
Subcontract. (Id.)
2
B.
ARBITRATION PROCEEDINGS
The Subcontract, dated May 27, 2010, contains an arbitration provision that
states, in pertinent part:
14.2 AGREEMENT TO ARBITRATE. Any controversy or claim arising
out of or related to the Subcontract, or the breach thereof, shall, at the
election of RKS, be settled by either litigation or binding arbitration in
accordance with the Construction Industry Arbitration Rules of the
American Arbitration Association. RKS will make such election within
10 business days of being notified of Subcontractor’s intent to file a
formal action against RKS. In the event RKS initiates a claim, the choice
of forum (arbitration or litigation) shall be evident by the initiation of formal
proceedings in that forum by RKS.
If arbitration is elected, any award rendered by the arbitrator or arbitrators
shall be final, and judgment may be rendered upon it in accordance with
applicable law in any court having jurisdiction thereof.
(Doc. # 4, Ex. A at 12.)
On March 2, 2011, SSC gave notice to RKS of its intent to “commence
proceedings.” (Docs. ## 9, Ex. B at 4; 11 at 7.) SSC and RKS dispute whether this
amounted to notice of “Subcontractor’s intent to file a formal action against RKS” as
required by the arbitration provision. (Doc. # 9, Ex. B at 4.) The parties also dispute
whether this notice triggered the ten-day period for RKS to elect between arbitration and
litigation. (Doc. # 11 at 7.)
On April 14, 2011, RKS gave notice to SSC of its demand for arbitration. (Id.
at 8.) On April 26, 2011, RKS filed its demand for arbitration. (Doc. # 4 at 4.)
Subsequently, the parties initiated arbitration proceedings through the American
Arbitration Association (AAA). (Id.)
3
C.
PROCEDURAL HISTORY
On June 7, 2011, SSC initiated this action by filing a Complaint alleging the
following claims for relief: (1) breach of contract, (2) unjust enrichment, (3) negligent
misrepresentation, (4) breach of the covenant of good faith and fair dealing, and
(5) payment owed under the Miller Act, 40 U.S.C. § 3133. (Doc. # 1.)
On June 24, 2011, Defendants RK Mechanical and RKS filed a Motion to
Dismiss pursuant to Fed. R. Civ. P. 12(b)(1) and 12(b)(6), or alternatively, to stay
proceedings. (Doc. # 4.) In seeking dismissal, they argue that the arbitration clause
divested this Court of jurisdiction under Fed. R. Civ. P. 12(b)(1). (Id. at 6–9.) They also
seek dismissal under Rule 12(b)(6), arguing that SSC fails to state claims for unjust
enrichment, negligent misrepresentation, and breach of the covenant of good faith
and fair dealing. (Id. 10–13.) GAIC joined this Motion on June 29, 2011. (Doc. # 5.)
On July 25, 2011, SSC responded to the Motion to Dismiss, arguing that jurisdiction was proper because RKS and RK Mechanical waived their right to arbitrate the
dispute by failing to timely elect arbitration according to the Subcontract’s arbitration
provision. (Doc. # 11.) On August 9, 2011, RKS and RK Mechanical replied (Doc.
# 14), and on August 10, 2011, GAIC joined the Reply. (Doc. # 15.)
On July 25, 2011, SSC filed a Cross Motion to stay the arbitration and demand
a jury trial under 9 U.S.C. § 4. (Doc. # 12.) SSC again asserts that Defendants waived
their right to arbitrate or that a jury should resolve the issue if disputed issues of material
fact remain. (Id. at 8–9.) On August 15, 2011, Defendants responded. (Doc. # 16.)
4
Prior to filing its Response to the Motion to Dismiss (Doc. # 11) and its own
Cross Motion (Doc. # 12), SSC raised this same waiver issue when it moved to dismiss
the related arbitration proceedings. (Doc. # 9, Ex. B.) On June 24, 2011, the arbitrator
denied SSC’s motion to dismiss. (Id.) He found that SSC’s notice was insufficient and
that RKS’s arbitration demand initiated its own separate claim and therefore was not
an untimely election in response to SSC’s notice. (Id. at 8-9.) On July 18, 2011, the
arbitrator denied SSC’s motion to reconsider. (Doc. # 9, Ex. C.)
II. ANALYSIS
A.
THE COURT’S JURISDICTION TO CONSIDER THE CLAIMS
Defendants argue that initiation of arbitration proceedings under the arbitration
provision in the Subcontract divests this Court of subject matter jurisdiction and that
several of SSC’s claims should be dismissed under Fed. R. Civ. P. 12(b)(6). (Doc. # 4
at 6–9.) In the alternative, Defendants seek a stay of the proceedings pending
arbitration. (Id.) SSC asserts that jurisdiction is proper because Defendants waived
their right to arbitration by not timely electing it. (Doc. # 11 at 13–14.)1
Dismissal pursuant to Fed. R. Civ. P. 12(b)(1) is appropriate if the Court lacks
subject matter jurisdiction over claims for relief asserted in the complaint. “The burden
of establishing subject matter jurisdiction is on the party asserting jurisdiction.” Port City
Props. v. Union Pac. R.R. Co., 518 F.3d 1186, 1189 (10th Cir. 2008). Rule 12(b)(1)
1
Because, as discussed below, a stay of the action on the merits pending arbitration is
appropriate, the Court need not set out the standard of review or the relevant facts for the Rule
12(b)(6) motion.
5
challenges are generally presented in one of two forms: “[t]he moving party may
(1) facially attack the complaint’s allegations as to the existence of subject matter
jurisdiction, or (2) go beyond allegations contained in the complaint by presenting
evidence to challenge the factual basis upon which subject matter jurisdiction rests.”
Merrill Lynch Bus. Fin. Servs., Inc. v. Nudell, 363 F.3d 1072, 1074 (10th Cir. 2004)
(quoting Maestas v. Lujan, 351 F.3d 1001, 1013 (10th Cir. 2003)); see Ruiz v.
McDonnell, 299 F.3d 1173, 1180 (10th Cir. 2002).
“The mere existence of an arbitration agreement . . . does not divest a federal
court of subject matter jurisdiction.” Will v. Parsons Evergreene, LLC, No. 08-cv-00898,
2008 WL 5330681, at *1 (D. Colo. Dec. 19, 2008) (unpublished). Section 3 of the
Federal Arbitration Act (FAA) provides that the Court, “upon being satisfied that the
issue involved in such suit or proceeding is referable to arbitration under such an
agreement, shall on application of one of the parties stay the trial of the action until such
arbitration has been had in accordance with the terms of the agreement . . . .” 9 U.S.C.
§ 3.
The Tenth Circuit has long held that actions must be stayed, rather than
dismissed, pending arbitration. See Adair Bus Sales, Inc. v. Blue Bird Corp., 25 F.3d
953, 955 (10th Cir. 1994) (district court erred in dismissing action when “[t]he proper
course . . . would have been for the district court to grant Defendant’s motion and stay
the action pending arbitration”); Meyer v. Dans un Jardin, S.A., 816 F.2d 533, 538–39
(10th Cir. 1987) (“Section 3 of the Federal Arbitration Act contemplates continuing
6
supervision by the district court to ensure that arbitration proceedings are conducted
within a reasonable period of time, thus preventing any impairment of the plaintiffs’
rights to seek relief.”). The Court is bound by this precedent.
Therefore, the only remaining inquiry for the Court under 9 U.S.C. § 3 is the
arbitrability of SSC’s claims, i.e., whether an enforceable arbitration agreement exists
and whether the claims in this action are subject to that agreement. If the claims are
arbitrable, then a stay of the proceedings will be the appropriate disposition.
B.
ARBITRABILITY OF SSC’S CLAIMS
SSC argues that the claims pending in this Court are not arbitrable due to RKS’s
alleged waiver. (Doc. # 11 at 13–14.) SSC additionally seeks a stay of the arbitration
proceedings and a jury trial to resolve the issue of arbitrability. (Doc. # 12.) In
response, RKS and RK Mechanical point to the arbitration clause in the parties’
Subcontract and argue that SSC does not dispute that the agreement to arbitrate exists
but, rather, disputes whether RKS waived its existing right to arbitrate. (Docs. ## 14 at
4–5; 16 at 2–5.)
“[T]he question of arbitrability – whether a [contract] creates a duty for the parties
to arbitrate the particular grievance – is undeniably an issue for judicial determination.”
Riley Mfg. Co., Inc. v. Anchor Glass Container Corp., 157 F.3d 775, 779 (10th Cir.
1998) (quoting AT & T Techs., Inc. v. Commc’ns Workers, 475 U.S. 643, 649 (1986)).
The Court conducts only a “limited inquiry” into two substantive arbitrability issues:
(1) whether a valid agreement to arbitrate exists and (2) “whether the specific dispute
7
falls within the scope of that agreement.” Pikes Peak Nephrology Assocs., P.C. v. Total
Renal Care, No. 09-cv-00928, 2010 WL 1348326, at *5 (D. Colo. Mar. 30, 2010)
(unpublished) (quoting Houlihan v. Offerman & Co., 31 F.3d 692, 694–95 (8th Cir.
1994)).
Parties shall not be ordered to arbitrate until this Court is satisfied that “the
making of the agreement for arbitration . . . is not in issue.” 9 U.S.C. § 4. “The
existence of an agreement to arbitrate is a threshold matter which must be established
before the FAA can be invoked.” Avedon Eng’g, Inc. v. Seatex, 126 F.3d 1279, 1287
(10th Cir. 1997). To resolve this threshold matter, courts require the party seeking
arbitration, here Defendants RKS and RK Mechanical, to bear the initial burden of
presenting sufficient evidence to demonstrate the existence of an enforceable
arbitration agreement. See Goodwin v. H.M. Brown & Assocs., Inc., No. 10-cv-01205,
2011 WL 820025, at *3 (D. Colo. Mar. 2, 2011) (unpublished) (citing Stein v. Burt-Kuni
One, LLC, 396 F. Supp. 2d 1211, 1213 (D. Colo. 2005)). If this burden is met, the
burden shifts to SSC to show that there is a “genuine issue of material fact as to the
making of the agreement, using evidence comparable to that identified in Fed. R. Civ. P.
56.” Id. (quoting Stein, 396 F. Supp. 2d at 1213). A trial is required where a genuine
issue of material fact exists. Id.; see 9 U.S.C. § 4.
In this case, the parties do not dispute that an enforceable arbitration agreement
exists. Although SSC frames the “essential question” as whether “the parties mutually
agreed to submit the instant controversy to arbitration,” its arguments do not hinge
8
on whether the parties mutually intended to enter into an enforceable agreement to
arbitrate. (Doc. # 12 at 6.) Rather, SSC’s arguments center on whether arbitration
is allowed based on RKS’s alleged noncompliance with the existing agreement to
arbitrate. (Id. at 7–8.) In fact, SSC concedes that “RKS did have the contractual right at
one point in this matter to have this dispute arbitrated.” (Id. at 8.)
As to the second “limited inquiry” performed by the Court, the parties do not
dispute whether SSC’s claims fall within the agreement’s scope. It appears to the Court
that all five of SSC’s claims fall within the scope of the broad arbitration clause and are
therefore subject to arbitration. (Doc. # 4, Ex. A at 12) (allowing arbitration for “[a]ny
controversy or claim arising out of or related to the Subcontract, or the breach thereof”).
None of the parties have raised arguments to the contrary.
Thus, no other substantive arbitrability issues remain. The only disputed issue –
whether RKS and RK Mechanical waived their contractual right to arbitrate – is
a procedural one. “[I]n the absence of an agreement to the contrary . . . issues of
procedural arbitrability, i.e., whether prerequisites such as time limits, notice, laches,
estoppel, and other conditions precedent to an obligation to arbitrate have been met,
are for the arbitrators to decide.” Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79,
85 (2002) (quoting the Revised Uniform Arbitration Act of 2000 (RUAA) § 6(c) cmt. 2)
(emphasis in original). Therefore, the issue of waiver by failing to timely elect arbitration
is not a substantive arbitrability issue for the Court but a procedural one for the
arbitrator. Id. The Court notes that, prior to SSC’s filing of its Response to the Motion
9
to Dismiss (Doc. # 11) and Cross Motion (Doc. # 12), the arbitrator in the pending
proceedings had ruled, and had denied a motion to reconsider the ruling, that RKS’s
choice of arbitration was valid. (Doc. # 9, Ex. B; Ex. C.) The parties do not dispute
that the arbitrator had authority to decide the waiver issue.
Accordingly, RKS and RK Mechanical have met their initial burden to present
sufficient evidence demonstrating the existence of an enforceable arbitration
agreement. SSC has not demonstrated that a genuine issue of material fact exists as to
the making of that agreement or as to the scope of the agreement, and SSC is therefore
not entitled to a jury trial on the issue. Because the Court is satisfied that the claims
here are arbitrable, the Court concludes that a stay of this action pending the arbitration
is warranted under 9 U.S.C. § 3.2
2
Because the Court finds that a stay of this action is appropriate, Defendants’ Motion to
Dismiss pursuant to Fed. R. Civ. P. 12(b)(6) for SSC’s failure to state specific claims (Doc. # 4
at 10–13) will also be stayed pending the arbitration proceedings.
10
C.
DEFENDANTS’ REQUESTS FOR ATTORNEYS’ FEES
In their Motion to Dismiss (Doc. # 4 at 14–15) and their Response to SSC’s
Cross Motion (Doc. # 16 at 7–8), Defendants3 seek an award of costs and attorneys’
fees pursuant to 28 U.S.C. § 1927 and Fed. R. Civ. P. 11(b).4
Under 28 U.S.C. § 1927, “[a]ny attorney or other person . . . who so multiplies the
proceedings in any case unreasonably and vexatiously may be required by the court to
satisfy personally the excess costs, expenses, and attorneys’ fees reasonably incurred
because of such conduct.” “Sanctions are appropriate [under § 1927] when an attorney
acts recklessly or with indifference to the law; is cavalier or bent on misleading the
court; intentionally acts without a plausible basis; or when the entire course of the
proceedings is unwarranted.” Eberly v. Manning, 258 F. Appx 224, 227 (10th Cir.
2007) (unpublished). The Tenth Circuit does not require a finding of bad faith under
§ 1927. Hamilton v. Boise Cascade Express, 519 F.3d 1197, 1202 (10th Cir. 2008).
Awards under § 1927 are granted “only in instances evidencing a serious and standard
disregard for the orderly process of justice.” Dreiling v. Peugeot Motors of Am., Inc.,
768 F.2d 1159, 1165 (10th Cir. 1985) (internal quotation marks and citations omitted).
3
Although GAIC was not listed on the Motion to Dismiss (Doc. # 4) or the Reply (Doc.
# 14), it subsequently joined both motions. GAIC filed the Response to SSC’s Cross Motion
together with RKS and RK Mechanical (Doc. # 16), and therefore did not need to join it later.
4
They also seek attorneys’ fees pursuant to § 15.4 of the Subcontract (Doc. # 4 at 13),
which provides, in pertinent part, that “[s]hould Subcontractor bring a claim against RKS which
is unsuccessful in whole or in part, then the substantial prevailing party shall be entitled to
recover its attorney’s fees incurred in defending such claim.” (Doc. # 4, Ex. A at 12.) Because
the success of the claims on the merits is subject to arbitration, this Court defers any potential
award of attorneys’ fees under the Subcontract to the arbitrator.
11
However, sanctions can be imposed on counsel who “repeatedly attempt to litigate
matters that have been decided or who continue to pursue claims that are no longer
reasonable.” Sangui Biotech Intern., Inc. v. Kappes, 179 F. Supp. 2d 1240, 1243–44
(D. Colo. 2002).
The Court may award sanctions for violations of Rule 11 when a pleading or
motion is for an improper purpose, contains claims or contentions not “warranted by
existing law or by a nonfrivolous argument for extending, modifying, or reversing
existing law,” or contains factual contentions that lack evidentiary support. Fed. R. Civ.
P. 11(b)–(c). The Tenth Circuit has “adopted the view that an attorney’s actions must
be objectively reasonable in order to avoid Rule 11 sanctions.” White v. Gen. Motors
Corp., 908 F.2d 675, 680 (10th Cir. 1990) (citing Adamson v. Bowen, 855 F.2d 668, 673
(10th Cir. 1988)). “A good faith belief in the merit of an argument is not sufficient; the
attorney’s belief must also be in accord with what a reasonable, competent attorney
would believe under the circumstances.” Id.
1.
Costs and Fees in Connection with the Motion to Dismiss
In their Motion to Dismiss, Defendants seek attorneys’ fees and costs under
§ 1927 for SSC’s multiplication of proceedings by “filing this action with the knowledge
that arbitration is pending between the parties and that the claims asserted in this suit
are subject to the arbitration agreement contained in the Subcontract.” (Doc. # 4 at 14.)
However, the “unambiguous statutory language [of § 1927] necessarily excludes
the complaint that gives birth to the proceedings, as it is not possible to multiply
12
proceedings until after those proceedings have begun.” Steiner v. Winn Group, Inc.,
440 F.3d 1214, 1224–25 (10th Cir. 2006) (emphasis in original). Therefore, fees or
costs incurred in connection with the Motion to Dismiss cannot be awarded on the basis
of § 1927 because SSC could not have multiplied proceedings until after the Motion to
Dismiss. See Roth v. Spruell, 388 F. Appx 830, 836 (10th Cir. 2010) (unpublished).
Defendants also argue that SSC’s claims for negligent misrepresentation and
unjust enrichment are frivolous and groundless and subject to Rule 11 sanctions. (Doc.
# 4 at 15.) But because the Court has stayed the proceedings, including the Motion to
Dismiss to the extent it seeks dismissal on the merits, the Court will not address related
Rule 11 sanctions at this time. Furthermore, because these claims are subject to
arbitration and, therefore, to the arbitrator’s discretion to award attorneys’ fees pursuant
to § 15.4 of the Subcontract, as discussed above, this Court also defers to the arbitrator
any award of attorneys’ fees associated with these claims.
Accordingly, Defendants’ request for attorneys’ fees in connection with the
Motion to Dismiss (Doc. # 4) is denied.
2.
Costs and Fees after the Motion to Dismiss
Defendants also argue that SSC has multiplied the proceedings by filing its Cross
Motion in direct contradiction of existing Supreme Court precedent and after the
arbitrator had ruled on the issue. (Doc. # 16 at 8; see also Doc. # 14 at 10 (requesting
attorneys’ fees and costs in Reply to SSC’s Response to the Motion to Dismiss).)
13
As noted above, SSC’s Response to the Motion to Dismiss (Doc. # 11) and
Cross Motion (Doc. # 12) hinge on the argument that RKS and RK Mechanical waived
their right to arbitrate under the Subcontract. At the time RKS and RK Mechanical filed
their Motion to Dismiss on June 24, 2011, the arbitrator had not yet ruled on the waiver
issue. (Doc. # 4 at 4.) But on July 25, 2011, when SSC filed its Response to the Motion
to Dismiss and its Cross Motion, one week had passed since the arbitrator had denied
the motion to reconsider SSC’s waiver argument in seeking to dismiss the arbitration.
(Doc. # 9, Ex. C.)
Nonetheless, SSC raises before this Court the same waiver issue in its
Response and Cross Motion. Not only is this an attempt to re-litigate matters “after it
becomes clear that the position or claim is unfounded,” Shackelford v. Courtesy Ford,
Inc., 96 F. Supp. 2d 1140, 1144 (D. Colo. 2000), but SSC ignores clear precedent from
the Supreme Court that waiver and time limit issues are procedural matters for the
arbitrator, see Howsam, 537 U.S. at 84–85. Therefore, although the initiation of the
action is not subject to § 1927 sanctions, any filings by SSC after the Motion to Dismiss
are so subject, especially given the statute’s “incentive for attorneys to regularly reevaluate the merits of their claims and to avoid prolonging meritless claims.” Steinert,
440 F.3d at 1224; Roth, 388 F. Appx at 836. Accordingly, the Court finds that an award
of costs and attorneys’ fees reasonably incurred in connection with Defendants’ Reply
14
to SSC’s Response to the Motion to Dismiss (Doc. # 14) and with Defendants’
Response to SSC’s Cross Motion (Doc. # 16) is appropriate under § 1927.5
III. CONCLUSION
Accordingly, for the foregoing reasons, IT IS ORDERED THAT:
1.
RKS and RK Mechanical’s Motion to Dismiss, or Alternatively, to Stay
Proceedings (Doc. # 4) is DENIED IN PART to the extent it seeks dismissal under Fed.
R. Civ. P. 12(b)(1), GRANTED IN PART to the extent it seeks to stay the proceedings
pending arbitration, and STAYED IN PART to the extent it seeks dismissal under Fed.
R. Civ. P. 12(b)(6);
2.
SSC’s Cross Motion to Stay Arbitration and Demand for Jury Trial (Doc.
# 12) is DENIED;
3.
The parties are directed to continue arbitration of the underlying dispute
according to the terms of the Subcontract’s arbitration clause;
4.
This action shall be stayed pursuant to 9 U.S.C. § 3 until the conclusion
of arbitration;
5
Defendant’s also request attorneys’ fees and costs on the grounds that SSC violated
Rule 11 by filing groundless motions. (Docs. ## 14 at 10; 16 at 8.) Although Rule 11 and
§ 1927 have different procedures and underlying purposes, see Hutchinson v. Hahn, 402
F. Appx 391, 394 (10th Cir. 2010) (unpublished) (citing Hamilton, 519 F.3d at 1205; Steinert,
440 F.3d at 1224–25), courts generally view the two as alternative bases for imposing
sanctions. Colorado Chiropractic Council v. Porter Memorial Hospital, 650 F. Supp. 231,
238 n.5 (D. Colo. 1986). Therefore, although the Court concludes that SSC’s unreasonable
contentions in its Response to the Motion to Dismiss and Cross Motion may alternatively or
additionally rise to Rule 11 violations, the Court finds that sanctions under § 1927 suffice.
15
5.
This case shall be ADMINISTRATIVELY CLOSED until the parties submit
a status report regarding the conclusion of the proceedings before the AAA. Such
status report is to be submitted to the Court within 10 days of the AAA’s decision;
6.
This Court shall retain jurisdiction to review, modify, or vacate any
arbitration award, should any party choose to seek such action as permitted by the FAA;
7.
Defendants’ request for attorneys’ fees and costs incurred in connection
with the Motion to Dismiss (Doc. # 4) is DENIED; and
8.
Defendants are permitted to submit within fourteen days of this order a
motion and supporting documentation for reasonable costs and attorneys’ fees incurred
in connection with their Reply to SSC’s Response to the Motion to Dismiss (Doc. # 14)
and their Response to SSC’s Cross Motion to Stay Arbitration. (Doc. # 16.) Such
motion shall comply with the requirements set forth in Fed. R. Civ. P. 54(d)(2) and
D.C.COLO.LCivR 54.3.
DATED: October
31 , 2011
BY THE COURT:
_______________________________
CHRISTINE M. ARGUELLO
United States District Judge
16
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?