ORDER Denying 12 Defendant Power Mount Incorporateds Motion to Dismiss the Complaint, by Judge Wiley Y. Daniel on 9/2/2015.(evana, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Civil Action No. 14-cv-02475-WYD-CBS
STILLWATER MINING COMPANY,
Plaintiff,
v.
POWER MOUNT INCORPORATED,
Defendant.
_____________________________________________________________________
ORDER
_____________________________________________________________________
I.
INTRODUCTION AND BACKGROUND
THIS MATTER is before the Court on Defendant, Power Mount Incorporated’s
Motion to Dismiss the Complaint (ECF No. 12), filed October 22, 2014. Plaintiff,
Stillwater Mining Company filed a Response (ECF No. 16) on November 24, 2014 and the
Defendant filed a Reply (ECF No. 22) on December 15, 2014.
By way of background, this case involves a contract dispute over the repayment of
prepaid, undelivered services and materials. The parties originally entered into an
agreement in 2003, which was subsequently altered in 2005, 2012, and 2013. Under the
agreement, the Defendant would source and purchase spent catalyst materials from
automobile catalytic converters (“Materials”) and supply them to the Plaintiff. The
Plaintiff would then recycle the Materials through its smelting and refining facilities in
order to recover platinum, palladium, and rhodium. In order to initiate this process, the
Defendant would submit forms setting forth the metal it had sourced and intended to
purchase and deliver within a certain amount of days to the Plaintiff. Once the Plaintiff
received the forms, it would prepay a fixed percentage to the Defendant, after which the
Plaintiff would make additional payments per the agreement’s terms. In the event that
the Defendant failed to perform, it was required to repay the Plaintiff’s prepayment. In
2008, the Plaintiff prepaid the Defendant $28,542,201 to source and deliver Materials.
However, the Defendant failed to provide the services and Materials for which the Plaintiff
prepaid and the Plaintiff now seeks to recover its prepayment.
In the instant motion, the Defendant asserts that dismissal is proper based on the
concept of novation and the expiration of the three-year statute of limitations. After
carefully reviewing the applicable pleadings, the Defendant’s motion to dismiss is denied
as set forth below.
II.
STANDARD OF REVIEW
Federal Rule of Civil Procedure 12(b)(6) provides that a defendant may move to
dismiss a claim for “failure to state a claim upon which relief can be granted.” Fed. R.
Civ. P. 12(b)(6). The Court’s inquiry is “whether the complaint contains ‘enough facts to
state a claim to relief that is plausible on its face.’” Ridge at Red Hawk, LLC v.
Schneider, 493 F.3d 1174, 1177 (10th Cir. 2007) (quoting Bell Atlantic Corp. v. Twombly,
550 U.S. 544 (2007)). In reviewing a motion under Rule 12(b)(6), the Court “must accept
all . . . well-pleaded allegations of the complaint as true and must construe them in the
light most favorable to the plaintiff.” David v. City & Cnty. of Denver, 101 F.3d 1344,
1352 (10th Cir. 1996). A pleading that offers ‘labels and conclusions’ or a formulaic
recitation of the elements of a cause of action will not do. Nor does the complaint suffice
if it tenders ‘naked assertion[s]’ devoid of ‘further factual enhancement.’” Id. at 678
-2-
(quoting Twombly, 550 U.S. at 555, 557). Furthermore, conclusory allegations are “not
entitled to the assumption of truth.” Id. at 679.
III.
DISCUSSION
In its motion, the Defendant asserts that the Plaintiff’s complaint should be
dismissed based on the concept of novation and the expiration of the three-year statute of
limitations. These arguments are addressed in turn below.
A.
Novation
“The extinguishment of an old contract by the substitution of a new contract or
obligation is an original promise known as a novation.” Haan v. Traylor, 79 P.3d 114,
116 (Colo. App. 2003). “In order to find a novation, there must be 1) an existing and valid
contract; 2) an agreement to the new contract by all the parties; 3) a new valid contract;
and 4) an extinguishment of the old contract by the new one.” Prod. Credit Ass'n of S.
New Mexico v. Alamo Ranch Co., 989 F.2d 413, 418 (10th Cir. 1993). “The intention to
accomplish a novation need not be expressed in the agreement, but may be inferred from
the facts, circumstances, and conduct of the parties.” Haan, 79 P.3d at 116. “Whether
there has been a novation is ordinarily a question of fact, and proof of a novation may be
established by evidence of an express understanding to this effect or by circumstances
showing such assent.” Id. “A mere modification will not suffice; anything remaining of
the original obligation prevents a novation.” Moffat Cnty. State Bank v. Told, 800 P.2d
1320, 1323 (Colo. 1990). “An essential element of novation is that there must be a
release of all claims of liability against the original debtor on the old obligation.” Id.
-3-
Here, whether the fourth element of the novation analysis has been satisfied is in
dispute. As to the first three elements, there is an existing and valid contract, the parties
have agreed to the new contract, and the new contract is valid. Thus, I find that the first
three elements of the novation analysis have been satisfied. In considering the fourth
element, the Defendant contends that the new agreement extinguishes the old one, as
evidenced by a merger clause in the parties’ 2013 agreement. Specifically, paragraph
19.1 of the agreement provides: “Entire Agreement. This Agreement represents the
complete agreement between the Parties hereto and supersedes all prior or
contemporaneous oral or written agreements between Power Mount and Stillwater to the
extent they relate in any way to the subject matter hereof.” ECF No. 12-2, p. 14. For
this reason, the Defendant asserts that the 2013 agreement is a novation that
extinguished the alleged obligation.
In response, the Plaintiff argues that the merger clause does not extinguish the
debt or release the Defendant from liability on the debt. The Plaintiff explains that the
effect of the merger clause is prospective. For example, the Plaintiff notes that the
merger clause clarifies that when the Defendant sourced and supplied new materials
under the new agreement, the Defendant would receive payment in accordance with the
new agreement as opposed to under the prior agreements.
Based on the foregoing, I find that the entirety of the allegations, construing them
in the light most favorable to the Plaintiff, are sufficient to show that the Plaintiff has
asserted a plausible inference that the Defendant breached the contract by failing to
reimburse $28,542,201 to the Plaintiff. I note that a review of the 2013 agreement
-4-
reveals that it was entered into by the parties based on their desire to amend and restate
the terms of the previous agreement dated November 1, 2012. I also note that the
language of the new agreement is such that the parties “will” and “shall” carry out their
obligations as opposed to what had been accomplished previously.
B.
Statute of Limitations
Having determined that the Plaintiff has alleged facts sufficient to lead to the
plausible inference that the Defendant remains liable for the debt, I now turn to whether
dismissal is warranted under the statute of limitations. As to this issue, the parties
dispute whether the alleged debt is liquidated and/or determinable, and thus whether the
three-year or six-year statute of limitations applies.
All contract actions, except as otherwise provided in section 13-80-103.5, are
subject to the three-year statute of limitations. Colo. Rev. Stat. § 13-80-101. However,
if recovery of a liquidated debt or a determinable amount of money is sought, the action
must be commenced within six years after the cause of action accrues. Colo. Rev. Stat.
§ 13-80-103.5(1)(a). “[A]n amount is either liquidated or determinable for purposes of
§ 13-80-103.5(1)(a) if an agreement sets forth a method for determining the amount due,
regardless of the need to refer to facts external to the agreement.” Interbank
Investments, L.L.C. v. Vail Valley Consol. Water Dist., 12 P.3d 1224, 1230 (Colo. App.
2000) (citing Rotenberg v. Richards, 899 P.2d 365 (Colo.App.1995)). For example, “an
amount owed under a building contract was held to be ‘determinable’ where the amount
was a specified percentage of the estimated cost of construction, despite the parties'
dispute over the estimated cost.” Interbank Investments, L.L.C., 12 P.3d at 1230 (citing
-5-
Comfort Homes, Inc. v. Peterson, 37 Colo.App. 516, 549 P.2d 1087 (1976)). Moreover,
“[a] debt is liquidated if the amount due is capable of ascertainment by reference to an
agreement or by simple computation.” Portercare Adventist Health Sys. v. Lego, 286
P.3d 525, 528 (Colo.2012) (internal quotation marks omitted). “A debt may be liquidated
even if extrinsic evidence is necessary to compute its exact amount.” Id.
In its motion to dismiss, the Defendant argues that the alleged debt is not
liquidated or determinable and that the three-year statute of limitations applies. The
Defendant argues that the amount of services and Materials that it allegedly failed to
provide is not capable of determination by either reference to an agreement or simple
computation. The Defendant explains that in order for it to provide $28,542,201 worth of
Materials, it would first have to source and buy an unknown number of automotive
catalytic converters, break them down to their catalyst materials, and send them to the
Plaintiff. The Defendant further explains that the Plaintiff would then have to smelt them
and determine after a lab assay how much rare earth metal was present and the amount
the metal was valued at on the open market on that particular day. As a result of this
complex process, the Defendant concludes that the six-year statute of limitations does
not apply. Thus, the Defendant contends that the three-year statute of limitations, which
was triggered by the alleged breach in 2008, expired in 2011.
In response, the Plaintiff contends that the debt is liquidated and/or determinable,
and that the six-year statute of limitations applies. I agree. After all, an amount is
liquidated or determinable under section 13-80-103.5(1)(a) if, as here, an agreement
identifies the way in which amounts due are determined. See Interbank Investments,
-6-
L.L.C., 12 P.3d at 1230. In this case, the agreement sets forth the method for
determining the amounts due for prepayment and final payment. Specifically, sections
9.1 and 9.2 of the 2013 agreement provide:
9.1 Prepayment. Within one (1) Business Day following receipt of Shipping
Documentation from Power Mount and provided a Purchase Price has been
set, Stillwater may, at its option, forward Prepayment if it has been
requested by Power Mount for such Lot via wire transfer to Power Mount.
The “Prepayment” to Power Mount for such Offered Ounces shall equal (A)
the product of (i) the Prepayment Percentage and (ii) the sum of the Offered
Metal Values for each Metal less (B) the Prepayment Finance Charge.1
9.2 Calculation of Final Payment. Within two (2) Business Days following
notice to Power Mount of the Final Lot Value for a Lot of Secondary
Materials, Stillwater will forward the Final Payment via wire transfer to
Power Mount. The “Final Payment” shall be calculated as follows:
(a) the sum of the Final Lot Values for each Metal in such Lot; less
(b) the Prepayment; less
(c) the Prepayment Finance Charge; less
(d) the Final Payment Finance Charge; less
(e) the Final Treatment Charge; less
(f) any Section 5.0 lot charges.
Attached as Appendix B is a sample calculation of a Final Payment and
Final Payment Finance Charge. If the calculation of the Final Payment
pursuant to this Section 9.2 results in a negative number such that Stillwater
has overpaid for a given Lot, such amount will be deducted from future
amounts owed to Power Mount, and, if payments owed to Power Mount
1
“Offered Metal Value means, with respect to each Metal, the product of the
(i) Offered Ounces, (ii) the Return Percentage, and (iii) the Purchase Price.” ECF No. 12-2, p.3.
“Prepayment Percentage means the percentage of the Offered Metal Values used
to determine the amount, if any, of the Prepayment from Stillwater to Power Mount, which is set
forth on Schedule 1 hereto.” ECF No. 12-2, p.3. Schedule 1 indicates that the prepayment
percentage was 87.5%. ECF No. 12-2, p. 21.
“Prepayment Finance Charge means the interest assessed by Stillwater on the
amount of the Prepayment and calculated as the product of (i) the amount of the Prepayment
prior to deducting the Prepayment Finance Charge; (ii) Stillwater’s Cost of Borrowing; and
(iii) the number of days from the date of the Prepayment until the estimated Value Date divided
by 360.” ECF No. 12-2, p.3.
-7-
within three (3) months after such overpayment are insufficient to repay
Stillwater the amount of such overpayment, Power Mount shall promptly
(with two (2) Business Days) pay Stillwater all amounts remaining due.
ECF No. 12-2, p. 8.
Thus, having determined that the parties’ agreement sets forth a method for
determining the amounts due, I find that the six-year statute of limitations applies.
Therefore, the expiration of the three-year statute of limitations does not warrant
dismissal of this case.
IV.
CONCLUSION
Based on the foregoing, it is
ORDERED that Defendant Power Mount Incorporated’s Motion to Dismiss the
Complaint (ECF No. 12) is DENIED.
Dated: September 2, 2015.
BY THE COURT:
s/ Wiley Y. Daniel
WILEY Y. DANIEL,
SENIOR UNITED STATES DISTRICT JUDGE
-8-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.