SIMULATION TECHNOLOGY, LLC v. USA
Filing
13
PUBLISHED OPINION granting 9 Motion to Dismiss - Rule 12(b)(1). The Clerk is directed to enter judgment. Signed by Judge Edward J. Damich. (tb3) Copy to parties.
In the United States Court of Federal Claims
No. 11-408C
(Filed: January 25, 2012)
************************************
*
SIMULATION TECHNOLOGY, LLC, *
*
Plaintiff,
*
*
v.
*
*
THE UNITED STATES,
*
*
Defendant.
*
*
************************************
Contract Disputes Act;
41 U.S.C. §§ 7101-7109; motion to dismiss;
RCFC 12(b)(1); subject matter jurisdiction;
excusable delays; same operative fact;
Cerberonics
Edward R. Gay, Orlando, FL, for Plaintiff.
Russell J. Upton, Trial Attorney, Commercial Litigation Branch, Civil Division, United States
Department of Justice, Washington, DC, for Defendant.
___________________
OPINION
___________________
DAMICH, Judge:
This action involves a contract to build training simulation equipment for the United
States Air Force (“USAF”). Plaintiff Simulation Technology, LLC, has filed an appeal under the
Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101-7109, contesting the final decision of the
Contracting Officer (“CO”) to reduce the amount due under the contract from $93,000 to
$70,000 in consideration for Plaintiff’s belated delivery of the equipment. In its complaint,
Plaintiff alleges that it experienced excusable delays in the performance of critical activities, and
therefore, its delivery was not late and it is entitled to the full amount under the contract.
The Government has filed a Motion to Dismiss for lack of subject matter jurisdiction.
The Government alleges that the only claim Plaintiff made to the Contracting Officer was that
the Government agreed to modify the delivery schedule and waived its right to demand
consideration for the modification. The Government asserts that jurisdiction is improper because
Plaintiff never presented the excusable delays claim to the Contracting Officer for a final
decision, a prerequisite to this Court’s jurisdiction over the appeal.
Under the CDA, this Court has jurisdiction over a claim only if it is the same claim as
presented to the contracting officer. This standard does not require exact identity between the
claims, but only that they be sufficiently similar to give the contracting officer notice of the
amount of and basis for the claim. The Court finds that it does not have jurisdiction over
Plaintiff’s appeal because its claim that the Government agreed to waive consideration for late
delivery was insufficient to put the CO on notice of a claim that Plaintiff experienced excusable
delays. Accordingly, the Government’s Motion to Dismiss must be granted.
I.
Background
In September 2008, Plaintiff won a firm-fixed-price contract for $93,000 to build a High
Mobility Multi-Purpose Wheeled Vehicle (“HMMWV” or humvee) Egress Assistance Trainer
(“HEAT”). The HEAT is a humvee cab that is attached to a mechanical frame. The frame
rotates the humvee cab to simulate a rollover so that military personnel inside the cab can
practice escaping from an overturned vehicle. Def.’s Mot. Dismiss at 1. Under the contract,
Plaintiff was to deliver the HEAT on or about January 24, 2009.
According to its complaint, after being awarded the contract Plaintiff immediately
experienced problems that delayed its performance. Compl. ¶¶6-7. Plaintiff alleges that it was
expecting a humvee cab that was ready to insert into the simulation. Plaintiff asserts that the cab
the USAF provided was not ready to insert, but instead had significant amounts of equipment
attached to the cab and some interior damage. Compl. ¶7. On February 26, 2009, Plaintiff
advised USAF that the delivery schedule would need to be revised because it had been unable to
obtain certain parts and supplies. Compl. ¶8. On March 18, 2009, Plaintiff advised USAF that it
still was awaiting some parts. Compl. ¶9. Plaintiff and USAF continued to communicate in June
and July 2009. At that time, the USAF requested consideration for the delivery delay, but the
parties did not reach an agreement on what would be appropriate consideration. Compl. ¶10. On
September 1, 2009, a USAF representative visited Plaintiff’s facilities to see the progress of
construction. Compl. ¶11. On December 23, 2009, the HEAT was delivered to the USAF, 11
months after the delivery date specified in the contract.
In March 2010, the Contracting Officer requested a $23,000 reduction in price as
consideration for late delivery. Plaintiff rejected the offer, and on April 19, 2010, Plaintiff
submitted a claim for the full balance due on the contract. In its claim to the Contracting Officer,
Plaintiff asserted that the Government waived its right to consideration by agreeing to modify the
delivery schedule without requiring consideration. Final Decision at 5 (filed under Pl.’s Notice,
Sept. 21, 2011). It also asserted that the Government “waived any issues relating to delivery
delays” by “formally accepting delivery.” Id.
On June 21, 2010, the Contracting Officer issued her final decision on Plaintiff’s claim.
The CO found that the Government did not waive consideration because it requested and
discussed consideration with Plaintiff many times throughout the period of delay. Final Decision
at 6. She concluded that the Government was entitled to an equitable price reduction of $23,000,
which was equal to the costs incurred as a result of the delay.
2
On June 21, 2011, Plaintiff filed this complaint. Plaintiff alleges that it experienced
excusable delays in the performance of critical activities under the contract, and therefore, its
delivery of the HEAT complied with the contractual terms. Plaintiff claims it is entitled to the
full $93,000 under the contract.
The Government has filed a Motion to Dismiss under Rules 12(b)(1) and 12(h)(3) of the
Rules of the Court of Federal Claims (“RCFC”). The Government asserts that Plaintiff neither
explicitly asserted an excusable delays claim to the Contracting Officer nor impliedly asserted it
because Plaintiff did not present facts sufficient to establish an excusable delay claim. Because
an appeal of a contracting officer’s decision must arise from the same claim, the Government
argues that jurisdiction is improper.
II.
Discussion
A.
Standard of Review
A plaintiff bears the burden of establishing jurisdiction by a preponderance of the
evidence. See Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988)
(“[O]nce the [trial] court’s subject matter jurisdiction [is] put in question, it [is] incumbent upon
[the plaintiff] to come forward with evidence establishing the court’s jurisdiction”). When
deciding a motion to dismiss pursuant to RCFC 12(b)(1), the Court is “obligated to assume all
factual allegations to be true and to draw all reasonable inferences in [the] plaintiff’s favor.”
Henke v. United States, 60 F.3d 795, 797 (Fed. Cir. 1995); see Folden v. United States, 379 F.3d
1344, 1354 (Fed. Cir. 2004).
If subject matter jurisdiction is challenged, the plaintiff cannot rely merely on allegations
in the complaint, but must instead bring forth relevant, competent proof to establish jurisdiction.
See McNutt v. Gen. Motors. Acceptance Corp., 298 U.S. 178, 189 (1936); Reynolds, 846 F.2d at
747-48. When ruling on a motion to dismiss for lack of subject matter jurisdiction, a court may
consider evidence and resolve factual disputes over the jurisdictional facts. Reynolds, 846 F.2d
at 747; see also Rocovich v. United States, 933 F.2d 991, 994 (Fed. Cir. 1991); Int’l Mgmt.
Servs., Inc. v. United States, 80 Fed. Cl. 1, 2 n.2 (2007).
Plaintiff has filed the Contracting Officer’s final decision, and the Court considers the
decision in determining whether jurisdiction is proper.
B.
Jurisdiction over CDA Claims
Under the CDA, this Court has jurisdiction over appeals filed within 12 months of a
contracting officer’s final decision on a claim. § 7104(b). Jurisdiction is proper only if the
appeal is “‘based on the same claim previously presented to and denied by the contracting
officer.’” Scott Timber, Co. v. United States, 333 F.3d 1358, 1365 (Fed. Cir. 2003) (quoting
Cerberonics, Inc. v. United States, 13 Cl. Ct. 415, 417 (1987)). While a claim does not need to
follow a set form, the administrative claim must provide to the contracting officer adequate
notice of the basis for and amount of any claim made on appeal. M. Maropakis Carpentry, Inc.
v. United States, 609 F.3d 1323, 1328 (Fed. Cir. 2010); see Contract Cleaning Maint., Inc. v.
3
United States, 811 F.2d 586, 592 (Fed. Cir. 1987) (the claim must contain “a clear and
unequivocal statement that gives the contracting officer adequate notice of the basis and amount
of the claim”). However, if the complaint sets forth a new claim or a claim whose scope differs
from what was previously presented to the contracting officer, this Court will not have
jurisdiction over it. Santa Fe Eng’r v. United States, 818 F.2d 856, 859 (Fed. Cir. 1987); see
A.A.B. Joint Venture v. United States, 75 Fed. Cl. 414, 422-23 (2007).
When a contractor’s claim on appeal differs from the claim presented to the CO,
jurisdiction generally will be proper if the appeal is based on “the same set of operative facts
underlying the claim presented to the contracting officer.” Cerberonics, 13 Cl. Ct. at 417; see
Scott Timber, 333 F.3d at 1365. In determining whether two claims are the same, the “critical
test” is whether adjudication of the claim on appeal would “circumvent[] the statutory role of the
contracting officer to receive and pass judgment on the contractor’s entire claim.” Cerberonics,
13 Cl. Ct. at 417. While a plaintiff’s claim on appeal need not “rigid[ly] adhere[] to the exact
language or structure of the original administrative CDA claim,” Scott Timber, 333 F.3d at 1365,
the administrative claim must have been “sufficiently specific as to apprise [the contracting
officer] of the basis and amount of [the] claim” made on appeal, A.A.B. Joint Venture, 75 Fed.
Cl. at 422.
When a plaintiff makes two claims that request the same relief based on the occurrence of
the same events, courts typically have found that the claims are the same. In Scott Timber, the
Federal Circuit upheld the finding of the Court of Federal Claims (“CFC”) that it had
jurisdiction. In the administrative claim, the plaintiff had asserted that it was entitled to
consequential damages because the government suspended plaintiff’s contract for a prolonged
period. The plaintiff alleged that the unauthorized suspension breached several clauses of the
contract. In its appeal to the CFC, the plaintiff again sought consequential damages for the
prolonged suspension, but it asserted that the suspension breached different clauses of the
contract. The Federal Circuit found that the contracting officer was on notice that the plaintiff
was asserting the prolonged suspension was a breach of contract and was seeking consequential
damages for the breach. Even though the plaintiff “may have posed slightly different legal
theories for the breach, [] [the plaintiff’s] claim is essentially the same as presented to the
[contracting officer].” Scott, 333 F.3d at 1365-66.
Similarly, in Thermocor v. United States, 75 Fed. Cl. 480, 489 (1996), the plaintiff
submitted a claim to the contracting officer for an equitable adjustment based on work done in
excess of the contract, basing its claim on the Variance in Estimated Quantity clause. Plaintiff
later filed a claim requesting the same equitable adjustment based instead on the Changes clause,
under the cardinal change rule. Id. Although the legal theory was different, the CFC found that
jurisdiction was proper because Plaintiff requested the same equitable adjustment based on the
same operative facts. Id. at 489-90.
In contrast, when two claims request different relief and are based on the occurrence of
different events, courts have been less generous in finding that the two claims are the same. In
A.A.B. Joint Venture, this Court found that the plaintiff was asserting a new claim when the
plaintiff asserted the government’s response to a request for information (“RFI”) resulted in a
constructive change to the contract. 75 Fed. Cl. at 422-23. In its original claim, the plaintiff had
4
asserted that the contract contained two contradictory requirements, one that permitted the
contractor to choose a quality control method and another that required it to use a specific, more
expensive method. The plaintiff requested compensation for being required to use the more
expensive method, and the claim set forth an accounting of the associated costs. The original
claim did not mention the RFI nor the costs associated with the constructive change. The Court
found that “no statement was presented to the contracting officer that was sufficiently specific as
to apprise him of the basis and amount of a claim based on an alleged constructive change
arising from the government’s response to [the RFI].” Id. at 422. The Court found that it lacked
jurisdiction over that claim because the two claims differed in both the factual basis and the
proof required. Id. at 423.
C.
Plaintiff’s Administrative Claim Did Not Give the CO Notice of the Basis of
Its Claim on Appeal: Excusable Delays
Here, the Court must determine whether the operative facts of a claim for contract
modification due to excusable delay were before the Contracting Officer. If the facts before the
Contracting Officer were sufficient to give her notice that Plaintiff would request the full amount
under the contract because excusable delays permitted modification of the contractual delivery
schedule, the Court will have jurisdiction over Plaintiff’s appeal. To prove that it experienced
excusable delays, Plaintiff will need to establish that the delay was beyond its control and that it
was without fault or negligence. Plaintiff will need to present evidence showing the cause of the
delay, the duration of the delay, and its efforts to modify or overcome the delay. See Sauer Inc.
v. Danzig, 224 F.3d 1340, 1345 (Fed. Cir. 2000); see, e.g., 48 C.F.R. § (FAR) 52.212-4.
The Government asserts jurisdiction is improper because the facts presented to the CO
were insufficient to support an excusable delay claim. Because the relevant facts were not before
the CO, the CO was not on notice of the excusable delays claim and did not have an opportunity
to render a decision on it. Therefore, the Government asserts that the excusable delays claim did
not arise out of the same operative facts as Plaintiff’s administrative claim.
Plaintiff admits that it did not use the term “excusable delays,” but it asserts that it
brought the relevant issues regarding delays before the CO. Plaintiff cites to Scott Timber for the
proposition that its claim on appeal need not “‘rigid[ly] adhere[] to the exact language or
structure of the original administrative CDA claim.’” Pl.’s Br. at 2 (quoting Scott Timber, 333
F.3d at 1365). Plaintiff contends that it has satisfied the requirements of the CDA.
A comparison of Plaintiff’s two claims shows that the CO was not on notice of the
excusable delays claim. In its administrative claim, Plaintiff asserted that when a contractor fails
to make timely delivery, the contracting officer has discretion to terminate the contract or to
allow the contractor to continue performance under a new delivery schedule. Final Decision at
5-6. Plaintiff asserted that the Contracting Officer was aware of the delays and agreed to new
delivery dates without requiring consideration for the changes. Id. at 2-3, 5. Plaintiff claimed
that, even though the USAF did not require consideration, Plaintiff provided consideration in the
form of out of scope changes. Id. at 5. Those out of scope changes included, inter alia,
modification of the HEAT’s design and additional labor on the humvee cab because, according
to Plaintiff, the humvee cab the USAF delivered was not compliant with the contractual terms.
5
Id. at 4. Finally, it asserted that the Government waived any issues relating to delivery dates by
accepting final delivery of perfect tender. Id. at 5.
In her final decision, the Contracting Officer found that the issue of consideration for the
delays first was raised in February 2009, and that the Government requested and discussed
consideration with Plaintiff many times throughout the period of delay. Final Decision at 6. The
Contracting Officer found that though Plaintiff made several offers of consideration, the
Government did not accept any of them and informed Plaintiff they were insufficient
compensation for expenses incurred due to the delinquency. Id. at 6-7. The CO concluded that
the late delivery issue never was waived and that the Government was entitled to an equitable
price reduction as consideration for the delay. Id. at 7.
This case presents a close question of whether the two claims are the same. A claim on
appeal may diverge from the administrative claim without precluding jurisdiction, but only if the
facts and allegations contained in the administrative claim were sufficient to give the contracting
officer an opportunity to consider and rule on the claim made on appeal. When the
administrative claim focuses on one theory of relief and does not allege facts sufficient to satisfy
any of the elements of the theory of relief asserted on appeal, it is unlikely that the appeal has
arisen from the same operative facts. Such is the case here.
Plaintiff’s original claim narrowly focused on whether the Government agreed to accept
the late delivery and whether that acceptance extinguished any claim for consideration. The
claim focused on Plaintiff’s communications with the CO regarding the duration of the delays
and also on the parties’ agreement regarding a modified delivery date. Although Plaintiff’s
administrative claim referenced Plaintiff’s belief that the humvee cab was defective and resulted
in additional costs to Plaintiff, Plaintiff did not assert that the cab was responsible for the delay.
The administrative claim did not contain allegations that would have put the CO on notice of an
excusable delay—Plaintiff did not present evidence showing the duration of the uncontrollable
delays, assert that its late delivery was solely attributable to the uncontrollable delays, or present
facts showing that it tried to overcome the delays. See Sauer, 224 F.3d at 1345. In these
circumstances, the Court cannot find that the CO had notice of the excusable delays claim.
To be sure, Plaintiff is correct that the claims need not be identical and that its
administrative claim sets forth several facts relevant to its excusable delays claim. The test for
jurisdiction is not, however, merely whether the two claims have some overlapping facts. The
test for jurisdiction is whether the claims are based on the same operative facts, thereby giving
the contracting officer notice of the claim and an opportunity to render a decision on it. Here,
Plaintiff may have alleged that it experienced some delays beyond its control, but the focus of its
claim was that the CO agreed to modify the delivery schedule. The claim contained no statement
that would have alerted the CO to consider whether Plaintiff’s delinquency was excusable
because all the delays experienced were beyond Plaintiff’s control. Were this Court to hear
Plaintiff’s claim, it would allow the Plaintiff to circumvent the CO’s statutory role in resolving
disputes by depriving the CO of the opportunity to render a decision on the excusable delays
claim in the first instance.
6
III.
Conclusion
For the reasons set forth above, the Government’s Motion to Dismiss for lack of subject
matter jurisdiction is GRANTED. The Clerk is directed to dismiss the Plaintiff’s complaint.
s/ Edward J. Damich
EDWARD J. DAMICH
Judge
7
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?