In the United States Court of Federal Claims
No. 09-814C
(Filed: May 7, 2012)
_________
PEW FOREST PRODUCTS,
Plaintiff,
v.
THE UNITED STATES,
Defendant.
*
*
*
*
*
*
*
*
*
*
*
Timber contract case; Cross-motion for
summary judgment; Existence of contracts –
offer and acceptance; Implied-in-fact
contracts; Covenant of good faith and fair
dealing; No breach; Defendant’s motion for
summary judgment granted.
_________
OPINION
__________
Robert J. Tuerck, Jackson and Tuerck, Quincy, CA, for plaintiff.
Ellen M. Lynch, Commercial Litigation Branch, United States Department of Justice,
Washington, D.C., with whom was Assistant Attorney General Tony West, for defendant.
ALLEGRA, Judge:
In this government contract case, Pew Forest Products (Pew) alleges that the United
States Forest Service (the Forest Service) breached its timber sale contracts by delaying logging
operations, and by failing to provide plaintiff with the contractual remedies for that delay to
which it was entitled. The parties have filed cross-motions for summary judgment. Following
oral argument, and after further review of the briefs and accompanying appendices, the court
GRANTS defendant’s motion for summary judgment and DENIES plaintiff’s cross-motion for
partial summary judgment.
I.
BACKGROUND
A brief recitation of the underlying facts sets the context for this decision.
Pew is a family-owned logging company based in Crescent Mills, California. Pew has
been involved in the purchase and harvest of timber from the Forest Service for the past thirtyfive years.
In September 2006, the Forest Service approved the Freeman Project, a forest
management plan that included the sale and harvest of certain timber located in the Plumas
National Forest in California (Plumas). 1 On May 21, 2007, the Forest Service sent Pew and
other logging companies prospectuses for two timber sales: the Jenkins Multi-Product Thin
(Jenkins) and the Summit Bear Multi-Product Thin (Summit Bear). Both sales involved timber
located on the Beckwourth Ranger District in Plumas. The letter accompanying these
prospectuses indicated that bids for these projects would be opened on June 26, 2007. Both the
letter and the prospectuses, however, warned potential bidders that a pike eradication project,
planned by the California Department of Fish and Game for “areas immediately adjacent to Lake
Davis and perennial stream courses flowing into Lake Davis” could disrupt access to the timber
sale area for up to one month between July and October of 2007. These same documents
warned that ongoing environmental litigation regarding the Freeman Project could lead to the
suspension, modification or termination of any contract, adding that the contracts would provide
“for limited remedies” in the case of such litigation-generated action. 2
1
The Forest Service is charged with the management of our national forests through the
development and implementation of forest management plans. See The National Forest
Management Act, 16 U.S.C. § 1600 et seq. Through the latter plans, the Forest Service
organizes and administers timber sales. See 16 U.S.C. §§ 1611, 1613.
2
Regarding the period of contract, each prospectus stated –
The normal operating season covers the period between 06/01 and 10/31.
Contract termination date is 03/31/2010. Extensions of this contract may be
granted only when the purchaser has met specified conditions.
If an appeal or lawsuit is filed challenging the decision to award this contract or
upon determination by the Regional Forester that conditions existing on this
timber sale are the same as, or nearly the same as, conditions existing on other
timber sale(s) in appeal or litigation, Contracting Officer may delay award or
reject all bids. If delay in award is for 30 days or more during Normal Operating
Season after bid opening, Contracting Officer shall, upon award, adjust the
contract term to include additional calendar days in one or more Normal
Operating Seasons equal to the time award is delayed during Normal Operating
Season.
-2-
On May 22, 2007, as part of ongoing litigation involving timber sales, environmental
groups filed a motion for a preliminary injunction to prevent the Forest Service from “awarding
logging contracts or otherwise carrying out the Freeman Project.” The United States District
Court for the Eastern District of California denied the environmentalists’ motion on June 8,
2007. On June 26, 2007, Pew submitted bid forms for both timber sales. These bids were
submitted on preprinted forms supplied by the Forest Service. These forms contained language
that provided – “[s]igning this bid form binds the Bidder to accept award under the terms of the
sample contract and this bid form if its bid is accepted within 90 days after bid opening.” They
also stated that “[t]he Bidder whose bid is accepted will, within 30 days of the award letter’s
date, or any written extension thereof by the Forest Service, execute a timber sale contract which
shall be provided by the Forest Service and be based on the sample contract referenced in the
prospectus.” On June 26, 2007, Joseph Franco, the Forest Service contracting officer (CO) for
the Jenkins and Summit Bear contracts, determined that the Freeman Project could proceed and
opened the bids. As plaintiff was the only bidder for these contracts, it was declared the high
bidder.
The Forest Service’s regional office instructed the CO to delay awarding the contracts
while negotiations with the environmental groups progressed. The CO passed this information
along to Randy Pew, Pew’s owner, and asked him to attend a meeting with representatives from
the Forest Service and the environmental groups. Mr. Pew complied with this request. At that
meeting, the environmental groups explained their concerns with the Jenkins and Summit Bear
timber sales, but agreed to drop their opposition to those sales as long as the logging operations
did not begin until after September 15, 2007.
On August 31, 2007, the Forest Service sent Pew a letter for each of the Jenkins and
Summit Bear timber sales indicating that “[y]our bid has been accepted and you are hereby
awarded the timber sale contract.” Enclosed with each letter was a contract for the respective
timber sale. That same day, the CO and Mr. Pew signed an agreement that delayed operations on
the Jenkins and Summit Bear sales until after September 15, 2007. Shortly before the award of
these contracts, the CO and Mr. Pew also signed a “Pre-Award Waiver, Release and Limitation
of Liability Agreement” for each sales contract. These waivers both stated, in pertinent part, that
plaintiff “desires the Forest Service to proceed with the award of the contract, despite the
possibility that the Forest Service might delay or suspend operations, and/or modify or terminate
the contract.” Mr. Pew, who signed the waiver agreements on behalf of Pew, did not inform
anyone at the Forest Service that he was unwilling to accept this limitation. He alleges that he
felt that if he did not sign the waivers, Pew would be viewed by the Forest Service as having
repudiated the contracts.
Plaintiff moved its logging equipment to the Jenkins timber sale area on September 17,
2007. The parties dispute when plaintiff actually commenced logging. Plaintiff suffered further
delays when access to the logging site was disrupted by a pike eradication project run by the
California Department of Fish and Game. That project was completed on October 1, 2007. On
October 2, 2007, plaintiff removed the first load of timber from the Jenkins site.
-3-
On January 4, 2008, Pew requested a rate redetermination pursuant to paragraph B3.33 of
its contracts to compensate it for what it claimed was a drop in the value of the contract. That
paragraph provided that –
In the event of delay or interruption, exceeding 90 days, under B8.33, Contracting
Officer shall make an appraisal to determine for each species the difference
between the appraised unit value of Included Timber immediately prior to the
delay or interruption and the appraised unit value of Included Timber immediately
after the delay or interruption.
The CO granted the request and the rate determination was performed. However, the Forest
Service found that the value of the contract had increased and, therefore, denied plaintiff the
adjustment it sought. Pew completed logging operations on the Jenkins sale on January 8, 2008.
It never began logging operations on the Summit Bear sale because a decline in timber prices led
it to believe that the area could no longer be logged profitably under the 2007 contract. On
August 29, 2008, plaintiff submitted a certified claim to the CO, seeking damages for the losses
sustained as a result of the delays. On May 21, 2009, the CO denied this claim.
Plaintiff filed its complaint in this court on November 20, 2009. Following discovery, on
May 13, 2011, defendant filed a motion for summary judgment. On June 13, 2011, plaintiff
filed a cross-motion for partial summary judgment. Briefing and argument of these crossmotions has been completed.
II.
DISCUSSION
We begin with common ground. Summary judgment is appropriate when there is no
genuine dispute as to any material fact and the moving party is entitled to judgment as a matter
of law. See RCFC 56; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986). Disputes
over facts that are not outcome-determinative will not preclude the entry of summary judgment.
Id. at 248. However, summary judgment will not be granted if “the dispute about a material fact
is ‘genuine,’ that is, if the evidence is such that a reasonable [trier of fact] could return a verdict
for the nonmoving party.” Id.; see also Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475
U.S. 574, 587 (1986); Becho, Inc. v. United States, 47 Fed. Cl. 595, 599 (2000).
When making a summary judgment determination, the court is not to weigh the evidence,
but to “determine whether there is a genuine issue for trial.” Anderson, 477 U.S. at 249; see also
Agosto v. Immigration & Naturalization Serv., 436 U.S. 748, 756 (1978) (“a [trial] court
generally cannot grant summary judgment based on its assessment of the credibility of the
evidence presented”); Am. Ins. Co. v. United States, 62 Fed. Cl. 151, 154 (2004). The court must
determine whether the evidence presents a disagreement sufficient to require fact finding, or,
conversely, is so one-sided that one party must prevail as a matter of law. Anderson, 477 U.S. at
250-52; see also Ricci v. DeStefano, 129 S. Ct. 2658, 2677 (2009) (“‘Where the record taken as a
whole could not lead a rational trier of fact to find for the nonmoving party, there is no genuine
-4-
issue for trial.’” (quoting Matsushita, 475 U.S. at 587)). Where there is a genuine dispute, all
facts must be construed, and all inferences drawn from the evidence must be viewed, in the light
most favorable to the party opposing the motion. Matsushita, 475 U.S. at 587-88 (citing United
States v. Diebold, Inc., 369 U.S. 654, 655 (1962)); see also Stovall v. United States, 94 Fed. Cl.
336, 344 (2010); L.P. Consulting Grp., Inc. v. United States, 66 Fed. Cl. 238, 240 (2005).
“Where, as here, a court rules on cross-motions for summary judgment, it must view each
motion, separately, through this prism.” Carolina Plating Works, Inc. v. United States, 102 Fed.
Cl. 555, 559 (2011). 3
A.
When did the contracts come into existence?
It is undisputed that the parties entered into two timber sales contracts. What is disputed
is when those contracts came into existence. Plaintiff contends that the contracts came into being
on June 26, 2007, when plaintiff was declared the high bidder. Not so, defendant asseverates,
claiming that the contracts were not formed until August 31, 2007, the date on which the
contracts were signed.
Both parties agree that for there to be a contract with the United States, there must be a
mutual intent to contract including an offer, an acceptance, and consideration. See Chattler v.
United States, 632 F.3d 1324, 1330 (Fed. Cir. 2011); Trauma Serv. Grp. v. United States, 104
F.3d 1321, 1325 (Fed. Cir. 1997). In addition, the government representative who entered into
the agreement must have actual authority to bind the United States. Chattler, 632 F.3d at 1330.
In concluding whether and when these formation requirements are met, the court must give
effect to the plain meaning of the language employed by the parties in the various bidding and
contracting documents. See Stockton E. Water Dist. v. United States, 583 F.3d 1344, 1362 n.35
(Fed. Cir. 2009) (“Ordinarily when a provision is found to have a plain meaning, that is deemed
to conclusively establish the parties’ intent.”); McAbee Constr. Inc. v. United States, 97 F.3d
1431, 1434-35 (Fed. Cir. 1996) (same); Dobyns v. United States, 91 Fed.Cl. 412, 420 (2010).
In terms of the elements listed above, the focus on when the contracts arose here is on
offer and acceptance. The parties essentially agree that Pew’s bids constituted “offers” to
remove timber from the two tracts. Plaintiff claims that these offers were accepted when the
Forest Service CO opened the bids and determined that Pew was the winning bidder. But,
defendant argues that Pew improperly conflates the fact that it was declared the apparent high
bidder with the acceptance of its offers by the Forest Service.
3
See Chevron U.S.A. Inc. v. Mobil Producing Tex. & N. Mex., 281 F.3d 1249, 1252-53
(Fed. Cir. 2002); see also Estate of Hevia v. Portrio Corp., 602 F.3d 34, 40 (1st Cir. 2010);
Travelers Prop. Cas. Co. of Am. v. Hillerich & Bradsby Co., Inc., 598 F.3d 257, 264 (6th Cir.
2010); Stovall, 94 Fed. Cl. at 344; Northrop Grumman Computing Sys., Inc. v. United States, 93
Fed. Cl. 144, 148 (2010).
-5-
The record strongly supports defendant’s view. For one thing, the bid form used by Pew
indicates that the bidder would accept an award “if its bid is accepted within 90 days after bid
opening.” This language plainly suggests that the mere opening of a bid did not constitute the
acceptance of an offer and that, instead, the award would follow later. This reading is confirmed
by another statement in the bid form indicating that “[t]he Bidder whose bid is accepted will,
within 30 days of the award letter’s date . . . execute a timber sale contract which shall be
provided by the Forest Service and be based on the sample contract referenced in the
prospectus.” Again, this sentence plainly distinguishes between the acceptance of a bid, on the
one hand, and the award date and the execution of the contract, on the other. Consistent with this
reading of the bids, the formal contracts for the timber sales were signed within the period
prescribed in the bids, on August 31, 2007, on the same day the award letter was sent and 67
days after the bid opening. It is difficult to see how plaintiff could believe that the awards came
sooner. For one thing, it was not until August 31, 2007, that it received letters from the Forest
Service for each sale announcing that “[s]ealed bids for the [contract] were opened on
6/26/2007,” and adding that “[y]our bid has been accepted and you are hereby awarded the
timber sale contract.” And it was on that same day – August 31, 2007 – that plaintiff signed a
document entitled “Pre-Award Waiver, Release and Limitation of Liability Agreement” for each
of the timber sales, one of the recitals of which indicated that “[w]hereas Purchaser desires the
Forest Service to proceed with the award of the contract.” Taken together, the letter and waiver
agreement confirm what the bidding and contract documents themselves unambiguously reveal,
to wit, that no contracts arose here until August 31, 2007.
Certainly, these documents do not manifest the “unambiguous acceptance” required to
create a binding contractual obligation. See Peninsula Grp. Capital Corp. v. United States, 93
Fed. Cl. 720, 729-30 (2010); see also Essen Mall Prop. v. United States, 21 Cl. Ct. 430, 440
(1990); Uniq Computer Corp. for Benefit of U.S. Leasing Corp. v. United States, 20 Cl. Ct. 222,
231-32 (1990). Per contra. They unambiguously indicate that the opening of the bids and
declaration that plaintiff’s bids were highest was not tantamount to the acceptance of plaintiff’s
offers, which did not occur until the awards were made and the formal contracts signed. Plaintiff
should not be heard to argue otherwise – particularly based on the claim that Mr. Pew, despite
signing various contractual documents on August 31, 2007, secretly believed that the contracts
somehow had already been formed. The law is decidedly hostile to such claims. See Firestone
Tire & Rubber Co. v. United States, 444 F.2d 547, 551 (Ct. Cl. 1971) (“The unexpressed,
subjective unilateral intent of one party is insufficient to bind the other contracting party,
especially when the latter reasonably believes otherwise.”); see also Standard Oil Co. of Cal. v.
United States, 685 F.2d 1337, 1345 (Ct. Cl. 1982); Public Serv. Co. of Okla. v. United States, 88
Fed. Cl. 250, 262 (2009). 4 And this case warrants no departure.
4
Plaintiff implies that because Mr. Pew subjectively believed that the contracts were
already in place, while defendant did not, there was no meeting of the minds in the written
contracts. This court rejected a similar claim in Applegate v. United States, 52 Fed. Cl. 751, 756
n.6 (2002), stating “[t]his sort of contention is far too convenient, for it effectively would allow
one contracting party to renege on a contract at will based on unexpressed intentions.” The court
-6-
Plaintiff’s argument that the Forest Service accepted its offer by declaring plaintiff the
high bidder also runs afoul of the relevant Forest Service regulations governing timber sales. 5
Those regulations contemplate that, in the case of sealed bidding, the award will be made to the
“responsible bidder submitting the highest bid that conforms to the conditions of the sale as
stated in the prospectus” – but with some important caveats that make clear that such an award
is not automatic. See 36 C.F.R. § 223.100 (indicating, for example, that the agency may not
award the contract if the highest bidder is “notoriously or habitually careless with fire” or the
result would result in a “monopoly” over “large amounts of public and private timber”). Nor
may an award be made under this regulation to the high bidder unless it is determined to be
“responsible.” See 3 George Cameron Coggins and Robert L. Glicksman, Pub. Nat. Resources
L. § 34:30 (2d ed. 2012) ([a] contracting officer may not award a timber contract unless he or she
makes an affirmative determination of purchaser responsibility”); see also 36 C.F.R. §
223.101(a). In this regard, section 223.101 of these regulations lists six separate conditions that
must be satisfied before the contracting officer can determine that the highest bidder is
“responsible.” 36 C.F.R. § 223.101(b). 6 Other regulations require the agency to perform various
tasks “[i]f the highest bid is not accepted,” again indicating acceptance is not automatic. See 36
C.F.R. § 223.102. And still other provisions specify who within the agency has the authority
“formally to execute timber sale contracts,” 36 C.F.R. § 223.110 – a provision that would make
little sense if, as plaintiff claims, the Forest Service intended a timber sales contract to arise upon
the opening of the bids. Indeed, this last point is, in many ways, determinative, because it is
well-accepted that a contract is not deemed to arise if at least one of the parties anticipates that
the agreement will not occur until the agreement is reduced to writing and formally executed.
See Peninsula Grp. Capital Corp., 93 Fed. Cl. at 729; see also Restatement (Second) Contracts §
27 cmt. b-c.
added that “[s]uch is decidedly not the law, particularly where, as here, there is no ambiguity in
the contract itself. Id. (citing Restatement (Second) of Contracts § 2 cmt. b (1981)).
5
These regulations are relevant as courts have often held that a contract cannot arise
until the statutes or regulations governing its formation are followed. See Russell Corp. v.
United States, 537 F.2d 474, 477 (Ct. Cl. 1976); Peninsula Grp. Capital Corp., 93 Fed. Cl. at
730; Ruttenburg v. United States, 65 Fed. Cl. 43, 48-49 (2005).
6
This responsibility determination is anything but pro forma. In assessing
responsibility, the contracting officer is required by the regulations to determine that the
purchaser: (i) has adequate resources to perform the contract or the ability to obtain them; (ii) is
able to perform the contract within the contract term taking into account all other business
commitments; (iii) has a satisfactory performance record on timber sales; (iv) has a satisfactory
record of integrity and business ethics; (v) has or is able to obtain equipment and supplies
suitable for logging the timber and to provide resource protection; and (vi) is otherwise qualified
and eligible to receive the award under applicable laws and regulations. 36 C.F.R. § 223.101(b);
see also Thomas Creek Lumber and Log Co. v. United States, 22 Cl. Ct. 559, 561 (1991);
Northwest Ecosystem Alliance, 96-2 C.P.D. ¶ 12 (1996); 3 Pub. Nat. Resources L, at § 34:30.
-7-
In the court’s view, there are no questions of fact that prevent the court from determining
when the contracts here arose. “[N]o acceptance mean[s] no contact.” Fletcher-Harlee Corp. v.
Pote Concrete Contractor, Inc., 482 F.3d 247, 251 (3d Cir. 2007). Based on the foregoing, the
court concludes, as a matter of law, that the timber contracts between the parties arose no earlier
than August 31, 2007.
B.
Did the parties have other agreements?
Plaintiff asserts that, besides the timber contracts, it had two other agreements with
defendant that it claims were breached.
First, it contends that an implied in-fact contract governing the timber sales sprung into
existence on June 26, 2007, the date its bids were opened and deemed highest. But, there are
several problems with this assertion. For one thing, the requirements for an implied-in-fact
contract are the same as those for an express contract. See Sommers Oil Co. v. United States,
241 F.3d 1375, 1378 (Fed. Cir. 2001); City of El Centro v. United States, 922 F.2d 816, 820
(Fed. Cir. 1990). Accordingly, if, as demonstrated above, the requirements for the formation of
an express contract were not met here until August 31, 2007, the same is true for any implied-infact contract. In addition, “[i]t is well settled that the existence of an express contract precludes
the existence of an implied-in-fact contract dealing with same subject matter.” Schism v. United
States, 316 F.3d 1259, 1278 (Fed. Cir. 2002); see also Trauma Serv. Grp., 104 F.3d at 1326;
Atlas Corp. v. United States, 895 F.2d 745, 754-55 (Fed. Cir. 1990). This rule applies equally to
an implied-in-fact contract that is claimed to have arisen before an anticipated express contract,
simultaneously with the execution of the express contract, or after the express contract has been
formed. See Bank of Guam v. United States, 578 F.3d 1318, 1329 (Fed. Cir. 2009); Schism, 316
F.3d at 1278 (after); Rick’s Mushroom Serv., Inc. v. United States, 521 F.3d 1338, 1344 (Fed.
Cir. 2008); Atlas, 895 F.2d at 755; ITT Fed. Support Servs., Inc. v. United States, 531 F.2d 522,
528 (Ct. Cl. 1976); Jumah v. United States, 90 Fed. Cl. 603, 610 (2009) (simultaneous);
Ruttenburg, 65 Fed. Cl. at 49 (before). Accordingly, as a matter of law, the court rejects the
assertion that an implied-in-fact contract ever existed here.
Beyond this, defendant does not contest that two implied duties of good faith and fair
dealing arose here. The first of these required the Forest Service to “afford [the bidder’s]
submission fair and honest consideration.” Thomas Creek Lumber, 22 Cl. Ct. at 566 (citing
United States v. Grimberg Co., 702 F.2d 1362, 1373 (Fed. Cir. 1983)). But, there is no
contention that this duty was breached here.
The second implied duty of good faith and fair dealing was an implied term in the timber
contracts that were executed on August 31, 2007. See Centex Corp. v. United States, 395 F.3d
1283, 1304 (Fed. Cir. 2005); Link v. Dept. of the Treasury, 51 F.3d 1577, 1582 (Fed. Cir. 1995).
Thus, “[e]very contract . . . imposes an implied obligation ‘that neither party will do anything
that will hinder or delay the other party in performance of the contract.’” Essex Electro Eng’rs,
Inc. v. Danzig, 224 F.3d 1283, 1291 (Fed. Cir. 2000) (quoting Luria Bros. v. United States, 369
-8-
F.2d 701, 708 (Ct. Cl. 1966)); see also North Star Alaska Hous. Corp. v. United States, 76 Fed.
Cl. 158, 187 (2007); H & S Mfg., Inc. v. United States, 66 Fed. Cl. 301, 310 (2005), aff’d, 192
Fed. Appx. 965 (Fed. Cir. 2006). Such covenants require each party “not to interfere with the
other party’s performance and not to act so as to destroy the reasonable expectations of the other
party regarding the fruits of the contract.” Centex Corp., 395 F.3d at 1304; see also North Star
Alaska Hous. Corp.,76 Fed. Cl. at 187. This “duty not to hinder is breached when the
Government commits ‘actions that unreasonably cause delay or hindrance to contract
performance.’” H & S Mfg., 66 Fed. Cl. at 311 (quoting C. Sanchez & Son, Inc. v. United States,
6 F.3d 1539, 1542 (Fed. Cir. 1993)). Such a breach occurs when, in the words of Judge Posner,
there has been “sharp dealing,” defined as taking “deliberate advantage of an oversight by your
contract partner concerning his rights under the contract.” Mkt. St. Assocs. Ltd. v. Frey, 941 F.2d
588, 594 (7th Cir. 1991); see also North Star Alaska Hous. Corp., 76 Fed. Cl. at 187.
Finally on this count, there is no evidence to support plaintiff’s claim that yet another
covenant of good faith and fair dealing arose after plaintiff was declared the high bidder and ran
until the timber contracts were signed on August 31, 2007. Plaintiff does not identify the legal
basis for this covenant. And, upon further examination, it appears that the duty that plaintiff
claims sprung into existence – which required the Forest Service to allow plaintiff access to the
timber in question on an earlier date – is really nothing more than a reprise of plaintiff’s impliedin-fact contract claims in “covenant clothing.” In the court’s view, if no implied-in-fact contract
arose requiring the Forest Service to provide plaintiff with earlier access to the timber, then the
same conclusion must obtain vis-à-vis plaintiff’s covenant claim. Of course, it should not be
overlooked that even if such a covenant existed, plaintiff has provided absolutely no evidence
that the “delay” which occurred between the opening of its bids and the signing of the formal
contracts was attributable to a lack of good faith and fair dealing, i.e., to “some specific intent to
injure the plaintiff.” Torncello v. United States, 681 F.2d 756, 770 (Ct. Cl. 1982); see also Galen
Med. Assocs., Inc. v. United States, 369 F.3d 1324, 1330 (Fed. Cir. 2004). Hence, this claim
must also fail.
C.
Did defendant breach the timber sales contracts?
The court is left to decide whether defendant breached the timber contracts (and the
associated covenant of good faith and fair dealing) by delaying or hindering Pew’s logging
activities.
Of course, most of plaintiff’s breach arguments are predicated upon the misapprehension
that the timber sales contracts were formed at the time of the bid opening – and to that extent
must be rejected. But, plaintiff also claims that the Forest Service breached the timber contracts
by delaying logging operations: (i) from August 31, 2007, through September 15, 2007, to deal
with the concerns raised by environmental groups; and (ii) for some additional period owing to
the State of California’s pike eradication program. Both of these claims, however, are erroneous
as a matter of law.
-9-
Pew, of course, agreed to delay operations from August 31, 2007, through September 15,
2007, as a condition of receiving the award and as a supplemental contract term. Plaintiff,
however, asserts that Mr. Pew signed the waiver agreement under duress. Duress occurs when a
party involuntarily accepts another party’s terms because the circumstances permitted no
alternative and such circumstances were the result of the other party’s coercive acts. See North
Star Steel Co. v. United States, 477 F.3d 1324, 1334 (Fed. Cir. 2007). Plaintiff claims that it had
no choice but to sign the waiver due to its financial situation. However, it has failed to present
any evidence that would suggest that this hardship was caused by defendant or that defendant
committed any wrongful acts that would amount to coercion. See Peters v. United States, 694
F.2d 687, 694 (Fed. Cir. 1982); Johnson, Drake & Piper, Inc. v. United States, 531 F.2d 1037,
1042 (Ct. Cl. 1976); LaCrossee Garment Mfgr. Co. v. United States, 432 F.2d 1377, 1382 (Ct.
Cl. 1976). Therefore, Pew’s claim of duress fails and the release that it signed is valid and
enforceable. 7 As such, the “delay” in logging operations that occurred from August 31, 2007,
through September 15, 2007, cannot constitute a breach of the timber contracts, as it was fully
authorized by plaintiff. See Irwin v. United States, 104 Ct. Cl. 84, 110 (1945) (“no breach”
where actions “were authorized by the contract.”).
The court also rejects plaintiff’s claim that defendant breached the timber contracts by
delaying logging operations to permit the pike eradication project to proceed. Pew, of course,
received notice from the Forest Service, prior to bidding on the sales, warning it that a pike
eradication project was planned by the California Department of Fish and Game and that the
project could affect access to the timber sales area between July and October, 2007. That is what
happened – although the extent of the delay occasioned with that project is less than clear. What
is eminently clear is that there is not a shred of evidence that the Forest Service ever instructed
Pew to cease operations until the eradication program was completed. 8 One must assume, then,
7
Having explicitly agreed to this provision, plaintiff cannot, at the same time, contend
that it violated the implied covenants of good faith and fair dealing. A breach of that duty can
only be established by a showing that defendant “specifically designed to reappropriate the
benefits [that] the other party expected to obtain from the transaction, thereby abrogating the
government’s obligations under the contract.” Precision Pine & Timber, Inc. v. United States,
596 F.3d 817, 829 (Fed. Cir. 2010), cert. denied, 131 S. Ct. 997 (2011); see also Centex Corp.,
395 F.3d at 1304; Jay Cashman, Inc. v. United States, 88 Fed. Cl. 297, 308 (2009).
8
Plaintiff asserts that on September 17, 2007, the Forest Service “again required the
Pews to stop logging operations for the Lake Davis Pike Eradication.” In support of this claim, it
cites to Jared Pew’s deposition testimony. The cited pages of the transcript, however, do not
remotely support plaintiff’s claim. Accordingly, plaintiff has neither borne its burden of
establishing this fact nor even that of showing that a genuine issue of material fact exists thereon.
See RCFC 56(c)(1)(A); 56(e) (“If a party fails to properly support an assertion of fact . . . the
court may grant summary judgment . . . “); see also Anderson v. Liberty Lobby, Inc., 477 U.S.
242, 249-50 (1986) (“If the evidence [on which a party relies] is merely colorable . . . or is not
significantly probative summary judgment may be granted.”).
- 10 -
that if plaintiff ceased operations because of the eradication program, it did so at the behest or
instruction of the State of California. Defendant cannot be held liable for that conduct – and the
resulting unavailability of the site – unless government representatives are found to be at fault or
there is an express representation in the contracts that can be interpreted to insure an unqualified
warranty of accessibility. See United States v. Howard P. Foley Co., Inc., 329 U.S. 64, 66-67
(1946); Gilbane Bldg. Co. v. United States, 333 F. 2d 867, 869 (Ct. Cl. 1964); Ryco Const., Inc.
v. United States, 55 Fed. Cl. 184, 191-92 (2002). Neither has been shown here. Indeed, in terms
of accessibility, plaintiff was told quite to the contrary at least insofar as the pike eradication
project is concerned.
III.
CONCLUSION
Finding the remainder of plaintiff’s arguments likewise untenable, 9 the court GRANTS
defendant’s motion for summary judgment and DENIES plaintiff’s cross-motion for partial
summary judgment. The Clerk is hereby ordered to dismiss plaintiff’s complaint.
IT IS SO ORDERED.
s/ Francis M. Allegra
Francis M. Allegra
Judge
9
The court, for example, has considered and rejects plaintiff’s assertion that defendant
failed to provide it relief under contract provisions B8.33 and B3.33. A simple review of those
provisions makes clear that they did not deal with short-term delays of the sort alleged by
plaintiff. See Scott Timber Co. v. United States, 333 F.3d 1358, 1366-67 (Fed. Cir. 2003) (giving
effect to clause in timber contract that “expresses a clear purpose in clear language”).
- 11 -