Precision Foam Fabricators, Inc. v. Thomas Company, Inc. et al

Filing 258

MEMORANDUM OPINION. Signed by Judge Mary Pat Thynge on 11/19/20. (cak)

Download PDF
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWARE DELAWARE STATE UNIVERSITY, : : Plaintiff, : : v. : : THOMAS COMPANY, INC., LIBERTY : MUTUAL INSURANCE COMPANY, : RICHÄRD+BAUER, LLP, CZAR : ENGINEERING, LLC, and PRECISION : FOAM FABRICATORS, INC. : : AND : : WHITING-TURNER CONTRACTING, CO., : : AND : : ANTHONY P. ASHFORD, : : Defendants. : C. A. No. 15-1144-LPS-MPT MEMORANDUM OPINION This Memorandum Opinion addresses several motions submitted by the parties in what began in state court as a simple two-sided action based on alleged nonpayment due under a contract which was removed to this court. Over the years, the case was stayed, informal settlement discussions held, formal mediations with the court and with an outside expert conducted, parties incrementally added and finally realigned; resulting in a case that has morphed into a star-crossed constellation of eight parties asserting a plethora of claims, counter-claims, and cross-claims against and among each other. At this point, fact and expert discovery have concluded and the court’s determinations herein resolve many issues in this long, but ongoing, saga. I. PROCEDURAL HISTORY This action was initiated on December 11, 2015 by the filing of a Notice of Removal in this court1 of a complaint originally filed in Delaware Superior Court by Precision Foam Fabricators, Inc. (“Precision Foam” or “PFF”) against Thomas Company, Inc. (“Thomas” or “TCI”) and Liberty Mutual Insurance Company (“Liberty Mutual”) that sought sums allegedly due to Precision Foam for the fabrication of certain insulated metal wall panels in connection with construction of the Optical Science Center and Applied Research (the “OSCAR Facility” or “Project”) at Delaware State University (“DSU”).2 On January 4, 2016, Thomas filed a Third-Party Complaint against DSU.3 On February 19, 2016, Third-Party Defendant DSU answered, and filed a Counterclaim against Thomas.4 DSU’s Counterclaim, and other claims that followed, allege significant defects in the panel wall installed at the OSCAR Facility.5 On February 27, 2017, Thomas filed a Fourth-Party Complaint against Czar Engineering, LLC (“Czar”) arising out of the defect allegations raised by DSU.6 On March 10, 2017, DSU filed a Third-Party Complaint against Richärd+Bauer, LLC (“Richärd+Bauer” or “R+B”), the architect for the OSCAR Facility and the panel wall, also arising out of the alleged 1 D.I. 1. Id., Ex. A (Precision Foam Fabricators, Inc. v. Thomas Co., Inc., C.A. No. N15C-11-115-CLS (Del. Super. Nov. 13, 2015)); see also D.I. 73 (Consent Motion to Realign Parties) at 2 ¶ 1. 3 D.I. 8; D.I. 73 ¶ 2. 4 D.I. 15; D.I. 73 ¶ 2. 5 Id.; D.I. 73 ¶ 3. 6 D.I. 35; D.I. 73 ¶ 4. 2 2 defects in the panel wall.7 Various other cross-claims by the parties against and among each other followed.8 On April 27, 2019, the parties filed a Consent Motion to Realign Parties (“Motion to Realign”)9 and, contemporaneously, DSU filed a Second Amended Complaint joining The Whiting-Turner Contracting Company (“Whiting-Turner” or “W-T”) and Anthony P. Ashford (“Ashford”) as additional parties in connection with the defect claims.10 The Motion to Realign suggested in the then-current posture that the def ect claims among and between the various parties predominated the litigation, and it was no longer simply about payment allegedly due to Precision Foam.11 Because DSU’s defect allegations had become the heart of the litigation, and in light of the complex and confusing posture of the parties at that juncture, the parties jointly requested they be realigned to properly organize the practical posture of the parties and their claims appropriately, and to simplify the procedural posture of the matter for the court and the parties.12 The court ordered realignment of the parties on May 1, 2018, such that DSU is plaintiff and counter-defendant to the extent any counterclaims are filed against it; and Richärd+Bauer, Liberty Mutual, Thomas, Czar, Whiting-Turner, and Ashford are 7 D.I. 40; D.I. 73 ¶ 5. D.I. 73 ¶ 6. 9 D.I. 73. 10 D.I. 74 (Third Party Second Amended Complaint (“SAC”)). Other than filing a pro se Answer to the SAC, see D.I. 89, and being deposed on March 15, 2019, see D.I. 243-7, Ashford has not meaningfully participated in this action. 11 D.I. 73 ¶ 8. 12 Id. 8 3 defendants, counter-plaintiffs, and cross-claimants, where appropriate.13 On February 21, 2019, the parties consented to this m agistrate judge conducting all proceedings and entering a final order on case dispositive motions, and those motions were referred on in accordance with 28 U.S.C. § 636(c). 14 On June 11, 2019, DSU filed a Consent Motion for Leave to File Amended Complaint for the limited purpose of adding defendant Thomas to SAC Count III (Negligence) which had been named in DSU’s original negligence counterclaim and inadvertently omitted as such in the SAC. 15 DSU’s motion was granted on June 14, 2016,16 making Delaware State University’s Third Amended Complaint (“TAC”)17 its operative pleading. The TAC asserts four causes of action: Count I (Breach of Contract), Count II (Claim on the Performance Bond), Count III (Negligence), and Count IV (Unjust Enrichment).18 The co-defendants each broadly assert cross-claims against and among each other for indemnification and/or contribution. 19 Thomas also asserts claims for breach 13 So Ordered D.I. 73 Consent Motion (Docket Entry May 1, 2018); D.I. 73 at 3 (Wherefore clause). In the separate discussions of each motion, the court may generally refer to DSU as “plaintiff” and the parties advancing or opposing the particular motion collectively as “defendant(s)” and/or “movant(s).” 14 D.I. 147. 15 D.I. 180. 16 D.I. 181. 17 D.I. 180-2. 18 Id. Count I is alleged against Richärd+Bauer, Whiting-Turner, Thomas, Precision Foam, Czar, and Ashford. Id. ¶¶ 48-56. Count II is alleged against Liberty Mutual. Id. ¶¶ 57-60. Count III is alleged against Thomas, Precision Foam, Czar, and Ashford. Id. ¶¶ 61-69. Count IV is alleged against Precision Foam, Czar, and Ashford. Id. ¶¶ 70-72. 19 See D.I. 49 (PFF); D.I. 77 (R+B); D.I. 97 (W-T); D.I. 98 (Czar); D.I. 103 (TCI). 4 of contract, unjust enrichment, and breach of warranty against Precision Foam.20 Presently before the court are seven motions for summary judgment filed by DSU,21 Richärd+Bauer,22 Whiting-Turner,23 Thomas,24 Precision Foam,25 and Czar.26 Whiting-Turner and Precision Foam also filed a Joint Motion to Strike Expert Report of Thornton Tomasetti, Inc. and Mark E. Dannettel. 27 II. BACKGROUND–STIPULATED FACTS28 1. This case concerns Structural Insulated Panels or “SIPs” and their integration into an overall wall system that includes the SIPs, the design, construction and installation of the SIP connections to the building structure, and other related elements 20 D.I. 103. D.I. 211. 22 D.I. 203. 23 D.I. 208. 24 D.I. 207; D.I. 217. On July 9, 2020, DSU informed the court that it had settled its claims against TCI and Liberty Mutual, as well as TCI’s claims against DSU (the “DSU-TCI Settlement”). D.I. 255. On July 29, 2020, the court granted the voluntary dismissal of DSU’s claims against TCI and Liberty Mutual, and TCI’s claims against DSU (the “Settled Claims”). D.I. 257. “The sole effect of this order is dismissal of the Settled Claims. The action remains pending and unaffected with respect to the remaining claims.” Id. At the time of the DSU-TCI Settlement, TCI had a pending motion seeking, inter alia, summary judgment that DSU’s proposed repairs to the Panel Wall System constitute economic waste. D.I. 217. That part of TCI’s motion is denied as moot. DSU does not have a pending motion for summary judgment against TCI. 25 D.I. 205. 26 D.I. 215. 27 D.I. 201. 28 These facts are taken from the stipulated facts filed by all parties for purposes of the their respective summary judgment motions. D.I. 195 (“Stipulated Facts”). The documents referenced therein are cited as “Stip. Ex.” and designated by their deposition exhibit numbers inasmuch as all exhibits were consecutively numbered throughout the depositions. Id. at 2 n.1. The parties submitted their Joint Exhibits and Deposition Designations on October 4, 2019. See D.I. 243; D.I. 243-1 through 243-19. For consistency, citation to “Stip. Ex.” is maintained throughout the discussion of the parties’ respective motions. 21 5 (such as connectors, sealants, and the like) (collectively, the “Panel Wall System,” or “Wall System”) installed as part of constructing the OSCAR Facility, or Project, on DSU’s main campus in Dover, Delaware.29 2. This case also involves the structural design of the panel connections with the OSCAR Facility design. 3. The OSCAR Facility is a three-story building that houses classrooms, laboratories, and research facilities.30 4. The Wall System that comprises the exterior façade is comprised of composite panels consisting of the following: (a) the exterior side of the panel is stainless steel with a mirrored finish; (b) the interior side of the panel is galvanized steel that is corrugated and painted; and (c) “sandwiched” between the exterior and interior panels is rigid, expanded polystyrene or “EPS” insulating foam that is glued to the interior and exterior metal sheets with 3M® bonding material. 5. The panels are approximately 50 feet tall. 6. The Wall System is connected to the facility’s steel structure. 7. On or about January 20, 2012, DSU retained R+B as the Architect of Record for the OSCAR Facility pursuant to a contract titled AIA® Document B132™–2009, Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition. (D.I. 243-1, Stip. Ex. 47.)31 29 The building’s exterior walls consist of a combination of glass “curtain walls” and the Wall System at issue. D.I. 195 at 2 n.2. 30 See D.I. 243-5 (OSCAR Facility photographs), Photograph 1-A. 31 Throughout this opinion, all emphases are in the original document cited unless otherwise noted. 6 8. As the Architect of Record, R+B prepared the architectural drawings for the facility, which include design drawings for the Wall System. Portions of the Wall System drawings are attached as D.I. 243-1, Stip. Ex. 7, Drawing Pages A11.1 through A11.3. (See also, A11.0 through A11.8.) 9. R+B also issued Specification Section 07435 - INSULATED METAL WALL PANELS (Addendum 3, 11/14/2013) for the Wall System. (See D.I. 243-1, Stip. Ex. 3, “Specification 07435”.) 10. R+B used Permatherm, Inc. (“Permatherm”) as its basis of design for the panels, and Specification 07435 listed both Permatherm and PFF as acceptable panel manufacturers. 11. Specification 07435 provides, in pertinent part: ! Part 1, General: Construct panel system to provide for expansion and contraction of component materials without causing buckling, failure of joint seals, undue stress on fasteners, other detrimental effects to the panel system or adjacent building systems, or warping of faces of panel system. (D.I. 243-1, Stip. Ex. 3 at DSU 006176.) ! General Paragraph 1.4 – Performance Requirements: Design and construct panels to meet requirements as indicated. A. Structural and Wind load Tests: 1. Design panel composition to resist wind load mandated by code, with deflection limit of L/240. 2. No permanent damage to panels or connections when subjected to 1.5 times the design wind pressures for both inward and outward. B. Thermal Performance: 1. Panels shall produce no post manufacturing off gassing which could result in loss of future thermal resistance and 7 must have a certified Long Term R-Value (LTR) . . . . ¨ ! Submittals Paragraph 1.5.D – “Engineered Drawings and Calculations: For installed products indicated to comply with certain design loadings, include structural analysis data and design prepared by an independent third party signed and sealed by the qualified professional engineer responsible for their preparation.” ! Quality Assurance Paragraph 1.6.A – “Manufacturer’s qualifications: Company specializing in manufacturing all required aspects of insulated metal panel production. 1. No less than 10 years’ experience in the actual production of specified products. * * * * * 3. Successfully completed not less than 100 comparable projects using this system.” ! Quality Assurance Paragraph 1.6.B – “Installer’s Qualifications: Installer shall be responsible for installation of panel and support framing as specified . . . to comply with the following: Wind load engineering to comply with code requirements.” ! Quality Assurance Paragraph 1.6.D – “Mock-Up: Provide a mock-up for evaluation of surface preparation techniques, detail interfaces with other materials, corner condition, edge conditions, and application workmanship.” ! Products & Materials Paragraph 2.1.A – “Acceptable Manufacturers: a. Permatherm, Inc. b. Precision Foam Fabricators c. Or prior approved equal.” ! Paragraph 2.2.A – “Panel General Requirements: Roll-formed exterior and interior steel sheet faces laminated to panel grade Type IX expanded polystyrene (EPS) foam core . . . Insulated wall panels shall be supplied in widths . . . [as] indicated on drawings. Panel lengths shall be factory cut to meet required site dimensions.” ! Paragraph 2.2.A.1.a – “See drawings for panel thicknesses.” 8 ! Paragraph 2.3.A.1 – “Interior face of wall panels shall be clad with 26 gauge prepainted G90 galvanized steel where indicated. Smooth face finish.” ! Paragraph 2.3.B.2 – “Exterior face [indicated] to be polished stainless steel: clad on weather exposed side with 26 gauge Type 316 stainless steel with #8 polished mirror finish.” ! Paragraph 2.3.C.1 – “Metal skins shall be thermal-set to the Type IX EPS insulation. Insulated panels shall be manufactured individually laminated, insuring uniform adhesion between metal skins and EPS insulation.” ! Paragraph 2.3.D.1 – “Wall panels and ceiling panels shall consist of Type IX Expanded Polystyrene (EPS) insulation, density as indicated in drawings and as required for loading requirements of panels.” ! Paragraph 2.3.H – “Fasteners: Clips, anchoring devices, fasteners, and accessories for installation of panel system as recommended by panel manufacturer for the system specified.” ! Installation Paragraph 3.2.A – “Install in accordance with manufacturer’s instructions and industry standards.” ! Adjusting and Cleaning Paragraph 3.4.B – “Replace damaged panels and other components of work, which cannot be repaired by finish touch-up or similar minor repair.” 12. On January 12, 2012, DSU and Whiting-Turner entered into a contract titled AIA® Document C132™ – 2009, Standard Form of Agreement Between Owner and Construction Manager as Adviser, AIA® Document A232™ – 2009, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition, and Section 00730 – SUPPLEMENTARY GENERAL CONDITIONS TO THE CONTRACT (DSU Designee Tr. 12). (See D.I. 243-3, Stip. Ex. 94; D.I. 243-1, Stip. Ex. 48; and D.I. 243-3, Stip. Ex. 140, respectively.) 13. Whiting-Turner conducted a “descope meeting” with Thomas on November 9 26, 2013. 14. DSU entered into a contract with Thomas on or about December 27, 2013 titled AIA® Document A132™ – 2009, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition for the Wall System. (See D.I. 243-3, Stip. Ex. 139.) 15. On or about January 2, 2014, Thomas submitted a Performance Bond issued by Liberty Mutual for the Wall System project. (See D.I. 243-3, Stip. Ex. 139-A, AIA® Document 312-A 2010, Performance Bond, dated 12/20/2013 and 01/02/2014 transmittal letter.) 16. On or about January 15, 2014, Thomas made its initial submission of PFF’s Product Data to Whiting-Turner for review. (See D.I. 243-1, Stip. Ex. 33.) 17. On January 17, 2014, Whiting-Turner forwarded Thomas’s Submittal Number 07435-01-0 to R+B. (D.I. 243-1, Stip. Ex. 34.) 18. R+B reviewed the PFF Product Data and returned it to W hiting-Turner on January 23, 2014. (Id.) 19. The PFF product materials submittal was “approved as noted” by R+B on May 7, 2014. (D.I. 243-1, Stip. Ex. 6.) Those materials state, in part: ! Engineering Design Data, Section 2.1.1 – “Design and control of thermal movement, heat flow, water vapor transmission and air movement in environments where a high level of appearance and durability are essential. Precision Insulated Panels (hereinaf ter referred to as PIP) and liners offer systems that will satisfy these needs economically. The data contained herein should be used f or selection and identification of insulating panel systems.” ! Engineering Design Data, Section 2.1.2 – “The purpose of the design data in this bulletin is to assist the architect and/or eng ineer 10 when considering the use of the PIP. However, the responsibility for the final design is that of the architect or engineer.” ! Engineering Design Data, Section 2.6.1 – “Flatness of structural sandwich panels is affected by dimensional change of the facings. When the panel is subjected to a temperature differential, the contraction of the cold facing will cause warping of the panel. A practice of cutting the interior skin at midpoint of girt is used to relieve the stress on panels required connection to intermediate girt lines.” ! Engineering Design Data, Section 2.6.2 – Calculation for thermal expansion is provided. “Actual measured deflections are generally less than predicted due to shear strain of the core; however, the predicted deflection should be used for design. Addition of intermediate bracing, to restrain thermal flatness changes is generally not recommended.” ! Engineering Design Data, Section 2.9.1 – “Effective design of connections should provide for the structural function as well as accommodate thermal movements. In addition, the connections must prevent excessive moisture and air migration, resist heat gain and maintain acceptable appearance.” ! Engineering Design Data, Section 2.13.2 – “Installation specifications apply generally to holding freezers and holding coolers unless otherwise note[ed].” 20. On or about March 6, 2014, Czar issued a proposal to Thomas for engineering services in connection with the Wall System. (D.I. 243-3, Stip. Ex. 130.) 21. The shop drawings prepared by Ashford on Thomas’s behalf did not include the “V” grooves, or channels, (“V-Channels”) referenced in PFF’s Product Data and R+B’s construction documents. 22. On September 8, 2014, there was an email discussion regarding the absence of V-Channels, in the shop drawings submitted by Thomas. (D.I. 243-1, Stip. Ex. 44; D.I. 243-3, Stip. Ex. 129.) 23. The V-Channels were not field cut in panels when Thomas installed them. 11 24. Installation of the Wall System on the building commenced in September 2014. 25. The first batch of panels was delivered to the site on September 30, 2014. (D.I. 243-3, Stip. Ex. 124 at 2.) PARTIES’ MOTIONS Because of its impact on the parties’ motions for summary judgment, the court first discusses Whiting-Turner and Precision Foam’s Motion to Strike, and then proceeds to the parties’ motions for summary judgment. Whiting-Turner and Precision Foam’s Joint Motion to Strike Expert Report of Thornton Tomasetti, Inc. and Mark E. Dannettel Whiting-Turner and Precision Foam move pursuant to Federal Rule of Evidence 702 (“F.R.E. 702") to strike the FEDERAL RULE OF CIVIL PROCEDURE 26(b)(2) Expert Report of Thornton Tomasetti, Inc. and Mark E. Dannettel (“Thornton Tomasetti Report” or “Report”) as it pertains to claims asserted by DSU against W-T and PFF (“Motion to Strike”).32 Alternatively, they move in limine requesting the Thornton Tomasetti Report, 32 D.I. 201. Briefing on the motion is found at D.I. 202 (W-T and PFF Opening Brief); D.I. 231 (DSU Consolidated Answering Brief); and D.I. 237 (W-T and PFF Reply Brief). On January 24, 2020, TCI filed a Notice of Adoption of the Motion to Strike and the movants’ opening brief in support thereof. D.I. 251 (“Notice of Adoption”). On January 31, 2020, DSU filed a Response to the Notice of Adoption urging the court to reject TCI’s filing as untimely under the Scheduling Order or, in the alternative, deny it for the substantive reasons set forth in DSU’s original opposition. D.I. 252. Separately, DSU emphasizes the nature of the motion in its response: “[t]hough titled a ‘Motion to Strike,’ it is indisputably a Daubert motion as it seeks to excluded expert evidence based on F.R.E. 702 and Daubert v. Merrell Dow Pharm., Inc., 509 U.S. 579 (1993) and its progeny.” Id. at 1 n.1. The court does not disagree with DSU’s characterization of the motion, however, consistent with the parties’ references in briefing, the court uses “Motion to Strike” when discussing this motion. With regard to TCI’s filing, it is rejected as untimely. It is also superfluous as it does nothing more than adopt the movants’ positions without adding any substantive argument, and the court’s determination that 12 and any testimony associated therewith by Dannettel or any other witness identified as providing expert testimony on behalf of DSU, be excluded from the evidence in support of DSU’s claims against them.33 I. BACKGROUND–W-T and PFF Motion to Strike DSU’s OSCAR Facility is a three story structure with a triangular floor plan.34 The OSCAR Facility’s three sides generally face north, east, and west and are enclosed primarily by 50 ± foot tall insulated metal panels, commonly referred to as structural insulated panels (“SIPs” or “Panels”). 35 As installed on the Project, the Panels are composite, comprised of a 6 inch rigid foam core that is bonded between two metal facings.36 As specified by the Project architect of record, R+B, the Panels’ exterior facings are thin (1/64th inches), 26 gauge polished stainless steel sheets. 37 The Panels’ exterior facings make up part of the OSCAR Facility’s façade.38 The Panels’ interior facings are thin (1/64th inches) 26 gauge corrugated and painted galvanized steel.39 As designed and specified by R+B, the Panels attached to the OSCAR Facility by “gravity load connections” that “hang” the Panels from the OSCAR Facility’s third floor.40 The Panels are suspended from the OSCAR at the point of the gravity load the Report does not meet the requirements of F.R.E. 702 removes the Report’s application to all defendants. 33 D.I. 201. 34 D.I. 195 ¶ 3. 35 D.I. 202-1, Ex. A, DSU 9575-77 (photographs of OSCAR Facility); D.I. 195 ¶¶ 1-5. 36 D.I. 195 ¶ 4. 37 D.I. 243-1, Stip. Ex. 3 § 2.3.B. 38 D.I. 243-12 (George Dep.) at 43:7-15. 39 D.I. 243-1, Stip. Ex. 3 § 2.3.A. 40 D.I. 195 ¶¶ 8-9; D.I. 243-1, Stip. Ex. 7. 13 connection.41 Two “lateral connections,” one above, and one below, the gravity connections, connect the Panels to the building while allowing for some horizontal movement to control wind forces that affect the Panels. 42 As specified by R+B, the Panels served as both the exterior façade and as an insulated wall to which drywall was attached to create the interior of the OSCAR Facility.43 R+B used Permatherm as its basis of design for the panels, and Specification 07435 listed both Permatherm and PFF as acceptable panel manufacturers.44 DSU alleges design and construction defects relating to the construction of the insulated panel façade of DSU’s OSCAR Facility.45 DSU contracted with W-T to serve as the Construction Manager (“CM”) as Adviser for the Project.46 DSU contracted with TCI to furnish and install the metal panels and provide design/engineering services for the panel façade system, including all connections thereof.47 TCI, in turn, entered into a purchase order (“PO”) with PFF to procure the panels. 48 As pertinent to the Motion to Strike, DSU contends the m etal panels failed by horizontally deforming or “buckling” on the exterior skin.49 DSU sued W-T for breach of contract, and PFF for breach of contract, negligence, and unjust enrichment.50 DSU 41 D.I. 243-12 (George Dep.) at 123:2-5. D.I. 243-1, Stip. Ex. 7; D.I. 243-12 (George Dep.) at 123:10-19. 43 D.I. 243-12 (George Dep.) at 44:22-45:13. 44 D.I. 195 ¶ 10. 45 D.I. 202 at 1. 46 D.I. 195 ¶ 12. 47 D.I. 202 at 1 (citing (D.I. 195 ¶¶ 10, 14; D.I. 243-1, Stip. Exs. 3, 48; D.I. 243-3, Stip. Exs. 139, 140)). 48 Id. 49 Id. 50 Id. 42 14 retained Thornton Tomasetti, Inc. and its principal, Mark E. Dannettel (“Dannettel”), (collectively, “Thornton Tomasetti”) to issue the Report pursuant to F EDERAL RULE OF CIVIL PROCEDURE 26(B)(2) with respect to, inter alia, the alleged responsibility of various entities for the purported failures in the panels. 51 W-T and PFF maintain neither the Report and/or Dannettel meet the requirements of FEDERAL RULE OF EVIDENCE 702 and, therefore, the Motion to Strike must be granted.52 II. GOVERNING LAW–W-T and PFF Motion to Strike The admissibility of expert testimony is governed by FEDERAL RULE OF EVIDENCE 702, which provides: A witness who is qualified as an expert by knowledge, skill, experience, training, or education may testify in the form of an opinion or otherwise if: (a) the expert’s scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact in issue; (b) the testimony is based on sufficient facts or data; (c) the testimony is the product of reliable principles and methods; and (d) the expert has reliably applied the principles and methods to the facts of the case.53 In Daubert v. Merrell Dow Pharmaceuticals, Inc., the Supreme Court interpreted Rule 702 to “confide[] to the judges some gatekeeping responsibility in deciding questions of the admissibility of proffered expert testimony.”54 The Third Circuit stated 51 Id.; D.I. 243-3, Stip. Ex. 147 (Thornton Tomasetti Report). The Report was authored by Dannettel and Christopher E. Pinto, P.E. Id. 52 D.I. 202 at 2. 53 FED. R. EVID. 702 (emphasis added). 54 509 U.S. 579, 600 (1993) (Rehnquist, J., concurring in part and dissenting in part); see also Pineda v. Ford Motor Co., 520 F.3d 237, 243 (3d Cir. 2008) (Daubert 15 that Rule 702 “embodies a trilogy of restrictions on expert testimony: qualification, reliability and fit.”55 The question of whether an expert’s testimony is admissible based on his qualifications, reliability, and fit is committed to the court’s discretion. 56 The party proffering the expert bears the burden of demonstrating that the expert’s opinion is reliable and fits the facts by a preponderance of the evidence.57 III. DISCUSSION–W-T and PFF Motion to Strike A. Positions of the Parties–W-T and PFF Motion to Strike58 1. W-T and PFF The movants contend Dannettel is not qualified to serve as an expert as relates to Whiting-Turner or Precision Foam, and, even if found to be qualified, he fails to meet any of the required elements because: (1) Dannettel is not qualified to speak on the contractual obligations or responsibilities of Whiting-Turner or Precision Foam; (2) his opinion is not based on sufficient facts or data; and (3) his opinion is inherently unreliable, and, therefore, inadmissible.59 2. DSU imposes upon the court a duty to act as a “gatekeeper” where the court must “ensure that ‘any and all expert testimony or evidence is not only relevant, but also reliable.’”) (quoting Kannankeril v. Terminix Int'l, Inc., 128 F.3d 802, 806 (3d Cir. 1997)); Sonos, Inc. v. D & M Holdings Inc., 297 F. Supp. 3d 501, 507 (D. Del. 2017) (W hen an expert’s testimony is challenged, “the district court has a ‘basic gatekeeping obligation’ to ensure that the expert’s testimony ‘is not only relevant, but reliable.’”) (quoting Kumho Tire Co. v. Carmichael, 526 U.S. 137, 147 (1999)). 55 Estate of Schneider v. Fried, 320 F.3d 396, 404 (3d Cir. 2003). 56 In re Paoli R.R. Yard PCB Litig., 35 F.3d 717, 749 (3d Cir. 1994). 57 Oddi v. Ford Motor Co., 234 F.3d 136, 144 (3d Cir. 2000). 58 The parties’ positions for each motion are taken from the argument summary, or argument sections of their respective opening briefs. 59 D.I. 202 at 2, 16-20. 16 DSU argues the Motion to Strike should be denied beca use: (1) Dannettel’s extensive experience as a façade consultant and façade contractor qualify him to testify on defendants’ obligations and responsibilities; (2) Dannettel’s testimony is based on sufficient facts and data; and (3) Dannettel’s testimony is the product of reliable principles and methods that were properly applied to the facts of this case.60 B. Analysis–W-T and PFF Motion to Strike 1. Whether Dannettel is Qualified to Opine on the Contractual Obligations or Responsibilities of WhitingTurner or Precision Foam “Qualification refers to the requirement that the witness possess specialized expertise.”61 The Third Circuit has “‘interpreted [the qualification] requirement liberally,’ holding that ‘a broad range of knowledge, skills, and training qualify an expert as such,’”62 but “ha[s] not pursued a policy of qualifying any proffered witness as an expert.”63 “The basis of this specialized knowledge ‘can be practical experience as well as academic training and credentials.’”64 The Third Circuit has “eschewed imposing overly rigorous requirements of expertise and ha[s] been satisfied with more 60 D.I. 231 at 24-34. Estate of Schneider, 320 F.3d at 404. 62 Calhoun v. Yamaha Motor Corp., U.S.A., 350 F.3d 316, 321 (3d Cir. 2003) (quoting Paoli, 35 F.3d at 741). 63 Waldorf v. Shuta, 142 F.3d 601, 625 (3d Cir. 1998) (quoting American Tech. Resources v. United States, 893 F.2d 651, 656 (3d Cir. 1990)). 64 Waldorf v. Shuta, 142 F.3d 601, 625 (3d Cir. 1998) (quoting Hammond v. Int’l Harvester Co., 691 F.2d 646, 653 (3d Cir. 1982)); see also id. (“[I]n considering the qualification of witnesses as experts, we stress that ordinarily an otherwise qualified witness is not disqualified merely because of a lack of academic training.”) (citing Hammond, 691 F.2d at 653 (determining that a witness could testify as an expert regarding a rollover protective structure on a tractor even though he did not have a formal degree in engineering or physics, but did have experience in the field)). 61 17 generalized qualifications.”65 “[I]t is not necessary that the expert have expertise in the precise technology” at issue,66 and “[a]n expert should not be excluded ‘simply because the trial court does not deem the proposed expert to be the best qualified or because the proposed expert does not have the specialization that the court considers most appropriate.’”67 DSU contends Dannettel’s education and general experience as a façade consultant demonstrate he is qualified to offer expert testimony in this case.68 The movants counter that Dannettel does not have the required specialized knowledge as it relates to W-T and PFF because he has never served as, or worked for, a construction manager (“CM”), has no prior experience with similar SIPs, lacks any education or training related to the duties of a CM or SIP panel manufacturer, and does not know the difference between a CM and a general contractor.69 The movants also argue that because Dannettel is not a licensed architect, is not registered as a professional engineer, and is not an engineer of any kind, he is precluded from testifying as an expert in Delaware.70 Addressing the last argument first, the movants rely on two unreported cases from the Superior Court of Delaware that discuss the qualifications required for an 65 Paoli, 35 F.3d at 741 (citations omitted). Sonos, 297 F. Supp. 3d at 510 (citing Paoli, 35 F.3d at 741); see, e.g., Knight v. Otis Elevator Co., 596 F.2d 84, 87-88 (3d Cir. 1979) (holding that an expert could testify that unguarded elevator buttons constituted a design defect despite expert's lack of specific background in design and manufacture of elevators). 67 Sonos, 297 F. Supp. 3d at 508 (quoting Pineda v. Ford Motor Co., 520 F.3d 237, 244 (3d Cir. 2008)). 68 D.I. 231 at 26. 69 D.I. 202 at 16. 70 Id. at 16-17. 66 18 expert to testify in Delaware state court.71 Those cases considered whether a proffered expert who was not licensed in the field at issue was precluded from offering expert testimony in view of certain Delaware state statutory licensing/registration requirements.72 While acknowledging those requirements, the Talley court also stated “[t]he Act was never intended to override the Court's gatekeeping function under D.R.E. 702 or affect the Court's analysis under Daubert.”73 This court has also recently noted that, in contrast to certain parties recognized by Delaware as subject to professional negligence causes of action, e.g., architects and engineers, that require a license to practice, “[e]xpert witnesses . . . are not required to hold a license to offer opinions or testimony.”74 Given the Third Circuit’s clear statement that specialized knowledge can be found without “academic training and credentials,”75 and this court’s recent statement in Verition, the court rejects the argument Dannettel is precluded from testifying because he is not a licensed architect or engineer. DSU is ultimately unable, however, to demonstrate Dannettel has the required specialized knowledge to offer his proffered testimony. DSU suggests the movants “overlook the fact that [the Report] was co-authored by Christopher E. Pinto, P.E., who 71 Id. (citing Talley v. Tri-State Waste Solutions, Inc., C.A. No. 05C-08-311-PLA, 2007 WL 1816356 (Del. Super. June 25, 2007); Burkett-Woods v. Haines, C.A. No. 02C-10-263-CLS, 2006 WL 1579770 (Del. Super. May 2, 2006)). 72 See Talley, 2007 WL 1816356, at *3; Burkett-Woods, 2006 WL 1579770, at *3. 73 Talley, 2007 WL 1816356, at *3. Talley cited the same section of the Delaware code the movants cite. See D.I. 202 at 17 n.16; see also Burkett-Woods, 2006 WL 1579770, at *1 (“D.R.E. 702 is identical to its f ederal counterpart, F.R.E. 702.”). 74 Verition Partners Master Fund, Ltd. v. Cornell, C.A. No. 19-377-CFC, 2020 WL 2917258, at *4 (D. Del. June 3, 2020) (citations om itted). 75 Hammond, 691 F.2d at 653. 19 is a licenced engineer in Delaware (among other states), supported by a team of three other Thornton Tomasetti engineers.”76 Dannettel is the only DSU testifying expert witness.77 His qualifications are not implicated by the qualifications of others involved with the Report. The suggestion that Dannettel can somehow rely upon the credentials of others associated with the Report to establish his qualification is provided without support and rejected. 78 DSU also argues Dannettel’s specialized knowledge is based on his education and extensive experience as a façade consultant. 79 The court first notes Dannettel’s degrees are in architecture rather than engineering. DSU’ argument that Dannettel’s experience as a façade consultant and façade contractor qualifies him to testify on defendants’ obligations and responsibilities relies almost exclusively on Dannettel’s September 20, 2019 affidavit which comprises 253 paragraphs spanning forty-six pages, and was submitted contemporaneously with DSU’s consolidated answering brief.80 The movants object to DSU’s reliance on that affidavit because it was not included in the Thornton Tomasetti Report as mandated by FED. R. CIV. P. 26(a)(2), or 76 D.I. 231 at 26. See D.I. 202 at 3 (citing D.I. 202-1, Ex. D (Kelly e-mail dated 04/02/2019 and D. Rea e-mail dated 04/04/2019)). 78 See, e.g., Talley, 2007 WL 1816356, at *3 (“The licensing status of [two other] . . . engineers employed by the same firm as [the proffered expert], has no impact on the Court’s analysis of [the proffered expert’s] qualifications.”). 79 Dannettel received a Bachelor of Science Degree in Architecture from the University of Maryland and a Master of Science Degree in Architecture from Arizona State University, is a principal of the international engineering firm Thornton Tomasetti, is a member of the American Society of Civil Engineering and the American Institute of Architects (“AIA”), author of numerous technical articles in the industry, and has taught and lectured across the country and abroad. See D.I. 243-3, Stip. Ex. 147 (Dannettel’s curriculum vitae attached to Report). 80 See D.I. 231-1, App’x A (“Dannettel Affidavit”). 77 20 disclosed in Dannettel’s two days of deposition testimony, despite repeated questioning about his relevant qualifications and experiences.81 Rule 26(a)(2) requires a testifying expert’s report contain, inter alia, “the witness’s qualifications . . . .”82 The scheduling order provided for expert discovery to close August 23, 2019. 83 The Thornton Tomasetti Report is dated March 1, 2019, 84 and Dannettel provided deposition testimony on April 15 and May 31, 2019.85 Unfortunately, other than stating their objection to DSU’s reliance on the affidavit, the movants do not explicitly ask the court to disregard the affidavit or provide case citation upon which the court could rely to do so. Had they done so, the court would have seriously considered the request because Dannettel’s qualifications go to the heart of the Rule 702 analysis. For instance, in Doe v. Luzerne County, the court declined to strike expert affidavits for failure to comply with Rule 26(a)(2)(B)(iii) & (vi) (inclusion of exhibits used to support opinions, and statement of compensation, respectively) with the court finding failure to fully comply with the rule did not prejudice the plaintiff “because the summary judgment motion can be decided without this information,” and exclusion based on “remedial oversights would be an extreme and unwarranted sanction,” 86 Here, the failure to include the information in Dannettel’s Report now offered via his affidavit goes to the heart of the issue of his qualifications to testify as an expert. Nevertheless, the 81 D.I. 237 at 1-2 (citing D.I. 243-9 (Dannettel Dep. Vol. I) at 64:4-66:9; 129:22-130:1; 135:7-21; D.I. 243-10 (Dannettel Dep. Vol. II) at 14:10-18:10). 82 FED. R. CIV. P. 26(a)(2)(B)(iv). 83 D.I. 146 ¶ 4; D.I. 169; D.I. 177. 84 D.I. 243-3, Stip. Ex. 147 at 1. 85 D.I. 243-9; D.I. 243-10 (Dannettel Dep. Vols. I and II). 86 C.A. No. 3:08-cv-1155, 2010 WL 2245578, at *4 (M.D. Pa. June 1, 2010). 21 court determines Dannettel’s affidavit does not demonstrate he is qualified to offer his proffered testimony. DSU spends several pages of briefing reciting Dannettel’s “extensive experience working at architecture firms, an international engineering firm and a façade contractor.”87 Nowhere, however does DSU tie Dannettel’s impressive resume to the specialized knowledge required to offer his proffered testimony. The movants present unrebutted evidence suggesting he does not. Dannettel acknowledges he has never served as, worked for, or been responsible for overseeing, a CM as Advisor, i.e., the position W-T held on the Project.88 He testified to not knowing if he ever worked on a project where there was a CM as Advisor, “if there is a construction manager on the project, the distinction of whether that’s an adviser or a standard construction manager, would not be made to someone like me so I wouldn’t know.”89 Dannettel also stated he did not know the difference between the positions of a general contractor, or CM at Risk, and a CM as Adviser.90 DSU does not specifically address Dannettel’s knowledge of the roles played by the various entity-positions. His apparent lack knowledge indicates the absence of his specialized knowledge. 87 See D.I. 231 at 26-31. See D.I. 243-9 (Dannettel Dep. Vol. I) at 64:25-65:25. 89 Id. at 66:1-9. 90 Id. at 137:7-12. According to the movants, a CM at Risk or General Contractor enters into a contract with an owner to deliver a final and finished product, contracts directly all trades necessary to complete the final product, and is, therefore, responsible for the performance of the trade contractors that actually perform the work. D.I. 202 at 13 n.13 (citing D.I. 202-1, Exs. E, F; id., Ex. G (George Aff.) ¶¶ 4-6). 88 22 The movants also contend that, prior to the OSCAR Facility, Dannettel’s lack of work on a project that specified, used, or contained a SIP panel system further demonstrates he is unqualified to testify here.91 The court agrees. Dannettel testified he “never used these panels before. I‘ve never been involved in a project using these panels before.”92 He also has no special training in the use or design of SIP panels or systems,93 no experience with SIP panel manufacturing, and has never worked for a panel manufacturer like PFF.94 DSU’s surprising response is not to counter, but rather emphasize, Dannettel’s testimony that he lacks experience with the panels at issue. So I haven’t done SIP panels and SIP panels are not normally used for the type of commercial construction that I normally engage with, which would include a building like this, but my suspicion is that because SIP panels are used for kind of a lower grade of construction like warehouses, that would never have a façade consultant involved with a cheap job like that, like for a warehouse, that would really just be the architect and the engineer. So I’m suspecting that the common practice is that the design team just fully engineers and details that based on manufacturer’s information, and the installer is really just an installer, but I don’t know that for a fact if that is standard practice for the SIPs.95 Based on Dannettel’s lack of experience with SIPs, and suppositions as to their use, DSU remarkably proclaims “Dannettel is not experienced in these particular panels because they are not used in high-end architectural applications, but in warehouses 91 D.I. 202 at 14 (citing D.I. 243-9 (Dannettel Dep. Vol. I) at 64:4–11; D.I. 243-10 (Dannettel Dep. Vol. II) at 14:10–16, 15:10–13). 92 D.I. 243-9 (Dannettel Dep. Vol. I) at 129:22-130:1. 93 D.I. 243-10 (Dannettel Dep. Vol. II) at 14:17-23. 94 Id. at 15:24-16:2, 16:23-25. 95 D.I. 231 at 32-33 (emphasis added). 23 and industrial freezer units.”96 Thus, the court determines Dannettel is not qualified to opine as to defendants’ liability. This determination is sufficient to grant the Motion to Strike. The court will, however, discuss DSU’s failure to meet its burden of demonstrating the additional Rule 702 restrictions on expert testimony. 2. Whether Dannettel’s Opinion is Based on Sufficient Facts or Data The movants assert Dannettel’s opinion is not based on suf ficient facts or data. They do not take issue with the Report’s identification that the cause of the panel-failure resulted from the panels being restrained in a way that failed to allow them to expand under the heat of the sun, and that the connections are the cause of that restraint.97 Instead, they argue Dannettel’s assignment of responsibility for that failure lacks a basis in science or his experience.98 The movants state that in assigning responsibility to PFF for the alleged panel failures, Dannettel did not rely on the contracts, and he did not perf orm any forensic or destructive testing, or product analysis, on the PFF panels. 99 They contend Dannettel was unable to identify any product defect that caused the alleged panel failures.100 The 96 Id. at 33 (emphasis added). D.I. 202 at 17. 98 Id. 99 Id. (citing D.I. 243-10 (Dannettel Dep. Vol. II) at 28:12-23; 56:7-10). T he movants suggest, and DSU does not argue otherwise, that the contracts/purchase orders are the source of any responsibilities they had to DSU and TCI. D.I. 237 at 8 n.8. 100 D.I. 202 at 17. 97 24 movants conclude that because Dannettel did not conduct any product analysis, combined with his purported lack of education, training, or experience in working with a SIP system or SIP manufacturing, that his opinions with respect to PFF are mere conjecture.101 DSU provides very little in support of this requirement. In less than one page of argument, it merely states the Report and Dannettel’s testimony demonstrates, “Thornton Tomasetti engaged in a thorough cause and origin analysis of the failure of the Precision Foam panels.”102 The extent of that argument is as follows: At Thornton Tomasetti’s direction, Intertek conducted a thermal study for a period of 14 days in July 2018, using thermocouple sensors installed on the stainless steel facings of the panels throughout the exterior and interior of the building. Thornton Tomasetti then conducted an extensive engineering analysis of the Precision Foam composite panels to determine the cause and origin of the failure. This analysis included extensive computer modeling to assess various stresses the panels are subject to including solar exposure, thermal variations, and wind loads. Thornton Tomasetti also engaged in a thorough review of the design, engineering, and construction of the OSCAR Facility contained in documents produced by all parties. Based on the results of extensive independent engineering analysis, Thornton Tomasetti determined the panels were failing due to the effect of thermal loads. There was no need to conduct material testing as Thornton Tomasetti determined the cause and origin of the panel failure.103 As the movants note, DSU “does not provide a record citation for these enumerated studies and analysis[.]”104 The court’s review of the Report reveals Intertek conducted a fourteen-day thermal study in July 2018, using thermocouple sensors 101 Id. at 17-18. D.I. 231 at 33 (emphasis added). 103 Id. at 33-34. 104 D.I. 237 at 5 n.6. 102 25 installed on the stainless steel facings of the panels throughout the exterior and interior of the building.105 The only “studies” Thornton Tomasetti performed of the PFF panels to determine the cause and origin of the failure, were: Element Analysis to determine the stresses in the Panels’ stainless steel as attached to the OSCAR Building caused by differential temperatures; and three analyses to determine the stresses in the Panels’ stainless steel facings due to differential temperature, but including relief-notches (V-Channels).106 As the movants indicate, however, Dannettel’s testimony, shows that neither he nor Thornton Tomasetti: (1) tested how or to what extent making the V-Channels might lead to structural failures in the panels; 107 (2) analyzed how the V-Channels could challenge the panels’ abilities to support their own weight;108 or (3) investigated either the beneficial or detrimental effects of making the VChannels in the panels at places other than the second and third f loor connections. 109 The movants also indicate neither DSU nor Thornton Tomasetti produced the electronic data and models that were requested to be produced in the Finite Element Analysis.110 As the movants note, “there is not a lot of dispute” that the panels were failing due to the effect of thermal loads111 and the court finds DSU’s mere statement “[t]here was no need to conduct material testing as Thornton Tomasetti determined the cause 105 See D.I. 243-3, Stip. Ex. 147 at 13-14 § 3.1.5, 18 § 3.2.1; id., App. C (Interteck Thermal Observation Report). 106 Id. at 19-21 § 3.2.4 (Engineering Analysis of Composite Panel). 107 D.I. 243-9 (Dep. Tr. Dannettel, Vol. I) at 86:14-88:7. 108 Id. at 88:8-91:5. 109 Id. at 86:14-88:7. 110 D.I. 237 at 5-6 n.6. 111 Id. 26 and origin of the cause and origin of the panel failure”112 unpersuasive. The court agrees with the movants that the Report is not based on sufficient facts or data to support Dannettel’s opinion “assigning responsibility to every company involved in any way with the panels.” 113 The movants also contend Dannettel’s conclusion that W -T contributed to the panel failures is deficient as he was unable to cite any supporting facts or data.114 W-T maintains its obligations to DSU are defined by its contract, but Dannettel testified that though he read the contracts at issue, he did not rely upon them in assigning responsibility, thereby creating responsibilities having contractual bases. 115 DSU acknowledges the movants’ argument that Dannettel did not rely on any parties’ contract in assigning liability, but states that lack of reliance does not show his Report and testimony were not based on sufficient facts and data because Thornton Tomasetti engaged in the tests and analysis discussed above.116 The court agrees with the movants that Dannettel’s opinion that defendants’ failures may have contributed to the Panel’s buckling never specifically states how 112 D.I. 231 at 34. DSU also defends the failure to conduct any forensic or destructive testing of PFF’s panel’s based on the movants failure to reference the expert opinion of any other parties’ expert supporting the argument that such testing is necessary and/or specifically pointing to what testing or opinion of PFF’s expert did, or did not, conduct or offer, as well as W-T’s adopting the opinion of others in leu of designating its own expert. Id. at 36-37. The court does not understand the actions or opinions of other experts in this case as having a determinative impact on the court’s analysis as to the sufficiency of Dannettel’s Report under a Rule 702. DSU has the burden of establishing its Report’s compliance with Rule 702. 113 D.I. 202 at 17; D.I. 237 at 6 (emphasis added). 114 D.I. 202 at 17. 115 Id. (citing D.I. 243-9 (Dannettel Dep. Vol. I) at 41:23-42:6; 44:5-16). 116 D.I. 231 at 33 (citing D.I. 202 at 17-18). 27 those failures fell below the standard of care applicable to any defendant, including W-T and PFF, or what those standards of care are.117 Despite DSU’s contention that Dannettel “did opine that [all] Defendants breached various standards of care and duties governing their performance,”118 and citation to several pages of testimony by Dannettel in support, 119 the court rejects the sufficiency of that testimony. DSU acknowledges the Report does not use the words “standard of care” with regard to any defendant’s purported failures, but relies on this court’s opinion in McCuster v. Surgical Monitoring Associates, Inc. to argue the failure to use those “magic words” is not necessarily fatal to an expert’s opinion.120 That opinion is not persuasive based on the evidence presented here. The court disagrees with DSU’s argument that McCuster is analogous to this case. 121 In rejecting the defendant’s argument that its “conduct only ‘possibly’ could have caused the injury at issue,” the court stated that, although the expert did not use the “magic words” “standard of care,” she specifically testified the doctor’s error was “the only possible explanation” for the plaintiff-patient’s injuries,122 and that the doctor made “technical errors,” which the expert equated to a breach of the standard of care.123 As movants stress, Dannettel’s Report and deposition testimony, and affidavit, contain no similar assertion that 117 D.I. 202 at 9 (emphasis added). D.I. 231 at 15-16 (citing D.I. 243-3, Stip. Ex. 147 at 23-27 §§ 4.0-4.3) (emphasis added). 119 Id. at 18-23 (specifically referencing PFF, W-T, and R+B). 120 See id. at 16-18 (citing McCuster v. Surgical Monitoring Assocs., Inc., C.A. No. 01-891-KAJ, 2005 WL 348307 (D. Del. Feb. 7, 2005)). 121 Id. at 16 (citing McCuster, 2005 WL 348307, at *4). 122 McCuster, 2005 WL 348307, at *5 (emphasis added). 123 Id. at *5 and n.11. 118 28 defendants’ alleged “failures” or “responsibilities” were the “only explanation”; they were merely possible proximate causes of the Panel defects.124 The court concludes, therefore, DSU fails to meet its burden to show the Report and Dannettel’s opinion are based on suf ficient facts or data. 3. Whether Dannettel’s Opinion is Product of a Reliable Methodology. The movants assert Dannettel’s opinion as to their liability is unreliable and fails to meet the Daubert standard because, in arriving at his opinions, Dannettel and the Report do not state that either W -T or PFF’s acts or omissions conclusively, or within any reasonable degree of certainty, actually caused the alleged defects.125 They also reiterate that neither Dannettel’s Report nor testimony assign any responsibility to W-T or PFF for failing to meet contractual obligations, or articulate what the standard is for the CM Advisers or a panel manufacturer’s alleged duty of care, or that W-T or PFF did not meet that duty.126 An expert’s opinion is typically reliable if it is ‘“based on the ‘methods and procedures of science’ rather than on ‘subjective belief or unsupported speculation’; the expert must have ‘good grounds for his or her belief.’”127 The purpose of this reliability requirement “is to make certain that an expert, whether basing testimony upon professional studies or personal experience, employs in the courtroom the same level 124 D.I. 237 at 7 and n.7. D.I. 202 at 19. 126 Id. 127 Izumi Prods. Co. v. Koninklijke Philips Elecs. NV, 315 F. Supp. 2d 589, 600 (D. Del. 2004). 125 29 of intellectual rigor that characterizes the practice of an expert in the field.”128 As a gatekeeper, the “district court must examine the expert's conclusions in order to determine whether they could reliably follow from the facts known to the expert and the methodology used.”129 “[N]othing in either Daubert or the [F.R.E.] requires a district court to admit opinion evidence that is connected to existing data only by the ipse dixit . . . of the expert. A court may conclude that there is simply too great an analytical gap between the data and the opinion prof fered.”130 The Third Circuit considers the following non-exhaustive factors when evaluating the reliability of a particular methodology: (1) whether a method consists of a testable hypothesis; (2) whether the method has been subject to peer review; (3) the known or potential rate of error; (4) the existence and maintenance of standards controlling the technique’s operation; (5) whether the method is generally accepted; (6) the relationship of the technique to methods which have been established to be reliable; (7) the qualifications of the expert witness testifying based on the methodology; and (8) the non-judicial uses to which the method has been put. 131 “When the methodology is sound, and the evidence relied upon sufficiently related to the case at hand, disputes about the deg ree of relevance or accuracy (above this minimum threshold) may go to the testimony’s weight, but not its admissibility.”132 Indeed, “in most cases, objections to the inadequacies of a study are more 128 Kumho Tire Co., Ltd. v. Carmichael, 526 U.S. 137, 152 (1999). Heller v. Shaw Indus., Inc., 167 F.3d 146, 153 (3d Cir. 1999). 130 Gen. Elec. Co. v. Joiner, 522 U.S. 136, 146 (1997). 131 Hologic, Inc. v. Minerva Surgical, Inc., 325 F. Supp. 3d 507, 520 (D. Del. 2018) (citation omitted). 132 Id. at 521 (quoting i4i Ltd. P’ship v. Microsoft Corp., 598 F.3d 831, 852 (Fed. Cir. 2010), aff’d, 564 U.S. 91 (2011)). 129 30 appropriately considered an objection going to the weight of the evidence rather than its admissibility.”133 DSU cited the above block-quoted language from Hologic listing factors considered when a court evaluates the reliability of a particular methodology,134 but did not discuss them other than to state: “Dannettel applied standard m ethods to conduct an extensive engineering analysis of the Precision Foam composite panels to determine the cause and origin of their failure. Additionally, Mr. Dannettel thoroughly reviewed all architectural, structural, and design drawings, Precision Foam’s Product Data, email correspondences throughout the project and technical standards.” 135 DSU then quotes sections of the Report listing conclusions with respect to W-T and PFF.136 Having discussed the insufficiency of the Dannettel’s Report and testimony to meet the facts and data requirement, including the standard of care applicable to the movants’ respective contractual obligations and proximate cause of their actions with respect to the panel failures, the court likewise determines Dannettel’s Report and testimony are not the product of a reliable methodology. The party proffering the expert bears the burden of demonstrating that the expert’s opinion is reliable and fits the facts by a preponderance of the evidence.137 The court finds DSU fails to meet that burden with respect to each of the Rule 702 requirements. 133 Hemmings v. Tidyman’s Inc., 285 F.3d 1174, 1188 (9th Cir. 2002). See D.I. 231 at 34. 135 Id. at 35. 136 Id. at 35-36. 137 Oddi v. Ford Motor Co., 234 F.3d 136, 144 (3d Cir. 2000). 134 31 IV. CONCLUSION–W-T and PFF Motion to Strike For the reasons discussed above, The Whiting-Turner Contracting Company and Precision Foam Fabricators, Inc.’s Joint Motion to Strike Expert Report of Thornton Tomasetti, Inc. and Mark E. Dannettel (D.I. 201) is GRANTED. Parties’ Motions for Summary Judgment Because of the overlapping nature of the issues and arguments between and among the parties’ motions for summary judgment, the court decides the motions in separate sections, grouping motions that lend themselves to consolidated analysis to the extent possible. The court begins with a section discussing DSU, W-T, and R+B’s cross-motions for summary judgment on DSU’s breach of contract against those two defendants. Next, the court addresses the summary judgment motions of Czar, TCI, and R+B. The final section resolves PFF’s motion for summary judgment on claims alleged against it by DSU, followed by PFF and TCI’s cross-motions on TCI’s breach of contract claim against PFF, and on the discrete issue of alleged damages relating to the first set of panels PFF produced and delivered. That section concludes with the court’s determination of PFF’s motion for summary judgment on TCI’s remaining claims against PFF. As will become apparent, despite attempting to address common issues in each section of the opinion, there are instances of overlap within, and among, the sections. Governing Law–Parties’ Motions for Summary Judgment A grant of summary judgment pursuant to F ED. R. CIV. P. 56 is appropriate if materials on the record, such a deposition, docum ents, electronically stored 32 information, admissions, interrogatory answers, affidavits and other like evidence show that there is no genuine issue as to any material fact, and the moving party is entitled to judgment as a matter of law.138 The movant bears the burden of establishing the lack of a genuinely disputed material fact by demonstrating “that there is an absence of evidence to support the nonmoving party’s case.”139 “Facts that could alter the outcome are ‘material,’ and disputes are ‘genuine’ if evidence exists from which a rational person could conclude that the position of the person with the burden of proof on the disputed issue is correct.”140 “Where the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there is no genuine issue for trial.”141 This standard does not change because there are cross-motions for summary judgment.142 Cross-motions for summary judgment: are no more than a claim by each side that it alone is entitled to summary judgment, and the making of such inherently contradictory claims does not constitute an agreement that if one is rejected the other is necessarily justified or that the losing party waives judicial consideration and determination whether genuine issues of material fact exist.143 “The filing of cross-motions for summary judgment does not require the court to grant summary judgment for either party.”144 138 FED. R. CIV. P. 56 (a) and (c). Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986). 140 Horowitz v. Fed. Kemper Life Assurance Co., 57 F.3d 300, 302 n.1 (3d Cir.1995) (internal citations omitted). 141 Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986) (internal quotations omitted). 142 Appelmans v. City of Philadelphia, 826 F.2d 214, 216 (3d Cir. 1987). 143 Rains v. Cascade Indus., Inc., 402 F.2d 241, 245 (3d Cir. 1968). 144 Krupa v. New Castle County, 732 F. Supp. 497, 505 (D. Del. 1990). 139 33 Delaware State University’s Motion for Partial Summary Judgment Whiting-Turner Contracting Co.’s Motion for Summary Judgment Richärd+Bauer, LLC’s Motion for Summary Judgment DSU moves for summary judgment in its favor on its breach of contract claim against R+B and W-T.145 W-T moves for summary judgment in its favor on DSU’s breach of contract claim against W-T, and/or to limit DSU’s damages.146 R+B moves for summary judgment in its favor on DSU’s breach of contract claim against R+B.147 I. BACKGROUND–DSU, W-T, and R+B Cross-Motions for Summary Judgment on DSU’s Count I (Breach of Contract) DSU’s breach of contract claim against R+B and W-T alleges breaches of various provisions of defendants’ respective contracts with DSU related to the Project. As described above, DSU contracted with R+B to serve as the Architect for the Project, and with W-T to serve as the Construction Manager (“CM”) as Adviser.148 Each contract required, inter alia, that W-T and R+B report errors, omissions, defects or deficiencies in the work to DSU as the Owner.149 DSU alleges both defendants 145 D.I. 211 (Delaware State University Motion for Partial Summary Judgment). Briefing on the motion is found at D.I. 213 (DSU Opening Brief); D.I. 226 (R+B Answering Brief); D.I. 229 (W-T Answering Brief); and, D.I. 236 (DSU Consolidated Reply Brief). 146 D.I. 208 (Whiting-Turner Contracting Co. Motion for Summary Judgment). Briefing on the motion is found at D.I. 210 (W-T Opening Brief); D.I. 231 (DSU Consolidated Answering Brief); and D.I. 239 (W-T Reply Brief). 147 D.I. 203 (Richärd+Bauer, LLC Motion for Summary Judgment). Briefing on the motion is found at D.I. 204 (R+B Opening Brief); D.I. 231 (DSU Consolidated Answering Brief); and, D.I. 233 (R+B Reply Brief). R+B’s motion also seeks summary judgment in its favor and against all other defendants on all cross-claims against R+B. The parties’ arguments on those claims are addressed elsewhere in this opinion. 148 D.I. 195, Stip. Fact 7; id. Stip. Fact 12. 149 D.I. 213 at 1. 34 breached their contracts by failing to meet their respective reporting requirements.150 W-T and R+B contend DSU’s breach of contract claim fails due to the lack of expert testimony showing they breached their respective professional standards of care and/or the evidence shows each fulfilled their contractual obligations, or that questions of fact preclude summary judgment in favor of DSU.151 The specific contracts, documents, and provisions relevant to the parties’ motions follow. On R+B January 20, 2012, DSU and R+B entered into a contract titled AIA® Document B132™–2009, Standard Form of Agreement Between Owner and Architect, Construction Manager as Advisor Edition) (“DSU-R+B Contract”).152 Pursuant to its contract, R+B prepared the Design Drawings for the Panel Wall System designated as “100% Construction Documents.”153 R+B also prepared the specification for the Panel Wall System, entitled “Specification 07435–INSULATED METAL WALL PANELS” (Addendum 3, 11/14/2013) (“Specification 07435").154 Section 1.6.A of Specification 07435 requires that the approved manufacturers possess certain qualifications and experience. Manufacturer’s Qualifications: Company specializing in manufacturing of all required aspects of insulated metal panel production. 1. No less than 10 years’ experience in the actual production of specified products, 150 Id. D.I. 210; D.I. 229; D.I. 204; D.I. 226. 152 D.I. 195, Stip. Fact 7; D.I. 243-1, Stip. Ex. 47 (R+B Contract). 153 D.I. 243-1, Stip. Ex. 7 (Design Drawings A11.1 through A11.3.). 154 Id., Stip. Ex. 3. 151 35 2. Third party certification of Quality Control program and materials utilized, in compliance with rigid factory guidelines, which includes quarterly unannounced inspections by independent testing laboratories, capable of providing reports directly to code authority. 3. Successfully completed not less than 100 comparable scale projects using this system. 4. Company specializing in manufacturing factory continuous lamination of insulated metal panels with a minimum documented experience of ten years. 5. Company specializing in on site manufacturing rigid foam insulation for the purpose of insulated metal panels with a minimum documented experience of ten years.155 Provisions of the DSU-R+B Contract relevant to the parties’ motions include the following: R+B’s contract required it to oversee the services provided by other contractors, and to coordinate with those contractors and DSU as the Owner. Section 2.3 provides: The Architect shall provide its services in conjunction with the services of a Construction Manager as described in AlA Document C132 TM–2009, Standard Form of Agreement Between Owner and Construction Manager. The Architect shall not be responsible for actions taken by the Construction Manager.156 Pursuant to § 3.1.2: The Architect shall coordinate its services with those services provided by the Owner, the Construction Manager and the Owner’s other consultants. The Architect shall be entitled to rely on the accuracy and completeness of services and information furnished by the Owner, the Construction Manager, and the Owner’s other consultants. The Architect shall provide 155 156 Id., Stip. Ex. 3 at DSU_006179-80. Id., Stip. Ex. 47 § 2.3. 36 prompt written notice to the Owner if the Architect becomes aware of any error, omission or inconsistency in such services or information.157 DSU argues that although § 3.1.2 entitles R+B to rely on the accuracy of information provided by others, it is required to report known errors, omissions, and deficiencies in the work or submittals to DSU.158 R+B was required to provide “construction phase services,” including conducting periodic site visits, and keeping DSU as Owner reasonably informed about the quality and progress of the Work. Section 3.6.2.1 provides: The Architect shall visit the site at intervals appropriate to the stage of construction . . . to become generally familiar with the progress and quality of the portion of the Work completed, and to determine, in general, if the Work observed is being performed in a manner indicating that the Work, when fully completed, will be in accordance with the Contract Documents. . . . On the basis of the site visits, the Architect shall keep the Owner reasonably informed about the progress and quality of the portion of the Work completed, and report to the Owner and the Construction Manager (1) known deviations from the Contract Documents and from the most recent construction schedule, and (2) defects and deficiencies observed in the Work.159 DSU states R+B was required to review all submittals, including engineering submittals made by other contractors under any so-called “performance specifications.”160 157 Id., Stip. Ex. 47 § 3.1.2 (emphasis added); see also id., Stip. Ex. 47 § 3.1.1 (“The Architect shall manage the Architect’s services, consult with the Owner and the Construction Manager, research applicable design criteria, attend Project meetings, communicate with members of the Project team and report progress to the Owner.”). 158 D.I. 213 at 4. 159 D.I. 243-1, Stip. Ex. 47 § 3.6.2.1. 160 D.I. 213 at 4. 37 Section 3.6.4.2 specifies: [The] Architect shall review and approve or take other appropriate action upon the Contractor’s submittals such as Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. Review of such submittals is not for the purpose of determining the accuracy and completeness of other information such as dimensions, quantities, and installation or performance of equipment or systems, which are the Contractor’s responsibility.161 In addition to R+B’s obligation to report nonconforming or defective work to DSU, R+B had authority to reject such work, and an obligation to notify DSU of any rejection.162 Section 3.6.2.2 states: The Architect has the authority to reject Work that does not conform to the Contract Documents and shall notify the Construction Manager about the rejection.163 Finally, R+B was required to perform its work according to the applicable professional standard of care, and was responsible for its own breaches of that standard.164 Section 2.2 provides: The Architect shall perform its services consistent with the professional skill and care ordinarily provided by architects practicing in the same or similar locality under the same or similar circumstances.165 161 D.I. 243-1, Stip. Ex. 47 § 3.6.4.2. D.I. 213 at 4 (citing D.I. 243-1, Stip. Ex. 47 § 3.6.2.2; D.I. 243-17 (Kennedy Dep.) at 206-07). 163 D.I. 243-1, Stip. Ex. 47 § 3.6.2.2. 164 D.I. 213 at 5 (citing D.I. 243-1, Stip. Ex. 47 §§ 2.2, 3.6.1.2). 165 D.I. 243-1, Stip. Ex. 47 § 2.2. 162 38 Section 3.6.1.2 recites: The Architect shall be responsible for the Architect's negligent acts or omissions, but shall not have control over or charge of, and shall not be responsible for, acts or omissions of the Construction Manager, or the Contractor or of any other persons or entities performing portions of the Work.166 On January 12, 2012, DSU and W-T entered into a contract titled AIA® Document C132™ – 2009, Standard Form of Agreement Between Owner and Construction Manager as Adviser; AIA® Document A232™ – 2009, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition; and Section 00730–SUPPLEMENTARY GENERAL CONDITIONS TO THE CONTRACT (“DSU-W-T Contract”).167 DSU asserts, as it does with respect to the DSU-R+B Contract, that the DSU-W-T contract obligated it to oversee the work of other contractors and to coordinate communications and services with those contractors and DSU as the Owner.168 According to DSU, W-T required all project communications flow through it as the Construction Manager.169 Provisions of the DSU-W-T Contract relevant to the parties’ motions include the following: Section 3.3.19 of W-T’s contract provides: The Construction Manager shall promptly review all Shop Drawings, 166 Id., Stip. Ex. 47 § 3.6.1.2. D.I. 195, Stip. Fact 12; D.I. 243-3, Stip. Ex. 94 (DSU-W-T contract); D.I. 2431, Stip. Ex. 48 (General Conditions); D.I. 243-3, Stip. Ex. 140 (Section 00730). 168 D.I. 213 at 5. 169 Id. (citing D.I. 243-12 (George Dep.) at 157-58; D.I. 243-17 (Kennedy Dep.) at 166-67 & 175-76; D.I. 243-11 (Thomas Dep.) at 243; D.I. 243-7 (Ashford Dep.) at 22; D.I. 243-13 (Bartlett Dep.)). 167 39 Product Data, Samples and other submittals from the Multiple Prime Contractors for compliance with the submittal requirements of the Contract, coordinate submittals with information contained in related documents, and transmit to the Architect those that the Construction Manager recommends for approval.170 Pursuant to § 3.3.9: The Construction Manager shall endeavor to obtain satisfactory performance from each of the Multiple Prime Contractors. The Construction Manager shall recommend courses of action to the Owner when requirements of a Contract are not being fulfilled.171 As with R+B’s contract, § 3.3.14 of W-T’s contract required W-T to report defects and deficiencies in any of the Work to DSU, and any rejection of nonconforming work. The Construction Manager shall determine in general that the Work of each Contractor is being performed in accordance with the requirements of the Contract Documents and notify the Owner, Contractor and Architect of defects and deficiencies in the Work. The Construction Manager shall have the authority to reject Work that does not conform to the Contract Documents and shall notify the Architect about the rejection. 172 Finally, W-T’s contract contains a parallel provisions to R+B’s contract requiring W-T to perform its work according to the applicable professional standard of care, and that W-T was responsible for its own breaches of that standard. 170 D.I. 243-3, Stip. Ex. 94 § 3.3.19; see also id., Stip. Ex. 94 § 3.2.5 (requiring W-T to “review design documents during their development and advise the Owner and Architect on proposed site use and improvements, selection of materials, and building systems and equipment. The Construction Manager shall also provide recommendations to the Owner and Architect on constructability . . . .”); id., Stip. Ex. 94 § 3.2.8 (providing that “Construction Manager shall consult with the Owner and Architect and make recommendations whenever the Construction Manager determines that design details adversely affect constructability, cost or schedules.”); see also D.I. 243-12 (George Dep.) at 90-91, 252-53 (acknowledging that W-T’s review of submittals was for the purpose of ensuring their conformance with the Contract Documents and design). 171 D.I. 243-3, Stip. Ex. 94 § 3.3.9. 172 Id., Stip. Ex. 94 § 3.3.14 (emphasis added). 40 Section 2.2 provides: The Construction Manager shall perform its services consistent with the skill and care ordinarily provided by construction managers practicing in the same or similar locality under the same or similar circumstances.173 Section 3.3.15 states: The Construction Manager shall be responsible for the Construction Manager's negligent acts or omissions, but shall not have control over or charge of, and shall not be responsible for, acts or omissions of the Contractor or Multiple Prime Contractors, Subcontractors, or their agents or employees, or any other persons or any other persons or entities performing portions of the Work.174 II. GOVERNING LAW–DSU, W-T, and R+B Cross-Motions for Summary Judgment on DSU’s Count I (Breach of Contract) To prove a breach of contract claim, the plaintiff must show: (1) the existence of a contract, (2) breach of the an obligation imposed by that contract, and (3) the resultant damage to the plaintiff.175 Where professional negligence is the basis for a breach of contract claim, expert testimony is generally required to establish the standard of care applicable to that professional.176 In Seiler, the Delaware Supreme Court explained: As a general rule the standard of care applicable to a professional can only be established by way of expert testimony. See Christian, supra. However, “. . . if a layman is as competent as an expert to judge whether or not a particular design created an unusual risk, evidence by experts 173 Id., Stip. Ex. 94 § 2.2. Id., Stip. Ex. 94 § 3.3.15. 175 VLIW Tech., LLC v. Hewlett-Packard Co., 840 A.2d 606, 612 (Del. 2003) (citations omitted). 176 See Seiler v. Levitz Furniture Co. of Eastern Region, Inc., 367 A.2d 999, 1008 (Del. 1976) (citation omitted). 174 41 is inadmissible because their proof that the defendant followed standard practice would not necessarily show he was not negligent.” Comment, Architect Tort Liability In Preparation of Plans and Specifications, 55 Cal. L .Rev. 1361, 1364 (1967) (citations omitted). That exception is consistent with the law of this State. Larrimore v. Homeopathic Hospital Ass’n of Del., Del. Supr., 4 Storey 449, 54 Del. 449, 181 A.2d 573 (1962). 177 III. POSITIONS OF THE PARTIES –DSU, W-T, and R+B Cross-Motions for Summary Judgment on DSU’s Count I (Breach of Contract) DSU contends the undisputed facts demonstrate R+B and W-T materially breached the clear and unambiguous terms of their respective contracts with DSU.178 DSU argues it is entitled to summary judgment in its favor because: 1. As the Architect of Record and Construction Manager, R+B and W-T, were each obligated by their respective contracts to notify DSU of material errors, omissions, inconsistencies and defects in any of the work. 2. As the Architect of Record, R+B was contractually obligated to prepare Design Drawings and Specification 07435 for the Panel Wall System. In that capacity, R+B incorrectly approved PFF as a panel manufacturer without conducting any due diligence regarding whether the company or its product was 177 Id.; see also Brown v. Interbay Funding, LLC, 417 F. Supp. 2d 573, 579 (D. Del. 2006) (“To state a claim for professional negligence, . . . , the standard of care applicable to a professional can only be established through expert testimony.”) (citations omitted). “Common law has created a local standard of care for professionals in which the fact finder evaluates whether the actions of the professional conform to the profession’s standards of skill, care and competence, as adhered to by professionals who are in good standing in the community.” Norfleet v. Mid-Atlantic Realty Co., Inc., No. Civ.A 95C-11-008WLW, 2001 WL 695547, at *5 (Del. Super. Apr. 20, 2001) (citing Seiler, 367 A.2d at 1007). “Delaware has recognized professional negligence causes of action [against] lawyers, doctors, accountants, architects, engineers, insurance agents, and massage therapists . . . .” Verition Partners Master Fund, Ltd. v. Cornell, C.A. No. 19-377-CFC, 2020 WL 2917258, at *4 (D. Del. June 3, 2020) (listing cases). DSU does not appear to dispute the status of either W-T or R+B as “professionals” in the context of their contractual obligations. 178 D.I. 213 at 2. 42 suitable for this application. 3. Both R+B and W-T were on express notice that the PFF product was unsuitable for the specified application, but failed to either notify DSU of that fact or select another product. 4. Both R+B and W-T repeatedly failed to notify DSU of material errors, omissions, inconsistencies and defects in the design, engineering, fabrication, and performance of the Panel Wall System. R+B and W-T’s failure to notify DSU constitutes a material breach of their respective contracts.179 R+B’s opposition to DSU’s affirmative motion, and its own affirmative motion, states R+B has a specialized “industry” contract with DSU which requires DSU to provide an expert opinion on industry customs and standards to assist the court in interpreting its contract, and determining whether R+B met the relevant standard of care before any legal conclusions can be rendered. 180 Absent expert testimony, R+B maintains DSU cannot establish its prima facie case and, therefore, DSU’s motion must be denied, and R+B’s motion granted.181 R+B also argues there is no evidence of nonperformance to support DSU’s breach of contract claim.182 R+B contends, however, that even if DSU could prove its contract required R+B to do something it did not do, there is no evidence that any such failure to perform a contractual requirement caused any of the alleged damages.183 179 Id. D.I. 226 at 1-2; D.I. 204 at 9-15. 181 D.I. 226 at 2; D.I. 204 at 9-15. In its Counter-Statem ent of Facts opposing DSU’s affirmative motion, R+B emphasizes it is not asking the court to make findings of fact or accept R+B’s, or W-T’s, factual presentations as true; rather, R+B argues disputed facts are an additional reason that precludes sum mary judgment in DSU’s favor. D.I. 226 at 2 n.1. 182 D.I. 204 at 15-16. 183 Id. at 16. 180 43 W-T similarly argues DSU’s motion must be denied for lack of expert testimony showing it breached the relevant standard of care, and/or because neither the facts nor its contract entitle DSU to judgment.184 W-T’s affirmative motion asserts it is entitled to summary judgment on DSU’s breach of contract clam because its contract contains specific disclaimers as to liability for actions of the architect (R+B) or the panel wall contractor (TCI), and reiterates that DSU’s expert is not qualified to opine as to W-T’s purported liability.185 Moreover, W-T contends evidence demonstrating it did perform its contractual obligations shows it is entitled to summary judgement.186 Separately, W-T argues that if DSU’s breach of contract claim moves forward, it is entitled to summary judgment that the damages DSU seeks are excessive and must be limited to the cost of replacing the buckled panels with the same type of panels that were originally installed.187 IV. DISCUSSION–DSU, W-T, and R+B Cross-Motions for Summary Judgment on DSU’s Count I (Breach of Contract) According to W-T, DSU’s corporate designee, J.D. Bartlett, testified that the following is a comprehensive list of its allegations pertaining to W-T: failed to perform its services consistent with the skill and care ordinarily provided by construction managers practicing in the same or similar locality in breach of § 2.2 of the Contract; failed to adequately review the design and construction documents or submittals and shop drawings, and advise DSU of the effectiveness and constructability of the panel wall system in breach of §§ 3.2.5, 3.2.8 and 184 D.I. 229 at 1. D.I. 210 at 1. 186 Id. at 2. 187 Id. at 15-18. 185 44 3.3.19 of the Contract; failed to notify DSU in a timely manner of these defects, as well as defects noted in the panels themselves such as buckling, folding, oil-canning and other material defects in the exterior surface of the panels; failed to provide adequate onsite administration of the Contract or to properly inspect the panel wall system installed for the Project, and failed to identify material defects in the panel wall, including but not necessarily limited to the installer’s failure to cut “V Channels” in the panels, which was not in compliance with the drawings, shop drawings, and/or specifications; failed to ensure that the panel wall system was fabricated and installed in a nondefective and workmanlike fashion such that it did not suffer the material defects identified in the Complaint; failed to properly monitor the performance of the parties fabricating and installing the panel wall system to ensure compliance with the Contract Documents, and failed to properly advise and consult with DSU in breach of §§ 3.3.3, 3.3.9, 3.3.14, 3.3.15, and 3.3.24; and failed to stop the Work in order to address these material defects and issues in a timely manner as it had the ability to do under the terms of the Contract Documents.188 DSU and W-T each argue summary judgment should be granted and/or denied in their respective favors as to some, or all, of these allegations. R+B sets forth the following averments against it from the TAC:189 188 D.I. 210 at 2-3 (citing D.I. 243-13 (Bartlett Dep.) at 54:21-55:3; D.I. 243-3, Stip. Ex. 141, Ans. and Supp. Ans. 4 and 5; D.I. 180-2 ¶¶ 44-46, 55). 189 D.I. 204 at 2-3. With the exception of the title of R+B’s Contract, R+B provided the emphasized terms in the following quoted paragraphs which it contends pertain to its performance and subjective determinations as a licensed architect that must be determined according to the standard of care. D.I. 204 at 2 n.1. R+B stresses this is the point of its motion: to sustain the claims against R+B, expert opinion is required that identifies the standard of care, how R+B failed to meet it, and how that failure caused damages. Id. R+B asserts the claims cannot be sustained for lack of the required expert opinion. Id. 45 a) On January 20, 2012, DSU and the architectural firm Richärd+Bauer entered into that certain AIA® Document B132™ -- 2009, Standard Form of Agreement Between Owner and Architect, Construction Manager as Advisor Edition (the “Design Management Agreement”) . . .;190 b) The . . Agreement obligated R+B to provide construction plans and specifications . . .;191 c) . . . further obligated R+B to provide “construction phase services,” including periodic inspections . . ., evaluation of the work performed during each phase and the provision of notice and information to DSU . . .;192 d) . . . was contractually obligated to conduct at least thirty-six (36) separate inspections . . . for the express purpose of particularly familiarizing itself with the progress and quality of the work performed, and specifically determining that such work was performed in a manner consistent with the . . . its plans, specifications, product recommendations and approvals;193 e) . . . obligated R+B to keep DSU reasonably informed regarding the quality of the work performed and to report any deviations from the contract documents or any defects or deficiencies observed in the performance of the work [(See § 3.6.1.2)]; 194 f) . . . obligated R+B to review and approve all shop drawings and submittals for the purpose of determining their conformity or nonconformity with the plans and specifications . . .;195 g) . . . obligated R+B to “perform its services with the professional skill and care ordinarily provided by architects practicing in the same or similar locality under the same or similar circumstances.” (§ 2.2, at p. 6) 190 D.I. 180-2 ¶ 16. R+B objects to the TAC’s use of the term “Design Management Agreement” because the contract is not so named and this term does not appear in the contract. D.I. 204 at 2 n.2. 191 D.I. 180-2 ¶ 17. 192 Id. ¶ 18. 193 Id. ¶ 19. 194 Id. ¶ 20. 195 Id. ¶ 21. 46 [of Exh. 47]);196 h) The defects are due . . . to flaws in the design and specifications prepared and approved by R+B for the Project. R+B failed to adequately research and specify panels that would not result in the defects experienced by the system as installed;197 i) The defects are also due . . . to R+B’s failure to fulfill its . . . duties (a) to inspect and report on all design, specification, fabrication and installation defects as required; (b) to provide DSU with ongoing and appropriate information regarding the nonconforming work; and (c) to reject the nonconforming work;198 j) . . . R+B also failed to review and properly approve or reject relevant shop drawings, product data, samples and other submittals . . . for compliance . . . and to report to DSU regarding any deficiencies . . .;199 k) Defendants’ various defective performances, either individually or in conjunction with each other, directly and proximately caused a defective and nonconforming panel wall system to be installed at the OSCAR; 200 and l) The panel wall system is failing and will cost DSU millions of dollars to remediate, and will cause damages to the existing structure and other property as a result of remediation.201 DSU and R+B each argue summary judgment should be granted and/or denied in their respective favors as to some, or all, of these allegations. Before delving into the relevant facts cited in support of the parties’ respective positions on the merits, the court must address the threshold issue of whether expert testimony is required to support DSU’s breach of contract claims against R+B and W-T. 196 Id. ¶ 22. Id. ¶ 36. 198 Id. ¶ 42. 199 Id. ¶ 43. 200 Id. ¶ 46. 201 Id. ¶ 47. 197 47 DSU alleges W-T and DSU breached distinct provisions of their respective contracts. In response to defendants’ affirmative motions, DSU accuses defendants of lumping all their alleged breaches into one amalgam to argue a professional negligence standard of care applies to all. 202 In opposition to that tactic, DSU asserts the standard of professional care applicable to claims founded on negligent conduct does not apply to commonplace breaches that are based on clear and unam biguous terms, i.e., defendants’ obligation to report known errors, omissions, and defects in the work to DSU.203 Relatedly, DSU maintains even if a negligence standard was applicable to defendants’ alleged breaches of their reporting obligations, expert testimony is not required because those breaches are so clear and obvious they fall within the common knowledge of a lay juror.204 For this related argument, DSU contends the facts of Seiler are analogous to those here and demonstrate the common knowledge exception is applicable to defendants’ breaches. At issue in Seiler was an architect’s negligent design plans and specifications for a furniture store which failed to account for potential flooding.205 In defense to the plaintiff furniture store’s allegation of negligence, the architect argued, inter alia, that “expert testimony was required to establish the standard of care to which he was bound.”206 The Delaware Supreme Court rejected the argument and affirmed the trial 202 D.I. 231 at 5. Id. at 5-8. 204 Id. at 8-15. 205 Seiler v. Levitz Furniture Co. of Eastern Region, Inc., 367 A.2d 999, 1001-02 (Del. 1976). 206 Id. at 1006. 203 48 court’s finding against the architect: “the Trial Judge concluded that Seiler's mistake was so apparent that plaintiff was not obliged to produce expert testimony at trial to establish the bench mark by which his standard of care is measured. We agree.”207 The Seiler court reasoned: In the final analysis Seiler, by his own testimony, admitted that an investigation as to the possibility of flooding was necessary; he went on to say that he had investigated that possibility. The crux of the Superior Court decision is that in such investigation Seiler was “put on notice” that flood waters had topped Naamans Road on previous occasions and that he failed to design the warehouse accordingly. Id. at 1008. Based on those facts, the Supreme Court held “[t]here is evidence to support the conclusion that Seiler knew or should have known of the flooding potential of the area and in accordance with settled law, we affirm it.”208 DSU maintains that, to the extent a professional standard of care is applicable, the court’s reasoning in Seiler governs the determination of whether the common knowledge exception applies here. 209 DSU also cites Jaeger v. Henningson, Duncan & Richardson, Inc. 210 for the proposition that, in addition to their fundamental failure to report known errors and omissions, Federal law equally provides that defendants’ failure to correct those errors 207 Id. at 1008. Id. at 1009. 209 D.I. 231 at 9. 210 714 F.2d 773, 775 (8th Cir. 1983). In Jaeger, the Eighth Circuit applied South Dakota law on the issue of an architect’s liability. Id. (citations omitted). As did Seiler, the Eighth Circuit observed that issue generally requires expert testimony, but noted the existence of a “common knowledge” exception that “permits juries to pass on issues of negligence that do not require a knowledge of professional skills.” Id. (citation omitted). 208 49 does not require expert testimony.211 There, plaintiffs alleged the project architect “negligently failed to detect and correct the shop drawings providing for a 14-gauge steel stairway landing pan” where the architect’s design drawings and specifications required a 10-gauge steel landing pan.212 The contract at issue required the architect to review and approve certain drawings and submissions for conformance with other documents; The Architect shall review and approve shop drawings, samples, and other submissions of the Contractor only for conformance with the design concept of the Project and for compliance with the information given in the Contract Documents.213 Discussing the architect’s failure to detect and correct an incorrect gauge of steel on the shop drawings, the Jaeger court held: There is nothing so highly technical about the facts of this case which is not within the common experience or understanding of the average laymen. The specifications called for the landing pans to be made from 10-gauge steel with angle stiffeners as required. The shop drawing, however, provided that the landing pan in question should be made from 14-gauge steel without angle stiffeners or supports. Moreover, we observe that there was expert testimony supporting the view that had the pan been built with 10-gauge steel and angle stiffeners, it would not have collapsed under circumstances similar to those of the accident in this case.214 The Eighth Circuit, therefore, concluded the action against the architectural firm was one for negligent failure to supervise the shop drawings, and because a jury of lay persons could determine whether failure to supervise an employee was negligent, the 211 D.I. 231 at 13. Jaeger, 714 F.2d at 775. 213 Id. at 775. 214 Id. at 776. 212 50 case did not require expert testimony on the appropriate standard of care.215 DSU contends the provision in Jaeger is substantively the same as the review and approval requirements in R+B and W-T’s respective contracts.216 Like Jaeger, DSU maintains the gravamen of the complaint against W-T and R+B is that they failed to (i) review and approve submittals from TCI for conformance with the contract documents or (ii) supervise its work and shop drawings to ensure that they conformed.217 DSU asserts the submittals and the shop drawings failed to conform to the contract documents in two material respects admitted by both defendants: (1) no one provided the engineering of the panels for thermal loads required by R+B’s Specification; and (2) the shop drawings omitted the V-Channels required not only by the design drawings but also PFF’s Product Data. 218 Lastly, DSU contends “as to the breaches that do involve the application of a professional standard of care, the expert opinion and testimony of Dannettel and his team are sufficient to present a genuine issue of material fact to the jury.”219 In that regard, and specifically in response to defendants’ cross-motions, DSU states there is a 215 Id. The court emphasized its previous distinction between actions against architects for negligence-in-preparing plans and actions for negligence-in-supervising plans, with only the former typically requiring expert testimony. Id. (citations omitted). Because it found the gravamen of the complaints was a failure to supervise the shop drawings pursuant to the contract and that negligence was the proximate cause of plaintiffs’ injuries, the court determined expert testimony on the appropriate standard of care was not required. Id. 216 D.I. 231 at 13 (citing D.I. 243-1, Stip. Ex. 47 (R+B Contract) § 3.6.4.2; D.I. 243-3, Stip. Ex. 94 (W-T Contract) §§ 3.2.5 & 3.3.19). 217 D.I. 231 at 14-15. 218 D.I. 231 at 15. 219 Id. at 2 (emphasis added); id. at 15-24. 51 dispute of fact as to whether the Specifications provided for a “delegated design” that absolves R+B of its obligations for the Panel Wall System.220 DSU asserts Dannettel’s expert opinion explains “the engineering and design standards required to properly account for the single most important issue resulting in the defects in these panels.”221 As to the additional allegations subject to defendants’ motions that require expert testimony, DSU avers “[t]he report discusses ALL of the Defendants’ failures to address thermal loads, comprehensive engineering, sufficient validation and verification of issues, and several other duties, as well as the facts showing that Defendants’ deficient performance was the proximate cause of the resulting defects.”222 DSU specifically references the sections of Dannettel’s Report opining as to specific breaches by defendants of various standards of care and duties governing their performance,223 as 220 D.I. 231 at 2. Id. (emphasis added). DSU emphasizes that separate from the question of whether the design was delegated to TCI or not, defendants’ failure to notify DSU that no one was engineering the panels is the basis for its summary judgment motion. Id. at 32-33 (“Even assuming the responsibility to design these panels properly was on [TCI’s] shoulders, Defendants were on notice that [TCI] failed to fulfill that obligation.”). 222 Id. at 2. 223 Id. at 15-16 (citing D.I. 243-3, Stip. Ex. 147 §§ 4.0-4.3). DSU also singles out allegations that W-T lists in its opening brief as requiring expert testimony. Id. at 2 (citing D.I. 210 at 13-14 (W-T arguing expert testimony was required on the following allegations but, even if the Motion to Strike was denied, the evidence shows that: (1) W-T was not contractually obligated to require R+B provide documentation to demonstrate the Panel Wall System’s suitability and fitness for use on the OSCAR Facility, because it had no design obligations; (2) W-T was not contractually obligated to identify the methods available to contract the exterior wall panel work, or to evaluate and determine whether the exterior wall panel work could effectively be executed as a delegated design contract; (3) W-T was not contractually obligated to prequalify the exterior wall panel contract bidders because DSU did not specif y that any bidders had to be qualified under Chapter 69 of Title 29 of the Delaware Code; (4) W-T fulfilled confirmed at the descope meeting, and through further consultation, that TCI: (a) was a responsive and responsible bidder qualified to perform the work; (b) bid to perform the 221 52 well as Dannettel’s deposition testimony explaining his opinions.224 The court addresses the last category first, i.e., the allegations DSU identifies as presenting questions of fact in light of Dannettel’s opinions expressed in his expert report. Because the court granted the Motion to Strike, no admissible evidence is available to create a question of fact it as to those allegations. Thus, summary judgment is granted in favor of R+B and W-T on those allegations. With respect to DSU’s allegation that R+B and W-T breached § 2.2 of their respective contracts, it is clear expert testimony is required to describe the relevant professional standards of care and how each defendant breached that standard. Section 2.2 provides that each defendant “shall perform its services with the professional skill and care ordinarily provided by [architects/construction manages] practicing in the same or similar locality under the same or similar circumstances.”225 DSU’s corporate designee testified DSU intended to rely solely on its expert report to support its claim that W-T breached § 2.2 of its contract.226 In light of the court’s grant of the Motion to Strike, the court grants W-T’s motion for breach of contract with respect entire contract, including the work outlined in Specification 07435; and (c) reviewed and understood the technical requirements of the drawings and specifications; (5) W-T clearly indicated in TCI’s Scope of Work that TCI was responsible for all of the work and engineering delegated in the Specification; (6) W-T took the necessary steps to ensure TCI and its subcontractors provided Panel engineering for the specific engineering lapses identified by R+B, and despite TCI’s attempts to disclaim responsibility therefore; and, (7) W-T addressed the absence of V-Channels in TCI’s shop drawings before TCI began installing any panels on the project, and provided R+B with TCI’s response)). 224 D.I. 231 at 18-23. 225 See D.I. 243-1, Stip. Ex. 47 § 2.2; D.I. 243-3, Stip. Ex. 94 § 2.2 (emphasis added). 226 D.I. 243-13 (Bartlett Dep.) at 81:3-22. 53 to § 2.2 and denies DSU’s motion on this section. For the same reason, R+B’s motion is granted, and DSU’s motion is denied, as to R+B’s alleged breach of § 2.2.227 The court also addresses another specifically-alleged provision of R+B’s contract to illustrate the legal support for the court’s grant of summary judgment to R+B and W-T on each of the alleged breaches for which DSU relies on Dannettel’s Report and testimony for support. Section 3.6.2.1 of R+B’s Contract require it perform “construction phase services,” including periodic inspections of the work performed, to determine whether such work was performed in a manner consistent with the plans and specifications, and to keep DSU “reasonably informed” and report any deviations from the contract documents or any defects or deficiencies observed.228 R+B states there is no standard of care opinion on what its site visit inspections include, on what constitutes keeping DSU “reasonably” informed, and on what an architect would consider to be a deviation from the “performance specification” (delegated design) level plans and specifications.229 DSU responds that § 3.6.2.1 is not the section upon w hich its summary judgment motion is based, and reiterates that its motion against R+B is based on § 3.1.2, which does not contain the “reasonably” informed caveat; § 3.1.2 mandates the “Architect shall provide prompt written notice to the Owner if the Architect becomes aware of any 227 See D.I. 180-2 ¶ 22 (“The Design Management Agreement obligated Richärd+Bauer to ‘perform its services with the professional skill and care ordinarily provided by architects practicing in the same or similar locality under the same or similar circumstances.’ (See [D.I. 243-1, Stip. Ex. 47] § 2.2[]).”). 228 D.I. 204 at 12 (citing D.I. 243-1, Stip. Ex. 47 § 3.6.2.1 (emphasis added)). 229 Id. 54 error, omission or inconsistency in such services or information.”230 In opposition to R+B’s affirmative motion on § 3.6.2.1, DSU contends that keeping the owner “reasonably” informed regarding the work is not so highly technical and complex that it requires exert testimony.231 R+B’s reliance on the Delaware Superior Court’s decision in Oliver v. Bancroft Const. Co.,232 applying Seiler, provides persuasive rebuttal to DSU’s argument. In Oliver, the plaintiff tripped over the side of a newly-constructed concrete ramp, and was injured.233 The parties opposing the relevant defendants’ motions for summary judgment argued: [N]umerous provisions in the relevant contracts demonstrate that the architectural firms assumed oversight duties for the project. Additionally, it was the responsibility of the architects to respond to the construction manager's design questions, to inspect the renovations, and to ensure that each phase of the construction process had been com pleted correctly as designed. Thus, they contend, if the ramp was not installed as originally designed, or if the ramp was negligently designed, the architects are liable. . . .234 No expert opined that either architect breached the applicable standard of care.235 The court explained its finding that expert testimony was required to assist the fact finder interpret the relevant contract provisions as follows: Certain terms are beyond the comprehension of lay persons. For example, although the contracts may require the architect to inspect the project, only an expert can provide guidance as to how often inspections 230 D.I. 231 at 7. Id. at 7-8. 232 C.A. No. 09C-05-174-MMJ, 2011 WL 5042389 (Del. Super. Oct. 21, 2011). 233 Id. at *1. 234 Id. (emphasis added). 235 Id. at *2. 231 55 are to be made, as well as the nature and extent of any inspection . Even if plaintiff . . . can demonstrate that the architects had, or should have had, notice of the allegedly defective condition of the ramp, expert testimony is necessary to establish the professional standard of care. A lay person is unqualified to determine whether and when the architect should have been on notice, and what steps the architect may have been required to take to rectify the situation. Other issues in this case are whether the design was defective, or whether the construction was completed in accordance with the plans prepared by the architect. Again, these question require standard-of-care expert testimony. It is beyond the ability of an unassisted lay person to ascertain who is responsible for interpretation of design plans and how any construction professional should interpret the architect’s design.236 Because no expert opined that either architect breached any professional architectural standard of care, or that any alleged breach caused the injury, the court granted the architects’ motion and dismissed the claims against them with prejudice.237 Here, the Oliver decision leads to court to conclude expert testimony is necessary to show R+B breached its professional standard of care with respect to § 3.6.2.1 of R+B’s Contract.238 Because there is no admissible expert testimony to make that showing, R+B’s motion for summary judgment is granted. Section 4.2.3 of the Supplementary General Conditions to W-T’s Contract contains similar language requiring W-T to keep DSU “reasonably informed” of certain deviations, defect, and deficiencies.239 To the extent DSU’s breach of contract claim is based on that section, it 236 Id. (emphasis added). Id. at *3. 238 The court notes DSU does not make any attempt to distinguish Oliver, or otherwise argue why its reasoning does not apply to the contracts at issue here. 239 D.I. 243-1, Stip. Ex. 48 § 4.2.3 (“The Construction Manager will determine in general if the Work observed is being performed in accordance with the Contract Documents will keep the Owner reasonably informed of the progress of the Work, and 237 56 is also dismissed for lack of expert testimony showing W-T breached its professional standard of care with respect to that provision. Based on the above reasoning, and DSU’s position that Dannettel’s testimony and report raises questions of fact precluding a grant of R+B and W-T’s motions, the court grants summary judgment in favor of R+B and W-T on their alleged breaches of contract that DSU avers are shown through Dannettel’s now-stricken Report and testimony. Those allegations are specifically found in §§ 4.3.1 (R+B) and 4.3.3 (W -T) of the Thornton Tomasetti Report, and examples from Dannettel’s deposition testimony cited by DSU that purportedly demonstrate defendants’ negligent acts.240 The court next turns to the category of breaches DSU contends does not require expert testimony, i.e., commonplace breaches of clear and unambiguous terms, or are within the common knowledge exception whereby a lay person would understand the alleged breach without the assistance of expert testimony. DSU asserts expert testimony regarding a negligent breach of a standard of care is not required for every commonplace breach of contract.241 As to those breaches of contract, DSU argues defendants cannot impose an additional professional negligence standard where negligence is not the basis of the claim or defendants’ liability.242 As an example of such breach, DSU posits that if a contractor fails to pay subcontractors, an will report to the Owner and Architect (I) known deviations from the Contract Documents and the most recent Project schedule and (2) defects and deficiencies observed in the Work.”) (emphasis added). 240 See D.I. 243-3, Stip. Ex. 147 §§ 4.3.1, 4.3.3; D.I. 231 at 15-16, 18-23. 241 D.I. 231 at 6. 242 Id. at 1. 57 owner is not required to prove that it breached this straightforward obligation but also that it somehow breached a duty of care by doing so.243 DSU places W-T and R+B’s alleged breaches of what it describes as the clear an unambiguous notice requirements in their contracts into the category not requiring additional proof that defendants “negligently” failed to provide any notice at all to DSU. DSU relies on the following specific sections from each defendants’ contract requiring that they report errors, omissions, defects, deficiencies, or inconsistencies in the submittals, information, or services provided to DSU for that argument: Richärd+Bauer Contract § 3.1.2: The Architect shall provide prompt written notice to the Owner if the Architect becomes aware of any error, omission or inconsistency in such services or information.244 Whiting-Turner Contract § 3.3.14: The Construction Manager shall determine in general that the Work of each Contractor is being performed in accordance with the requirements of the Contract Documents and notify the Owner, Contractor and Architect of defects and deficiencies in the Work.245 DSU states that, despite those requirements, each defendant repeatedly failed to notify DSU of material errors, omissions and defects in the submittals and performance regarding this Panel Wall System. DSU submits the facts concerning their failures to report to DSU are undisputed. 246 At least with respect to R+B’s contract, the court agrees with DSU that the binary 243 Id. at 6. As another example, DSU contends if a contractor fails to perform work altogether, an owner is not subject to an additional burden to prove that the contractor was also negligent, but only that it was required to do the work and did not. Id. 244 D.I. 243-1, Stip. Ex. 47 § 3.1.2. 245 D.I. 243-3, Stip. Ex. 94 § 3.3.14. 246 D.I. 213 at 31. 58 question of whether it provided the specified notice does not require expert testimony as to R+B’s professional standard of care. R+B’s Contract is explicit in requiring “prompt” “written notice” “to the Owner [DSU]” if it “becomes aware” of “any error, omission or inconsistency” of the relevant services or information. This is a different question than addressed in Oliver as to the timing and extent of inspections, or whether or when the architect was on notice, as well as what may have been required by the architect to rectify the situation. 247 There is no indication in Oliver that the architects’ contracts included notice provisions that were allegedly breached. In contrast to Oliver, which was solely a professional negligence action, DSU alleges breach of contract claims, some aspects of which implicate professional negligence, but other aspects may not. Here, either R+B knew of “any error, omission or inconsistency” and it gave prompt written notice to DSU, or it did not. Such a straightforward question does not require expert testimony for its answer. The court arrives at a different conclusion with respect to the less explicit notification provision of W-T’s contract that DSU specifies was breached. W-T was required to “determine in general” whether each contractor’s Work was “being performed in accordance with” contract document requirements, and “notify the Owner, Contractor and Architect” “of defects and deficiencies” in the Work.248 Consistent with Oliver, expert testimony is required as to a CM as Advisor’s professional standard of care. A lay person is unqualified to determine how a CM as Advisor would “generally” 247 248 See Oliver, 2011 WL 5042389, at *2. See D.I. 243-3, Stip. Ex. 94 § 3.3.14. 59 determine whether work was “in accordance” with contract document requirements, as well as, when, and how, W-T was to “notify” DSU, the Owner, Contractor, and Architect of (some, any, all?) “defects and deficiencies in the Work.” Are whatever notifications that are required to be in the made same way and have the same timing when made to each entity? Because there is no admissible expert evidence to assist the finder of fact in answering these questions, summary judgment is granted in favor of W-T and against DSU on the alleged breach of § 3.3.14 of its contract.249 Because the court determines the entirely of DSU’s breach of contract allegations against W-T are beyond the common knowledge of a lay person and/or 249 To the extent they may, or may not, overlap with alleged breaches the court specified, above, as requiring dismissal for lack of expert testimony on W-T’s professional standard of care, the court comes to the same conclusion with regard to several other provisions of W-T’s contract that DSU references, see D.I. 213 at 5-6; D.I. 231 at 13, and determines each are outside the common knowledge of a lay person as to whether a CM met the recited obligations. These provisions include W-T contract provisions recited in: § 3.3.19 (CM “shall promptly review all Shop Drawings, Product Data, Samples and other submittals from the Multiple Prime Contractors for compliance with the submittal requirements of the Contract, coordinate submittals with information contained in related documents, and transmit to the Architect those that the Construction Manager recommends for approval.”); § 3.2.5 (CM to expeditiously review the Architect’s review design documents for constructability and “provide recommendations to the Owner and Architect on constructability”); § 3.2.8 (CM to “consult with the Owner and Architect and make recommendations whenever the Construction Manager determines that design details adversely affect constructability”); § 3.3.9 (CM to “endeavor to obtain satisfactory performance from each of the Multiple Prime Contractors [and] recommend courses of action to the Owner when requirements of a Contract are not being fulfilled”): and § 3.3.15 (CM “shall be responsible for the Construction Manager’s negligent acts of omissions” in connection with its obligations). The same conclusion is reached with respect to provisions not specified in DSU’s briefing, but identified by its corporate designee as implicating W-T’s obligations, i.e., § 3.3.3 (CM “shall provide on-site administration of the Contracts for Construction with the Architect as set forth below and in [the] . . . General Conditions of the Contract for Construction”), and § 3.2.24 (CM “shall assist the Architect in conducting inspections to determine whether the Work or designated portion thereof is substantially complete”). 60 require expert testimony to support those allegations, W-T’s motion for summary judgment is granted, and DSU’s motion for summary judgment is denied. In light of this determination, the court need not address W -T’s separate argument seeking summary judgment limiting the amount of damages sought by DSU and it is denied as moot. The court returns now to the parties’ arguments as to R+B’s alleged breach of its notification obligations that either do not implicate a professional standard of care or do not require expert testimony because they fall in the under the “common knowledge” exception as discussed in Seiler and Jaeger. The court determines genuine issues of material fact preclude summary judgment in favor of either party. DSU alleges R+B’s complete failure to conduct any investigation of PFF’s product before approving it as a manufacturer in Specification 07435, as opposed to the question of whether it conducted an “adequate” investigation, is not so “highly technical and complex” that a lay person could not understand a breach occurred.250 As supporting evidence of R+B’s alleged failure, DSU cites the deposition testimony of R+B corporate designee Stephen J. Kennedy.251 R+B disputes the alleged facts, explaining why Kennedy’s testimony does not unequivocally support DSU’s assertions, and citing emails purportedly documenting and supplementing that testimony that raises questions of fact on the issue. 252 DSU’s allegation that the subsequent bidding process confirmed the PFF product was unsuitable and was not 250 D.I. 213 at 7; D.I. 231 at 10. D.I. 213 at 8-9 (citing D.I. 243-17 (Kennedy Dep.)). 252 D.I. 226 at 6-8. 251 61 reported to DSU253 is likewise disputed by R+B’s proffered evidence and argument to the contrary.254 Similar factual disputes as to DSU’s allegation that R+B’s knew PF’s product was not suitable for the architectural application specified255 are shown by competing evidence and argument presented by R+B on that issue. 256 The court reaches the same conclusion with respect DSU’s allegations concerning R+B’s failure to notify it that no one engineered the panels as required by Specification 07435, 257 and that R+B ignored the absence of V-Channels, or “thermal breaks,” purportedly required by the Design Drawings and PFF Product Data. 258 V. CONCLUSION–DSU, W-T, and R+B Cross-Motions for Summary Judgment on DSU’s Count I (Breach of Contract) For the reasons discussed above: 1. Delaware State University’s Motion for Partial Summary Judgment (D.I. 211) is DENIED; 2. Whiting-Turner Contracting, Co.’s Motion for Summary Judgment (D.I. 208) is GRANTED in part and DENIED in part as MOOT.; and 3. Richärd+Bauer, LLC’s Motion for Summary Judgment (D.I. 203) is GRANTED in part and DENIED in part. 253 D.I. 213 at 9-10. See D.I. 226 at 8-11. 255 D.I. 213 at 12-19. 256 See D.I. 11-13. 257 D.I. 213 at 19-25. 258 Id. at 25-27. See D.I. 226 at 13-15 (R+B presenting evidence and argument raising genuine issues of material fact as to these issues). R+B’s alleged failure to report deficiencies in the work, specifically exterior panel buckling, D.I. 213 at 27-28, is addressed by R+B raising questions of fact, inter alia, as to whether the referenced buckling referred to a certain unrelated “wrinkle” in an interior side of one of the panels. See D.I. 226 at 16-17. 254 62 Czar Engineering, LLC’s Motion for Summary Judgment Thomas Company, Inc.’s Motion for Partial Summary Judgment Richärd+Bauer, LLC’s Motion for Summary Judgment Czar moves for summary judgment in its favor as to all claims asserted against it by DSU, R+B, Liberty Mutual, PFF, and Ashford.259 Czar also moves for partial summary judgment as to the claims of TCI limiting any liability to TCI in accordance with its contract.260 TCI moves for summary judgment that: (1) Czar’s limitation of liability clause is unenforceable; (2) the Panel Wall design was not delegated to TCI; (3) R+B’s Panel Wall System was not constructible; and (4) DSU’s proposed repairs constitute economic waste.261 R+B moves for summary judgment in its favor and against all other parties on all claims against R+B.262 The court has ruled, above, on R+B’s motion for summary judgment as to DSU’s breach of contract claim against R+B. As relevant to this section of the opinion, the court considers R+B’s motion for summary judgment in its favor as to 259 D.I. 215 (Czar Engineering, LLC Motion for Summary Judgment). Briefing on the motion is found at D.I. 216 (Czar Opening Brief); D.I. 224 (TCI Answering Brief); D.I. 225 (R+B Answering Brief); D.I. 231 (DSU Consolidated Answering Brief); and D.I. 241 (Czar Reply Brief). 260 D.I. 215. 261 D.I. 217 (Thomas Company, Inc. Motion for Partial Summary Judgment). Briefing on the motion is found at D.I. 218 (TCI Opening Brief); D.I. 225 (R+B Answering Brief); D.I. 230 (Czar Answering Brief); D.I. 231 (DSU Consolidated Answering Brief); and D.I. 235 (TCI Reply Brief). 262 D.I. 203 (Richärd+Bauer, LLC Motion for Summary Judgment). Briefing on the motion is found at D.I. 204 (R+B Opening Brief); D.I. 227 (R+B Amendment to Opening Brief); D.I. 224 (TCI Answering Brief); D.I. 228 (W-T Answering Brief); and D.I. 233 (R+B Reply Brief). 63 the cross-claims against it by the other co-defendants.263 I. BACKGROUND–Czar, TCI, and R+B Motions for Summary Judgment The following facts relevant to the motions discussed in this section of the opinion are taken from the parties’ stipulated facts, exhibits, and deposition excerpts. As previously discussed, this case concerns Structural Insulated Panels or “SIPs” and their integration into the Panel Wall System that includes the SIPs, the design, construction and installation of the SIP connections to the building structure, and other related elements (such as connectors, sealants, and the like) installed as part of constructing the OSCAR Facility on DSU’s main campus in Dover.264 Relevant to Czar’s participation in the Project, this case also involves the structural design of the panel connections with the OSCAR Facility.265 DSU entered into a contract with TCI on or about December 27, 2013 titled AIA® Document A132™–2009, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition for the Wall System (the “DSUTCI Contract”).266 The general terms and conditions governing the DSU-TCI Contract were the AIA232-2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition,267 and all modifications thereto found in “Section 00730–Supplementary General Conditions to the Contract.” 268 263 D.I. 203; D.I. 204 at 16-19. D.I. 195, Stip. Fact 1. 265 Id., Stip. Fact 2. 266 Id., Stip. Fact 14; D.I. 243-3, Stip. Ex. 139. 267 D.I. 243-1, Stip. Ex. 48. 268 D.I. 243-3, Stip. Ex. 140. 264 64 The General Conditions governing DSU and TCI’s relationship states: § 1.1.2 The Contract. [. . .] The Contract Documents shall not be construed to create a contractual relationship of any kind [. . .] (5) between the Owner and a Subcontractor [. . .], or (7) between any persons or entities other than the Owner and Contractor.[ . . .] 269 On or about March 6, 2014, Czar issued a written subcontract proposal to TCI for engineering services in connection with the Panel Wall System, which TCI signed that day and returned along with a purchase order (“TCI-Czar PO”).270 Czar’s contract with TCI incorporates by reference, and physically includes, “CZAR ENGINEER, L.C.C. CONTRACT PROVISIONS” (“TCI-Czar Subcontract”) which provides: 1. CONTRACT - These Contract Provisions and the accompanying Proposal and Fee Schedule constitute the entire Ag reement of the parties, and supersede all prior negotiations, agreements, and understandings with respect to the subject matter of this Agreement. These Contract Provisions shall take precedence over any inconsistency or contradictory provisions contained in any proposal, contract, purchase order, requisition, notice to proceed, or like document. The parties may only amend this Agreement by a written document duly executed by both parties. [. . .] 13. LIABILITY - Czar Engineering, LLC and client each recognize the risks, rewards and benefits of the work that is the subject of this agreement. In recognition of this reality, consultant and client agree that, to the fullest extent permitted by law, the total liability, in the aggregate, of the consultant, and its agents, servants and employees, for all injuries, damages (including damage to the project itself), losses, expenses or claims whatsoever related to services provided by the consultant under this agreement, including but not limited to negligence, errors, omissions, Strict liability, breach of contractor any claim whatsoever, shall not exceed six times the total fees paid to the consultant under this agreem ent, or 269 D.I. 243-1, Stip. Ex. 48 § 1.1.2 (emphasis added). D.I. 195, Stip. Fact 20; D.I. 243-1, Stip. Ex. 2; see also D.I. 243-11 (Thomas Dep.) at 81:9-21. 270 65 S50,000, whichever is greater. Furthermore, consultant and client agree that the consultant's liability shall not exceed the available amount of the professional liability insurance coverage for the sub-consultant at the time that the claim is resolved either by settlement, arbitration award or final judgment. Any requests by client that the sub-consultant increase its limits of professional liability insurance coverage must be made in writing to consultant within fourteen (14) days of the date of this agreement. [. . .] 15. INDEMNIFICATION - Czar Engineering, L.L.C. shall, subject to the limitation of liability contained in Section 13, indemnify the Client for any loss or damage caused solely by the professional negligence of Czar Engineering, L.L.C. in performance of the services under this Agreement.271 The purchase order that TCI emailed back to Czar after signing the contract contains the language as follows: THIS ORDER IS COMPLETE WITH ALL THE ITEMS NECCESSARY [sic] AND INCIDENTAL THERE TO IN STRICT ACCORDANCE WITH THE ENTIRE CONTRACT DOCUMENTS PREPARED [sic] THE OWNER AND/OR THEIR CONSULTANT, INCLUDING WITHOUT LIMITATION: THE GENERAL, SPECIAL AND OTHER CONDITIONS, ALL SPECFICIATIONS, [sic], DRAWINGS, AND INVITATIONS FOR BIDS, BULLETINS, ADDENDA AND MODIFICATIONS THERETO. NO OTHER CHANGES WILL BE ACCEPTED EXCEPT THOSE STATED HEREIN AND AS PER THE CONTRACT DOCUMENTS. PROVIDE WRITTEN DOCUMENTATION INDICATING IMPACTS FOR CHANGES AND REVISIONS, WHEN REQUESTED.272 TCI’s Corporate Designee, George J. Thomas, testified that, pursuant to the TCICzar Subcontract, Czar provided engineering calculations and design detailing for the connections which held the Panels to the exterior of the building.273 TCI also entered 271 D.I. 243-1, Stip. Ex. 2 at “CZAR ENGINEER, L.C.C. CONTRACT PROVISIONS” ¶¶ 1, 13, 15 (emphasis added). 272 D.I. 243-1, Stip. Ex. 2 (emphasis added). 273 D.I. 216 at 5 (citing D.I. 243-11 (Thomas Dep.) at 81:9-82:20, 260:17-262:4). 66 into agreements with Ashford to provide computer aided design drafting services and separately with PFF to manufacture and supply the SIPs.274 Czar had no other contract with any other party involved in the Project. 275 In addition to its contract with TCI, DSU also entered into written agreements with R+B to provide overall design services, and W-T to provide construction management services for the Project.276 The original cost of the SIPs was $749K.277 Sometime early in 2015, following installation of the SIPs but before full construction of the building was completed in the summer of 2015, some Panels began to exhibit deformations.278 The condition of the building façade has existed for over four years since the problems were noted, though the conditions have progressed.279 There were no personal injuries that resulted from the alleged defects. No water intrusion has been noted, but Bartlett testif ied he believed advanced study would be required to make a definitive determination.280 The building is occupied and being used for its intended purpose. 281 No equipment has been damaged because of the alleged defects.282 DSU’s corporate designee agreed that there have been no resulting effects from the panels’ present condition “other than 274 Id. Id. 276 Id. 277 D.I. 243-3, Stip. Ex. 96. 278 D.I. 243-13 (Bartlett Dep.) at 98:4-18; D.I. 216 at 5. 279 Id. (Bartlett Dep.) at 98:19-99:7. 280 Id. (Bartlett Dep.) at 99:11-100:2. 281 Id. (Bartlett Dep.) at 100:3-14. 282 Id. (Bartlett Dep.) at 101:8-10. 275 67 it doesn’t look good.”283 II. DISCUSSION–Czar, TCI, and R+B Motions for Summary Judgment A. Positions of the Parties–Czar, TCI, and R+B Motions for Summary Judgment 1. Czar Czar argues it is entitled to summary judgment because: 1. As to DSU’s Count I (Breach of Contract), there is no contract between DSU and Czar, and the General Conditions governing the Project expressly state that DSU is not a third-party beneficiary of the agreement between Czar and TCI;284 2. As to DSU’s Count III (Negligence), the Economic Loss Doctrine precludes any tort claims, and no exception applies; 285 3. As to DSU’s Count IV (Unjust Enrichment), DSU’s relationships with all codefendants are governed by valid contracts;286 4. As to all cross-claims for contribution, the co-defendants are not tort-feasors as there is no underlying tort–merely alleged breaches of contractual obligations;287 and 5. As to all indemnification claims asserted by all defendants, with the exception of TCI, there are contracts between them.288 6. Czar also argues it is entitled to partial summary judgment limiting its liability 283 Id. (Bartlett Dep.) at 102:13-19. D.I. 216 at 2. 285 Id. 286 Id. 287 Id. 288 Id. 284 68 because the TCI-Czar Subcontract expressly limits Czar’s ultimate liability to $50,000. 289 2. DSU DSU argues Czar’s motion should be denied because as DSU is an intended third-party beneficiary of its subcontracts with TCI.290 3. TCI TCI argues that Czar’s motion for summary judgement seeking enforcement of its limitation of liability provision should be denied because the provision is void under 6 Del. C. § 2704 which prohibits the enforcement of an agreement, relative to the construction of a building, “purporting” to indemnify or hold a contracting party harmless, as against public policy.291 TCI also affirmatively moves for summary judgment that Czar’s limitation of liability provision is void under § 2704 and/or that provision is ambiguous.292 Additionally, TCI affirmatively moves for summary judgment in its favor that: 1. The Panel Wall System Design was not delegated to TCI;293 2. R+B’s Panel Wall System was not constructible; 294 and 3. DSU’s proposed repairs constitute economic waste.295 4. R+B R+B opposes Czar’s motion asserting Czar’s purported limitation of liability is 289 Id. D.I. 231 at 4. 291 D.I. 224 at 1. 292 D.I. 217; D.I. 218 at 1. 293 D.I. 218 at 2-5, 9-15. 294 Id. at 5-6, 16-17. 295 Id. at 7, 19-20. 290 69 untenable–contractually, statutorily, under applicable precedent, and as a violation of public policy.296 R+B also affirmatively moves for summary judgment in its favor on all crossclaims asserted against it.297 R+B argues no defendant can sustain a prima facie crossclaim against it because they are not supported by required expert opinion on the standard of care, the economic loss doctrine bars the cross-claims in tort, and R+B’s contract was with DSU such that there are no cognizable cross-claims sounding in contract.298 R+B’s Amended Opening Brief contends it is entitled to summary judgment on W-T’s cross-claim for Implied in Contract Indemnification because there is no relationship between R+B and W-T on which the cause of action is based. 299 B. Analysis–Czar, TCI, and R+B Motions for Summary Judgment The court first addresses Czar’s arguments for summary judgment in its favor on DSU’s breach of contract (Count I), negligence (Count III), and unjust enrichment claims (Count IV). Following resolution of DSU’s claims, Czar’s arguments for summary judgment in its favor on all contribution and indemnification cross-claims are addressed. Next the court resolves Czar and TCI’s cross-motions for summary judgment on Czar’s limitation of liability. Finally, as to Czar’s motion, the court resolves R+B’s arguments in 296 D.I. 225 at 2. D.I. 203. 298 D.I. 204 at 2. 299 D.I. 227 at 1-3. With respect to W-T’s cross-claim for Implied Contract Indemnification, R+B originally argued there was no such cause of action. D.I. 204 at 17-18. After filing its opening brief, W-T made R+B aware that Delaware courts have recognized that cause of action, and R+B filed an amended opening brief making its current argument. D.I. 227 at 1-3. 297 70 its affirmative motion that it is entitled to summary judgment on Czar’s cross-claims asserted against R+B. The court concludes this section of the opinion by addressing the remaining issues in the affirmative motions of TCI and R+B, respectively. DSU’s breach of contract claim alleges it “was an intended third-party beneficiary of the agreements reached between Thomas and its subcontractors and suppliers . . . Czar Engineering . . . for the products, services and ongoing information they were obligated to provide specifically for the benefit of DSU[.]”300 and “[u]pon information and belief . . . Czar Engineering . . . was duly bound by the terms and conditions of [its] . . . agreement[], and such obligations extend to DSU as an intended third-party beneficiary of those agreements.”301 Czar asserts it is entitled to summary judgment on that claim because there is no contract between DSU and Czar, and the General Conditions governing the Project expressly state that DSU is not a third-party beneficiary of the agreement between Czar and TCI.302 Whether a party is a third party beneficiary is a question of law for the court.303 Because it is an issue of substance rather than procedure, it is governed by the state law of the forum.304 “‘It is well settled in Delaware that a third-party may recover on a contract made for his benefit. . . . But in order for there to be a third party beneficiary, the contracting parties must intend to confer the benefit.’”305 “The intent to confer a third 300 D.I. 180-2 ¶ 52. Id. ¶ 53. 302 D.I. 216 at 2. 303 Pierce Associates, Inc. v. Nemours Found., 865 F.2d 530, 535 (3d Cir.1988). 304 Id. 305 Id. (quoting Ins. Co. of North America v. Waterhouse, 424 A.2d 675, 679 (Del. Super. 1980)); see also Hadley v. Shaffer, No. CIV.A. 99-144-JJF, 2003 W L 21960406, 301 71 party beneficiary benefit is to be determined from the language of the contract.”306 The party attempting to assert third-party beneficiary status bears the burden of demonstrating that status.307 Thus, the intent to confer third-party beneficiary status on DSU must be determined from the language of the TCI-Czar Subcontract. As in Pierce, however, “[t]he language of a contract . . . cannot be divorced from the context in which it was written. Here, we are dealing with a general contract and a subcontract in the construction industry.”308 The court determines that DSU is not an intended third-party beneficiary of the TCI-Czar Subcontract. DSU argues Czar entered into its subcontract with TCI knowing it was for the benefit of DSU.309 The reality that DSU would ultimately benefit from the TCI-Czar at *5 (D. Del. Aug. 12, 2003) (“Under Delaware law, the intention of the contracting parties is paramount in determining whether others have standing as third-party beneficiaries.” (citing See E.I. DuPont & Co. v. Rhone Poulenc Fiber & Resin Intermediates, S.A.S., 269 F.3d 187, 197 (3d Cir. 2001)). 306 Pierce, 865 F.2d at 535 (citing Oliver B. Cannon & Sons, Inc. v. Dorr-Oliver, Inc., 336 A.2d 211, 215 (Del.1975); Royal Indemnity Co. v. Alexander Indus., Inc., 211 A.2d 919, 920 (1965)). 307 See Corrugated Paper Prods., Inc. v. Longview Fibre Co., 868 F.2d 908, 910 (7th Cir. 1989) (applying New Jersey law, which, like Delaware law, “‘focuses on whether the parties to the contract intended others to benef it from the existence of the contract, or whether the benefit so derived arises merely as an unintended incident of the agreement’”) (quoting Broadway Maint. Corp. v. Rutgers, the State Univ., 447 A.2d 906, 909 (N.J. 1982)); see also Beth Schiffer Fine Photographic Arts, Inc. v. Colex Imaging, Inc., C.A. No. 10-cv-5321 (MHW), 2014 WL 1908500, at *4 (D.N.J. May 13, 2004) (“The party attempting to assert third party beneficiary status bears the burden.” (applying New Jersey Law) (citing Corrugated Paper Prods., 868 F.2d at 910)). 308 Pierce, 865 F.2d at 535. 309 D.I. 231 at 37. 72 Subcontract does not establish that DSU was an intended third-party beneficiary of that contract. “In every construction subcontract the owner is the one which ultimately benefits from its performance. However, this does not create a third party beneficiary relationship.”310 The Pierce court explained the usual industry practice in the construction field. Typically when major construction is involved an owner has neither the desire nor the ability to negotiate with and supervise the multitude of trades and skills required to complete a project. Consequently an owner will engage a general contractor. The general contractor will retain, coordinate and supervise subcontractors. The owner looks to the general contractor, not the subcontractors, both for performance of the total construction project and for any damages or other relief if there is a default in performance. […] Thus the typical owner is insulated from the subcontractors both during the course of construction and during the pursuit of remedies in the event of a default. Conversely, the subcontractors are insulated from the owner. The owner deals with and, if necessary, sues the general contractor, and the general contractor deals with and, if necessary, sues the subcontractors. These typical construction contract relationships have long been recognized.311 Pierce and the Delaware Supreme Court in Oliver B. Cannon & Son, Inc. v. Dorr-Oliver, Inc., each noted this usual contractual relationship creates a “buf fer” 310 Pierce, 865 F.2d at 538 (emphasis added); see also Hadley v. Shaffer, No. CIV.A. 99-144-JJF, 2003 WL 21960406, at *5 (D. Del. Aug. 12, 2003) (“Thus, if it was not the promisee's intention to confer direct benefits upon a third party, but rather such third party happens to benefit from the performance of the promise either coincidentally or indirectly, then the third party will have no enforceable rights under the contract.” (citing Guardian Constr. Co. v. Tetra Tech Richardson, Inc., 583 A.2d 1378, 1386 (Del. Super. 1990)). 311 Pierce, 865 F.2d at 535-36. 73 between the owner and subcontractors. 312 Examining the DSU-TCI Contract and TCI-Czar Subcontract reveals no intent to create third-party beneficiary status on DSU with respect to Czar. TCI’s obligations to DSU are governed by the AIA ® Document A132™--2009, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition for the Wall System, executed on or about December 27, 2013. 313 Article 1 of that contract incorporates the general terms and conditions enumerated by the AIA232-2009 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition (“DSU-TCI Contract”).314 The general conditions which govern the DSU-TCI relationship state: § 1.1.2 The Contract. [. . .] The Contract Documents shall not be construed to create a contractual relationship of any kind […] (5) between the Owner and a Subcontractor [. . .], or (7) between any persons or entities other than the Owner and Contractor.[. . .] 315 Thus, the DSU-TCI Contract explicitly disclaims an intent to create third-party beneficiary status on DSU with respect to TCI’s subcontractors on the Project. As stated in Pierce, however, the court’s analysis “cannot be divorced from the context in 312 Id. at 536 (“In Cannon the Delaware Supreme Court referred to the ‘buffer zone’ which a general contract creates between the owner and a subcontractor. . . .”); Cannon, 336 A.2d at 216 (finding the “buffer zone” in that case extinguished where the subcontract evidence of intention to confer third-party beneficiary status on owner); see also Galvagna v. Marty Miller Constr., Inc., No. CIV. A. 96L-01-015, 1997 W L 720463, at *3 (Del. Super. Sept. 19, 1997) (“In construction m atters, the parties generally craft their contracts to insulate the owner from the subcontractor; the owner and general contractor deal with one another while the general contractor and subcontractor deal with one another.” (citing Pierce, 865 F.2d at 535-39)). 313 D.I. 195, Stip. Facts, ¶ 14; D.I. 243-3, Stip. Ex 139. 314 D.I. 243-2, Stip. Ex. 48. 315 D.I. 243-2, Stip. Ex. 48, § 1.1.2. 74 which it was written. Here, we are dealing with a general contract and a subcontract in the construction industry.”316 After review of the TCI-Czar PO, the court concludes it also does not evidence an intent to bestow that third-party beneficiary status on DSU. The PO provides: THIS ORDER IS COMPLETE WITH ALL THE ITEMS NECCESSARY [sic] AND INCIDENTAL THERE TO IN STRICT ACCORDANCE WITH THE ENTIRE CONTRACT DOCUMENTS PREPARED [sic] THE OWNER AND/OR THEIR CONSULTANT, INCLUDING WITHOUT LIMITATION: THE GENERAL, SPECIAL AND OTHER CONDITIONS, ALL SPECFICIATIONS, [sic], DRAWINGS, AND INVITATIONS FOR BIDS, BULLETINS, ADDENDA AND MODIFICATIONS THERETO. NO OTHER CHANGES WILL BE ACCEPTED EXCEPT THOSE STATED HEREIN AND AS PER THE CONTRACT DOCUMENTS. PROVIDE WRITTEN DOCUMENTATION INDICATING IMPACTS FOR CHANGES AND REVISIONS, WHEN REQUESTED317 DSU argues this language shows Czar is “subject to performing its work in strict compliance with the contract documents and General Conditions prepared by the Owner.”318 That argument is little more than saying the language provides DSU, as owner, will benefit from the TCI-Czar Subcontract; the expected result of every subcontract. DSU also argues the TCI-Czar Subcontract does not disclaim the creation of a third-party beneficiary relationship between the Owner and subcontractor. 319 This is precisely the wrong inquiry; the court must determine whether there was an intent to create third-party beneficiary status on the part of DSU, not whether such status exists 316 Pierce, 865 F.2d at 535. D.I. 243-1, Stip. Ex. 2. 318 D.I. 231 at 38. 319 D.I. 231 at 38. 317 75 absent disclaimer.320 The language quoted above evidences no such intent. Additionally, DSU does not point to any other evidence from the TCI-Czar Subcontract showing an intent that DSU would have enforceable rights thereunder against Czar. By way of comparison, such evidence of intent was found by the Delaware Supreme Court in Oliver B. Cannon & Son, Inc. v. Dorr-Oliver, Inc., where the court found the owner was a third-party beneficiary of a subcontract that contained indemnification and warranty provisions directly conveying benefits from the subcontractor to the owner.321 Here, in contrast, the liability and indemnification provisions in “CZAR ENGINEER, L.C.C. CONTRACT PROVISIONS,” which DSU does not dispute is incorporated by reference in Czar’s contract with TCI, speaks only to Czar’s obligations with respect to TCI. Consequently, because the court determines DSU is not an intended third-party beneficiary to the TCI-Czar Subcontract, Czar’s motion to for summary judgment on DSU’s breach of contract claim is granted. DSU’s Count III negligence claim alleges “Czar . . . provided . . . engineering and design information on an ongoing basis throughout the instant project, and answered questions posed in connection with that information. The engineering and design information and recommendations provided by [Czar] was not incidental to [its] overall engagement in this case” upon which DSU relied and was damaged, “including but not 320 Cf. William M. Young Co. v. Bacon, C.A. No. 89L-JA2, 1991 WL 89817, at *4 (Del. Super. May 1, 1991) (“Young argues that Pierce holds that a third-party beneficiary status will exist unless the parties have negated same in the language of the contract. Young's position is incorrect.”). 321 See Cannon, 336 A.2d at 215-16. 76 limited to damages to the building structure and property other than the panel wall itself.”322 Czar contends DSU’s attempt to put forth a theory of recovery based on an independent negligence or negligent misrepresentation claim cannot be sustained because the economic loss doctrine bars any tort claim unless DSU can show facts sufficient to allow recovery under one of the exceptions allowed by Delaware case law.323 Czar asserts DSU cannot make that showing.324 The economic loss doctrine prohibits a party who has suffered only economic loss from maintaining a tort claim: rather it must sue in contract. 325 Czar contends DSU’s allegation it has suffered “damages to the building structure and property other than the panel wall system itself” is not supported by the evidence.326 According to Czar, DSU’s corporate designee testified he agrees there have been no resulting effects from the panels’ condition “other than it doesn’t look good.”327 Czar argues there are no allegations of personal injury, and, there is no 322 D.I. 180-2 ¶¶ 64-69. D.I. 216 at 8. 324 Id. 325 Danforth v. Acorn Structures, Inc., 608 A.2d 1194 (Del. 1992) (“The economic loss doctrine is a judicially created doctrine that prohibits recovery in tort where a product has damaged only itself (i.e., has not caused personal injury or damage to other property) and, the only losses suffered are economic in nature.”) (footnote omitted); see also Noramco (Delaware), Inc. v. Carew Assoc., Inc., C.A. No. 85C-MY54, 1990 WL 251572, at *3 (Del. Super. Nov. 29, 1990) (“When damages consist solely of a financial nature and there is no personal injury or other property damage, the economic loss doctrine will apply and a claim under a contract or warranty theory may lie as opposed to a claim of negligence, i.e., a tort liability claim.”). 326 D.I. 216 at 8 (quoting D.I. 180-2 ¶ 69). 327 Id. (quoting D.I. 243-13 at 102:13-19). 323 77 evidence of “other” damage based on DSU’s corporate designee’s testimony that the building is being used for its intended purpose, no equipment has been damaged, and he was not aware of any water intrusion.328 Czar insists, therefore, the economic loss doctrine precludes all tort claims, absent an exception to that doctrine. 329 “Delaware has recognized an exception to the economic loss doctrine with the adoption of § 552 of the Restatement (Second) of Torts.”330 The Restatement provides: (1) One who, in the course of his business, profession or employment, or in any other transaction in which he has a pecuniary interest, supplies false information for the guidance of others in their business transactions, is subject to liability for pecuniary loss caused to them by their justifiable reliance upon the information, if he fails to exercise reasonable care or competence in obtaining or communicating the information. (2) [t]he liability stated in Subsection (1) is limited to loss suffered (a) by the person or one of a limited group of persons for whose benefit and guidance he intends to supply it; and (b) through reliance upon it in a transaction that he inten ds the information to influence or knows that the recipient so intends or in a substantially similar transaction.331 “[F]or a plaintiff to maintain a claim under § 552 in Delaware, two elements must be present: (1) ‘the defendant supplied the information to the plaintiff for use in business transactions with third parties’ and that (2) ‘the defendant is in the business of 328 Id. Id. 330 Delaware Art Museum v. Ann Beha Architects, C.A. No. 06-481-GMS, 2007 WL 2601472, * 2 (D. Del. Sept. 11, 2007) (citing Guardian Constr. Co. v. Tetra Tech Richardson, Inc., 583 A.2d 1378, 1386 (Del. Super. 1990)). 331 Restatement (Second) of Torts § 552 (emphasis added). 329 78 supplying information.’”332 Czar argues that because DSU does not allege other than economic damages, Czar would have to fall within the § 552 exception to the economic loss doctrine for it to be potentially liable, but DSU cannot show either element applies.333 Czar contends the first exception does not apply because DSU does not allege, and cannot show, that the information Czar supplied by way of engineering and designing the connections was relied upon by DSU to pursue a business transaction with any other party.334 By the time Czar was engaged by TCI, in March 2014,335 DSU had already entered into its contracts with R+B, W-T, and TCI.336 Czar also states that prior to the TCI-Czar Subcontract, TCI had already entered into its agreements with PFF and Ashford.337 Czar was the last of the parties to be brought onto the project in March 2014, thus demonstrating this element is not met.338 As support, Czar cites Figg Bridge Engineers, Inc., where the court dismissed a similar § 552 claim by the 332 Delaware Art Museum, 2007 WL 2601472, at *2 (quoting Christiana Marine Servs. Corp. v. Texaco Fuel and Marine Mktg. Inc., C.A. No. 98C–02–217WCC, 2002 WL 1335360, at *6 (Del. Super. June 13, 2002) and citing Millsboro Fire Co. v. Constr. Mgmt. Serv., C.A. No. 05C-06, 2006 WL1867705, at *2 (Del. Super. June 7, 2006)); see also State Dep't of Transp. v. Figg Bridge Engineers, Inc. , C.A. No. S11C-01-031 RFS, 2011 WL 5593163, at *5 (Del. Super. Nov. 9, 2011). 333 D.I. 216 at 9. 334 Id. 335 D.I. 195, Stip. Fact, ¶ 20. 336 Id., Stip. Facts, ¶ 7 (R+B, Jan. 20, 2012), ¶ 12 (W -T, Jan. 12, 2012), ¶ 14 (TCI, Dec. 27, 2013). 337 D.I. 216 at 10; see D.I. 195, Stip. Facts, ¶ 16 (“On or about January 15, 2014, Thomas Co. made its initial submission of PFF’s Product Data to Whiting-Turner for review.” (See Stip. Ex. 33.)), ¶ 18 (“R+B reviewed the PFF Product Data and returned it to Whiting-Turner on January 23, 2014.” (See Stip. Ex. 34)). 338 D.I. 216 at 10. 79 Delaware Department of Transportation (“DelDOT”) against an engineering firm for the same reason: “[i]t cannot be said that DelDOT relied on the reports to pursue a business transactions with [the general contractor] because the DelDOT[‘s contract with the general contractor] was executed long before [the engineering firm’s] reports were prepared.”339 Thus, Czar asserts DSU could not have relied on information it supplied in pursuit of business transactions with the other defendants because those transactions occurred prior to Czar providing the information at issue.340 Demonstration that the first § 552 element is not met, alone, is enough to grant Czar’s motion for summary judgment on the negligence claim.341 Czar also contends the second element, being “in the business of supplying information,” is not met because, for Czar to fall within this exception, it must have been a “pure information provider.”342 Under Delaware law, architects and engineers who design particular components of a project are not pure information providers and, therefore, do not fall within the second element of the § 552 exception to the economic loss doctrine.343 339 D.I. 216 at 10 (quoting Figg Bridge Engineers, 2011 WL 5593163, at *5). Id. 341 See Figg Bridge Engineers, 2011 WL 5593163, at *5 (finding the first element not met, “whether [the engineering firm] is a pure information provider is not reached”). 342 D.I. 216 at 10 (citing Delaware Art Museum, 2007 WL2601472, at *2; RLI Ins. Co. v. Indian River School Dist., 556 F. Supp. 2d 356, 361-2 (D. Del. 2008); Millsboro Fire Co., 2006 WL 1867705, at *2; Christiana Marine Servs. Corp., 2002 WL 1335360, at *5; Riverbend Cmty., LLC v. Green Stone Eng'g, LLC, C.A. No. N10C-07-042 MMJ, 2012 WL 1409013 (Del. Super. Apr. 4, 2012) aff'd, 55 A.3d 330 (Del. 2012)). 343 See, e.g., Millsboro, 2006 WL 1867705, at *1 (finding defendant engineer, responsible for designing the “heating, ventilation and air conditioning (‘HVAC’), as well as the electrical and plumbing systems on the Project” to be outside of § 552); Delaware Art Museum, 2007 WL 2601472, at *4 (dismissing the plaintiff’s negligence 340 80 Czar contends there is no dispute that it provided engineering and design for the connections of the Panel Wall System to the main building structure as part of the overall Project and that all parties have testified and will acknowledge at trial that Czar designed a component part of the Project.344 Based on Czar’s role in the Project, and the authority it cites, Czar urges the court to determine the second § 552 element is not met because Czar is not a pure information provider and, therefore any potential tort claims against it by DSU are barred by the economic loss doctrine.345 The court agrees that Czar was not a pure information provider and is also entitled to summary judgment on DSU’s Count III negligence claim. Additionally, DSU did not respond to Czar’s arguments regarding its Count III negligence claim. “[W]here a party responds to a dispositive motion, but only addresses some subset of the arguments that are the subject of the motion, courts have consistently misrepresentation claim based on the engineer defendant’s design of parts of the project did not meet the § 552 information provider exception to the economic loss doctrine). This court’s opinion in Kuhn Const. Co. v. Ocean & Coastal Consultants, Inc. relied on Delaware state cases when it applied the economic loss doctrine and dismissed negligence/negligent misrepresentation claims by a builder against an engineer, stating “the current weight of authority suggests that the exception does not apply; the provision of plans and drawings in connection with a construction project is considered to be information that is incidental to the sale of a finished, tangible product.” 844 F. Supp. 2d 519, 529 (D. Del. 2012) (citing Christiana Marine, 2002 WL 1335360, at *7 (adopting Tolan and Son, Inc. v. KLLM Architects, Inc., 719 N.E.2d 288, 296 (Ill. 1999)); Millsboro, 2006 WL 1867705, at *3)). 344 D.I. 216 at 11. 345 Id. 81 held that the claims that are not defended are deemed abandoned.” 346 DSU was on notice of Czar’s arguments that there are no genuine issues of material fact precluding summary judgment in its favor on Count III. DSU chose to challenge only a subset of Czar’s arguments, its status as third-party beneficiary to the TCI-Czar Subcontract. Based on DSU’s failure to respond, and the evidence and argument Czar provides in support of its motion on DSU’s negligence claim, the court determines that claim is abandoned and Czar’s motion for summary judgment on Count III is granted. Lastly, DSU alleges separate claims of breach of contract and unjust enrichment against Czar.347 Czar argues that DSU’s unjust enrichment claim in Count IV fails because such a claim may not be asserted along with a contract claim.348 In Wood v. Coastal States Gas Corp., the Delaware Supreme Court stated that “[b]ecause the contract is the measure of plaintiffs’ right, there can be no recovery 346 Baldonado v. Avrinmeritor, Inc., C.A. No. 13-833-SLR-CJB, 2014 W L 2116112, at *7 (D. Del. May 20, 2014) (citing cases), report and recommendation adopted, C.A. No. 13-833-SLR/CJB, 2014 W L 2621119 (D. Del. June 10, 2014). The Baldonado court contrasted cases, as here, where a party responded to a dispositive motion and addressed only a subset of the movant’s arguments from cases where a party fails to respond in any way to a dispositive motion. Id. at *7 n.6 (citation omitted). The court reiterated that where a party responds to only a subset of the movant’s arguments, “the unaddressed claim is deemed abandoned.” id.; see also Blakeman v. Freedom Rides, Inc., C.A. No. 12-416-LPS-CJB, 2013 W L 3503165, at *13 (D. Del. July 10, 2013) (same); Butorin v. Blount, C.A. No. 15-283-LPS, 2018 W L 4700217, at *1 n.1 (D. Del. Sept. 30, 2018) (determining that by responding to arguments with respect to one claim in a motion to dismiss all claims, the plaintiff abandoned its other claims); Seals v. City of Lancaster, 553 F. Supp. 2d 427, 432 (E.D. Pa. 2008) (“Plaintif f's failure to mention these issues in her summary judgment response constitutes abandonment of those claims.”). 347 D.I. 180-2 (Counts I and IV). 348 D.I. 216 at 11. 82 under an unjust enrichment theory independent of it.”349 Following Wood, the Delaware Court of Chancery explained in Kuroda v. SPJS Holdings, L.L.C.: Unjust enrichment is “the unjust retention of a benefit to the loss of another, or the retention of money or property of another against the fundamental principles of justice or equity and good conscience.” A claim for unjust enrichment is not available if there is a contract that governs the relationship between parties that gives rise to the unjust enrichment claim. In other words, if “the contract is the measure of [the plaintiff's] right, there can be no recovery under an unjust enrichment theory independent of it.” Thus, “[w]hen the complaint alleges an express, enforceable contract that controls the parties' relationship . . . a claim for unjust enrichment will be dismissed.”350 DSU alleges, albeit unsuccessfully on a third-party beneficiary theory, the existence of a contract and seeks to enforce that contract through Count I.351 Czar maintains that even if DSU were to argue that the unjust enrichment claim should not be dismissed as to Czar because DSU is not party to the TCI-Czar Subcontract, or vice versa, that argument would fail “because unjust enrichment cannot be used to circumvent basic contract principles recognizing that a person not a party to a contract cannot be held liable to it.” 352 DSU did not respond to Czar’s arguments regarding Count IV. As with Count III, DSU was on notice of Czar’s arguments that there are no genuine issues of material fact precluding summary judgment in its favor on its unjust 349 401 A.2d 932, 942 (Del. 1979). 971 A.2d 872, 891 (Del. Ch. 2009) (citations om itted); see also Doberstein v. G-P Indus., Inc., C.A. No. 9995-VCP, 2015 W L 6606484, at *6 (Del. Ch. Oct. 30, 2015) (dismissing the plaintiff’s unjust enrichment claim because she could not identify “any factual basis for her unjust enrichment claim independent of the allegations relating to her breach of contract claim”). 351 D.I. 216 at 12. 352 D.I. 216 at 12 (quoting Kuroda, 971 A.2d at 891-92 (citation omitted)). 350 83 enrichment claim. Based on Czar’s arguments supporting its motion on that claim, and DSU’s failure to respond, the court determines that claim is abandoned and Czar’s motion for summary judgment on Count IV is granted.353 Czar next argues there can be no viable contribution claims where there is no underlying tort.354 Delaware’s Uniform Contribution Among Tortfeasors Law, 10 Del. C. § 6301 et seq. (“UCATL”) requires the establishment of joint tortfeasor status.355 As discussed above, the court has dismissed DSU’s tort claims against Czar. TCI and DSU have voluntarily dismissed all of the claims each asserted against each other. 356 As discussed below, the court dismisses DSU’s tort claims against PFF. DSU does not assert tort claims against R+B or W-T. As a result, there are no remaining codefendants that could establish joint tortfeasor status with Czar, and none have 353 In its opening brief, Czar argues that even if DSU is a third-party beneficiary of the TCI-CZAR Subcontract, DSU is subject to the same liability limitations in that contract. Id. at 7-8 (citing NAMA Holdings, LLC v. Related World Mkt. Ctr., LLC, 922 A.2d 417, 431 (Del. Ch. 2007)). By not responding to that argument, Czar argued DSU conceded that point. D.I. 241 at 2. Because the court determ ines DSU is not a thirdparty beneficiary of the TCI-Czar Subcontract, the issue with respect to DSU is moot. The court discusses Czar’s limitation of liability arguments in connection with TCI, and R+B’s arguments on the issue, below. 354 D.I. 216 at 12. 355 See Builders & Managers, Inc. v. Dryvit Sys., Inc., No. Civ. A. 00C11111JEB, 2004 WL 304357, at *2 (Del. Super. Feb. 13, 2004) (“T he right to contribution is triggered when it is appropriate for liability to be apportioned among codefendants. In Delaware, contribution is governed by the UCATL which provides the parameters for determining when contribution is appropriate and how it is to be decided. The inherent requirement is that the parties are joint tortfeasors who share a ‘common liability.’”). (citations omitted); New Zealand Kiwifruit Mktg. Bd. v. City of Wilmington, 825 F. Supp. 1180, 1186 (D. Del. 1993) (“Indispensable to a joint tortf easor relationship is a ‘common liability’ either ‘joint’ or ‘several’ that two or more parties have to the person injured. Without this dual liability . . . no right of contribution can exist.”) (omission in original) (citation omitted). 356 See D.I. 257. 84 responded to its motion on the contribution cross-claims. Thus, Czar’s motion is granted as to contribution cross-claims asserted against it. Other than TCI, no defendant has pled the existence of a contract with Czar whereby Czar is obligated to indemnify any defendant. Czar’s opening brief states all claims for indemnification by all defendants, except TCI, fail because there is no contract or common law right of indemnification and, therefore, none can claim a right of contractual indemnity against Czar.357 R+B, the remaining co-defendant generally alleging a cross-claim for indemnification against all other co-defendants,358 does not respond to Czar’s motion on that claim, and has not alleged a right of contractual indemnity against Czar. Thus, Czar’s motion is granted as to R+B’s indemnification cross-claim. Finally, Czar moves for summary judgment in its favor that Czar’s liability, if any, is limited to $ 50,000. 359 Czar contends its clear and unambiguous contractual obligation to indemnify TCI is entirely found in ¶ 15 of the TCI-Czar Subcontract, and is limited to the $50,000 cap specified in ¶ 13.360 TCI’s response to Czar’s motion on this issue is limited to arguing that Czar’s limitation of liability provision is unenforceable under 6 Del. C. § 2704, which TCI states prohibits the enforcement of an agreement, relative to the construction of a building, 357 D.I. 216 at 14. After filing its opening brief, Czar advised the court that it erroneously stated that all defendants had filed cross claims for indemnification against Czar, but that PFF and W-T did not file such claims and it was withdrawing any arguments in that section as to PFF and W -T. D.I. 220 at 1. 358 See D.I. 77. 359 See D.I. 216 at 14-20. 360 Id. at 17. 85 “purporting” to indemnify or hold a contracting party harmless, as against public policy.361 TCI also affirmatively moves for summary judgment in its favor restating its § 2704 argument, as well as arguing the limitation of liability clause is unenforceable because it is ambiguous.362 In R+B’s answering brief in opposition to the affirmative motions for summary of DSU, TCI, and Czar, R+B joined TCI’s opening-brief arguments on the limitation of liability issue.363 R+B’s brief does not substantively expand on TCI’s § 2704 unenforceability and ambiguity arguments.364 R+B additionally argues Czar’s limitation of liability clause is unenforceable because the possible damages flowing from the breach of the TCI-Czar Subcontract were easily known to Czar at the time of the contracting, and that the limitation prejudices DSU’s rights in contravention of the General Conditions of the DSU-TCI Contract.365 The court first addresses Czar and TCI’s cross-motions, followed by R+B’s two additional arguments against Czar’s motion on this issue. “The proper construction of any contract . . . is purely a question of law.”366 TCI asserts Czar’s limitation of liability provision is unenforceable under 6 Del. C. § 2704,367 which provides, in relevant part: (a) A covenant, promise, agreement or understanding in, or in connection 361 See D.I. 224 at 1, 3-8. See D.I. 217; D.I. 218 at 5-6, 17-19. 363 D.I. 225 at 10. 364 Id. at 11-12, 14. The court’s discussion of these points in the context of TCI’s arguments, therefore, also resolves R+B’s arguments. 365 D.I. 225 at 10-11, 14. 366 Rhone-Poulenc Basic Chems. Co. v. Am. Motorists Ins. Co., 616 A.2d 1192, 1195 (Del. 1992) (citation omitted). 367 D.I. 218 at 17; D.I. 224 at 3. 362 86 with or collateral to, a contract or agreement . . . relative to the construction, alteration, repair or maintenance . . . of a . . . building . . . purporting to indemnify or hold harmless the promisee or indemnitee . . . for damages arising from liability for bodily injury or death to persons or damage to property caused partially or solely by, or resulting partially or solely from, or arising partially or solely out of the negligence of such promisee or indemnitee or others than the promisor or indemnitor, or its subcontractors, agents, servants or employees, is against public policy and is void and unenforceable, even where such covenant, promise, agreement or understanding is crystal clear and unambiguous in obligating the promisor or indemnitor to indemnify or hold harmless the promisee or indemnitee from liability resulting from such promisee's or indemnitee's own negligence.368 In J.S. Alberici Construction Co. v. Mid-West Conveyor Company, Inc., the Delaware Supreme Court stated “[a]lthough section 2704(a) does not indicate the specific purpose underlying the policy expressed, it does express in broad terms the ‘promisee,’ ‘indemnitee’ and ‘others’ as a class prohibited from contracting away liability for their own negligence.”369 The court held “Section 2704(a) is clear on its face: a contractual provision requiring one party to indemnify another party for the second party's own negligence, whether sole or partial, ‘is against public policy and is void and unenforceable.’”370 Here, by contrast, the limitation of liability provision does not require TCI to indemnify Czar (the second party) from Czar’s (the second party’s) own liability: it places a ceiling on Czar’s liability to TCI for Czar’s liability, i.e., Czar is responsible for 368 6 Del. C. § 2704 (emphasis added). The statute recites three exceptions: any obligation owed to the Department of Transportation pursuant to a contract awarded under Title 17 or Chapter 69 of Title 29; policies of insurance issued by authorized insurance companies: and, indemnity obligations in a partnership agreement of a partnership (whether general or limited), limited liability company agreement, trust agreement, governing instrument of a trust, certificate of incorporation or bylaw. 6 Del. C. §§ 2704(a), (b), (c). 369 750 A.2d 518, 521 (Del. 2013). 370 Id. 87 its liability up to that ceiling. TCI contends Delaware State Legislature’s inclusion of the word “purporting” within § 2704 casts a broad net and is intended to encom pass all conceivable attempts to require one party to indemnify another within the context of a construction contract. 371 The court does not view Czar’s limitation of liability clause as one of those attempts swept into the net of § 2704 unenforceability. Pursuant to § 2704, a provision “purporting to indemnify or hold harmless the promisee or indemnitee . . . for [certain] damages . . . is against public policy and is void and unenforceable.” At issue here, by contrast, is a limitation of liability clause, not a provision attempting to “indemnify or hold harmless” Czar for its actions. The distinction between the two types of clauses made by the Third Circuit in Valhal Corp. v. Sullivan Associates, Inc. 372 is instructive. In an action governed by Pennsylvania law the court explained, “there are differences between a contract which insulates a party from liability and one which merely places a limit on that liability. The difference between the two clauses ‘is . . . a real one.’” 373 There, the court held a limitation of liability clause in an architect’s contract was enforceable and not in violation of Pennsylvania’s Anti-Indemnity Act: The terms of the statute pertain only to indemnity and hold harmless provisions. We have already discussed the very real differences between such clauses and the one in the contract bef ore us. Those differences preclude an assumption that a statute expressing a prohibition against indemnity and hold harmless provisions announces a public policy against 371 D.I. 218 at 17. 44 F.3d 195, 203-07 (3d Cir. 1995). 373 Valhal, 44 F.3d at 202 (citations omitted). 372 88 something as distinct and accepted as limitation of liability clauses.374 The Pennsylvania statute, 68 Pa. Stat. Ann. § 491 (Purdons 1994), as q uoted in Valhal, provides: Every covenant, agreement or understanding . . . in connection with any contract or agreement made and entered into by owners, contractors, subcontractors or suppliers whereby an architect . . . or his[/her] agents . . . shall be indemnified or held harmless for damages . . . arising out of: (1) the preparation or approval by an architect . . . or his[/her] agents . . . of . . . opinions, reports, . . . or specifications, or (2) the giving or the failure to give directions or instructions by the architect . . . Or his[/her] agents . . . Shall be void as against public policy and wholly unenforceable.375 TCI states, but does not explain how, the Pennsylvania “statute’s scope is much narrower than § 2704’s” in dismissing the relevance of Valhal as it relates to this court’s analysis.376 The emphasis added by the Valhal court demonstrates that court’s analysis was focused on the distinction between indemnification or hold harmless provisions versus limitation of liability provisions, a distinction the court considers applicable to 6 Del. C. § 2704, as both the Delaware and Pennsylvania statutes prohibit agreement to indemnify or holding harmless.377 In Daimlerchrysler Corp. v. Pennsylvania Nat. Mut. Cas. Ins. Co., the Superior 374 Id. at 205. Id. at 204 (emphasis added by Valhal court). 376 D.I. 224 at 6. 377 Compare the Delaware Supreme Court’s decision in J.S. Alberici. There, a subcontracting agreement contained a clause to “indemnify, hold harmless and defend” and a Kansas choice of law provision, where the clause would be enforced. The court refused to enforce the choice of law agreement because enforcement of an indemnity agreement completely shielding the party from liability for its own negligent actions pursuant to Kansas law “would be clearly repugnant to the public policy of Delaware.” J.S. Alberici, 750 A.2d at 521. 375 89 Court of Delaware recognized the public policy purpose behind the Act as prohibiting “agreement[s] purporting to hold an owner or general contractor free from liability for its own negligence” because they “undermine[] the strong public policy of placing and keeping responsibility for maintaining a safe workplace on those parties [responsible].”378 In RHA Construction, Inc. v. Scott Engineering, Inc., the Superior Court of Delaware considered a contract for engineering services and construction drawings regarding property RHA intended to develop.379 After the project did not go forward, RHA filed suit and defendants moved for summary judgment that, inter alia, any award of damages arising from the litigation should be limited to fees paid in accordance with a limitation of liability clause in defendants’ contract. 380 Although § 2704 was not at issue in that case, the RHA court noted “[l]imitation of liability clauses that relieve a party of liability for its own negligence are generally disfavored under Delaware law,” but held, based on the facts of that case, limiting the plaintiff’s recovery to fees paid would not be unconscionable. 381 Although neither Daimlerchrysler nor RHA directly address the current issue, the court concludes that § 2704 does not prohibit enf orcement of a limitation of liability 378 No. CIV.A. 01C-04-036, 2003 W L 1903766, at *2-3 (Del. Super. Mar. 17, 2003) (emphasis added) (discussing the contrast between a contractual obligation to procure insurance with the indemnification prohibition of § 2704 in determining whether there was an enforceable action on an insurance policy in face of the statutory prohibition). 379 C.A. N11C-03-013 JRJ CCLD, 2013 WL 3884937 (Del. Super. July 24, 2013). 380 Id. at *7. 381 Id. at *8 (citations omitted). 90 clause. This conclusion is based on the distinction between indemnity and hold harmless clauses versus limitation of liability clauses, the prior enforcement of a similar limitation of liability clause in Delaware, and the purpose of the § 2704 prohibition of indemnity and hold harmless provisions to promote work place safety by incentivizing the parties to perform their work safely. The court also rejects TCI’s argument that effect of enforcing Czar’s limitation of liability clause results in TCI indemnifying Czar for amounts owed in excess of the limitation in contravention of § 2704's indemnification prohibition. 382 Here, setting a ceiling to Czar’s potential liability is not equivalent to TCI indemnifying Czar.383 Although the amount of Czar’s liability is capped, it is still potentially liable for substantial damages for its actions.384 382 D.I. 235 at 2-3. See, e.g., Posttape Assocs. v. Eastman Kodak Co., 537 F.2d 751, 755 (3d Cir. 1976) (“Though it is possible that an agreement setting damages at a nominal level may have the practical effect of avoiding almost all culpability for wrongful action, the difference between the two concepts is nevertheless a real one.”) (applying Pennsylvania law) (citation omitted); Thrash Commercial Contractors, Inc. v. Terracon Consultants, Inc., 889 F. Supp. 2d 868, 575-76 (S.D. Miss. 2012) (“Courts considering the issue have consistently held that a limitation of liability will be found unenforceable if it establishes a limitation of liability that “is so minimal compared to [a party's] expected compensation as to negate or drastically minimize [such party's] concern for the consequences of a breach of its contractual obligations.” (alteration in original) (quoting Valhal, 44 F.3d at 204)). 384 TCI suggests a holding that § 2704 does not bar enforcement of Czar’s limitation of liability will impermissibly amend, change, expand, or alter § 2704 by adding an exception to its application beyond the three specifically set forth in the statute. D.I. 224 at 7-8. An exception is not created by the court’s determination: the statute simply does not bar enforcement of a valid limitation of liability clause. TCI cites City of Dillingham v. CH2M Hill Northwest, Inc., 873 P.2d 1271 (Ak. 1994), where the Alaska Supreme Court considered the enforceability of a $50,000 limitation of liability provision in a contract between the city and an engineering firm. The engineer was required to design a facility for the EPA in connection with a sewage treatment system. 383 91 Thus the court denies TCI’s motion for summary judgment that Czar’s limitation of liability clause is unenforceable under § 2704, and grants Czar summary on that issue. TCI also argues Czar’s limitation of liability clause is unenforceable because it is ambiguous.385 “Clear and unambiguous [contract] language . . . should be given its ordinary and usual meaning. Absent some ambiguity, Delaware courts will not destroy or twist policy language under the guise of construing it.”386 “[A] contract is ambiguous only when the provisions in controversy are reasonably or fairly susceptible of different interpretations or may have two or more different meanings.”387 “If a contract is ambiguous, we will apply the doctrine of contra proferentem against the drafting party and interpret the contract in favor of the non-drafting party. . . . The determination of ambiguity lies Id. at 1273-1274. The Dillingham court examined Alaska’s ant-indemnification statute’s legislative history, and concluded the legislature would have included an exception permitting the enforcement of a limitation of liability provision had it so desired and found the provision void. Id. at 1276-78. Czar points out the Supreme Court of Arizona rejected the same public policy argument in 1800 Ocotillo, LLC v. WLB Grp., Inc., 196 P.3d 222, 226 (2008) where it stated the Dillingham decision “was largely premised upon the Alaska legislature's express rejection of a proposal to exempt liability-limitation provisions when it enacted its anti-indemnification statute.” (citing Dillingham, 873 P.2d at 1276–78) (emphasis added). This court believes, as did the Arizona court, that “[r]ather than presume that our legislature implicitly intended to proscribe liability-limitation provisions, we instead believe the legislature specified those contractual terms it meant to declare unenforceable.” 1800 Ocotillo, LLC, 196 P.3d at 226. 385 D.I. 218 at 18-19; D.I. 235 at 3-4. 386 Rhone-Poulenc Basic Chems. Co. v. Am. Motorists Ins. Co., 616 A.2d 1192, 1195 (Del. 1992) (citations omitted). 387 Rhone-Poulenc, 616 A.2d at 1192, 1196 (Del. 1992) (citations omitted). 92 within the sole province of the court.”388 “[W]here reasonable minds could differ as to the contract's meaning, a factual dispute results and the fact-finder must consider admissible extrinsic evidence. In those cases, summary judgment is improper.”389 TCI contends the terms of Czar’s limitation appear in two paragraphs, with unrelated intervening clauses which, when read together, are internally inconsistent, irreconcilable, and subject to more than one reasonable interpretation. 390 Paragraph 4 of Czar’s proposal letter states: Czar Engineering's work will be limited to work as described herein only. No other structure will be reviewed and we defer to the building contract documents for all other design information. If the Client, Owner, Contractor, or other interested party are aware of deficiencies in the balance of the structure, it is incumbent upon them to notify Czar Engineering, in writing, and additional services would follow under separate contract. Otherwise, Czar Engineering and/or Lamont H. Czar, P.E. cannot and will not accept liability for deficiencies in the balance of the structure.391 TCI contends this paragraph would permit Czar’s liability to TCI to be terminated by the failure of nonparties to notify Czar of deficiencies “in the balance of the structure.” TCI states it is unclear whether Czar’s liability would be limited to $50,000 or otherwise altogether excused if notice was not given to Czar, and that the words “balance of the structure” being undefined only adds to the confusion.392 Czar argues the italicized first sentence of paragraph 4, omitted from TCI’s brief, 388 Osborn ex rel. Osborn v. Kemp, 991 A.2d 1153, 1160 (Del. 2010). GMG Capital Investments, LLC v. Athenian Venture Partners I, L.P. , 36 A.3d 776, 783 (Del. 2012) (citations and footnotes omitted). 390 D.I. 218 at 18. 391 D.I. 243-1, Stip. Ex. 2, March 6, 2014 Czar letter submitting proposal to TCI at 3, ¶ 4 (emphasis added). TCI did not include the italicized first sentence in its brief. 392 D.I. 218 at 18. 389 93 elucidates the intent of the paragraph.393 According to Czar, it was contracted by TCI to design connections only for the exterior SIP panels, and a different engineering firm was separately contracted by DSU to engineer every other aspect of the building.394 Czar maintains that paragraph indicates it will rely on the work performed by DSU’s other engineers and is not liable for errors made by that other engineer in the rest of the building, which it contends is merely stating the obvious.395 Czar acknowledges, however, that “[w]hat may not be obvious . . . is CZAR’s statement here that if these errors become known to anyone along the way, CZAR will seek additional service fees if its work is impacted.”396 Czar insists this provision is not a limitation of liability clause: it is a statement that there is a division of liability between parties to a construction project, where each is responsible for their own conduct.397 The court finds reasonable minds could differ as to the meaning of this language. Czar acknowledges the lack of obviousness in the language, and the statement that Czar “will not accept liability for deficiencies in the balance of the structure” makes it uncertain whether this provision relates to, or impacts, its limitation of liability provision in paragraph 13 of its contract with TCI. These questions must be answered by the finder-of fact. Thus, summary judgment is denied. Paragraph 13 of Czar’s broadly states its liability to TCI for loss caused by Czar’s conduct: 393 D.I. 230 at 4. Id. at 9. 395 Id. 396 Id. (emphasis added). 397 Id. 394 94 shall not exceed six times the total fees paid to the consultant . . . , or $50,000, whichever is greater. Furthermore, consultant and client agree that the consultant’s liability shall not exceed the available amount of the professional liability insurance coverage for the sub-consultant at the tim e that the claim is resolved. . . .398 TCI maintains the italicized language makes this paragraph ambiguous because it suggests the possibility that “the available amount of professional liability insurance” may decrease, or render null, its previously stated $50,000 of insurance coverage.399 Czar argues paragraph 13 is not ambiguous because that language only creates a window for the limits, i.e., (1) the greater of 6X fees paid or $50,000.00; and (2) the available amount of the professional liability insurance coverage at the time that the claim is resolved.400 Czar then states, without citation to the record, the purported amounts of its applicable insurance policy and speculates that its coverage would not be exhausted by its legal fees and potential liability, which could be attested to if necessary.401 The court again finds that reasonable minds could differ as to the impact of Czar’s available amount of insurance coverage, and Czar’s arguments based on extrinsic evidence, and/or attestation thereto, does not allow the court to resolve the ambiguity on summary judgment.402 398 D.I. 243-1, Stip. Ex. 2, ¶ 13 (emphasis added). D.I. 218 at 19; D.I. 235 at 3-4. 400 D.I. 230 at 9. 401 Id. at 9-10. 402 See, e.g., Eagle Indus., Inc. v. DeVilbiss Health Care, Inc., 702 A.2d 1228, 1229, 1232-33 (Del. 1997) (reversing a grant of summary judgment where the court held an indemnification provision to be ambiguous, thus raising factual issues requiring consideration of extrinsic evidence to determine the intended meaning of the provision in light of the expectations of the contracting parties). 399 95 Thus, the court denies TCI’s motion for summary judgment that Czar’s limitation of liability provision is void under § 2703, grants Czar’s motion on the § 2704 issue, and denies Czar’s motion for summary judgment that the its limitation of liability in the TCICzar Subcontract is unambiguous. Because that issue must be resolved by the finder of fact, the court denies TCI’s motion for summary judgment that Czar’s limitation of liability under the contract is void, or unenforceable. R+B’s additional arguments against Czar’s limitation of liability are also unavailing. Delaware courts have evaluated the enforceability of liability limitation clauses using the same criteria for assessing enforceability of a liquidated damages clause.403 Under this analysis, a limitation clause “will not be enforced if possible damages are easy to ascertain or if the terms of the contract are found to be unreasonable.” 404 Here, R+B argues the "possible damages" were easily known at the time of contracting based on TCI’s original contract price of $749K.405 However, R+B then hypothetically contends if Czar's error were discovered at or shortly after the panels were installed, it was easily foreseeable that the cost to remove, replace and reinstall the panels plus any additional remedial actions would have exceeded TCI's original 403 See, e.g., Donegal Mut. Ins. Co. v. Tri-Plex Sec. Alarm Sys., 622 A.2d 1086, 1089 (Del. Super. 1992); Rob-Win, Inc. v. Lydia Sec. Monitoring Inc., No. 04C-11-276, 2007 WL 3360036, at *5 (Del. Super. Apr. 30, 2007) (citing Donegal, 622 A.2d at 1089). 404 RHA Constr., Inc. v. Scott Eng’g, Inc., C.A. N11C-03-013 JRJ CCLD, 2013 Del. Super. LEXIS 301 at *28 (Del. Super. July 24, 2013) (citing Rob-Win, 2017 WL 3360036, at *6). 405 D.I. 225 at 11 (citing D.I. 243-3, Stip. Ex. 139). 96 contract price to acquire and install the panels. 406 Thus, R+B asserts the limitation of $50,000 was unreasonable when made and, therefore, the purported limitation of liability is unenforceable.407 The court disagrees on both points. R+B’s own hypothetical admits the possible damages are not “easy to ascertain.” Damages could be some unknown amount in excess of TCI’s contract if Czar was somehow entirely liable for all damages because no damages could be attributed to the actions of any other party. That is an extremely speculative outcome given the multitude of claims against all defendants by DSU, and among defendants themselves.408 Separately, R+B’s declaration that the $50,000 limitation of liability is unreasonable is made without any analysis or support. Per the TCI-Czar PO, the total fees to be paid Czar were $6,500. 409 The $50,000 liability cap is more than seven times the contemplated payment for Czar’s services. Because R+B makes no showing that Czar’s limitation of liability was unreasonable at the time TCI and Czar agreed to the terms of their contract, the court declines to hold, as a m atter of law, it is unreasonable. 410 406 Id. Id. 408 In the case cited by R+B, RHA, the court found it “untenable to assert the parties would have been able to easily ascertain damages as a result of any alleged breach at the time of contracting” where, inter alia, the project “involved three construction or holding companies, real estate agents, lawyers, engineers, [and] the County government . . . .” RHA, 2013 Del. Super. LEXIS 301, at *28-29. 409 See D.I. 243-1, Stip. Ex. 2. 410 The court notes R+B’s answering brief in opposition to Czar’s motion concludes with the statement that “Czar’s arguments with regard to limitation of liability are untenable and should be rejected” and “requests summary judgment on [this] 407 97 Next, R+B urges the court to find Czar’s limitation of liability clause unenforceable because it somehow prejudices DSU’s rights under DSU’s contract with TCI,411 an argument not advanced by either DSU or TCI themselves. R+B cites the requirement in § 5.3 (Subcontractual Relations) of the General Conditions of the Contract for Construction between DSU and TCI to preserve all such rights in the subcontracts and not to prejudice the Owner’s rights.412 R+B’s theory is that § 5.3 governs TCI’s subcontracting with Czar, Czar’ limitation of liability prejudices DSU’s rights because DSU did not contract for a limitation of liability on the services TCI was required to provide, and, therefore, there should be no limitation of liability for TCI’s subcontractors, i.e., Czar.413 The General Terms and Conditions of the DSU-TCI Contract were not incorporated in the TCI-Czar Subcontract, a contract to which the court has determined DSU is not a third-party beneficiary. The provision R+B cites is an obligation of TCI to DSU, a breach of which creates a potential claim by DSU against TCI, not against Czar. R+B’s argument is rejected. issue[].” D.I. 225 at 15. R+B’s affirmative motion for summary judgment (D.I. 203) seeks judgment in its favor on Czar’s cross-claims against R+B. See D.I. 204 at 4, 1617 (addressing Czar’s cross-claims for indemnity and contribution). R+B did not move for summary judgment on the disputed limitation of liability clause in the TCI-Czar Subcontract. 411 D.I. 225 at 13. 412 Id. (citing D.I. 243- Stip. Ex. 48, General Conditions, § 5.3 (“. . . Each subcontract agreement shall preserve and protect the rights of the Owner, Construction Manager and Architect under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights . . . .”)). 413 Id. 98 The remaining issues from TCI’s affirmative motion is whether the design of the Panel Wall System was delegated to TCI, and whether the Panel System was constructible. TCI asserts the panel design was not delegated to TCI. TCI contends whether it was responsible for the panel design depends upon whether the court determines Specification 07435 pertaining to the Wall Panels, is a “performance” specification or a “design” specification.414 R+B argues TCI’s position that the Panel Design was not delegated to TCI is based on the erroneous, and disputed, prem ise that the Specification is not a Performance Specification that delegated design to TCI.415 R+B prepared Specification 07435 - INSULATED METAL WALL PANELS (Addendum 3, 11/14/2013) for the Panel Wall System.416 R+B used Permatherm as its basis of design for the panels, and the Specifications listed both Permatherm and PFF as acceptable panel manufacturers.417 The Specification provided in part at Part I: General: Construct panel system to provide for expansion and contraction of component materials without causing buckling, failure of joint seals, undue stress on fasteners, other detrimental effects to the panel system or adjacent building systems, or warping of faces of panel system.418 It further provided in part at Part 1.5, Submittals: 414 D.I. 218 at 9 (citing D.I. 243-1, Stip. Ex. 3). TCI explains the term the term “performance specification” is synonymous with “delegated design. Id. at 9 n.14. 415 D.I. 225 at 6. 416 D.I. 243-1, Stip. Ex. 3; D.I. 195, Stip. Fact 9 (identifying this as the “Specifications”). 417 D.I. 195, Stip. Fact. 10. 418 D.I. 243-1, Stip. Ex. 3 at DSU 006176. 99 D. Engineered Drawings and Calculations: For installed products indicated to comply with certain design loadings, include structural analysis data and design prepared by an independent third party signed and sealed by the qualified professional engineer responsible for their preparation. 1. Panel engineering to be prepared by the following, or another qualified engineer submitted and approved in accordance with prior approval process. a. Paul D. Hatch, PE, PC, [xxxx xxxxxx xxxxx xxxx], Ellijay, GA 30540. Phone: [xxx-xxx-xxxx]; E-mail: [xxxxxxxx]@bellsouth.net. 419 On December 27, 2019, DSU entered into a contract with TCI entitled AIA® Document A132™ – 2009, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition for the Wall System.420 On January 17, 2014, TCI advised W-T it had selected PFF as its manufacturer of record on the Project. 421 TCI and R+B each submit evidence suggesting disagreements as to what the Specifications require of TCI with respect to its contested Panel W all System design responsibilities,422 TCI acknowledges “Courts have confronted [the] issue [of whether a contract provides a performance specification or a design specification], with varying results as the inquiry is largely fact driven.”423 The court finds this to be a case where the competing arguments and facts preclude the court holding, as a matter of law, that the TCI was not delegated design responsibility. Thus, TCI’s motion for summary 419 Id., Stip. Ex. 3 at DSU 00617. D.I. 243-3, Stip. Ex. 139; D.I. 195, Stip. Fact 14. 421 D.I. 243-1, Stip. Ex. 33. 422 See D.I. 218 at 2-5; D.I. 225 2-4. 423 D.I. 218 at 10 (emphasis added). 420 100 judgment is denied on this issue. TCI’s also seeks summary judgment that R+B’s Panel Wall System was not constructible.424 In its opening brief, TCI cites the testimony of DSU’s expert, Dannettel, for support.425 R+B asserts, to the extent TCI relies on DSU’s expert testimony, TCI asks the court to weigh and accept expert opinion to resolve the constructability.426 R+B argues that because the court is not permitted to weigh evidence at the summary judgment stage, TCI’s motion must be denied. 427 In its reply brief, TCI does not directly counter R+B’s argument; instead it incorporates DSU’s consolidated-answering-brief argument that expert testimony is not required to establish R+B’s negligence.428 In the end, TCI’s apparent reversal in first arguing DSU’s expert testimony entitles it to summary judgment, and then promoting DSU’s argument that the same testimony is not required to establish R+B’s negligence, does not affect the outcome of its motion. Because court has determined, above, the constructability issue is one of several that require expert testimony, and by granting the Motion to Strike that testimony is absent, TCI’s motion for summary judgment that the Panel Wall System was not constructible is denied. TCI moves for summary judgment that DSU’s proposed repairs constitute economic waste. TCI and DSU dismissed all claims against each other, 429 therefore, 424 D.I. 218 at 5-6. Id. 426 D.I. 225 at 9. 427 Id. 428 D.I. 235 at 5. 429 See D.I. 257. 425 101 TCI’s motion is denied as moot. The court concludes this portion of the opinion by addressing the remaining issues from R+B’s motion for summary judgment, i.e., whether it is entitled to summary judgment on the cross-claims against it by Czar, TCI, and W-T. R+B argues the negligence cross-claims must be supported by expert opinion on the standard of care.430 TCI and W-T do not proffer any expert opinion, and Czar’s expert opinions are offered only to defend Czar, not fault R+B.431 Czar did not respond to R+B’s motion. Czar’s cross-claims, however, are premised on it being found liable to DSU, which threat has been removed by the court’s grant of summary judgment in Czar’s favor on DSU’s claims against it. Moreover, the court found that there are no joint tortfeasors among Czar and any of its co-defendants. Therefore, R+B’s motion is granted as to Czar’s negligence claim against R+B. TCI argues no expert testimony is required to establish R+B’s negligence, citing the “common knowledge” exception to the general rule that expert testimony is required to establish the applicable standard of care for professionals.432 The court has already determined, in its discussion of DSU and R+B’s cross-motions for summary judgment on DSU’s breach of contract claim, that expert testimony is required maintain a negligence claim with respect to R+B’s professional obligations here.433 Because TCI 430 D.I. 204 at 16. D.I. 204 at 17 (citing D.I. 243-4, Stip. Ex. 175 (Czar expert report by Michael Johannes Paul, P.E., of Larsen & Landis)). 432 D.I. 224 at 8 (citing Seiler v. Levitz Furniture Co., 367 A.2d 999, 1008 (Del. 1976). 433 The case cited by TCI, Dailey v. Purse, C.A. No. 06C-04-015 RFS, 2008 W L 4824075 (Del. Super. Oct. 15, 2008), to suggest the common knowledge exception 431 102 proffers no expert opinion on R+B’s professional standard of care, and how that was breached, R+B’s motion is granted as to TCI’s negligence claim against R+B.434 The court also notes, TCI’s cross-claims against R+B are premised its liability to DSU.435 Because TCI and DSU have dismissed all of their claims against each other, the premise of TCI’s cross-claims cannot occur. Thus, this is an additional reason to grant R+B’s motion as to TCI’s cross-claims. W-T alleges cross-claims for contribution, implied in law indemnification, and implied in contract indemnification. W-T’s cross-claim for contribution fails because there are no joint tortfeasors from whom W-T could receive contribution. Each of crossclaims is premised on W-T’s liability to DSU.436 The court has dismissed DSU’s only claim against W-T, breach of contract; thus, DSU is not entitled to recover damages from W-T. Consequently, R+B’s motion for summary judgment on W-T’s cross claims is granted. III. CONCLUSION–Czar, TCI, and R+B Motions for Summary Judgment For the reasons discussed above: I. Czar Engineering, LLC’s Motion for Summary Judgment (D.I. 215) is applies is not persuasive. The plaintiff there was injured when he fell from scaffolding, allegedly erected negligently by defendant. Id. at *1. The scaffold’s wheels should have been held in place by pins, which were absent. Id. While moving the scaffolding, a wheel fell off causing the plaintiff injury from a resulting fall. Id. The court held that because the alleged negligence in not putting the pins in place was within a layman’s common knowledge, no expert testimony was required. Id. This is in no way similar to R+B’s allegedly negligent design of the Panel Wall System, which the court has determined is not something within the common knowledge of a lay person. 434 TCI 435 See D.I. 103 (Cross-Claims). 436 See D.I. 97 (Cross-Claims). 103 GRANTED in Part and DENIED in part: A. B. GRANTED as to all co-defendants’ contribution cross-claims; C. GRANTED as to R+B’s indemnity cross-claim; and D. II. GRANTED as to DSU’s Count I (Breach of Contract), Count III (Negligence), and Count IV (Unjust Enrichment); DENIED as to its limitation of liability. Thomas Company, Inc.’s Motion for Partial Summary Judgment (D.I. 217) is: A. B. DENIED as to the whether the only engineering required by TCI was the connections back to the building; C. DENIED as to the constructability of R+B’s Panel Wall System; and D. III. DENIED as to the enforceability of Czar’s limitation of liability provision; DENIED as MOOT as to whether DSU’s proposed repairs constitute economic waste. Richärd+Bauer, LLC’s motion for summary judgment (D.I. 215) is: A. GRANTED as to the negligence, contribution, and indemnity cross-claims by TCI, W-T, and Czar. Precision Foam Fabricators, Inc.’s Motion for Summary Judgement against Delaware State University and Thomas Company, Inc. Thomas Company, Inc.’s Motion for Partial Summary Judgment against Precision Foam Fabricators, Inc. PFF moves for summary judgment in its favor on DSU’s Counts I (Breach of Contract), III (Negligence), and IV (Unjust Enrichment) against PFF in the TAC (D.I. 180-2); and TCI’s claims for Breach of Contract, Unjust Enrichment, Breach of Warranty, Common Law Indemnification and Contribution, and Contractual Indemnification of TCI’s Counterclaim in its Answer to Answer, Affirmative Defenses 104 and Counterclaim to [PFF’s] Complaint in TCI’s Answer to Plaintiff Delaware State University’s Second Amended Complaint, Counterclaim, Cross-Claims and Denial of All Cross-Claims and Future Cross-Claims.437 TCI moves for summary judgment in its favor on its Breach of Contract claim against PFF.438 The court first addresses PFF’s motion for summary judgment in its favor on DSU’s Counts I, III, and IV in the TAC. Next, the court analyzes PFF and TCI’s crossmotions for summary judgment on TCI’s claim against PFF for breach of contract. Lastly, the court discusses PFF’s motion for summary judgment in its favor on TCI’s remaining claims against PFF for Unjust Enrichment, Breach of Warranty, Common Law Indemnification & Contribution, and Contractual Indemnification alleged in its counterclaims. I. DISCUSSION–PFF and TCI Motions for Summary Judgment A. DSU’S Claims against PFF Beginning with PFF’s motion for summary judgment on DSU’s claims against it, DSU’s breach of contract claim alleges it “was an intended third-party beneficiary of the agreements reached between Thomas and its subcontractors and suppliers . . . PFF . . . for the products, services and ongoing information they were obligated to provide 437 D.I. 205 (Precision Foam Fabricators, Inc. Motion for Summary Judgement against Delaware State University and Thomas Company, Inc.). Briefing on the motion is found at D.I. 206 (PFF Opening Brief); D.I. 222 (TCI Answering Brief); D.I. 231 (DSU Consolidated Answering Brief); D.I. 234 (PFF Reply Brief to TCI); and D.I. 238 (PFF Reply Brief to DSU). 438 D.I. 207 (Thomas Company, Inc. Motion for Partial Summary Judgment against Precision Foam Fabricators, Inc.). Briefing on the motion is found at D.I. 209 (TCI Opening Brief); D.I. 223 (PFF Answering Brief); and D.I. 232 (TCI Reply Brief). 105 specifically for the benefit of DSU[,]”439 and “[u]pon information and belief . . . PFF . . . was duly bound by the terms and conditions of their respective agreements, and such obligations extend to DSU as an intended third-party beneficiary of those agreements.”440 PFF contends it is entitled to summary judgment on DSU’s breach of contract because DSU is not a third-party beneficiary of PFF’s contract with TCI.441 With respect to DSU’s status as a third-party beneficiary to the TCI-PFF contract, PFF’s arguments, DSU’s response, and the court’s analysis are substantially identical to those on the issue discussed with respect to Czar’s motion for summary judgment. Therefore, the court incorporates its analysis of that issue from Czar’s motion and briefly summarizes PFF and DSU’s respective arguments here. PFF argues DSU’s third-party beneficiary theory fails because the TCI-PFF PO is an express contract, lacking any warranty or indemnity obligations, and not even referring to, or making, DSU a third-party beneficiary.442 PFF states its obligation under that PO was simply to manufacture and deliver panels to the Project as specified, which obligations it met.443 PFF points to the same provisions of the contract between DSU and TCI, AIA® Document B132™–2009, Standard Form of Agreement Between Owner and Architect, 439 D.I. 180-2 ¶ 52. Id. ¶ 53. 441 D.I. 206 at 9-10. 442 Id. at 2. 443 Id. 440 106 Construction Manager as Advisor Edition, which govern TCI’s obligations to DSU444 as Czar highlighted. Section 1.1.2 of the General Conditions 445 governing DSU and TCI’s relationship explicitly disclaims an intent to create third-party beneficiary status on DSU with respect to TCI’s subcontractors on the Project. The court thus reviews the TCI-PFF contract which provides in nearly identical language as the TCI-Czar contract: THIS ORDER IS COMPLETE WITH ALL THE ITEMS NECCESSARY [sic] AND INCIDENTAL THERE TO IN STRICT ACCORDANCE WITH THE ENTIRE CONTRACT DOCUMENTS PREPARED [sic] THE OWNER AND/OR THEIR CONSULTANT, INCLUDING WITHOUT LIMITATION: THE GENERAL, SPECIAL AND OTHER CONDITIONS, ALL SPECFICIATIONS, [sic], DRAWINGS, AND INVITATIONS FOR BIDS, BULLETINS, ADDENDA AND MODIFICATIONS THERETO. NO OTHER CHANGES WILL BE ACCEPTED EXCEPT THOSE STATED HEREIN AND AS PER THE CONTRACT DOCUMENTS. PROVIDE WRITTEN DOCUMENTATION INDICATING IMPACTS FOR CHANGES AND REVISIONS, WHEN REQUESTED.446 DSU’s argument with respect to this language in the TCI-PFF PO is substantially identical to its argument with respect to the TCI-Czar PO, i.e., that it shows PFF is “subject to performing its work in strict compliance with the contract documents and General Conditions prepared by the Owner.”447 The court again finds that argument to be little more than saying the language provides DSU as owner will benefit from the TCI-Czar contract, the expected result of every subcontract. The court also reiterates that DSU’s parallel statement it made in connection with Czar’s motion, i.e., that PFF’s 444 D.I. 195, Stip. Fact 14; D.I. 243-3, Stip. Ex 139; D.I. 206 at 10. D.I. 243-1, Stip. Ex. 48 § 1.1.2 (emphasis added); D.I. 238 at 3. 446 Id., Stip. Ex. 8. 447 D.I. 231 at 38. 445 107 subcontract does not disclaim the creation of a third-party beneficiary relationship between the Owner and subcontractor, 448 is not the proper inquiry. The proper inquiry is whether there was an intent to create third-party beneficiary status on the part of DSU, not whether such status exists absent disclaimer.449 The language in the TCI-PFF PO evidences no such intent and DSU offers no other evidence showing otherwise. The court agrees with PFF that its contract with TCI “does not contain terms and conditions, or anything approaching the detail of the prime contract between DSU and TCI.”450 Consequently, because the court determines DSU is not an intended third-party beneficiary to the TCI-PFF PO, PFF’s motion to for summary judgment on DSU’s Count I breach of contract claim is granted. DSU’s Count III negligence claim alleges “PFF manufactured and provided the defective panels for the Project” upon which DSU relied and was damaged, “including but not limited to damages to the building structure and property other than the panel wall itself.”451 PFF argues it is entitled to summary judgment on DSU’s claim of negligence design because DSU identifies no standard of care or duty owed by PFF, or PFF’s breach of that duty, and that the negligence claim is barred by the economic loss 448 Id. Cf. William M. Young Co. v. Bacon, C.A. No. 89L-JA2, 1991 WL 89817, at *4 (Del. Super. May 1, 1991) (“Young argues that Pierce holds that a third-party beneficiary status will exist unless the parties have negated same in the language of the contract. Young's position is incorrect.”). 450 D.I. 206 at 10. 451 D.I. 180-2 ¶¶ 63, 66-69. 449 108 doctrine.452 In its analysis of Czar’s motion on DSU’s Count III, the court determined that the economic loss doctrine bars DSU’s negligence claim against Czar because no exception to that doctrine allows recovery. PFF’s arguments on the application of the doctrine are substantially similar to Czar’s. The same analysis applies to that claim as alleged against PFF. Therefore, the court incorporates its analysis of that issue from Czar’s motion and briefly summarizes PFF’s arguments.453 PFF cites the Third Circuit’s Pierce decision for the proposition that under Delaware law, absent privity of contract, a party may not maintain a cause of action sounding in negligence to recover for purely economic loss.454 PFF notes the Superior Court of Delaware’s opinions in Guardian, adopting of § 552 of the Restatement (Second) of Torts, and Millsboro, recognizing that adoption. 455 PFF argues the exceptions do not apply, asserting no party in the present case disputes that: (1) DSU and PFF are not in privity of contract or its equivalent; and (2) 452 D.I. 206 at 10-14. Thus, the court need not address PFF’s arguments regarding DSU’s failure to identify the standard of care or duty owed by PFF. The court notes, however, that elsewhere in this opinion the court grants W-T and PFF’s Motion to Strike the Thornton Tomasetti Report because, inter alia, Dannettel is not qualified to offer the opinions contained therein. The court also notes DSU does not directly address PFF’s arguments for summary judgment based on the standard of care/duty issue in its consolidated answering brief. DSU limits its to arguments to the assertion that it is a third party beneficiary to the TCI-PFF contract. See D.I. 231 at 37-39. 454 D.I. 206 at 12 (citing Pierce Assocs., Inc. v. Nemours Found., 865 F.2d 530, 539 (3d Cir. 1988)). 455 Id. (citing Guardian Const. Co. v. Tetra Tech Richardson, Inc., 583 A.2d 1378, 1386 (Del. Super. 1990) and Millsboro Fire Co. v. Constr. Mgmt. Serv., C.A. No. 05C06, 2006 WL1867705, at *2 (Del. Super. June 7, 2006)). 453 109 DSU’s alleged losses are purely economic and do not involve property damage or personal injury.456 Analogizing its position to Pierce, PFF maintains DSU cannot recover against PFF for negligence where its damages are purely economic and there is no privity of contract.457 PFF also contends there are no allegations of negligent misrepresentation to allow the court to disregard the privity requirements.458 DSU did not respond to PFF’s arguments regarding Count III. Despite being on notice of PFF’s arguments that there are no genuine issues of material fact precluding summary judgment in its favor on its unjust negligence claim, DSU responded only to the breach of contract subset of arguments advanced by PFF in its briefing. Thus, based on the evidence and argument PFF provides in support of its motion, and DSU’s failure to respond, the court determines that claim is abandoned. There is no genuine issue of material in dispute, and PFF’s motion for summary judgment on Count III is granted.459 DSU’s Count IV unjust enrichment claim alleges “Defendant[] . . . PFF . . . [was] directly and unjustly enriched by [its] actions to DSU’s impoverishment and detriment[,]”460 and “[a]s a result of [PFF’s] defective and deficient work, [its] enrichment 456 Id. Id. (citing Pierce, supra, at 865 F.2d 539-41 (under Delaware law, owner had neither a third party beneficiary claim nor a negligence claim against a subcontractor)). 458 Id. at 13. 459 See Baldonado v. Avrinmeritor, Inc., C.A. No. 13-833-SLR-CJB, 2014 W L 2116112, at *7 (D. Del. May 20, 2014) (responding to only a subset of arguments subject to a dispositive motion is deemed abandonment of the un-responded to claims) (citing cases), report and recommendation adopted, C.A. No. 13-833-SLR/CJB, 2014 WL 2621119 (D. Del. June 10, 2014). 460 D.I. 180-2 ¶ 71. 457 110 was unjustified, and there is no remedy available to DSU.”461 PFF contends it is entitled to summary judgment in its favor on DSU’s Count IV unjust enrichment claim because DSU’s contracts with TCI and other parties provide full relief.462 PFF makes substantially similar arguments as Czar which were addressed in the court’s analysis of Czar’s motion. Here again, DSU’s claim fails. In summary, DSU alleges separate breach of contract and unjust enrichment claims against PFF.463 PFF argues quasi-contractual relief against a third party is not appropriate where a contract exists and provides for full relief.464 PFF argues DSU possess multiple direct contracts upon which it seeks relief.465 The prime contracts DSU entered regarding the design, engineering, drawings, oversight, furnishing, and installation of the Panels at issue purportedly provide for complete relief in the event of 461 Id. ¶ 72. D.I. 206 at 13. 463 D.I. 180-2 (Counts I and IV). 464 D.I. 206 at 13 (citing Kuroda v. SPJS Holdings, L.L.C., 971 A.2d 872, 891 (Del. Ch. 2009); Chrysler Corp. v. Airtemp Corp., 426 A.2d 845, 855 (Del. Super. 1980) (“‘The mere fact that a person benefits another is not itself sufficient to require the other to make restitution.’ Ibid, comment c. In order to warrant restitution, the retention of the benefit must be unjust. Ibid.” (citing Restatement of Restitution, Section 1). Absent a showing that the plaintiff was unable to gain contractual relief, it was not entitled to pursue its claims for quantum meruit, implied contract, or restitution against a third party not in privity of contract.). 465 Id. at 13-14. PFF notes DSU contracted with TCI for the design, engineering, drawings, furnishing and installation of the Wall System, which provides for relief in the event of a contract breach. D.I. 195, Stip. Fact 14. T hose obligations were assured by Liberty Mutual under the performance bond issued on TCI’s behalf and in favor of DSU. D.I. 195, Stip. Fact 15. DSU contracted with R+B for the design, Drawings and Specifications for, inter alia, the façade, which likewise provides relief for design or defects. D.I. 195, Stip. Fact 7. DSU contracted with W-T for Construction Manager as Advisor services, which also provides for relief for W-T’s breaches. D.I. 195, Stip. Fact 12. 462 111 a breach.466 PFF asserts DSU’s failure to show a lack of basis for recovery under these contracts that might otherwise justify quasi-contractual relief against PFF demonstrates the unjust enrichment claim against PFF should be dismissed.467 DSU did not respond to PFF’s arguments regarding Count IV. DSU’s Count I alleges a breach of contract claim against PFF; a claim it argues in its opposition brief is supported under a third-party beneficiary argument.468 Despite being on notice of PFF’s arguments that there are no genuine issues of material fact precluding summary judgment in its favor on its unjust enrichment claim, DSU responded only to the breach of contract subset of arguments PFF advanced in briefing on its motion. Thus, based on the evidence and argument PFF provides in support of its motion, and DSU’s failure to respond, the court determines that claim is abandoned, there is no genuine issue of material in dispute, and PFF’s motion for summary judgment on Count IV is granted.469 Thus, PFF’s motion for summary judgment on all claims asserted against it by DSU is granted in its entirety. B. PFF and TCI’s Cross-Motions on TCI’s Breach of Contract Claim against PFF The court next proceeds to PFF and TCI’s cross-motions for summary judgment on TCI’s breach of contract claims against PFF, followed by PFF’s motion for summary judgment on TCI’s claims against PFF for unjust enrichment, breach of warranty, 466 D.I. 206 at 14. Id. 468 See D.I. 231 at 37-38. 469 See Baldonado, 2014 WL 2116112, at *7. 467 112 common law indemnification and contribution, and contractual Indem nification. The following procedural background is relevant to TCI’s breach of contract claim against PFF. On November 13, 2015, PFF initiated this litigation by filing suit against TCI in New Castle County Superior Court.470 PFF asserted it had not been paid in full for the metal panels it supplied on the Project, and asserted a claim against TCI for breach of contract and a payment bond claim against TCI’s surety, Liberty Mutual.471 Thereafter, the matter was removed to this court on the basis of diversity jurisdiction.472 TCI asserted counterclaims against PFF and joined DSU as a third-party defendant.473 On December 18, 2015, TCI filed its Answer, Affirmative Defenses and Counterclaim to [, PFF’s,] Complaint, alleging Breach of Contract (Count I), Unjust Enrichment (Count II), Breach of Warranty (Count III), Common Law Indemnification and Contribution (Count IV), and Contractual Indem nification (Count V) against PFF.474 On January 4, 2016, TCI filed a Third Party Complaint against DSU, alleging Breach of Contract (Count I), Unjust Enrichment (Count II), and Violation of 29 Del. C. § 6516(f) (Count III).475 Ultimately, the other parties were joined and the court granted a joint motion to realign the parties with DSU as the plaintiff.476 On July 13, 2018, after 470 See D.I. 1-1 (PFF Complaint). Id. 472 See D.I. 1 (Notice of Removal). 473 See D.I. 7 (TCI Answer and Counterclaim); D.I. 8. (TCI Third Party Complaint). 474 D.I. 7. 475 D.I. 8. 476 See D.I. 73 (Joint Motion to Realign Parties). The court ordered the realignment of the parties on May 1, 2018. See Docket Entry, May 1, 2018 (SO 471 113 realignment of the parties, TCI filed its Answer to Plaintiff Delaware State University’s Second Amended Complaint, Counterclaim, Cross-Claims and Denial of All CrossClaims and Future Cross-Claims.477 TCI’s July 13, 2018 filing reiterated its original claims against PFF, but under different Count numbers.478 TCI’s breach of contract claim alleges it “entered a contract with [PFF] to purchase certain metal panels and related material for use on the Project[,] that “required PFF to deliver materials ‘in strict accordance’ with the ‘general, special and other conditions, all specifications, drawings, initiations for bids, bulletins, addenda and modifications thereto’ issued for Project.”479 “PFF failed to timely deliver its materials to the Project, resulting in delay and additional costs to [TCI,]” and “when PFF did deliver its materials, they were deemed defective by DSU and/or its representatives, causing [TCI] to incur additional costs to investigate, mitigate, remove and reinstall the materials.”480 ORDERED D.I. 73 Joint MOTION Re-align parties filed by Delaware State University). 477 D.I. 103. 478 TCI’s original complaint includes these claims against PFF. See D.I. 7. After additional parties entered the litigation, and the court’s realignment making DSU the plaintiff, TCI’s July 13, 2018 filing reiterated its claims against DSU made in D.I. 8, added a cross-claim for indemnification against R+B, Czar, PFF, W-T, and Ashford (D.I. 103, Cross-Claim Count I), and reiterated its breach of contract, unjust enrichment, and breach of warranty claims against PFF. Id. (Cross-Claims II, III, and IV, respectively). Although TCI references the claims recited in D.I. 103 at the beginning of its opening brief in support of its affirmative motion for summary judgment, and in its opposition brief to PFF’s affirmative motion, (see D.I. 209 at 1; D.I. 222 at 1, respectively), TCI and PFF each refer to the Count numbers from D.I. 7 in their respective briefs. To avoid confusion, the court refers to the basis of the claim being discussed rather than count number, e.g., “breach of contract,” rather than “Count x.” 479 D.I. 103 at 13-14, ¶¶ 3-4. 480 Id. at 14, ¶ 6. 114 To prevail on a breach of contract under Delaware law, a party must show: (1) the existence of a contract; (2) breach of an obligation imposed by the contract; and (3) damages resulting from said breach.481 PFF asserts TCI cannot demonstrate facts essential to elements 2 and 3 and it is entitled to summary judgment.482 Specifically, PFF argues no party has established that PFF is the cause of the Panel deformations.483 PFF asserts there is no evidence that it is the cause of the deformations, which all parties agree are caused by differential temperature between the outside and interior panel skins. 484 PFF maintains it met its contractual obligation to TCI manufacture and deliver panels to the Project as specified.485 TCI argues the evidence shows that PFF breached its contract with TCI related to the first set of panels PFF supplied on the Project because those panels did not m eet the requirements of the Project Specifications and did not match the approved panel sample PFF supplied.486 As a result of that alleged breach, TCI maintains it is entitled to partial summary judgment related to damages it suffered due to delays resulting from PFF’s breach.487 It is important to reiterate that TCI’s breach of contract claim against PFF only 481 Markow v. Synageva Biopharma Corp., C.A. No. C.A. No. N15C–06–152 WCC CCLD, 2016 WL 1613419, at *4 (Del. Super. Mar. 3, 2016). PFF acknow ledges “there is no dispute that TCI and PFF entered into a valid PO,” but assets “that PO was strictly limited only to PFF’s manufacture and delivery of the Panels per the specifications TCI provided PFF. . . .” D.I. 234 at 6. 482 D.I. 206 at 15. 483 Id. at 1-2. 484 Id. at 2. 485 Id. 486 Id. 487 Id. 115 concerns the first set of panels PFF supplied, and the damages, if any, TCI suffered as a result of the purported breach. The following are relevant contracts, requirements, time lines, and events relevant to PFF and TCI’s cross-motions. On January 12, 2012, DSU and W-T entered into a contract titled AIA® Document C132™ – 2009, Standard Form of Agreement Between Owner and Construction Manager as Adviser; AIA® Document A232™ – 2009, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition; and Section 00730–SUPPLEMENTARY GENERAL CONDITIONS TO THE CONTRACT.488 On January 20, 2012, DSU retained R+B as the Architect of Record for the OSCAR Facility pursuant to an AIA® Document B132™--2009, Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition.489 On December 27, 2013, DSU entered a contract with DSU entered a contract with TCI entitled AIA® Document A132™--2009, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition for the Wall System in connection with the Project.490 On January 20, 2014, TCI entered into a valid and binding purchase order contract with PFF to purchase insulated panels for the 488 D.I. 195, Stip. Fact 12; D.I. 243-2, Stip. Ex. 94 (DSU-W-T contract); D.I. 2432, Stip. Ex. 48 (General Conditions); & D.I. 243-3, Stip. Ex. 140 (Section 00730), respectively. 489 D.I. 243-1, Stip. Ex. 47. 490 D.I. 195, Stip. Fact 14; D.I. 143-3, Stip. Ex. 139. 116 benefit of the Project and Owner,491 which states: THIS ORDER IS COMPLETE WITH ALL THE ITEMS NECCESSARY [sic] AND INCIDENTAL THERE TO IN STRICT ACCORDANCE WITH THE ENTIRE CONTRACT DOCUMENTS PREPARED [sic] THE OWNER AND/OR THEIR CONSULTANT, INCLUDING WITHOUT LIMITATION: THE GENERAL, SPECIAL AND OTHER CONDITIONS, ALL SPECFICIATIONS, [sic], DRAWINGS, AND INVITATIONS FOR BIDS, BULLETINS, ADDENDA AND MODIFICATIONS THERETO. NO OTHER CHANGES WILL BE ACCEPTED EXCEPT THOSE STATED HEREIN AND AS PER THE CONTRACT DOCUMENTS. PROVIDE WRITTEN DOCUMENTATION INDICATING IMPACTS FOR CHANGES AND REVISIONS, WHEN REQUESTED.492 Section 3.12.3 of the Project’s General Conditions requires the Contractor to recites “Samples are physical examples that illustrate materials, equipment or workmanship and establish standards by which the Work will be judged.493 W-T had “the authority to reject work that does not conform to the Contract Documents.”494 On May 14, 2014, the Project architect, R&B, approved a sample of the metal panels supplied by PFF.495 The Specifications required the PFF supplied panels to have a mirrored finish,496 491 D.I. 1-1 (Precision Foam Fabricators, Inc. v. Thomas Co., Inc., C.A. No. N15C-11-115 CLS (Del. Super. Nov. 13, 2015), ¶¶ 9, 17; D.I. 243-1, Stip. Ex. 8. 492 D.I. 243-1, Stip. Ex. 8. 493 Id., Ex. 48 (General Conditions) § 3.12.3. 494 Id., Stip. Ex. 48 (General Conditions) § 4.2.8; see also D.I. 243-3, Stip. Ex. 94 (DSU-W-T Contract) § 3.3.14. 495 D.I. 207-2, Ex. A (May 14, 2014 Approval) at Thomas0044 (“The sample submitted is acceptable . . . .”). 496 D.I. 243-1, Stip. Ex. 3 (Specifications, Nov. 14, 2013, Addendum 3) at § 2.3.B.2 (“Exterior face . . . to be polished stainless with . . . with [ ] polished mirror finish”). 117 which PFF acknowledges was provided the Specifications.497 The first set of PFF panels was timely delivered to the Project on September 30, 2014.498 The Project schedule issued by W-T in effect at the time required panel installation be completed by October 27, 2014. 499 Installation began on October 6, 2014.500 When installation began, W-T advised TCI that the finish on the installed panels “does not match the samples.”501 Specifically, the delivered panels had a “dull,” “hazy” or “cloudy” look rather than the mirrored appearance of the samples.502 On October 8, 2014, DSU formally notified TCI that there was a “discrepancy between the exterior finish of the insulated panels that have been supplied and the sample that was reviewed and approved by the Architect” and requested an immediate meeting with TCI, PFF, W-T and R&B to address the issue. 503 PFF participated in an October 9, 2014, telephonic conf erence and an October 497 D.I. 223 at 1; D.I. 234 at 6. D.I. 195, Stip. Fact 25; see also D.I. 2007-2, Ex. B (Oct. 13, 2014 DSU email) at Thomas005. 499 D.I. 207-2, Ex. C (Sept. 1, 2014 Project Schedule Update) at T homas009. PFF states the PO made no reference to any schedule and no schedule–or any of the other alleged contract documents–accompanied the PO. D.I. 223 at 1 (Disputed Fact 2). 500 D.I. 243-3 Stip. Ex. 124 (Oct. 30, 2014 Project Minutes), at DSU0003821; D.I. 243-12 (George Dep.) at 309:9-23 (confirming minutes are accurate). 501 D.I. 243-3, Stip. Ex. 125 (Oct. 6, 2014 email). 502 D.I. 207-2, Ex. D (Oct. 8, 2014 email) at Thomas014-017 (describing panels as “‘dull’ not mirror like samples”); id., Ex. B (Oct. 13, 2014 DSU email) at Thomas005 (describing panels as “cloudy”); D.I. 243-16 (Mefferd Dep., PFF corporate designee) at 176:25-177:20 (describing panels as “cloudy” and not “shiny”); D.I. 243-12 (George Dep., W-T corporate designee) at 309:24-310:7 (“[W]e . . . started looking at the finish, it was a little blurry, it wasn’t that mirror finish that the sample was original provided was.”), 176:13-19 (“the first panels were rejected because the finish was not correct”). 503 D.I. 243-1, Stip. Ex. 21 (Oct. 8, 2014 Letter). 498 118 10, 2014 in-person meeting to address the issue. 504 At the time, all parties present, including PFF, “agreed that the metal finish on the first batch of panels that was fabricated does not all align with what was represented by the product sample that was submitted and approved.”505 Thereafter, DSU formally rejected the PFF panels, confirming the rejection in a formal notice subsequently issued on October 21, 2014. 506 At deposition, PFF’s corporate designee, Ricky Mefferd, testified that the first set of Panels were rejected due to their appearance. Q. . . . Ultimately, the first batch of panels that were delivered to the site were rejected, were they not? A. They were rejected based on the appearance or esthetics of the panel. Q. Okay. A. That is correct. Q. And what is your understanding the problems or issues with the appearance and the esthetics of the panels that were delivered? A. My understanding is that the owner did not believe that it matched or appeared–it was a different shade than what his–what he had agreed upon, I'll call it. Q. A different shade? A. A different–not a shade–appearance, I guess, not shade, but . . . 504 D.I. 243-3, Stip. Ex. 127 (Minutes of Oct. 9, 2014 Telephonic Conference); D.I. 207-2, Ex. B (October 13, 2014 DSU Email) at Thomas005 (summarizing Oct. 10, 2014 meeting). 505 D.I. 207-2, Ex. B (Oct. 13, 2014 DSU email) at Thomas005 (summarizing Oct. 10, 2014 meeting). 506 See D.I. 243-3, Stip. Ex. 104 (Oct. 21, 2014 Letter); D.I. 243-12 (George Dep.) at 176:18-19 (“the first panels were rejected because the finish was not correct”). 119 Q. It was cloudy? A. It was cloudy. Q. It wasn't shiny? A. Right.507 As a result of the aesthetic defect, Mefferd testified PFF manufactured, and paid for, new panels. A. What, if anything, did [PFF] do to correct—did you manufacture new panels? A. We did. Q: Who paid for that? A. PFF. Q. Okay. So PFF paid for it acknowledging that the ones delivered were unacceptable? A. Based on the finish, correct, yes.508 Mefferd testified PFF acknowledged, and accepted responsibility for, the rejection. Q. You acknowledge that the panels were rejected? A. I do. Q. And you accepted responsibility for the rejection, correct? [Objection] A. We did. 507 508 D.I. 243-16 (Mefferd Dep.) at 176:25-177:20 (emphasis added). Id. (Mefferd Dep.) at 178:17-24 (emphasis added). 120 Q. And you agreed to provide replacement panels that met the specifications, correct? A. Yes.509 The court finds the evidence shows, with respect to the first panels delivered, that PFF breached its contract with TCI. PFF admits “there is no dispute that TCI and PFF entered into a valid PO, that PO was strictly limited only to PFF’s manufacture and delivery of the Panels per the [S]pecifications TCI provided PFF . . . .”510 PFF states the panels were only rejected “on aesthetic grounds.511 That, however, is the point. The Specifications required the PFF supplied panels to have a mirrored finish.512 Correspondence, contemporaneous documentation, and Mefferd’s testimony confirm the first set of panels PFF delivered did not meet that requirement. In an attempt to negate the impact of Mefferd’s testimony, PFF submits the affidavit of former PFF employee Daniel Garner attached to its brief opposing TCI’s motion,513 and challenges TCI’s arguments for: TCI blindly rel[ying] on PFF’s corporate designee, who testified that (a) PFF’s assets were sold in 2016; (b) he only had knowledge that PFF had a contract and was not involved in the Project; and (c) disputed much of what TCI now relies upon. Mr. Garner . . . was the better person to testify to these items. Mr. Garner retired in 2016 and no party subpoenaed him for deposition testimony.514 509 Id. (Mefferd Dep.) at 211:22-212:6 (emphasis added). D.I. 234 at 6. 511 D.I. 206 at 2; D.I. 234 at 1. 512 D.I. 243-1, Stip. Ex. 3 (Specifications, Nov. 14, 2013, Addendum 3) § 2.3.B.2 (“Exterior face . . . to be polished stainless with . . . with [ ] polished mirror finish”). 513 D.I. 223-1 (Garner Aff.). 514 D.I. 223 at 4 n.7 (citing D.I. 243-16 (Mefferd Dep.) at 11:1-8, 19:9-16; 19:21-20:3); D.I. 234 at 4 n.4 (same). 510 121 The court finds PFF’s criticism is unwarranted. A “Rule 30(b)(6) designee presents the corporation's, rather than his personal, ‘position’ on a topic and, in addition to testif ying about facts within the corporation's knowledge, testifies about the corporation's subjective beliefs and opinions, and its interpretation of documents and events.”515 “A corporation has an affirmative duty to produce a representative who can answer questions that are within the scope of the matters described in the notice.” 516 “The duty of preparation goes beyond the designee's personal knowledge and matters in which the designee was personally involved. If necessary, the deponent must use documents, past employees, or other resources to obtain responsive information.”517 Generally, “[a] party may not retract prior 30(b)(6) testimony with a later affidavit, and then use that affidavit to preclude summary judgment.”518 As the Daubert Court explained: Where the nonmovant in a motion for summary judgment submits an affidavit that directly contradicts an earlier Rule 30(b)(6) deposition and the movant relied upon and based its motion on the prior deposition, several courts have disregarded the later affidavit. However, where the affidavit is ‘accompanied by a reasonable explanation’ of why it was not offered earlier, courts have allowed a contradictory or inconsistent affidavit to nonetheless be admitted to supplement the earlier submitted Rule 30(b)(6) testimony.519 515 Ethypharm S.A. France v. Abbott Labs., 271 F.R.D. 82, 93 (D. Del. 2010). Crawford v. George & Lynch, Inc., 19 F. Supp. 3d 546, 554 (D. Del. 2013). 517 Id. (internal citations omitted) (emphasis added). 518 Daubert v. NRA Grp., LLC, 189 F. Supp. 3d 442, 458–59 (M.D. Pa. 2016), aff'd in relevant part, 861 F.3d 382 (3d Cir. 2017). W hether to disregard an affidavit under the sham-affidavit doctrine is up to the court’s discretion. See Daubert, 861 F.3d at 389. 519 Id. at 258 (citations omitted). 516 122 As TCI contends, Mefferd’s testimony was undoubtedly within the scope of the topics about which he was to testify.520 Here, PFF provides no explanation why the information Garner provides was not offered earlier, or why that information was unavailable to Mefferd prior to his deposition. Mefferd testified Garner was the most knowledgeable individual about the subject matter of the litigation and would have “extremely” important information.521 He was sure PFF had Garner’s contact information, but he did not attempt to speak to Garner in preparation for his Rule 30(b)(6) deposition. 522 Thus, the court grants TCI’s motion, and denies PFF’s motion, to the extent each seek summary judgment on TCI’s breach of contract claim against PFF.523 The court must now determine whether summary judgment is appropriate on TCI’s claim for damages as a result of that breach. TCI argues it should be granted judgment in its favor and against PFF in the 520 D.I. 232 at 5 (citing D.I. 243-1, Stip. Ex. 4 (Rule30(b)(6) Notice of Deposition to PFF); id., Stip. Ex. 24 (Supplemental Rule 30(b)(6) Notice to PFF); D.I. 234-16 (Mefferd Dep.) at 11:22-24, 201:5-8 (confirming designee was prepared to testify as to all topics in the notices)). 521 D.I. 234-16 (Mefferd Dep.) at 136:23-137:17; 201:18-24. 522 Id. In response to PFF’s criticism that no other party subpoenaed Garner, TCI states that once PFF’s 30(b)(6) witness acknowledged the finish defect in the first set of panels, it relied on that testimony and had no need to subpoena Garner. Separately , PFF’s argument that Mefferd’s testimony “only confirms PFF’s present general understanding of why the Owner rejected the Panels by an individual who had no involvement in the Project contemporaneously . . . not that it agreed with any rejection or the existence of any alleged aesthetic defects[,]” D.I. 234 at 4, is similarly unpersuasive. Mefferd was PFF’s 30(b)(6) witness, his contemporaneous involvement in the Project was not necessary for him to testify in that role. 523 Because the court determines the first set of panels breached the contract for lack of compliance with the specification, it need not address the parties’ argument that a breach is also shown because the first set of panels did not match the sample panels. 123 amount of $163,622.68 plus prejudgment interest of $46,398.80 through the date of its motion (and accruing at $25.78 per day thereafter) related to the first set of defective panels PFF supplied on the Project. 524 PFF argues its motion should be granted on TCI’s claim for damages because TCI did not provide any expert report or testimony that PFF delayed the Project or caused TCI field inefficiency or additional costs.525 PFF argues TCI’s failure to provide expert testimony that PFF breached any duty or caused delay to the Project precludes recovery for claimed delay damages, particularly, where, as here, TCI has sought recovery for delays from the Owner, not PFF.526 Similarly, PFF argues TCI’s motion should be denied because TCI has not met its burden of showing the rejection of the first set of panels actually delayed and impacted TCI or that TCI’s damages resulted from PFF’s breach and not for other causes, including TCI’s own failures to mitigate.527 The following evidence is relevant to the damages issue. The first set of PFF panels was timely delivered to the Project on September 30, 2014.528 Installation began on October 6, 2014 529 despite finish issues being noted and TCI notifying PFF of the issue that day.530 On October 8, 2014, DSU issued a letter 524 D.I. 209 at 2. D.I. 206 at 6. 526 Id. at 2. 527 D.I. 223 at 1. 528 D.I. 195, Stip. Fact 25; see also D.I. 2007-2, Ex. B (Oct. 13, 2014 DSU email) at Thomas005. 529 D.I. 243-3 Stip. Ex. 124 (Oct. 30, 2014 Project Minutes), at DSU0003821; D.I. 243-12 (George Dep.) at 309:9-23 (confirming minutes are accurate). 530 See D.I. 207-2, Ex. B (Oct. 13, 2014 email) at Thomas005. 525 124 identifying the concern and TCI ceased panel installation that day.531 On October 10, 2014, the parties met to discuss a path forward.532 At that meeting, the parties agreed that the overall project schedule it did not appear the overall project schedule would be impacted by the panel replacement issue.533 PFF agreed to manufacture replacement panels at its cost. 534 DSU and W-T approved PFF’s proposed replacement panels on October 29, 2014. 535 The replacement panels were delivered to the Project on October 31, 2014 and were confirmed to have the appropriate mirrored finish.536 After the first set of panels was rejected, W-T advised TCI that the rejection cased a delay to the Project and that TCI would have to establish a recovery schedule to avoid impact to the overall schedule.537 W-T also advised TCI it would not be paid for any work on the Project until the replacement panels were delivered.538 W-T further instructed TCI to provide a “make-up once the panels are onsite due to the f inish delay” and that it was expecting 10-hour days 5 days per week and an additional 8-hour shift 531 Id. Id. 533 Id. at Thomas006. W-T’s designee stated it was able to mitigate the affect of TCI’s delay relating to panel replacement on other trades involved in the Project. D.I. 243-12 (George Dep.) at 208:1-4. 534 See D.I. 243-16 (Mefferd Dep.) at 178:17-24. 535 See D.I. 207-2, Ex. G (Oct. 29, 2014 Email) at Thomas022. 536 See D.I. 207-2, Ex. H (Nov. 4, 2014 Email) at Thomas023-024. At the time of rejection, Thomas had already installed 12 panels. See D.I. 243-3, Stip. Ex. 127 (Minutes of Oct. 9, 2014 Telephonic Conference). 537 See D.I. 243-3, Stip. Ex. 104 (Oct. 21, 2014 Letter). 538 See D.I. 207-2, Ex. F (Oct. 13, 2014 Email) at Thomas019. 532 125 on Saturdays.539 Mefferd’s testimony acknowledged there was a cost to remove the rejected panels that had been installed, and that som e period of time necessarily elapsed after the first set of panels was rejected until it delivered replacement panels to be installed.540 Although he assumed TCI had a schedule it was required to keep with respect to the Project, he was not privy to that schedule. 541 The TCI-PFF PO did not reference any schedule and there is no evidence TCI provided PFF any other documents, except for the Specifications, when TCI issued the PO to PFF. 542 TCI submits a lengthy summary of its damages from October 5, 2014 through July 23, 2015 in support of the amount of damages it seek from PFF.543 Based on the 539 See, e.g., Id., Ex. I (Oct. 22, 2014 email) at Thomas025; id., Ex. J (Oct. 29, 2014 email) at Thomas026 (confirming Thomas would work “10-hour days plus Saturdays to get back on schedule.”); D.I. 243-12 (George Dep.) at 297:9-17(testifying that W-T advised TCI of the need to continue working overtime to make up for time lost because of the rejected PFF panels). 540 D.I. 243-16 (Mefferd Dep.) at 203:13-17, 205:13-17, 211:2-6. 541 Id. (Mefferd Dep.) at 203:7-12. He testified that PFF “do[esn’t] get production schedules on a normal basis for all of our customers.” Id. (Mefferd Dep.) at 207:18208:1. 542 Mefferd testified PFF did not receive other relevant documents until the issues with the first set of panels arose. See id. (MefferdvDep.) at 24:14-23, 51:14-19, 56:613; 207:18-208:1. 543 D.I. 207-2, Ex. K (Audited Damages Calculation and Project Payroll and Expense Records). Expenses TCI attributes to the delay caused by the rejection of the first set of PFF panels are: $53,345 in direct labor costs to erect the orig inal defective panels, id., Ex. K at Thomas052 (calculation of direct labor costs to erect panels) and Thomas044-200 (audited payroll and Project expense records); $54,074.65 in direct labor costs to remove the erected defective panels, id., Ex. K at Thomas033 (calculation of direct labor costs to remove panels) and Thomas044-200 (audited payroll and Project expense records); $32,758.94 in overtime costs as a result of accelerating work to mitigate the delay caused by the original defective panels. id., Ex. K at Thomas034 (calculation of overtime costs incurred related to first set of defective panels) and Thomas044-200 (audited payroll and Project expense records). TCI 126 expenses set forth therein, and the amount it attributes to PFF, TCI calculates its damages resulting from PFF’s breach of contract are $163,622.68. 544 It calculates statutory interest on $163,622.68, from the date of breach, September 30, 2014, to the date of this motion totals $46,398.80. 545 The court denies TCI’s motion with respect to damages. Compensation for injury due to a breach of a contract should “place [the injured party] in the same position that he would have been in if the contract had been performed. The measure of damages is the loss actually sustained as a result of the breach of the contract.”546 However, “[a] court must . . . reduce the calculated damages by the amount of loss ‘that [the plaintiff] could have avoided by reasonable efforts.’”547 [O]n a motion for summary judgment the evidence and inferences drawn from it are viewed in the light most favorable to the non-moving party . . . . It is axiomatic that a plaintiff, in order to recover damages from a defendant for breach of contract, must demonstrate with reasonable certainty that defendant's breach caused the loss. Reasonable certainty is not equivalent to absolute certainty; rather, the requirement that plaintiff asserts that, overall, it was delayed 10 months in the completion of the Project, resulting in additional field/general conditions costs of $193,340.875 (for supervision, equipment rentals, job trailer, etc.) and additional home office overhead of $41,092.20. id., Ex. K at Thomas039 (calculating delay and additional field/general conditions costs). TCI attributes one month of that delay (Sept. 30, 2014-Oct. 31, 2014), or 10%, to PFF, resulting in additional field/general condition costs of $19,334.09 in costs and additional home office overhead costs of $4,109. See D.I. 195, Stip. Facts 25 (showing initial panels delivered Sept. 30, 2014); D.I. 243-3, Stip. Ex. 124 and D.I. 207-2, Ex. H (Nov. 4, 2014 email) at Thomas023 (showing replacement panels delivered Oct. 31, 2014). 544 See D.I. 207-2, Ex. K (Audited Damages Calculation and Payroll Records) at Thomas027-200. 545 D.I. 207-2, Declaration of George Thomas, at Thomas004-005 ¶ 4 (calculating prejudgment simple interest of 5.75% per annum with daily interest of $25.78). 546 J.J. White, Inc. v. Metro. Merch. Mart, 107 A.2d 892, 894 (Del. Super. 1954). 547 Vici Racing, LLC v. T-Mobile USA, Inc., 763 F.3d 273, 294-95; 299 (3rd Cir. 2014) (alteration in original) (internal quotation marks and citations omitted). 127 show defendant's breach to be the cause of his injury with “reasonable certainty” merely means that the fact of damages must be taken out of the area of speculation.548 TCI argues its actual costs in correcting PFF’s defective performance is the correct measure of damages here, and the only method of demonstrating that cost is through TCI’s financial records.549 With respect to TCI’s motion for damages, the focus is the damages TCI allegedly suffered due to the delay resulting from PFF’s rejected first set of panels, and the extent those damages are attributable to PFF with reasonable certainty. PFF asserts TCI fails to meet its burden to prove its resulting damages.550 PFF states the delay in the installation of the replacement panels did not impact the overall Project schedule. 551 The overall Project schedule is not the precise issue, however, the issue is what damages TCI specifically suffered as a result of the delay from the rejection of the first set of panels. TCI requests summary judgment as to a specific amount of damages, but PFF presents arguments raising a reasonable doubt as to the amount of damages to which TCI may be entitled. First, PFF raises the issue of whether TCI attempted mitigation with respect to TCI’s extra expenses, noting TCI continued to install additional panels from the first set delivered after being apprised of the finish issue, and now seeks 548 Tanner v. Exxon Corp., No. 79C-JA-5, 1981 WL 191389, at *1 (Del. Super. 1981) (citations omitted); see also Vici Racing, 763 F.3d at 294 (stating damages may not be speculative). 549 D.I. 232 at 9-10. 550 D.I. 223 at 9. 551 Id. 128 damages for the installation and removal of those additional panels. 552 PFF also contends TCI’s support for its claims to recover direct and indirect costs from PFF for the installation and removal of rejected panels, and alleged acceleration and delay costs, is dubious and speculative.553 Despite TCI’s representation its damages are based on an audited financial statements reflecting actual payroll costs and expenses incurred as a result of PFF’s breach,554 that exhibit includes the following statement from the accounting firm that compiled the report: We have not audited or reviewed the accompanying summary, nor were we required to perform any procedures to verify the accuracy or completeness of the information contained in the summary, which was prepared by management, and, accordingly, we do not express an opinion, a conclusion, nor provide any assurance about whether the summary is in accordance with the contractual basis of accounting that is a basis of accounting the entity uses to comply with terms of a contract with third-parties.555 PFF argues, therefore, that the amounts on which TCI requests summary judgment are nothing more than TCI’s self-allocation of costs allegedly attributable to PFF, with no corresponding analysis or rationale justifying those costs.556 PFF also argues TCI makes no effort to trace or substantiate these claimed costs against the materials allegedly provided in support thereof, and that it is not possible to reverse engineer or back into these numbers using the information TCI provided.557 552 TCI states it mitigated the delay to the overall Project by its acceleration of work, see, e.g., D.I. 222 at 11, at great costs that it now seeks to recover from PFF. 553 D.I. 234 at 8. 554 See, e.g., D.I. 209 at 9 (citing D.I. 207-2, Ex. K); D.I. 222 at 13 (same). 555 D.I. 207-2, Ex. K at Thomas029 556 D.I. 223 at 5, 9. 557 Id. 129 TCI responds that PFF provides no effective defense to its calculations and cites no evidence to dispute the veracity of the damages calculations.558 It also suggests PFF could have challenged TCI about the legitimacy of its damages claim or questioned the underlying data at the 30(b)(6) deposition of TCI.559 TCI does not convincingly respond to either PFF’s questioning of its effort to mitigate its own damages, as opposed to avoiding delay of the overall Project, or the veracity of the unaudited calculation of expenses. It is TCI’s burden to establish the damages for which it seeks summary judgment. PFF has raised reasonable questions creating a genuine issue of material fact as to the appropriate amount of damages. Therefore, although PFF’s breach is established, TCI has not proven its entitlement to the amount of damages it seeks and its motion for summary judgment as to that amount is denied. Because the court granted TCI’s breach of contract claim against PFF, the court need not examine the parties’ arguments as to whether to sever trial on the issue of the first set of panels. The court determines that the sole determination at trial of TCI’s damages as a result of that breach does not warrant severance of that discrete issue. Thus, the court denies TCI’s request for severance and/or a separate trial on its breach of contract claim against PFF. C. TCI’s Remaining Claims Against PFF TCI’s breach of warranty claim alleges that PFF “expressly and impliedly 558 559 D.I. 232 at 9. Id. 130 warranted the fitness of its materials for use on the Project, but PFF has breached that warranty.”560 TCI contends the TCI-PFF contract contains an express warranty and the evidence in the record supports a claim for breach of implied warranty.561 PFF maintains TCI offers no evidence to establish that PFF breached any such warranties.562 It states there are no express warranty provisions in the TCI-PFF PO and, although the PO generically references some documents, none provide an express or affirmative warranty by PFF; and, except the for the Specifications, none of the documents mentioned in the final paragraph of the PO were provided to PFF until after the PFF’s work was done.563 PFF maintains that absent any language in the PO expressly stating that PFF warrants the panels or any specific provision, there is no express warranty and, therefore, nothing upon which TCI can rely to show that PFF breached an express warranty.564 TCI does dispute PFF’s assertion it did not receive certain documents. It argues, however, whether PFF reviewed the incorporated documents before it entered into the TCI-Czar Contract is irrelevant because PFF is bound by their terms.565 TCI also maintains the document PFF admits to reviewing, the Specifications, contains the 560 D.I. 103 at 15, ¶ 11. D.I. 222 at 2. 562 D.I. 206 at 16. 563 Id. (citing D.I. 231-1, Stip. Ex. 8 (TCI-PFF PO); D.I. 243-16 (Mefferd Dep.) at 24:14-23; 51:14-20; 56:6-13; 207:18-208:1; D.I. 243-1, Stip. Ex . 11 (Feb. 16, 2015 email from Dan Garner of PFF to George Thomas of TCI) (PFF received specification (only) on 11-18-13)). 564 D.I. 206 at 16-17. 565 D.I. 222 at 14. 561 131 warranty provision.566 The court finds the evidence does not support TCI’s claim for breach, or existence of, an express warranty. First, in response to PFF’s motion, TCI provides scant legal support for its statement that whether PFF reviewed the purportedly incorporated documents prior to entering its contract with TCI is irrelevant.567 PFF, however, notes that Delaware courts have held “[a] contract may be created by reference to the terms of another instrument if a reading of all documents together gives evidence of the parties’ intention and the other terms are clearly identified.”568 However, “[a] mere reference in one agreement to another agreement, without more, does not incorporate the latter agreement into the former by reference.”569 Read together, the Specifications PFF acknowledges receiving, and other documents 566 D.I. 234 at 9 (citing D.I. 243-1, Stip. Ex. 3 § 1.9 (requiring provision of a one year warranty that “panels are free from defects in materials and workmanship” and to replace or repair any defective panels during that timeframe). 567 TCI cites a footnote several pages earlier in its brief raising the issue of an affidavit negating concessions in previous deposition testimony about rejection of PFF’s panels. D.I. 222 at 14 (citing id. at 5 n.5). Neither the affidavit nor deposition testimony addressed a warranty. The extent of its legal citation on the topic in TCI’s opening brief in support of its motion is that a party “is presumed to have read the [] agreement and, by signing it, agreed to be bound by the terms set forth in the agreement and those incorporated by reference[,]” Rose Heart, Inc.v. Ramesh C. Batta Assocs., P.A., C.A., 1994 WL 164581, at *4 (Del. Super. Apr. 12, 1994), and that a “Def endant is presumed with knowledge of the terms of the contract it executed, including those terms incorporated by reference.” Healy v. Silverhill Const. Co., 2007 WL 2769799, at *3 (Del. Com. Pl. Sept. 19, 2007). D.I. 209 at 12 n.6. T CI’s attempted reliance on the Garner affidavit has been discussed above. 568 Realty Growth Investors v. Council of Unit Owners of Pilot Point Condominium, 453 A.2d 450, 454 (Del. 1982). 569 Wolfston v. Supermarkets General Holdings Corp., C.A. No. 17047, 2001 W L 85679, at *5 (Del. Ch. Jan. 23, 2001). 132 identified by TCI,570 do not show that intent. The express warranty provisions in each of those document concern TCI’s obligations to DSU, not PFF’s obligations to TCI. The court has determined elsewhere in this opinion that DSU does not have third-party beneficiary status with respect to the subcontracts of any defendants with which it has direct contracts for the Project. Thus, the court grants PFF’s motion for summary judgment on TCI’s express warranty claim. PFF also argues TCI fails to demonstrate how it breached an implied warranty of fitness. Under Delaware law, a plaintiff claiming breach of the implied warranty of fitness for a particular purpose, must prove that: (1) plaintiff had a special purpose for the goods; (2) defendant knew or had reason to know of that purpose; (3) defendant knew or had reason to know that the plaintiff/buyer was relying on the seller’s superior skill to select goods that fulfilled that purpose; and (4) the plaintiff in fact relied on defendant’s superior skill.571 PFF does not challenge the first two elements under consideration: TCI had a special purpose for the panels, and PFF knew or had reason to know of that purpose. PFF argues no evidence supports TCI’s contention that it relied on PFF’s superior skill to select the panels, or that PFF had reason to know of such alleged reliance.572 The 570 D.I. 222 at 14 (citing D.I. 243-1, Stip. Ex. 48 (General Conditions) § 3.5 (“The Contractor warrants to the Owner, Construction Manager, and Architect that materials and equipment furnished under the Contract will be of good quality and new . . . [and] that the Work will conform with the requirements of the Contract Documents . . . .); D.I. 243-3, Stip. Ex. 140 (Supplemental General Conditions) § 3.5 (reciting additional one year warranty requirements). 571 Atamian v. Ryan, C.A. No. 03C-12-038(RBY), 2006 WL 1816936, *4 (Del. Super. June 9, 2006) (citation omitted). 572 D.I. 206 at 2 (¶ 1), 4, (¶¶ 8-11), 18. 133 court determines that questions of fact on these issues precludes summary judgment on TCI’s breach of implied warranty claim against PFF. PFF does not dispute that it was one of only two acceptable manufacturers of the panels,573 thus at least leading to a reasonable question as to whether PFF had reason to know that TCI was relying on PFF’s superior skill to provide panels that fulfilled their purpose in the Project. W hether TCI relied on that skill is at issue with, for instance, PFF’s recommendation, or not, to make V-Channels in the panels, a decision implicated in the panel deformations. PFF argues the evidence shows its product data made TCI aware that making V-Channels in the panels was recommended to relieve stress when they are subjected to a temperature differential that could cause warping of the panels.574 For its part, TCI submits deposition testimony which states it relied on that PFF advised against making V-Channels in the panels. 575 The court, therefore, denies PFF’s motion for summary judgment on TCI’s implied breach of warranty claim. TCI contends PFF’s motion for summary judgment on its common law indemnification and contribution claim should survive summary judgment because DSU asserted a negligence claim against both TCI and PFF, and those claims have yet to be adjudicated.576 TCI also argues that, while no adjudication has been made, and therefore no payments made by TCI, that does not bar TCI from pursuing contribution 573 See D.I. 195, Stip. Fact ¶ 10. D.I. 206 at 18. 575 D.I. 222 at 14 (citing D.I. 243-1 (Thomas Dep.) at 93:9-94:3; 104:22; 234:16574 25.). 576 Id. at 15. 134 from PFF under Delaware’s Uniform Contribution Among Tortfeasors Law, 10 Del. C. § 6301 et seq. (“UCATL”). 577 TCI and DSU have recently dismissed their respective claims against each other.578 The court has granted summary judgment in favor of PFF and Czar, on DSU’s tort claims against each. Those claims are now adjudicated. Section 6301 requires the establishment of joint tortfeasor status.579 Dismissal of DSU’s tort claims against PFF and Czar, and DSU’s dismissal of its claims against TCI, means no joint tortfeasor status can be established. Thus, PFF’s motion for summary judgment on TCI’s common law indemnification and contribution claim is granted. TCI concedes to summary judgment in favor of PFF on its Unjust Enrichment and Contractual Indemnification claims against PFF.580 Thus, the court grants PFF’s motion for summary judgment on those claims by TCI against PFF. 577 Id. D.I. 257. 579 See Builders & Managers, Inc. v. Dryvit Sys., Inc., 2004 WL 304357, at *2 (Del. Super. Feb. 13, 2004) (“The right to contribution is triggered when it is appropriate for liability to be apportioned among codefendants. In Delaware, contribution is governed by the UCATL which provides the parameters for determining when contribution is appropriate and how it is to be decided. The inherent requirement is that the parties are joint tortfeasors who share a “common liability.”) (citations omitted); New Zealand Kiwifruit Mktg. Bd. v. City of Wilmington, 825 F. Supp. 1180, 1186 (D. Del. 1993) (“Indispensable to a joint tortfeasor relationship is a ‘common liability’ either ‘joint’ or ‘several’ that two or more parties have to the person injured. Without this dual liability . . . no right of contribution can exist.”) (omission in original) (citation omitted). 580 See D.I. 222 at 15 n.7 (“As it is now undisputed that Thomas and PFF are parties to express contract, Thomas does not object to the dismissal of its unjust enrichment claim. Thomas likewise recognizes that proscriptions contained in 6 Del. C. § 2704 apply to the contractual indemnification provisions at issue in this case.”). 578 135 II. CONCLUSION–PFF and TCI Motions for Summary Judgment For the reasons discussed above: I. Precision Foam Fabricator’s Motion for Summary Judgment against Delaware State University and Thomas Company, Inc. (D.I. 205) is: A. GRANTED as to DSU’s Count I (Breach of Contract); Count III (Negligence); and Count IV (Unjust Enrichment); B. C. GRANTED as to TCI’s claims for Unjust Enrichment; Common Law Indemnification and Contribution; and Breach of Express Warranty; and D. II. DENIED as to TCI’s Breach of Contract claim against PFF. DENIED as to TCI’s Breach of Implied Warranty. Thomas Company, Inc.’s Motion for Partial Summary Judgment against Precision Foam Fabricators, Inc. (D.I. 207) is: A. GRANTED on its Breach of Contract claim against PFF. B. DENIED on its request to sever its Breach of Contract claim. C. DENIED as to the specific amount of damages TCI seeks against PFF. An appropriate order shall issue. November 19, 2020 /s/ Mary Pat Thynge Chief U.S. Magistrate Judge 136

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?