GEOMC Co, Ltd. v. Competitive Technologies, Inc.
Filing
395
ORDER denying 376 Motion for TRO. For the reasons described in the attached ruling and order, the Court DENIES the motion for a TRO and preliminary injunction. The Court further DENIES as moot the motion to amend the scheduling order, and GRANTS in part and DENIES in part the motion to compel discovery and obtain additional discovery. Signed by Judge Victor A. Bolden on 09/13/2021. (Dalton, A.)
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 1 of 14
UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF CONNECTICUT
GEOMC CO., LTD,
Plaintiff,
v.
No. 3:14-cv-01222 (VAB)
CALMARE THERAPEUTICS, INC.,
Defendant.
RULING AND ORDER ON MOTION FOR TEMPORARY RESTRAINING ORDER
AND PRELIMINARY INJUNCTION
GEOMC Co., Ltd. (“GEOMC” or “Plaintiff”) has filed a motion for a temporary
restraining order (“TRO”) and preliminary injunction against Calmare Therapeutics, Inc.,
(“Calmare” or “Defendant”). GEOMC seeks to enjoin defendant Calmare from dissipating,
disposing or otherwise removing from storage the pain management medical devices (the
“Devices”) that are the subject of this litigation. If injunctive relief is not ordered, GEOMC
moves to modify the existing scheduling order, as well as to compel discovery responses and
obtain addition discovery information.
For the reasons stated below, the Court DENIES the motion for a TRO and preliminary
injunction. The Court further DENIES as moot the motion to amend the scheduling order, and
GRANTS in part and DENIES in part the motion to compel discovery and obtain additional
discovery.
I.
FACTUAL AND PROCEDURAL BACKGROUND
Familiarity with the factual allegations and procedural history of this action is assumed.
See Summary Order, ECF No. 244 (May 14, 2019); Mandate, ECF No. 245 (June 4, 2019).
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 2 of 14
On March 14, 2019, the Second Circuit issued a summary order vacating the Court’s
September 29, 2017 judgment and remanding the case for further proceedings consistent with the
summary order. Summary Order.
On July 3, 2019, the Court issued a scheduling order setting November 22, 2019, as the
deadline for the completion of discovery. Stipulation and Scheduling Order, ECF No. 250 (July 3,
2019).
On November 12, 2019, the parties jointly moved for an extension of time to complete
discovery. Joint Mot. for Extension of Time, ECF No. 254 (Nov. 12, 2019). The next day, the
Court granted the motion. Order, ECF No. 255 (Nov. 13, 2019).
On December 10, 2019, the parties jointly moved for a discovery conference, stating that
although they had met and conferred in good faith, they were unable to resolve a series of discovery
disputes. Joint Mot. The next day, the Court scheduled a discovery conference for January 6, 2020.
Order, ECF No. 264 (Dec. 11, 2019).
On December 20, 2019, the parties provided their respective submissions on issues to be
addressed at the discovery conference. See GEOMC Submission, ECF No. 265 (Dec. 20, 2019);
Calmare Submission, ECF No. 266 (Dec. 20, 2019). On January 3, 2020, the parties filed their
respective responses. See GEOMC Response, ECF No. 270 (Jan. 3, 2019); Calmare Response,
ECF No. 271 (Jan. 3, 2019).
After several adjournments, see Order, ECF No. 268 (Jan. 3, 2020); Order, ECF No. 277
(Jan. 8, 2020); Order, ECF No. 280 (Jan. 14, 2020); Order, ECF No. 285 (Feb. 7, 2020), the status
conference was cancelled, see Cancellation Notice (Mar. 6, 2020).
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 3 of 14
On July 17, 2020, GEOMC moved for a telephonic status conference, noting that they had
retained new counsel. Mot. for Status Conference, ECF No. 307 (July 17, 2020). On July 20, 2020,
the Court granted the motion, Order, ECF No. 308 (July 20, 2020).
On August 18, 2020, following a status conference, the Court ordered that the parties, by
September 25, 2020, file a joint status report to include any outstanding discovery issues and a
proposed schedule. Order, ECF No. 318 (Aug. 18, 2020).
On September 25, 2020, the parties filed a joint status report. Joint Status Report, ECF No.
321 (Sept. 25, 2020) (the “Joint Status Report”). The report stated that though the parties had met
and conferred in good faith, they were unable to resolve the majority of the issues identified in the
Joint Motion. 1 Id. at 1.
On October 6, 2020, the Court held a discovery conference by Zoom to discuss the Joint
Status Report. Minute Entry, ECF No. 326 (Oct. 6, 2020).
On May 11, 2021, the Court ordered an additional scheduling order as to outstanding
discovery issues, including for records of sales, contracts, invoices, purchase orders, and receipts
relating to the Devices. Scheduling Order, ECF No. 362 (May 11, 2021) (“May 11 Order”).
On July 27, 2021, GEOMC filed an emergency motion for a TRO. Emergency Mot. for
Temporary Restraining Order, ECF No. 368 (July 27, 2021).
On July 28, 2021, the Court denied the motion for a TRO without prejudice to renewal
following the filing of a proper motion and memorandum of law. Order, ECF No. 369 (July 28,
2021). The Court further ordered Defendant Calmare “not to dissipate, dispose of or otherwise
remove” any of the Devices from their current place until [a] discovery conference is held[.]” Id.
The Court ordered the discovery conference sua sponte. Id.
Specifically, the Joint Status Report stated that the parties had resolved only “one issue identified in the Joint
Motion[:] (Item A(1)(a)).” Id.
1
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 4 of 14
On August 5, 2021, the Court held a discovery conference via Zoom. Minute Entry, ECF
No. 373 (Aug. 5, 2021). That same day, the Court granted GEOMC leave to file a formal motion
for a TRO accompanied by briefing and set a schedule for such briefing and replies. ECF No. 374
(Aug. 5, 2021). In the interim, the Court declined to impose restraints on the conduct of Calmare
towards the Devices. Id.
On August 6, 2021, GEOMC Co. filed a second emergency motion for a TRO, with an
accompanying memorandum of law. Emergency Mot. for Temporary Restraining Order, ECF No.
376 (Aug. 6, 2021); Pl.’s Mem. Of Law in Support of Mot. for Temporary Restraining Order, ECF
No. 376-1 (Aug. 6, 2021) (“Emergency Mot. for TRO”).
On August 9, 2021, Calmare filed a motion for clarification regarding the Court’s Order
on August 5, 2021. Mot. for Clarification, ECF No. 377 (Aug. 9, 2021). The Court granted the
motion and clarified that the Court’s August 5, 2021 Order “lifted only the July 28, 2021 Order
‘not to dissipate, dispose of or otherwise remove any pain management devices the subject of this
litigation from their current place until this discovery conference is held [. . . .]’” Order Granting
Mot. for Clarification, ECF No. 378 (Aug. 10, 2021). The Court further clarified that its order
“cannot and should not be construed as adjudicating or otherwise affecting any applicable
agreement between GEOMC and Calmare Technologies Incorporated regarding the pain
management devices [and] . . . the rights of any party under any applicable agreement have not
been altered or affected in any way by this Court's August 5, 2021 Order, ECF No. 374.” Id.
On August 13, 2021, Calmare filed a memorandum in opposition to the emergency motion
for a TRO, see Mem. in Opp’n, ECF No. 379 (Aug. 13, 2021) (“Opp’n”), in addition to an affidavit
signed by counsel, see Affidavit in Opp’n to TRO Request, ECF No. 380 (Aug. 13, 2021)
(“Uretsky Decl.”).
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 5 of 14
On August 18, 2021, GEOMC filed a reply to the response to the emergency motion for a
TRO. Reply to Resp. to Emergency Mot. for TRO, ECF No. 381 (Aug. 18, 2021) (“Reply”).
On August 20, 2021, GEOMC filed a supplemental affidavit signed by counsel in support
of its reply. Supp. Decl. Of Crew Schielke in Support of Mot. for TRO, ECF No. 382 (Aug. 20,
2021) (“Supp. Schielke Decl.”).
On August 23, 2021, the Court ordered a hearing on the emergency motion for September
3, 2021. Notice, ECF No. 383 (Aug. 23, 2021).
On August 24, 2021, the Court granted a motion for extension of time to complete
discovery and set October 28, 2021 as the discovery end date. Order Granting Mot. for Extension
of Time, ECF No. 385 (Aug. 24, 2021).
On September 3, 2021, the Court held an evidentiary hearing regarding the TRO. See
Minute Entry, ECF No. 393 (Sept. 3, 2021).
II.
Motion for Preliminary Injunction
Preliminary injunctive relief “is an extraordinary and drastic remedy [. . .] that should not
be granted unless the movant, by a clear showing, carries the burden of persuasion.” Moore v.
Consol. Edison Co. of New York, Inc., 409 F.3d 506, 510 (2d Cir. 2005) (internal quotation
marks and citation omitted). To show entitlement to a preliminary injunction, the moving party
must demonstrate (a) that he or she will suffer “irreparable harm” in the absence of an injunction,
and (b) either (1) a “likelihood of success on the merits or (2) sufficiently serious questions going
to the merits [of the case] to make them a fair ground for litigation and a balance of hardships
tipping decidedly toward the party requesting the preliminary relief.” Cacchillo v. Insmed, Inc.,
638 F.3d 401, 405–06 (2d Cir. 2011) (internal quotation marks and citation omitted). To
demonstrate irreparable harm, plaintiff must show an “injury that is neither remote nor
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 6 of 14
speculative, but actual and imminent.” Grand River Enter. Six Nations, Ltd. V. Pryor, 481 F.3d
60, 66 (2d Cir. 2007) (citation and internal quotation marks omitted); see also City of Los
Angeles v. Lyons, 461 U.S. 95, 111–12 (1983) (injunctive relief cannot be provided if claimed
injury is speculative or remote).
GEOMC argues that it is entitled to a preliminary injunction because it can demonstrate
(1) irreparable harm if relief is not granted restraining Calmare from moving the Devices
“outside the normal course of business,” as Calmare allegedly is insolvent; and (2) a likelihood
of success on the merits based on Calmare’s alleged breach of the parties’ May 1, 2012 Security
Agreement (“Security Agreement”). See Emergency Mot. for TRO.
The Court will address each of these arguments below.
A. Irreparable Harm
In a motion for injunctive relief, it is the burden of the moving party to demonstrate
irreparable harm. See Rockwell Intern. Systems, Inc. v. Citibank, N.A., 719 F.2d 583, 586 (2d
Cir. 1983) (In a motion for injunctive relief, “the moving party . . . bears the burden of proving
irreparable injury.”). Irreparable harm typically means an “injury for which a monetary award
cannot be adequate compensation[.]” Jayaraj v. Scappini, 66 F.3d 36, 39 (2d Cir. 1995) (quoting
Jackson Dairy, Inc. v. H.P. Hood & Sons, Inc., 596 F.2d 70, 72 (2d Cir. 1979) (per curiam)). “As
a general matter, because monetary injury can be estimated and compensated, the likelihood of
such injury usually does not constitute irreparable harm.” Brenntag Intern. Chemicals, Inc. v.
Bank of India, 175 F.3d 245, 249 (2d Cir. 1999) (citing Jackson Dairy, 596 F.2d at 72).
An exception exists to this rule where a defendant is insolvent, or where, based on the
totality of the circumstances, the court finds that a defendant is likely to frustrate any future
monetary judgment. See Gelfand v. Stone, 727 F. Supp. 98, 100–01 (S.D.N.Y. 1989) (“A
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 7 of 14
preliminary injunction may issue to preserve assets as security for a potential monetary judgment
where the [totality of the] evidence shows that a party intends to frustrate any judgment on the
merits by making it uncollectible.” (citing Republic of the Philippines v. Marcos, 806 F.2d 344,
356 (2d Cir. 1986)); Brenntag, 175 F.3d at 250 (“[C]ourts have excepted from the general rule
regarding monetary injury situations involving obligations owed by insolvents.” (citing, inter
alia, Carter–Wallace, Inc. v. Davis–Edwards Pharmacal Corp., 443 F.2d 867, 874 (2d Cir.
1971))).
GEOMC alleges that Calmare is insolvent, and allegedly attempting to frustrate any
judgment by “remov[ing] the Devices from storage to sell them without notice to GEOMC,
disclosure of the sale price, payment to GEOMC and/or an accounting for any past or future
sales.” Emergency Mot. for TRO at 3. On these grounds, GEOMC argues that it has
demonstrated irreparable harm. Id. at 7–8.
The Court disagrees.
Based on the filings and the evidence presented at the hearing, the allegation that
Calmare intends to dissipate assets by “mov[ing] the Devices in a manner outside the normal
course of business,” Reply at 5, is not sufficiently supported, and therefore insufficient for the
actual and concrete injury necessary to permit injunctive relief. Furthermore, the action that
GEOMC seeks to restrain is specifically permitted by the Security Agreement, which states:
[W]hile any sum payable under the terms of purchase of the Calmare
machines is outstanding, [Calmare] covenants and warrants to
[GEOMC] that it will . . . [g]ive [GEOMC] written notice of each
location at which the Collateral is or will be kept other than for
temporary processing, storage or similar purposes[,] and, except to
the extent such notice is given, all Collateral shall be kept at the
Connecticut Warehouse and/or the North Carolina Warehouse.
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 8 of 14
Security Agreement at ¶ 5(c). GEOMC has provided no evidence to support that Calmare has
moved or sought to move the Devices for reasons other than “temporary processing, storage or
similar purposes[.]” Id.
As to the insolvency exception, GEOMC has produced evidence that Calmare cannot pay
its current debts, including but not limited to evidence of a lien placed on the Devices by the
warehouse, past failure to pay attorneys, and overall net losses filed with the SEC. See
Emergency Mot. for TRO at 7. This evidence alone, however, does not establish irreparable
harm. Since the insolvency exception was established in the Second Circuit in Brenntag, the
Supreme Court held in Grupo Mexicano de Desarrollo S.A. v. All. Bond Fund, Inc., 527 U.S.
308, 333 (Jun. 17, 1999) that district courts have “no authority to issue a preliminary injunction
preventing petitioners from disposing of their assets pending adjudication of [a] contract claim
for money damages.” Allied Bldg. Prod. Corp. v. George Parsons Roofing & Siding, Inc., No.
16CV4161 (JMA) (SIL), 2017 WL 2964018, at *2 (E.D.N.Y. Mar. 31, 2017). Courts in the
Second Circuit generally “have interpreted Grupo to stand for the principle that courts cannot
issue preliminary injunctions based solely on the insolvency of debtors where the plaintiffs'
underlying claims primarily seek monetary damages.” Id. (citing Vis Vires Grp., Inc. v.
Endonovo Therapeutics, Inc., 149 F. Supp. 3d 376, 393 (E.D.N.Y. 2016)); see also Levy v.
Young Adult Inst., Inc., No. 13-cv-286, 2015 WL 170442, at *6 (S.D.N.Y. Jan. 13, 2015)
(“Lower courts have generally interpreted Grupo Mexicano to bar preliminary injunctions in
cases that seek primarily legal remedies.”). This is an action for monetary damages, 2 and, as a
result, GEOMC’s claims are primarily legal, rather than equitable, and therefore can be repaired
by money damages.
The operative Complaint in this matter, which dates to 2016, seeks equitable relief in the form of possession of the
Devices, or, in the alternative, damages. See Second Am. Compl. at 18–19, ECF No. 137 (June 15, 2016).
2
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 9 of 14
The existence of a security interest in the Devices, moreover, also does not establish
irreparable harm. Irreparable harm “may”, but does not necessarily, exist in situations where a
creditor has a security interest in a debtor’s assets. Quantum Corp. Funding, Ltd. v. Assist You
Home Health Care Servs. of VA., 144 F. Supp. 2d 241, 248 (S.D.N.Y. 2001). Harm is irreparable
in such situations where a debtor seeks to “mak[e] a judgment uncollectible”, id., as evidenced
by, for example, multiple unpaid judgments owed to other corporate entities and the state. See,
e.g., id. at 245–46, 248. While the Court understands GEOMC’s concern, given the evidence
presented about Calmare’s potential financial difficulties, this evidence is not sufficient to
demonstrate that Calmare intends to thwart any future judgment in this matter and thereby permit
the Court to order the extraordinary remedy of injunctive relief.
Furthermore, GEOMC has failed to show that it will be unable to recover monetary
damages in the future, for example, in bankruptcy or even in this matter, if the case is promptly
tried. Cf. Carter-Wallace, 443 F.2d at 874 (insolvency exception did not apply where “in a[n]
[ongoing] Chapter XI proceeding[,]” “it is not unreasonable to believe that [the alleged debtor]
will have sufficient assets to respond to plaintiff’s recoverable damages for infringement if . . .
the action is promptly tried”). The likelihood of GEOMC recovering damages in a bankruptcy
proceeding, should it occur, is evidenced by the Security Agreement itself, which provides
remedies to GEOMC in such a proceeding in the event of insolvency. See Security Agreement ¶¶
8–9 (defining remedies available to GEOMC upon the “filing of any petition for relief under the
Bankruptcy Code” or similar events). Moreover, GEOMC has not alleged that any other
creditors would have priority over its claims, if such a proceeding took place. The Court
therefore does not find irreparable harm.
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 10 of 14
B. Likelihood of Success on the Merits
Even if GEOMC would suffer irreparable harm, it is not likely to succeed in obtaining
relief, at least on the facts currently before the Court. 3 Even if true, the new allegations that
Calmare breached the Security Agreement by allowing a warehouse lien to be placed against the
Devices, failing to maintain insurance on the Devices, and failing to provide GEOMC notice of
Calmare’s recent attempt to remove thirty (30) Devices from the warehouse do not constitute an
“event of default” that would entitle GEOMC to repossess the Devices. See Emergency Mot. for
TRO at 9–10; Security Agreement ¶¶ 8–9.
Under the Security Agreement, an “event of default” includes:
(a) The failure of [Calmare] to pay any of the amounts due
under the Obligations as and when due and payable[;] (b) The
determination that any material representation or warranty of
[Calmare] contained in this Agreement is not true, accurate and
complete and is materially misleading[;] (c) The filing of any
petition for relief under the Bankruptcy Code or any similar
federal or state statute by or against [Calmare] or the principals
of [Calmare] or the failure by [Calmare] or the principals of
[Calmare] to generally pay their debts as they become due[;]
(d) An application for the appointment of a receiver for the
making of a general assignment for the benefit of creditors by,
or the insolvency of[] [Calmare] or the principals of
[Calmare][;] (e) The dissolution, merger, consolidation, or
reorganization of [Calmare][;] [and] (f) If there is any change
of control of the Company, whether voluntary or involuntary,
by sale, merger, consolidation, reorganization or otherwise.
Security Agreement ¶ 8; see also id. ¶ 9 (remedies for default). An “event of default” does not
explicitly include, under this provision, a breach of the Security Agreement ¶ 5(b) (requiring
Calmare to “[k]eep the [Devices] free of any lien”), ¶ 5(c) (requiring Calmare to “give written
The Court notes that, at the September 2, 2021 hearing, it understood that neither party would be submitting
additional memoranda or exhibits after the hearing. On September 9, 2020, however, Plaintiffs filed an additional
declaration in support of the TRO, with accompanying exhibits. See Decl. of S.B. Oh in Support of GEOMC’s
Motion for a TRO, ECF No. 394 (Sept. 10, 2021).
3
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 11 of 14
notice of each location at which the Collateral is or will be kept”), or ¶ 6 (requiring Calmare to
“insure the [Devices]”). Even if the Court accepted as true all of these allegations of breach, and
interpreted Security Agreement ¶¶ 5(b), 5(c), and 6 as “warrant[ies]” in the Agreement that have
been misrepresented, leading to an “event of default”, see Security Agreement ¶ 8(b), the harm
remains reparable, for the reasons explained above, and injunctive relief therefore is
inappropriate.
As to the issue of Calmare’s alleged default for non-payment, the Court lacks sufficient
information to determine likelihood of success on the merits for the issues remanded by the
Second Circuit. See Summary Order. Although the Court’s understanding from the evidentiary
hearing, especially from the testimony of Thomas Richtarich, the Chief Financial Officer
(“CFO”) of Calmare Therapeutics, Inc., is that Calmare has sold approximately 100 Devices
since December of 2011, the Court lacks clarification as to how many Devices were sold as
opposed to merely delivered, and further lacks sufficient information to determine by what
amount, if any, the total owed by Calmare under the Security Agreement should be offset by
sales under the Korea Agreement. 4 Even if the Court accepts the argument by Plaintiff,
moreover, that it is owed a substantial sum, regardless of any offset that may apply from the
Korea Agreement, Plaintiff’s request that the Court engage in this calculation on the merits
underscores the monetary and reparable nature of the alleged harm.
Accordingly, the motion for a preliminary injunction will be denied.
The Court notes that the additional evidence submitted by Plaintiff on September 10, 2021 provides clarification as
to whether GEOMC sold any Devices other than those identified in the relevant spreadsheet, see Ex. 2 to Decl. of
S.B. Oh in Support of GEOMC’s Motion for a TRO, ECF No. 394 (Sept. 10, 2021), as well as to its relationship
with DIS&L, see Decl. of S.B. Oh ¶¶ 7–10. But this evidence, although supportive of the likelihood of GEOMC’s
success at trial, does not establish irreparable harm.
4
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 12 of 14
III.
Motion for Temporary Restraining Order
In the Second Circuit, “[t]he same standards used to review a request for a preliminary
injunction govern consideration of an application for a temporary restraining order.” Stagliano v.
Herkimer Cent. Sch. Dist., 151 F. Supp. 3d 264 (N.D.N.Y. 2015); Local 1814 Int'l
Longshoreman's Ass'n v. New York Shipping Assoc., Inc., 965 F.2d 1224, 1228 (2d Cir. 1992)
(standard for TRO is the same as preliminary injunction standard). Irreparable harm is the “most
significant condition which must be present to support the granting of a temporary
injunction.” Capital City Gas Co. v. Phillips Petroleum Co., 373 F.2d 128, 131 (2d Cir. 1967)
(citation omitted). As with a request for preliminary injunctive relief, irreparable harm must be
shown by the moving party to be “not remote or speculative but actual and imminent.” Jackson
Dairy, Inc. v. H. P. Hood & Sons, Inc., 596 F.2d 70, 72 (2d Cir. 1979) (internal citations
omitted). For the same reasons that the Court finds a lack of irreparable harm in the motion for a
preliminary injunction, the motion for a temporary restraining order also will be denied.
IV.
Outstanding Discovery
Given the need for additional information to resolve the merits of this case, and the
request by GEOMC for additional discovery, see Reply at 7–9, the Court issues the following
order as to the parties’ outstanding discovery issues.
•
•
GEOMC shall produce to Calmare, by October 28, 2021, all sales contracts,
invoices, purchase orders, lease agreements, and receipts relating to the Devices
GEOMC sold and leased in Korea under the parties’ Korea Agreement from January
1, 2013 to the present, with identifying customer information redacted, including
customer’s names, phone numbers, and addresses. Serial numbers and prices paid for
the Devices shall not be redacted. GEOMC shall supplement such responses for any
sales or leases under the Korea Agreement from the date the documents are provided
until the trial-ready date.
Calmare shall produce to GEOMC, by October 28, 2021, all sales contracts,
invoices, purchase orders, lease agreements, and receipts relating to Devices Calmare
sold and leased since January 1, 2017, with identifying customer information
redacted, including customer’s names, phone numbers, and addresses, and insurance
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 13 of 14
•
policies Calmare maintained covering Devices in Calmare’s possession, custody, or
control or stored in warehouses at Calmare’s discretion since January 1, 2017. Serial
numbers and prices paid for the Devices shall not be redacted. Calmare shall
supplement such responses for any sales or leases from the date the documents are
provided until the trial-ready date.
Both parties shall submit, by October 28, 2021, interrogatory responses to one
another as to whether all documents have been provided in response to the above
orders, and, to the extent that a party lacks documents about a sale or lease, or the
produced document(s) lack serial numbers and/or sale/lease prices, the parties shall
describe all other evidence of the sale or lease, including but not limited to the serial
number and sale price of each sold or leased Device.
The Court has already granted the motion to amend the June 13, 2021 scheduling order,
see Order Granting Mot. for Extension of Time, ECF No. 385 (Aug. 24, 2021), and therefore
Plaintiff’s request to modify the scheduling order, see Reply at 3, 6–9, will be denied as moot.
The Court’s most recent scheduling order, which sets an end date for discovery of October 28,
2021, remains in effect. Id.
The Court notes that it is not inclined to grant any further extensions of the discovery
deadline in this case, given the age of the case, the alleged failure to comply with discovery by
both parties, and the ample time provided for discovery to date. See Dietz v. Bouldin, 136 S. Ct.
1885, 1892 (2016) (noting "a district court's inherent power to . . . manage its docket and
courtroom with a view toward the efficient and expedient resolution of cases" (internal citations
omitted)). Of course, if GEOMC or Calmare wishes to shorten the current discovery deadline to
expedite the resolution of this case, given the age of this case, the Court would be amenable to do
so.
V.
CONCLUSION
For the foregoing reasons, the Court DENIES the motion for a TRO and preliminary
injunction. The Court further DENIES as moot the motion to amend the scheduling order, and
Case 3:14-cv-01222-VAB Document 395 Filed 09/13/21 Page 14 of 14
GRANTS in part and DENIES in part the motion to compel discovery and obtain additional
discovery.
SO ORDERED at Bridgeport, Connecticut, this 13th day of September, 2021.
/s/ Victor A. Bolden
Victor A. Bolden
United States District Judge
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?