Fountain Valley Investment Partners, LLC v. Continental Western Insurance Company
Filing
60
OPINION AND ORDER OVERRULING OBJECTIONS AND ADOPTING RECOMMENDATION IN PART: The Plaintiff's Objections (#49) are OVERRULED. The Recommendation 48 is ADOPTED IN PART AND REJECTED IN PART. The Plaintiff's Motion to File Second Amended Complaint 33 is DENIED in its entirety. by Chief Judge Marcia S. Krieger on 12/3/15. Text Only Entry(msksec, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Chief Judge Marcia S. Krieger
Civil Action No. 14-cv-01906-MSK-NYW
FOUNTAIN VALLEY INVESTMENT PARTNERS, LLC,
Plaintiff,
v.
CONTINENTAL WESTERN INSURANCE COMPANY,
Defendant.
OPINION AND ORDER OVERRULING OBJECTIONS
AND ADOPTING RECOMMENDATION IN PART
THIS MATTER is before the Court on the Plaintiff Fountain Valley Investment
Partners, LLC’s Motion to File Second Amended Complaint (#33), the Defendant Continental
Western Insurance Company’s Response (#40), and the Plaintiff’s Reply (#46). The matter was
referred to a Magistrate Judge, who issued a Report and Recommendation (#48) recommending
that the motion be granted in part and denied in part. The Plaintiff filed timely Objections (#49)
to the Recommendation, and the Defendant filed a Response (#50).
Plaintiff initiated this action in the District Court for El Paso County, Colorado. On July
2, 2014, it filed a First Amended Complaint asserting claims for breach of contract, common law
bad faith, and statutory bad faith under Colo. Rev. Stat. §§ 10-3-1104, 10-3-1113, and 10-31116. Plaintiff’s claims are based on an allegation that the Defendant unreasonably delayed or
denied payment under an insurance policy for hail damage that occurred to Plaintiff’s property
on or about June 7, 2012.
1
The Defendant removed the action to this Court on July 8, 2014. The Scheduling Order
(#23) and subsequent amendment (#28) required the parties to (1) amend pleadings by December
3, 2014; (2) designate all experts no later than March 31, 2015; (3) complete discovery by May
22, 2015; and (4) file dispositive motions on or before May 22, 2015.
The Plaintiff filed the pending motion to amend on May 28, 2015. The Plaintiff seeks to
amend the complaint to add June 4, 2012, and June 18, 2013, as alternative dates of hail storms
that caused the alleged property damage. The Defendant does not oppose amendment to the
breach of contract claim as all dates are subject to contractual coverage, but opposes amendment
to the bad faith claims. The matter was referred to a Magistrate Judge.
After a hearing, the Magistrate Judge issued a Report and Recommendation (#48)
recommending that the motion be granted in part and denied in part. The Recommendation
determined that the motion should be granted with respect to the breach of contract claim
because the Defendant does not oppose amendment to that claim. With regard to the bad faith
claims, however, the Recommendation found that the Plaintiff failed to demonstrate good cause
to modify the scheduling order under Fed. R. Civ. P. 16(b) and therefore recommends that the
motion to amend those claims be denied. The Plaintiff filed timely objections to the
Recommendation.
The Court reviews the Recommendation de novo. See Fed. R. Civ. P. 72(b); U.S. v. One
Parcel of Real Prop. Known as 2121 E. 30th St., 73 F.3d 1057, 1060 (10th Cir. 1996). A twostep analysis is used to determine whether to allow amendment to the pleadings after the passing
of the deadline established by the scheduling order. First, the Court considers whether the
moving party has shown good cause under Fed. R. Civ. P. 16(b) to seek modification of the
scheduling order. See Gorsuch, Ltd., B.C. v. Wells Fargo Nat’l Bank Assoc., 771 F.3d 1230,
2
1242 (10th Cir. 2014). Second, the Court weighs whether amendment should be allowed under
Fed. R. Civ. P. 15(a). Id.
Rule 16(b) provides that a scheduling order “may be modified only for good cause and
with the judge’s consent.” This standard requires the movant to show that “the scheduling
deadlines cannot be met despite [the movant’s] diligent efforts.” Id. at 1240 (citing Pumpco, Inc.
v. Schenker Int’l, Inc., 204 F.R.D. 667, 668 (D.Colo. 2001)). The burden may be satisfied, for
example, when the movant learns new information through discovery or if the underlying law
has changed. Id. However, Rule 16(b) does not focus on the bad faith of the movant, or the
prejudice to the opposing party. Rather, it focuses on the diligence of the party seeking leave to
modify the scheduling order to permit the proposed amendment. Colo. Visionary Acad. v.
Medronic, Inc., 194 F.R.D. 684, 687 (D.Colo. 2000).
The Recommendation found that the latest date on which the Plaintiff reasonably learned
of an alternative date of loss was at a deposition on March 10, 2015. The Recommendation
further found that the Plaintiff failed to show that thereafter it had been diligent in seeking
amendment to the Complaint. The Plaintiff objects to these findings.
The Plaintiff admits that the Defendant produced a report indicating that a hailstorm
occurred at the particular location on June 18, 2013 at the deposition taken on March 10, 2015.
But, the Plaintiff argues that it did not realize the significance of the report – that the Defendant
was changing its theory of defense as to the date of loss. As a consequence, the Plaintiff
contends that it did not realize that amendment was necessary until discovery had proceeded
further and mediation occurred.
The Court finds the Plaintiff’s argument unpersuasive. First, what the Defendant’s theory
of defense was or when it was adopted is not a relevant inquiry. The question is when the
3
Plaintiff first learned of new information that it sought to include in its pleadings. Here, the
lawsuit is premised upon damage caused by a hailstorm. Thus, the date of the hailstorm that
caused the loss is material both as to a breach of contract and to claims of unreasonable delay or
denial of payment. The Plaintiff learned that at least one expert believed that the hailstorm that
caused the loss occurred on June 18, 2013 in March 2015 (giving the Plaintiff the benefit of the
doubt, the Court finds that the Plaintiff learned the new information no later than March 31,
2015, the date on which the Plaintiff concedes it received a defense expert report that concluded
the damage most likely occurred on June 18, 2013).
Assuming the Plaintiff first learned the new information on March 31, 2015, the Court
agrees with the Recommendation that the Plaintiff has failed to show that it was diligent in
seeking amendment thereafter. Because the deadline for amendment had already passed, it was
incumbent upon the Plaintiff to alert the court of its need to amend as soon as possible after
learning the new information. As noted in the Recommendation, the proposed amendments are
not lengthy and could have been accomplished quickly (the proposed amended complaint is five
pages long and simply inserts new dates of loss in a handful of places).
Instead, the Plaintiff waited until nearly six months after the deadline for amending the
pleadings, a month after the close of discovery, and a week after the dispositive motions deadline
to file its motion to amend. Plaintiff’s explanation is that discovery and settlement negotiations
were ongoing. That may be so, but no showing has been made as to why conclusion of
discovery and of settlement negotiation was necessary before Plaintiff made a request to amend
the pleadings. For example, there is no showing of an agreement between the parties to begin
settlement negotiation contingent on no amendment being sought, or an agreement that an
amendment could be sought if settlement negotiations did not prove fruitful. Without some
4
specific showing along those lines or otherwise, the Court finds that delay in filing of the motion
to amend until the conclusion of discovery and settlement negotiations was not diligent.
Accordingly, the Court finds that the Plaintiff has failed to show good cause to modify the
scheduling order under Rule 16(b) as to amendment of any claim. It is therefore unnecessary to
undertake a Rule 15(a) analysis.
Conceptually, there is no basis for distinguishing between the breach of contract claim
and the bad faith claims for purposes of amendment. The Rule 16(b) analysis turns on a showing
of diligence by the Plaintiff, which has not been satisfied. However, the Defendant has conceded
that the Plaintiff may amend its breach of contract claim, and on that basis the Magistrate Judge
recommended amendment only of the breach of contract claim.
The Court finds that all claims must be treated the same for purposes of amendment of
the scheduling order and of the pleadings. To suggest that the hail storm that caused the loss
occurred on one date for purposes of the breach of contract claim and on another date for
purposes of the bad faith claims bears no reasonable relationship to reality. Although the Court
appreciates that such distinction may reflect courtesy among counsel, or may change the
settlement dynamics in the esoteric litigation world, it does not withstand the weight of the
“search for the truth,” which is the function of the trial process. A jury cannot reasonably be
asked to assume that the date of the loss changes based on different legal theories.
5
For the forgoing reasons, the Plaintiff’s Objections (#49) are OVERRULED. The
Recommendation (#48) is ADOPTED IN PART AND REJECTED IN PART. The Plaintiff’s
Motion to File Second Amended Complaint (#33) is DENIED in its entirety.
Dated this 3rd day of December, 2015.
BY THE COURT:
Marcia S. Krieger
Chief United States District Judge
6
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?