FISHERIES SURVIVAL FUND et al v. JEWELL et al

Filing 73

MEMORANDUM OPINION regarding Plaintiffs' 61 Motion to Alter/Amend. Signed by Judge Tanya S. Chutkan on 2/14/2020. (lcdl)

Download PDF
UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA FISHERIES SURVIVAL FUND, et al., Plaintiffs, v. DAVID BERNHARDT, et al., Defendants, and EQUINOR WIND US LLC, Defendant-Intervenor. ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) Case No. 16-cv-2409 (TSC) Memorandum Opinion By Memorandum Opinion and Order dated September 30, 2018, this court found that Plaintiffs’ claims under the National Environmental Policy Act (NEPA) were not ripe. (ECF No. 59 (“Mem. Op.”); ECF No. 60 (“Order”).) Plaintiffs now move this court to reconsider that finding. (ECF. No. 61 (“Pls. Mot. to Alter”).) For the reasons stated below, Plaintiffs’ motion will be DENIED. I. BACKGROUND 1 This case concerns a Bureau of Ocean Energy Management (“BOEM”) plan to lease a nautical area off the coast of New York to Defendant-Intervenor Statoil Wind US, LLC (“Statoil”) for development of a wind energy facility. On December 15 and 16, 2016, BOEM 1 The court assumes the parties’ familiarity with the facts of this case and recites only what is necessary to resolve the issues now before it. Additional background information can be found in the court’s September 30, 2018 Memorandum Opinion. (ECF No. 59.) 1 held a lease auction, which Statoil won with a $42,469,725 bid. See Commercial Lease of Submerged Lands for Renewable Energy Development on Continental Shelf (NYAR-0046753). BOEM and Statoil executed the lease on March 15, 2017. See NYAR-0046759. The lease grants Statoil the exclusive right to conduct site characterization activities and, within one year of lease issuance, to propose a Site Assessment Plan. See NYAR-0046753; 30 C.F.R. §§ 585.601(a), 585.605. Upon BOEM’s approval of the Plan, Statoil has five years to engage in site assessment—including conducting surveys and using towers or buoys to evaluate wind resources—and propose a Construction and Operations Plan (“COP”), see 30 C.F.R. §§ 585.235(a)(2), 585.601(b), which must include detailed data and information to support the plan for the wind facility, and proposals for minimizing environmental impact. See 30 C.F.R. § 585.626(b). BOEM would then conduct “an appropriate NEPA analysis” based on the information included in the COP, before deciding whether to approve it. 30 C.F.R. § 585.628(b). Plaintiffs allege, inter alia, that this process violated NEPA because BOEM failed to produce an Environmental Impact Statement (EIS) before issuing the lease. (ECF No. 1 (Compl.) ¶¶ 106–11.) This court disagreed, holding that the issuance of the lease did not trigger an obligation under NEPA to produce an EIS, and thus Plaintiffs’ NEPA claims were not ripe. (Mem. Op. at 14–21.) Through a motion and three notices of supplemental authority, Plaintiffs ask this court to revisit that holding. (See Pls. Mot. to Alter; ECF No. 65 (Supp. Authority); ECF No. 67 (2nd Supp. Authority); ECF No. 70 (3rd Supp. Authority).) II. LEGAL STANDARD “A Rule 59(e) motion is discretionary and need not be granted unless the district court finds that there is an intervening change of controlling law, the availability of new evidence, or the need to correct a clear error or prevent manifest injustice.” Firestone v. Firestone, 76 F.3d 2 1205, 1208 (D.C. Cir. 1996) (internal quotations omitted). Rule 59(e) does not permit a litigant to “present evidence that could have been raised prior to the entry of judgment,” Kline v. Archuleta, 309 F.R.D. 91, 92 (D.D.C. 2015), and “a losing party may not use a Rule 59 motion to raise new issues that could have been raised previously.” Kattan v. District of Columbia, 995 F.2d 274, 276 (D.C. Cir. 1993). III. DISCUSSION Plaintiffs argue that they meet the Rule 59(e) standard because of the “availability of new evidence.” Firestone, 76 F.3d at 1208. They direct the court to allegedly new documents concerning the continued development of multiple offshore wind projects, including the one at issue here. Even assuming the evidence is in fact new, and further assuming that the court could take notice of it, the evidence does not alter the court’s original conclusion that the NEPA claims are not ripe. That original conclusion focused on whether issuing the lease to Statoil triggered BOEM’s obligation to produce an EIS. (See, e.g., ECF No. 48 (Pls. MSJ Reply) at 9–14.) The D.C. Circuit has held that an agency does have an obligation to produce an EIS upon initiation of a project, but only when the agency reaches a “critical stage of a decision which will result in irreversible and irretrievable commitments of resources.” Ctr. for Biological Diversity v. U.S. Dep’t of Interior, 563 F.3d 466, 480 (D.C. Cir. 2009) (quoting Wyo. Outdoor Council v. U.S. Forest Serv., 165 F. 3d 43, 49 (D.C. Cir. 1999) (“Wyo. Outdoor Council II”)). In cases like this, involving multiple-stage leasing programs, an agency does not reach this “critical stage” unless and until it “no longer retain[s] the authority to preclude all surface disturbing activities . . .” Wyo. Outdoor Council II, 165 F.3d at 49 (alteration in original) (quoting Sierra Club v. Peterson, 717 F.2d 1409, 1415 (D.C. Cir. 1983)). Here, this court reviewed the lease and the relevant 3 regulations and determined that even after issuing the lease, BOEM retained complete authority to preclude all surface disturbing activities. (Mem. Op. at 17, 19.) Accordingly, the court held that there was no obligation to issue an EIS and thus Plaintiffs’ NEPA claims were not ripe. (Id. at 20–21.) Plaintiffs now direct the court to four pieces of evidence, but because the evidence does not bear on BOEM’s legal authority to preclude construction, it does not undermine the court’s original holding. First, Plaintiffs provide evidence that various states and electric distribution companies have entered into power purchase agreements with offshore wind developers based on “nothing more than the existence of the developer’s lease with BOEM.” (Mot. to Alter at 4.) According to Plaintiffs, these agreements indicate that “multiple states and utilities are now staking their energy future and infrastructure needs on the same types of offshore wind energy leases at issue here.” (Id. at 2.) Plaintiffs argue that the existence of these power purchase agreements makes it “extremely unlikely that BOEM can retain the unilateral authority to revoke the leases or preclude wind farm development.” (Id. at 8.) But in making this argument Plaintiffs are not claiming that the power purchase agreements legally undermine BOEM’s authority to approve or disapprove of future construction. Therefore, this evidence does not alter the court’s prior judgment. Second, in their first Notice of Supplemental Authority, Plaintiffs point to a BOEM Notice announcing that three new leases for other offshore wind energy sites were recently purchased for approximately $135 million each. (Supp. Authority at 1– 2.) Plaintiffs argue that these high prices for similar leases show that private developers consider development of a revenue-generating wind farm to be “foreseeable” even at the lease stage. (Id.) But even if 4 companies are investing heavily in the possibility of construction, that fact does not undermine the court’s conclusion that BOEM nonetheless retains the right to preclude construction. Third, in a second Notice of Supplemental Authority, Plaintiffs point the court to an announcement by the New York State Energy Research and Development Authority (“NYSERDA”) that it awarded an offshore wind contract for the site at issue in this case. (2nd Supp. Authority at 2.) Plaintiffs argue that this evidence reveals the “foreseeable consequences” of issuing the lease. (Id. at 2.) But even if that is true, it does not alter BOEM’s legal authority to preclude construction even after issuing the lease. Finally, in a third notice of Supplemental Authority, Plaintiffs provide a BOEM statement from 2019 that “buildout of offshore wind capacity [including in the area relevant to this suit] is reasonably foreseeable.” (3rd Supp. Authority at 2.) Plaintiffs characterize this as a concession by BOEM that “build out of offshore wind capacity is a ‘reasonably foreseeable’ consequence of lease issuance.” (Id. at 3.) However, BOEM’s statement in 2019 that development is foreseeable does not mean that it was foreseeable at the time the lease was issued. Many events that occur after lease issuance, such as the results of evaluations and the development of power purchase agreements, can affect whether development is foreseeable. And even if development was foreseeable when the lease was issued, that fact does not mean that BOEM could not still preclude construction. In sum, none of the evidence Plaintiffs proffer undermines the fact that BOEM retains authority to preclude construction. At most, the evidence suggests that the lease gave way to various decisions (such as energy reliance and investments) that make BOEM unlikely to exercise its authority to preclude construction. But even if that is true, it is not enough to establish that in issuing the lease Defendants ceded “the authority to preclude all surface 5 disturbing activities.” Wyo. Outdoor Council II, 165 F.3d at 49. As this court previously found, “the lease sale does not represent the final word on anything, nor does it commit any resources, even putting aside the question of whether it does so irretrievably.” (Mem. Op. at 20.) The court finds no reason to alter or amend that conclusion. IV. CONCLUSION For the foregoing reasons, the court hereby concludes that Plaintiffs’ Motion to Alter or Amend will be DENIED. An appropriate order accompanies this memorandum opinion. Date: February 14, 2020 Tanya S. Chutkan TANYA S. CHUTKAN United States District Judge 6

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?