Joint Case Management Plan for Petitions for Review of Agency Action. Adm Plaintiffs Brief due by 10/17/2014. Adm Defendants Brief due by 11/17/2014. Adm Plaintiff Reply Brief due by 12/2/2014 by Judge John L. Kane on 06/25/14. (jhawk, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Civil Action No.: 14-cv-680-AP
SAN LUIS VALLEY ECOSYSTEM COUNCIL,
CONEJOS COUNTY CLEAN WATER, INC.,
Petitioners,
v.
UNITED STATES BUREAU OF LAND MANAGEMENT, an agency of the U.S. Department of
Interior; ANDREW ARCHULETA, in his official capacity as Field Manager, San Luis Valley
Field Office, Bureau of Land Management,
Respondents.
JOINT CASE MANAGEMENT PLAN FOR PETITIONS
FOR REVIEW OF AGENCY ACTION
1.
APPEARANCES OF COUNSEL
For Petitioners:
Travis E. Stills, CO Atty #27509
Energy & Conservation Law
1911 Main Ave., Suite 238
Durango, Colorado 81301
(970) 375-9231
stills@frontier.net
Allison N. Melton, CO Atty #45088
Of Counsel, Energy & Conservation Law
P.O. Box 3024
Crested Butte, CO 81224
(970) 349-7104 ext. 2
alli.melton@gmail.com
-1-
For Respondents:
Clare M. Boronow
Trial Attorney, Admitted to the Maryland Bar
U.S. Department of Justice
Environment and Natural Resources Division
Natural Resources Section
P.O. Box 7611
Washington, DC 20044-7611
Phone: (202) 305-0492
clare.boronow@usdoj.gov
2.
STATEMENT OF LEGAL BASIS FOR SUBJECT MATTER JURISDICTION
The Court has jurisdiction based on the presentation of federal question, 28 U.S.C. §
1331, the Mineral Leasing Act of 1920 ("MLA"), the Federal Land Policy and Management Act of 1976
("FLMPA"), and the National Environmental Policy Act 42 U.S.C. §§ 4321 et seq ("NEPA").
3.
DATES OF FILING OF RELEVANT PLEADINGS
A.
B.
Date Petition for Review Was Served on U.S. Attorney's Office:
April 1, 2014
C.
4.
Date Petition for Review Was Filed:
March 5, 2014
Date Answer or Other Response Was Filed:
May 30, 2014
STATEMENT(S) REGARDING WHETHER THIS CASE RAISES UNUSUAL
CLAIMS OR DEFENSES
None.
5.
OTHER MATTERS
Petitioners’ statement:
The federal mineral lessee has been provided a courtesy copy of the Complaint, but has not
responded or indicated any intention, one way or the other, regarding potential intervention.
-2-
Petitioners would not oppose should the federal lessee file a timely motion to intervene in the
present lawsuit to address the claims asserted in the Complaint.
Petitioners would like to avoid filing preliminary injunction motions in this case, which involves
the private development of federal minerals. However, Petitioners believe that a motion for a
temporary restraining order or preliminary injunction could be necessary should the federal lessee
decide to go forward with ground-disturbing activities before a decision on the merits issues. At
this time, the federal lessee has stated that it has no plans to seek the necessary local approvals and
it has no plans to conduct ground-disturbing activities until mid-2015.
To address the possibility that the project could go forward during the litigation, Petitioners have
opened discussions with Respondents regarding a potential stipulation to stay ground-disturbing
activities until the case is decided. Should ground-disturbing activities become imminent, the
proposed stipulation would involve sufficient notice to Petitioners to allow briefing and decision
on a preliminary injunction motion before any ground disturbing activities occur.
Respondents’ statement:
Respondents take no position as to the lessee’s intervention.
Respondents are willing to engage in discussions regarding a potential stipulation to stay grounddisturbing activities until this case is decided. However, as of the time of this filing, Respondents
have not agreed to such a stipulation.
6.
BRIEFING SCHEDULE
A.
Deadline for Filing Administrative Record:
Respondents shall have until July 18, 2014 to file the Administrative Record.
Respondents’ statement:
This deadline is 49 days after the filing of Respondents’ Answer, rather than the 30
days suggested by the Court. Although Respondents have already begun compiling
the administrative record, because Petitioner’s Petition asserts numerous claims, the
additional time is necessary to ensure that all relevant documents are located,
reviewed for privilege, redacted if necessary, scanned, and indexed.
Petitioner’s statement:
Petitioners do not oppose the July 18 deadline for the filing of the administrative
-3-
record.
B.
Deadline for Parties to Confer on Record Disputes:
Petitioners shall have until August 18, 2014 to notify Respondents of documents
they believe should be included in the Administrative Record.
C.
Deadline for Filing Motions to Complete and/or Supplement the
Administrative Record:
The deadline for filing motions to complete and/or supplement the Administrative
Record shall be September 17, 2014. Response and Reply deadlines for such
motions will be governed by D.C.COLO.L.Civ.R. 71(C).
D.
Petitioners’ Opening Brief Due: October 17, 2014
E.
Respondents’ Response Brief Due: November 17, 2014
F.
Petitioners’ Reply Brief (If Any) Due: December 2, 2014
7. STATEMENTS REGARDING ORAL ARGUMENT
A.
Petitioners’ Statement:
Petitioners request oral argument. Although Petitioners have not yet seen the
administrative record, it is likely that the Court could benefit from argument that explains
the complex series of decisions that led to the final federal agency action that gave rise to
this litigation. Oral argument could also help clarify the case-by-case application of the
NEPA caselaw applicable to federal oil and gas development to the facts found in the
administrative record.
B.
Respondents’ Statement:
Respondents take no position with respect to oral argument, but do not believe that this
case presents novel issues.
8. CONSENT TO EXERCISE OF JURISDICTION BY MAGISTRATE JUDGE
Indicate below the parties' consent choice.
-4-
A.
( )
All parties have consented to the exercise of jurisdiction of a
United States Magistrate Judge.
B.
(X)
All parties have not consented to the exercise of jurisdiction of a
United States Magistrate Judge.
9. OTHER MATTERS
Parties filing motions for extension of time or continuances must comply with D.C.COLO.LCivR
5.1G. by submitting proof that a copy of the motion has been served upon all attorneys of record
and all pro se parties. Parties filing motions for extension of time or continuances must comply
with D.C.COLO.LCivR 6.1E. by serving such motion on the Moving Attorney’s Client.
10. AMENDMENTS TO JOINT CASE MANAGEMENT PLAN
The parties agree that the Joint Case Management Plan may be altered or amended only upon a
showing of good cause.
DATED this 25th day of June, 2014.
BY THE COURT
s/John L. Kane
U.S. District Court Judge
-5-
APPROVED:
s/Travis E. Stills
Travis E. Stills, CO Atty #27509
Energy & Conservation Law
1911 Main Ave., Suite 238
Durango, CO 81301
Phone: (970) 375-9231
s/Clare M. Boronow
Clare M. Boronow
Trial Attorney, Admitted to the Maryland Bar
U.S. Department of Justice
Environment and Natural Resources
Division
Natural Resources Section
P.O. Box 7611
Washington, DC 20044-7611
Phone: (202) 305-0492
clare.boronow@usdoj.gov
stills@frontier.net
Allison N. Melton, CO Atty # 45088
Of Counsel Energy & Conservation Law
P.O. Box 3024
Crested Butte, CO 81224
Phone: (970) 349-7104 ext. 2
alli.melton@gmail.com
Attorneys for Petitioners
Attorney for Respondents
-6-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?