CROMAN CORPORATION v. USA
Filing
72
PUBLISHED OPINION and ORDER. The Court DENIES 33 plaintiff's motion for judgment on the administrative record; DENIES 43 defendant's motion to dismiss on grounds of mootness and lack of standing; DENIES 60 defendant's motion to strike; and GRANTS 43 defendant's and 41 defendant-intervenor Siller's cross-motions for judgment on the administrative record. Signed by Judge George W. Miller. (ps) Copy to parties.
In the United States Court of Federal Claims
BID PROTEST
No. 12-75C
(Filed Under Seal: August 17, 2012)
(Reissued for Publication: August 29, 2012)*
TO BE PUBLISHED
CROMAN CORPORATION,
Plaintiff,
v.
THE UNITED STATES,
Defendant,
and
MOUNTAIN WEST HELICOPTERS,
LLC,
and
COLUMBIA HELICOPTERS, INC.,
and
SILLER HELICOPTERS, INC.,
Defendant-Intervenors.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Forest Service solicitation to acquire
helicopters for use in fighting forest fires;
protests by plaintiff and other offerors at
GAO; Forest Service proposes corrective
action; plaintiff’s bid protest action seeks
to challenge corrective action; ripeness;
standing; mootness; evaluation of
proposals; FAR 15.305(a); rating methods
neither irrational nor contrary to law;
plaintiff fails to show prejudice due to
alleged errors in best-value tradeoff
determinations.
Alan I. Saltman, Stephen J. Kelleher, Smith, Currie & Hancock LLP, Washington, D.C.,
for plaintiff.
*
This Opinion and Order was originally filed under seal on August 17, 2012 (docket entry 69)
pursuant to the protective order entered on March 2, 2012 (docket entry 18). The parties were
given an opportunity to advise the Court of their views with respect to what information, if any,
should be redacted under the terms of the protective order. The parties filed a Joint Status Report
with proposed redactions on August 23, 2012 (docket entry 71). The Court has reviewed the
parties’ proposed redactions and concluded that they should be accepted. Accordingly, the Court
is reissuing its Opinion and Order dated August 17, 2012, with redactions indicated by three
consecutive asterisks within brackets ([***]).
Russell J. Upton, Trial Attorney, Scott D. Austin, Assistant Director, Jeanne E. Davidson,
Director, Commercial Litigation Branch, Stuart F. Delery, Acting Assistant Attorney General,
Civil Division, United States Department of Justice, Washington, D.C., for defendant. Elin M.
Dugan, Senior Counsel, Office of the General Counsel, United States Department of Agriculture,
Washington, D.C., of counsel.
Barry N. Johnson, Bennett Tueller Johnson & Deere, Salt Lake City, Utah, for defendantintervenor Mountain West Helicopters, LLC.
Robert K. Stewart, Jr., Davis Wright Tremaine LLP, Anchorage, Alaska, for defendantintervenor Columbia Helicopters, Inc.
V. Blair Shahbazian, Murphy Austin Adams Schoenfeld LLP, Sacramento, Cal., for
defendant-intervenor Siller Helicopters, Inc.
OPINION AND ORDER
GEORGE W. MILLER, Judge
Plaintiff Croman Corporation (“Croman”) filed a complaint against the United States
alleging that the U.S. Forest Service’s (“Forest Service”) evaluations of proposals in response to
a solicitation for helicopters for its exclusive use in fighting forest fires and its best-value
tradeoff determinations were irrational and contrary to law. For the reasons set forth below, the
Court DENIES plaintiff’s motion for judgment on the administrative record; DENIES
defendant’s motion to dismiss on grounds of mootness and lack of standing; DENIES
defendant’s motion to strike attachment 1 to plaintiff’s response brief and related portions of
plaintiff’s response brief; and GRANTS defendant’s and defendant-intervenor Siller Helicopters,
Inc.’s (“Siller”) cross-motions for judgment on the administrative record.1
1
See Pl.’s Mot. for J. on Administrative R. (“Pl.’s Mot.”) (docket entry 33, Apr. 27, 2012); Pl.’s
Supplemental Br. to Pl.’s Mot. on Administrative R. in Wake of Agency’s Resolicitation of
Cancelled Line Items 21, 22, 27, & 34 (“Pl.’s Supplemental Br.”) (docket entry 38, May 18,
2012); Def.-Intervenor Siller’s Opp’n to Croman’s Mot. for J. on Administrative R. & CrossMot. for J. on Administrative R. (“Def.-Intervenor Siller’s Mot. & Opp’n”) (docket entry 41,
June 6, 2012); Def.’s Mot. to Dismiss for Lack of Subject Matter Jurisdiction, Opp’n to Pl.’s
Mot. for J. upon Administrative R., & Cross-Mot. for J. upon Administrative R. (“Def.’s Mots. &
Opp’n”) (docket entry 43, June 6, 2012); Def.’s Reply to Pl.’s Resp. to Def.’s Mot. to Dismiss
for Lack of Subject Matter Jurisdiction & Cross-Mot. for J. upon Administrative R. & Def.’s
Mot. to Strike (“Def.’s Reply & Mot.”) (docket entry 60, July 3, 2012).
2
I.
Background
A.
Solicitation
In February 2011, the Forest Service issued an amended solicitation, RFP AG-024B-S11-9001 (“RFP 11-9001”), for helicopters for its exclusive use in fighting forest fires. See AR
Tab 7, at 46, 120. The Forest Service sought contracts at a fixed price with an economic price
adjustment not to exceed one base year and three one-year option periods. AR Tab 7, at 46. The
Forest Service indicated “[t]he performance requirements are a minimum and the helicopter[s]
will be evaluated for overall best value considering price and other factors.” Id. The Forest
Service stated that it “may award a single contract or multiple awards based on the outcome of
the evaluation process” and that it “reserves the right to award any combination of items and/or
number of items.” Id.
The solicitation called for 34 helicopters to be operated from host bases during
mandatory availability periods. AR Tab 7, at 47–114. Contract line item numbers (“CLIN”) 1 to
15 required helicopters with heavy-lift capabilities—helicopters that had the “capability of
hovering out of ground effect (HOGE) at 8,000 feet pressure altitude and 25 °Celsius with . . .
jettisonable payload of 5000 pounds.”2 AR Tab 7, at 117 (original capitalization and bold
omitted). In other words, for CLINs 1 to 15, the Forest Service sought helicopters that could
carry at least 5,000 pounds of water or retardant at 8,000 feet pressure altitude and 25 degrees
Celsius. CLINs 16 to 34 required helicopters with medium-lift capabilities—helicopters that had
the “capability of . . . [HOGE] at 7,000 feet pressure altitude and 20 °Celsius with . . .
jettisonable payload of 3300 pounds.” Id. (original capitalization and bold omitted). By
definition, a helicopter that had heavy-lift capabilities had medium-lift capabilities, but not vice
versa. The solicitation explained how the jettisonable payload would be determined. See AR
Tab 7, at 117, 211–12, 249.
The offerors were permitted to propose multiple helicopters for each CLIN and permitted
to propose the same aircraft for multiple CLINs. However, only one aircraft would be selected
for each CLIN, and the same aircraft could not be selected for multiple CLINs.
The solicitation indicated that the government would award contracts to the responsible
offerors on the basis of price and five technical factors. The technical factors were (1)
mandatory documentation, (2) aircraft performance, (3) safety/risk management (“safety/risk”),
(4) past performance, and (5) organizational experience. AR Tab 7, at 280. The non-price
factors, when combined, were “significantly more important” than price. Id. The mandatory
documentation factor was evaluated on a pass/fail basis. Id. If the proposal received a pass for
the mandatory documentation factor, the government would next determine whether the aircraft
performance was “acceptable (pass) or unacceptable (fail).” Id. Proposals that passed would
2
The solicitation defined “HOGE” as the “[m]aximum pressure altitude and temperature [at]
which a helicopter can hover (at maximum gross weight) without the effects of ground cushion
per the Flight Manual/Supplements and [Supplemental Type Certificate] performance charts.”
AR Tab 7, at 175. HOGE is not an issue in this protest.
3
“next receive qualitative evaluations for Aircraft Performance and for each of the remaining
three technical evaluation factors.” Id.
To determine the total price, the government would add (1) the price for the base year, (2)
the prices for the option periods, and (3) the flight rate multiplied by the estimated flight hours.
Id. The price proposals would be evaluated “to determine reasonableness and to determine the
demonstrated understanding of the level of effort needed to successfully perform the services.”
Id. The price proposals would also be evaluated using a “Best Value” formula set forth in the
solicitation. Id. “The ‘Best Value’ formula computes the amount it would cost to transport a
pound of product for the specific helicopter being offered” and would “be used to make trade-off
determinations to measure aircraft efficiencies of make and models of helicopters offered.” AR
Tab 7, at 275. Because offerors would be permitted to propose the same aircraft for multiple
CLINs, an aircraft’s total price and price per pound could differ depending on the CLIN for
which it was being offered. Similarly, because offerors would be permitted to propose multiple
helicopters for the same CLIN, a price proposal’s total price and price per pound for a CLIN
could differ based on the specific aircraft.
The technical factors were listed in the solicitation in order from most important to least
important: mandatory documentation, aircraft performance, safety/risk, past performance, and
organizational experience. AR Tab 7, at 280. If a technical factor had subfactors, the subfactors
were equal in importance. Id. The mandatory documentation factor listed twelve categories of
required documents. For the aircraft performance factor, the offerors were informed that a
proposed aircraft would be evaluated based on “Helicopter Load Calculation.” AR Tab 7, at
281. In short, the aircraft performance factor was concerned with how many pounds of water or
retardant an aircraft could carry. For the safety/risk factor, the offerors were informed that their
proposals would be evaluated based on (i) accident history (last 5 years)—(1) annual average
flight hours, (2) number of aircraft accidents and number of incidents, and (3) insurance carrier
verification letter—and (ii) safety management systems—(1) policy, (2) safety assurance, (3)
safety promotion, and (4) risk management. Id. The past performance factor would be evaluated
based on the following subfactors: (i) “capable, efficient, and effective”; (ii) “performance
conforms to the terms and conditions of [past] contracts”; (iii) “reasonable and cooperative
during [past] performance”; and (iv) “committed to customer satisfaction.” Id. The
organizational experience factor would be evaluated for (i) “[m]anagement [p]ersonnel
commensurate with size and complexity of operation, (ii) “[p]ilot(s) in [c]ommand,” and (iii)
“[m]aintenance [p]ersonnel.” AR Tab 7, at 281–82.
Offerors were informed that the awards would “be made to those offerors whose
proposals are technically acceptable and whose technical/price relationships are the most
advantageous to the Government.” AR Tab 7, at 282. The solicitation provided that “the
critical factor in making any price/technical trade-off is not the spread between the technical
scores, but, rather, the significance of that difference.” Id. The solicitation further provided:
The significance of the spread of scores will be determined on the basis of what
the difference might mean in terms of performance and what it would cost the
Government to take advantage of it. Award may not necessarily be made for
technical capabilities that would appear to exceed those needed for successful
4
performance of the work. The Government reserves the right to make
price/technical trade-offs that are in the best interest and advantageous to the
Government. The Government may reject any or all offers if such action is
determined to be in the best interest of the Government.
Id.
B.
Source Selection Plan
The Source Selection Plan (“SSP”) provided that the Technical Evaluation Team
(“TET”) was to “assign to each evaluation criterion a final adjective consensus.” AR Tab 3, at
24. The SSP defined the adjectival ratings of exceptional, acceptable, neutral, marginal, and
unacceptable. See AR Tab 3, at 24–25.
C.
Plaintiff’s Proposal
Eighteen small businesses, including plaintiff, submitted proposals in response to the
solicitation, proposing a total of 58 helicopters for the 34 CLINs. AR Tab 29, at 13393; see also
AR Tab 13 (plaintiff’s proposal). In its proposal submitted in March 2011, plaintiff offered 3 of
its helicopters (N611CK, N612CK, and N613CK) on all 34 CLINs and 2 helicopters (N1043T
and N1048Y) on CLINs 16 to 34. See Pl.’s Mot. for J. on Administrative R. (“Pl.’s Mot.”) 3–4
(docket entry 33, Apr. 27, 2012). In May 2011, the agency informed plaintiff that helicopters
N611CK, N612CK, and N613CK would not be evaluated for CLINs 1 to 15 because they did not
meet the minimum payload requirement. Id. at 4. Plaintiff withdrew helicopter N1048Y from
consideration because it became committed to other work. Id. Thus, this protest pertains to
plaintiff’s helicopters N611CK, N612CK, N613CK, and N1043T proposed for CLINs 16 to 34.
Id.
D.
Technical and Price Evaluations, Cancellation of 4 CLINs, Best-Value Tradeoff
Determinations, and 30 Awards
In March 2011, “the TET addressed issues with the proposals, identified proposal
clarifications, and documented concerns leading to discussions with the Offerors.” AR Tab 29,
at 13393. In May 2011, “discussions were conducted with all Offerors and after reevaluation of
the proposals and after further clarifications, technical negotiations were concluded” in June
2011. Id.; see also AR Tab 28.
All proposals passed the mandatory documentation factor. See AR Tab 29, at 13407. For
the aircraft performance factor, the proposals received a different numerical rating for each
proposed aircraft with respect to each CLIN for which the aircraft was proposed. See AR Tab
29, at 13395, 13405, 13407, 13414–15. A computer Optimization Model (“OM”), AR Tab 29, at
13413, calculated a numerical rating of 1 to 5 (1 being the best) carried out to multiple decimals
(e.g., 4.5745) for the aircraft performance factor. The numerical rating was based on both the
number of pounds by which the aircraft exceeded the minimum payload requirement of the
CLIN for which the aircraft was being evaluated and the number of pounds by which the other
helicopters proposed for the same CLIN by other offerors exceeded the minimum payload
requirement. Because the rating was based in part on the other helicopters proposed by other
5
offerors, the numerical rating allowed the agency to compare the proposed helicopters. The
calculation of the numerical rating was based on a formula created by the TET. See AR Tab 29,
at 13414–15.
It is not necessary to list plaintiff’s numerical ratings for each aircraft for each CLIN that
is relevant to this protest. The fact that is relevant is plaintiff (along with other offerors)
proposed helicopters that only exceeded the minimum payload requirement of 3,300 pounds for
CLINs 16 to 34 by hundreds of pounds, whereas some other offerors proposed helicopters that
exceeded the minimum payload requirement by thousands of pounds. See generally AR Tab 29,
at 13423–34 (rows 260–906, column S). As will become evident below in the discussion of the
best-value tradeoff determinations, an offeror proposing an aircraft that did not exceed a
minimum payload requirement by many pounds could still be awarded the CLIN, although it was
more difficult because the aircraft performance factor was the most important technical factor
that was qualitatively evaluated.
For the safety/risk factor, the TET assigned proposals an adjectival rating of exceptional,
acceptable, marginal, or unacceptable. See AR Tab 29, at 13395, 13397, 13405–07, 13413–15.
In this procurement, numerical ratings were used to “represent[] the unique differences within
the adjectival rating.” AR Tab 29, at 13397. To arrive at the adjectival and numerical ratings for
this factor, the TET’s lead safety officer assigned an adjectival rating and corresponding whole
number of exceptional-1, acceptable-2, marginal-4, and unacceptable-5 to the subfactors and
then averaged the ratings for the subfactors. The averaging of subfactor whole number
numerical ratings meant that a proposal could receive a numerical rating for the factor carried out
to multiple decimals.
Plaintiff’s proposal, along with every other proposal, received an exceptional rating for
the safety/risk factor. AR Tab 29, at 13396. All sixteen of the proposals either received a 1.0 or
1.8 numerical rating. Plaintiff’s proposal, as well as six other proposals, received a 1.8. See AR
Tab 29, at 13397.
The past performance factor was evaluated using the same adjectival and numerical
rating method that was used for the safety/risk factor, although the adjectival neutral and
numerical 3 ratings were also used for this factor. See AR Tab 29, at 13395, 13397, 13405–07,
13413–16. Proposals were assigned numerical ratings carried out to multiple decimals (e.g.,
1.4375). The TET arrived at its adjectival and numerical ratings for this factor by using the
evaluations of four expert groups (maintenance, operations, pilots, and safety). Each expert
group conducted its own evaluation. The group assigned an adjectival rating and corresponding
whole number of 1 to 5 to each of the subfactors and then averaged the subfactor ratings to arrive
at adjectival and numerical ratings for the factor. Once each expert group had assigned
adjectival and numerical ratings to the past performance factor, the four expert groups’ adjectival
and numerical ratings were averaged to arrive at the TET’s adjectival and numerical ratings for
the past performance factor.
Plaintiff’s proposal received exceptional and 1.4375 ratings for the past performance
factor. Three of the other fifteen proposals received numerical ratings better than plaintiff’s for
the past performance factor. AR Tab 29, at 13396–97.
6
The last technical factor, organizational experience, was evaluated using the same
adjectival and numerical rating method that was used for the safety/risk factor. Like the past
performance factor, the TET relied on the evaluations of four expert groups. See AR Tab 29, at
13395, 13397, 13405–07, 13413–16. Like the past performance factor, proposals were assigned
numerical ratings carried out to multiple decimals. Plaintiff received exceptional and 1.75
ratings. Five of the other fifteen proposals received better numerical ratings. See AR Tab 29, at
13397.
After requesting and analyzing proposed price revisions in August 2011, the agency
concluded that “a number of the aircraft proposed were higher than anticipated,” AR Tab 29, at
13393, and thus requested a second round of price revisions. The analyses of those were
completed in September 2011. Plaintiff did not revise its price proposal in response to either
request. Pl.’s Mot. 5; see AR Tab 13, at 5156, 5160.
Following a briefing by the TET on price in October 2011, the Forest Service
management recommended that the TET “[r]eview the pricing for aircraft that were priced
higher than other similarly performing aircraft.” AR Tab 29, at 13393. As a result of this
recommendation, the TET eliminated two helicopters of the same model proposed by [***] “due
to higher pricing compared to other similar performing aircraft and cost more than the Agency
was willing to pay.” Id. The management also recommended, due to budget concerns and based
on previous analysis, that “an optimum number of aircraft was determined to be thirty (30),” id.,
causing the TET to eliminate 4 CLINs from CLINs 16 to 34, which were chosen based on
“staffing and location requirements.” Id.; see also AR Tab 29, at 13405, 13408–09, 13413.
Plaintiff’s lowest total price for the CLINs related to this protest—CLINs 17, 23, 28, 29,
30, 32, and 33—was approximately [***]. See, e.g., AR Tab 29, at 13430 (row 647, column N).
Plaintiff’s lowest price per pound for an aircraft proposed for CLINs 17, 23, 28, 29, 30, 32, and
33 was [***]. See, e.g., id. (row 650, column O).
The TET Evaluation stated, “The proposed prices were evaluated after the technical
proposal evaluations were completed to determine price reasonableness and each offerors [sic]
level of understanding of effort needed to successfully perform the contract services.” AR Tab
29, at 13407. “The price evaluations included total overall price reasonableness, the best value
formula and cost per pound delivered for each helicopter . . . .” Id.; see also AR Tab 29, at
13397–98.
The TET then used the Optimization Model to assist it in recommending an aircraft for
each CLIN that represented the best value. AR Tab 29, at 13394–98, 13407, 13409, 13413–18.
The OM “is a goal programming solver,” which means that it “simultaneously minimize[s]
weighted deviations from pre-specified goals.” AR Tab 67, at 16042. “It accomplishes this by
solving the optimization problem, exploring all possible assignment sets, and searching for the
assignment set where improvements can no longer be made (e.g., until total deviations can’t be
reduced anymore).” Id. A detailed description of the OM’s calculations can be found in
Administrative Record Tab 29, at 13413 to 13418, and Administrative Record Tab 67, at 16040
to 16045. See also Def.’s Mot. to Dismiss for Lack of Subject Matter Jurisdiction, Opp’n to Pl.’s
Mot. for J. upon Administrative R., & Cross-Mot. for J. upon Administrative R. (“Def.’s Mots. &
7
Opp’n”) 14 (“The Forest Service developed the OM in order to more efficiently review and
evaluate what previously had required the TET to manually review more than 250 spreadsheets
(more than 1000 pages in all) and required an enormous amount of time and resources.”) (docket
entry 43, June 6, 2012).
In selecting the proposal that represented the best value for a CLIN, the OM considered
the “overall technical rating,” total price, and price per pound. The overall technical rating was
the average of the numerical ratings for the aircraft performance, safety/risk, past performance,
and organizational experience factors at the following weights selected by the TET: [***]
percent for the aircraft performance factor, [***] percent for the safety/risk factor, [***] percent
for the past performance factor, and [***] percent for the organizational experience factor (which
reflected the descending level of importance of these factors per the solicitation).3 The OM
“priorit[zed]” or “emphas[ized],” AR Tab 29, at 13414, the overall technical rating, total price,
and price per pound at the following weights set by the TET: [***] percent for the overall
technical rating, [***] percent for the total price, and [***] percent for the price per pound
(which reflected that the non-price factors, when combined, were significantly more important
than price per the solicitation).
The TET evaluated the OM’s results before making its recommendations to the
contracting officer (“CO”). The TET Evaluation stated, “The TET evaluated the aircraft
placement at the different bases by using professional judgement, historical knowledge of needs
and offerors [sic] capability and verified that [the selections] represented overall best value.” AR
Tab 29, at 13409. After reviewing all the data, the TET chair “consider[ed] the outputs and
determine[d] if the[y] [were] the correct Locations, Type, Model, appropriate costs that the
agency is willing to accept and other factors not represented in the OM.” Id.
The TET Evaluation further stated that “[i]t is important to understand that the OM is a
tool that assists with technical and cost outputs but there must be a human influence for the
overall evaluation and recommendations to be complete.” Id. The TET did not follow the OM
selections in two ways. First, the TET exchanged the helicopters selected for CLINs 6 and 15
because the OM had placed an aircraft “that was at a higher cost with less capability into a longer
[mandatory availability period CLIN].” Id. Second, an offeror with a total fleet of four that
would have been awarded four CLINs was only recommended for award of three CLINs “in
order to position the offeror for better support to the agency and enable them to be successful if
there were unforeseen problems.” Id.
During the evaluation process, in addition to the two helicopters proposed by Erickson
that were eliminated from consideration based on price, nine helicopters were withdrawn by four
offerors. AR Tab 29, at 13398, 13408. When withdrawing their helicopters, two offerors
withdrew their entire proposals. Ultimately, 47 helicopters from 16 small businesses were
available for awards of 30 CLINs.
3
Plaintiff’s overall technical ratings for the helicopters proposed for CLINs 16 to 34 ranged from
[***] to [***]. AR Tab 29, at 13397.
8
The TET recommended awards to 11 of the 16 remaining offerors. AR Tab 29, at 13399.
Plaintiff was not recommended for an award. Id. Defendant-intervenor Siller was recommended
for award of 3 CLINs, including CLIN 23, which is relevant to this protest. Non-party Firehawk
Helicopters, Inc. (“Firehawk”) was recommended for award of CLINs 17, 28, and 33, all of
which are subject to this protest. Defendant-intervenor Columbia Helicopters, Inc. (“Columbia”)
was recommended for award of 4 CLINs, including CLINs 29 and 30, which also are subject to
this protest. Non-party HeliQwest International (“HeliQwest”) was recommended for 2 CLINs,
one of which, CLIN 32, pertains to this protest.4
The CO requested and received source selection authority. AR Tab 29, at 13392–402.
Successful and unsuccessful offerors were notified by letter in December 2011. See AR Tabs
34–35. Plaintiff requested and received a debriefing. See AR Tab 38.
E.
Protests at the Government Accountability Office
Plaintiff and two other unsuccessful offerors filed protests at the Government
Accountability Office (“GAO”) in December 2011 and January 2012. See AR Tabs 42–43, 49.
Plaintiff claimed that (1) plaintiff’s technical proposal was not properly evaluated and, as a
result, the agency failed to perceive that plaintiff’s proposal was “significantly superior” to the
awardees’ proposals for CLINs 16 to 34 (except the cancelled CLINs) and should have been
awarded 4 of those CLINs; (2) any significance in the technical advantage perceived by the
agency for CLINs 17, 23, 28, 29, 30, 31 and 33 was insignificant because of the cost to take
advantage of it; (3) the award of CLIN 23 to defendant-intervenor Siller was improper because
“it was beyond the scope of competition reasonably contemplated based on the wording of the
solicitation and, resulted in the Forest Service’s acquisition of technical capabilities that greatly
exceeded those needed for the successful performance of the work . . . (and at an increased cost
of some [***])”; (4) the agency improperly cancelled part of the solicitation; and (5) the agency
failed to request a new round of best and final offers upon cancelling part of the solicitation. AR
Tab 43, at 14527–28.
The agency filed a motion to dismiss all three protests in January 2012, see AR Tab 50,
to which the three protestors responded. See AR Tabs 51–53. GAO submitted requests for
clarifications to plaintiff, another protestor, and the agency, to which each responded. See AR
Tabs 54–58. In January 2012, GAO dismissed plaintiff’s protest after deciding that plaintiff’s
first claim was an untimely challenge to the terms of the solicitation and plaintiff’s other claims
lacked merit. See AR Tab 59. GAO dismissed the other protests as academic in early February
2012 after the agency proposed corrective action in late January 2012 in response to those
protests. See AR Tabs 60–61. The agency’s proposed corrective action did not address the
issues raised in plaintiff’s protest.
4
As discussed below, the agency later implemented corrective action in response to protests at
the Government Accountability Office. See infra Part I.E–F. Defendant-intervenor Columbia
was awarded CLIN 32 as a result of the corrective action.
9
F.
Corrective Action
The Forest Service agreed to reevaluate three of the five technical factors of
all proposals: safety/risk, past performance, and organizational experience. AR Tab 67, at
15992; see also AR Tab 67, at 16006. The mandatory documentation and aircraft performance
factors were not reevaluated because, according to the Forest Service, “both were initially
sufficiently evaluated.” AR Tab 67, at 15992; see also AR Tab 67, at 16012. Because the
awards for CLINs 1 to 15 had not been protested, the reevaluations pertained only to CLINs 16
to 34. AR Tab 67, at 15992.
“The TET Chair reconvened a group . . . . [and the safety/risk, past performance, and
organizational experience factors] were reevaluated from each Offeror’s proposal, and the initial
ratings were either confirmed or revised as determined by the outcome of the reevaluations.” AR
Tab 67, at 16012. The evaluation of the safety/risk factor was “refined to allow the TET to
account for each vendor’s number of accidents and to reflect the differences between Offerors.”
AR Tab 67, at 16014; see also AR Tab 67, at 15996. The TET’s lead safety officer reevaluated
the proposals and the TET chair “concur[red] with the ratings assigned to each vendor.” AR Tab
67, at 16018. Plaintiff’s proposal was assigned an adjectival rating of exceptional, and its
numerical rating was [***], an improvement from its initial [***] numerical rating. AR Tab 67,
at 15997–98, 16011–16. The TET Reevaluation “narrative” attached to the Revised Request for
Source Selection Authority noted that plaintiff had one accident with a five year average of
20,000 flight hours per year and that plaintiff had a safety management system program. AR
Tab 67, at 16019.
The past performance factor was also reevaluated.5 “The CO and the TET Chair found
issues on four of the individual rating forms, which were revised and re-rated . . . .” AR Tab 67,
at 16022. Plaintiff received the same adjectival and numerical ratings that it received on the
initial evaluation: [***] and [***]. AR Tab 67, at 15997–98, 16011, 16024–25. The TET
Reevaluation narrative stated that plaintiff “[h]as been acceptable for past contracts” for
subfactor “[c]apable, [e]fficient and [e]ffective”; “[h]as been acceptable for conformance on past
contracts” for subfactor “[p]erformance conformed to terms and conditions of contracts”; “[h]as
been very reasonable and cooperative on past contracts” for subfactor “[r]easonable and
cooperative during performance”; and “[h]as been exceptionally committed to customer
satisfaction on past contracts” for subfactor “[c]ommitted to customer satisfaction.” AR Tab 67,
at 16024–25.
5
Defendant states that the expert-group approach used in the initial evaluation of the past
performance and organizational experience factors was not used on reevaluation. See Def.’s
Mots. & Opp’n 10 n.6; Def.’s Reply & Mot. 28–29. Even if the expert-group approach was not
used in the reevaluation, as plaintiff points out, the reevaluation resulted in the same numerical
rating, “down to the fourth decimal,” Pl.’s Resp. to Def.’s Mot. to Dismiss for Lack of Subject
Matter Jurisdiction, Opp’n to Pl.’s Mot. for J. upon Administrative R., & Cross-Mot. for J. upon
Administrative R. (“Pl.’s Resp.”) 37 (docket entry 54, June 20, 2012), in most of the numerical
ratings. See also id. at 37 n.36 (explaining the few instances in which the past performance
numerical ratings changed based on the reevaluation).
10
The organizational experience factor was also reevaluated. “The Technical Chair and
Contracting Officer reviewed the initial Technical Evaluation forms used by the Technical
Evaluation Team. The CO and Chair found no issues and therefore no changes were made to
this factor.” AR Tab 67, at 16029. Plaintiff received [***] and [***] ratings. AR Tab 67, at
15997–98. For the subfactors, the TET Reevaluation narrative stated that plaintiff proposed
acceptable management personnel, acceptable pilots in command, and above acceptable “A &
P’s.”6 AR Tab 67, at 16031.
Following the reevaluation of three of the technical factors, the numerical ratings were rerun through the OM with respect to CLINs 16 to 34, resulting in six changes. “For four of the
line items, the recommended vendor stayed the same, but the OM recommended a different
aircraft. For line items 31 and 32, the OM swapped aircraft, putting HeliQwest aircraft in the
spot previously awarded to Columbia and vice versa.” AR Tab 67, at 16012; see also AR Tab
67, at 16006, 16008. In a document explaining the OM that was attached to the Revised
Request for Source Selection Authority, the agency stated:
Note that the OM performs these calculations and assignments
simultaneously. Therefore, documentation of the tradeoff performed for each
separate line item (for example, “what tradeoff was made in order to justify the
award of CLIN 16 to X instead of Y?”) is not possible.
The best we can do to demonstrate the tradeoffs at individual line items
that were considered by the OM is to compare the set of assignments from the
weighted OM solution to single objective solutions: the lowest adjectival score,
the lowest total cost and the lowest price per pound. Attachment 7 provides a
comparison between the weighted OM solution for line items 16-34 and the OM
assignments when 100 percent of the weight is applied to each of the three single
objectives.
AR Tab 67, at 16044; see also AR Tab 67, at 16210.
The TET Reevaluation stated, “After fully evaluating the outputs and confirming
appropriateness, we have concluded that the recommendations should be awarded, as modeled,
without necessitating any human element changes. The OM has in effect identified the optimum
configuration of helicopters, the best make/model and provided the most reasonable price for the
agency . . . .” AR Tab 67, at 16034–35.
The Source Selection Authority (“SSA”) agreed with the recommendations made by the
CO. In the Source Selection Certification, the SSA stated:
Each of the 15 awards reflects the best overall value to the Government,
considering that our intent was to emphasize technical superiority (especially
payload capacity) over low price. The importance of technical superiority is
6
“A & P’s” appears to refer to a Federal Aviation Administration certificate for maintenance
personnel—“Airframe & Powerplant.” See AR Tab 13, at 4665.
11
shown in the assignment of a weight of [***] percent to those factors, as
compared with the [***] percent assigned to price factors. The Optimization
Model used those weights to perform tradeoffs reflecting the greater importance
of technical ratings. I have reviewed the model’s results and confirm that they
represent best value and prioritized aircraft performance over price, while still
taking price into account.
AR Tab 68, at 16213.
In March 2012, the agency sent letters to successful and unsuccessful offerors regarding
the result of the corrective action. See AR Tabs 69–70. Plaintiff did not receive an award.
Plaintiff requested and received a debriefing. See AR Tab 72.
G.
Recent Solicitation for Four Helicopters
In May 2012, over three months after this bid protest was filed, the agency issued a
solicitation, RFP AG-024B-S-12-9025 (“RFP 12-9025”). See Pl.’s Mot. to Supplement
Administrative R. attach. (docket entry 37, May 18, 2012). Plaintiff asserts that the latest
solicitation seeks “the exact same services and equipment that were the subject of the partial
cancellation of RFP-9001.” Pl.’s Supplemental Br. to Pl.’s Mot. in Wake of Agency’s
Resolicitation of Cancelled Line Items 21, 22, 27, & 34 (“Pl.’s Supplemental Br.”) 2 (docket
entry 38, May 18, 2012). However, defendant notes that the solicitations were issued “one year
apart and for performance at different locations, during different time periods.” Def.’s Opp’n to
Pl.’s Mot. to Supplement Administrative R. 10 (docket entry 40, June 4, 2012). Plaintiff
submitted a proposal in response to the latest solicitation, but it received notice in June 2012 that
it did not receive an award. See Pl.’s Resp. to Def.’s Mot. to Dismiss for Lack of Subject Matter
Jurisdiction, Opp’n to Pl.’s Mot. for J. upon Administrative R., & Cross-Mot. for J. upon
Administrative R. (“Pl.’s Resp.”) attach. 1 (docket entry 54, June 20, 2012).
H.
Instant Action
Plaintiff filed this bid protest in early February 2012, a few days after the corrective
action was proposed and approximately one month before the corrective action was completed.
See Compl. (docket entry 1, Feb. 3, 2012). Plaintiff’s complaint alleged claims similar to the
claims it alleged before GAO, although it also alleged that the Forest Service’s proposed
corrective action would not cure the alleged errors.
The Court granted defendant-intervenors Mountain West Helicopters, LLC’s (“Mountain
West”), Columbia’s, and Siller’s motions to intervene (docket entry 16, Mar. 2, 2012; docket
entry 21, Mar. 22, 2012).7 The Court held status conferences on February 6 and 13, 2012; on
March 2, 16, and 22, 2012; and on May 16, 2012.
7
As plaintiff did not protest CLINs awarded to defendant-intervenor Mountain West, defendantintervenor Mountain West did not participate in the briefing on the merits. Its counsel was
present by phone at the July 16, 2012 oral argument, but did not participate. Defendantintervenor Columbia filed an “Opposition to Plaintiff’s Motion for Judgment on the
Administrative Record” (docket entry 44, June 6, 2012) and a “Reply to Plaintiff’s Motion for
12
Plaintiff filed its motion for judgment on the administrative record in late April 2012,
which was after the agency completed its corrective action in March 2012 and plaintiff was again
not awarded any CLINs. Plaintiff did not file a new bid protest or supplemental pleadings after
the corrective action was completed.
In plaintiff’s motion for judgment on the administrative record, supplemental brief in
support of its motion, and response brief, plaintiff appears to have modified its claims from what
it alleged at GAO and in its complaint before the Court in light of the fact that the corrective
action had been completed and the administrative record had been filed. In sum, plaintiff now
claims (1) the rating methods used to evaluate the aircraft performance, safety/risk, past
performance, and organizational experience factors were irrational or contrary to law; (2) the
agency failed to sufficiently document strengths and weaknesses of the proposals; (3) the agency
improperly failed to eliminate defendant-intervenor Siller’s proposal in response to CLIN 23
based on price; (4) the agency’s best-value tradeoff determinations were irrational or contrary to
law; and (5) the agency’s decision to partially cancel the solicitation was irrational and based on
pretext. Plaintiff’s claims pertain solely to CLINs 17, 23, 28, 29, 30, 32, and 33—which were
awarded to defendant-intervenor Siller, defendant-intervenor Columbia, and non-party Firehawk
after the corrective action—and to CLINs 21, 22, 27, and 34, which were cancelled. Notably,
plaintiff alleges that many of the errors allegedly committed by the agency in the initial
evaluations and initial best-value tradeoff determinations were repeated during the corrective
action. Plaintiff contended in its complaint that this would happen when the agency proposed the
corrective action.
Defendant filed a motion to dismiss for lack of jurisdiction arguing that plaintiff’s bid
protest is moot and that plaintiff lacks standing to assert its claims. Defendant also filed a crossmotion for judgment on the administrative record. Defendant-intervenor Siller filed a crossmotion for judgment on the administrative record. The Court heard oral argument on the parties’
motions on July 16, 2012.
II.
Discussion
A.
Plaintiff’s Protest of the Agency’s Corrective Action Is Within the Court’s Bid
Protest Jurisdiction and Is Ripe for Review
Pursuant to the Tucker Act, as amended by the Administrative Dispute Resolution Act of
1996, this court has exercised jurisdiction to hear bid protests in three circumstances:
Judgment on the Administrative Record” (docket entry 57, July 3, 2012). Defendant-intervenor
Siller filed an “Opposition to Croman Corporation’s Motion for Judgment on the Administrative
Record and Cross-Motion for Judgment on the Administrative Record” and a “Reply in
Opposition to Croman Corporation’s Motion for Judgment on the Administrative Record and in
Support of Its Cross-Motion for Judgment on the Administrative Record” (docket entry 58,
July 3, 2012). Counsel for defendant-intervenors Columbia and Siller participated by phone in
the July 16, 2012 oral argument.
13
(1) a pre-award protest, which is an objection to “a solicitation by a Federal
agency for bids or proposals for a proposed contract or to a proposed award . . . of
a contract”; (2) a post-award protest, which objects to “the award of a contract”;
or (3) a protest objecting to “any alleged violation of statute or regulation in
connection with a procurement or a proposed procurement.”
Magnum Opus Techs., Inc. v. United States, 94 Fed. Cl. 512, 527 (2010) (alteration in original)
(citations omitted) (quoting 28 U.S.C. § 1491(b)(1)). “The jurisdictional grant in 28 U.S.C.
§ 1491(b)(1) applies to the entire procurement process.” Sys. Application & Techs., Inc. v.
United States, 100 Fed. Cl. 687, 705 (2011). The Federal Circuit has broadly interpreted
“procurement” to encompass the period from the agency’s determination that it requires
contracted goods or services through final contract award and completion. Distributed Solutions,
Inc. v. United States, 539 F.3d 1340, 1345 (Fed. Cir. 2008).
Here, defendant argues that plaintiff’s protest is moot:
As Croman’s complaint was filed over a month before the corrective
action was completed, logically Croman could only have been challenging the
December 16, 2011 award decisions. But the corrective action by definition
replaced the December 2011 award decisions. The corrective action was an
intervening event. As such, Croman’s complaint is challenging award decisions
that no longer exist.
Although this Court possesses jurisdiction to review corrective action
decisions, see, e.g., The Centech Group, Inc. v. United States, 78 Fed. Cl. 496,
506 (2007), Croman has yet to protest the corrective action.
Def.’s Mots. & Opp’n 23–24; see also Def.’s Reply to Pl.’s Resp. to Def.’s Mot. to Dismiss for
Lack of Subject Matter Jurisdiction & Cross-Mot. for J. upon Administrative R. & Def.’s Mot. to
Strike (“Def.’s Reply & Mot.”) 3–7 (docket entry 60, July 3, 2012).
The mootness doctrine is one of several justiciability doctrines originating from the “case
or controversy” requirement of Article III of the Constitution.8 “A case is moot when the issues
presented are no longer ‘live’ or the parties lack a legally cognizable interest in the outcome.”
NEC Corp. v. United States, 151 F.3d 1361, 1369 (Fed. Cir. 1998) (quoting Powell v.
McCormack, 395 U.S. 486, 496 (1969)) (internal quotations marks omitted). Under the Supreme
Court’s two-part test, a case is moot if “(1) it can be said with assurance that ‘there is no
reasonable expectation . . .’ that the alleged violation will recur and (2) interim relief or events
have completely and irrevocably eradicated the effects of the alleged violation.” Cnty. of L.A. v.
8
The Court of Federal Claims is established under Article I of the Constitution, 28 U.S.C.
§ 171(a), and is not bound by the “case or controversy” requirement of Article III. Zevalkink v.
Brown, 102 F.3d 1236, 1243 (Fed. Cir. 1996). This court has, however, applied the Article III
justiciability doctrines for prudential reasons. See Anderson v. United States, 344 F.3d 1343,
1350 n.1 (Fed. Cir. 2003).
14
Davis, 440 U.S. 625, 633 (1979) (alteration in original) (citations omitted) (quoting United States
v. W. T. Grant Co., 345 U.S. 629, 633 (1953)).
The Court agrees with defendant that the protest as it relates to the original awards is
moot. See Eskridge Research Corp. v. United States, 92 Fed. Cl. 88, 93–94 (2010). However,
the Court disagrees with defendant that the entirety of plaintiff’s protest is moot. Plaintiff filed a
complaint challenging more than just the initial evaluations and initial best-value tradeoff
determinations. Plaintiff also challenged the agency’s corrective action as being insufficient to
cure the alleged errors committed by the agency in the initial evaluations and initial best-value
tradeoff determinations.9 See Compl. ¶¶ 6, 58, 65, 79–80, 97, 104. Plaintiff’s objection to the
corrective action, which was completed approximately one month after the protest was filed and
approximately one month before briefing on the merits began, is not moot. Accordingly, the
Court DENIES defendant’s motion to dismiss for lack of jurisdiction on grounds of mootness.
Plaintiff’s contention that the corrective action was inadequate to address the alleged
errors falls within this court’s bid protest jurisdiction and is ripe10 for review despite the fact that
plaintiff filed this bid protest approximately one month before the corrective action was
completed. Cf. McTech Corp. v. United States, No. 12-122C, 2012 WL 2878157, at *6 (Fed. Cl.
July 10, 2012) (“[T]he court has juridical power to entertain a complaint challenging proposed
corrective action, and [the plaintiff] has stated a potentially viable challenge to the scope of the
[agency’s] corrective action in the amended complaint.” (citations omitted)); Jacobs Tech. Inc. v.
United States, 100 Fed. Cl. 179, 182 (2011) (“Although there is a possibility that [the plaintiff]
may be awarded the contract as a result of the reprocurement, this fact does not make [the
plaintiff]’s claim unripe. . . . [T]his is a pre-award bid protest in which [the plaintiff] is alleging
flaws in the reprocurement process. The reprocurement process is virtually complete. There is
no indication that the flaws [the plaintiff] complains of will be recognized and remedied by the
agency.”); Eskridge Research Corp., 92 Fed. Cl. at 94–95 (holding that claims “regarding
speculative and potential improprieties in the re-evaluation process” were not ripe, but noting
9
The Forest Service’s corrective action did not address plaintiff’s objections at GAO because
GAO dismissed plaintiff’s first claim as untimely and the remaining claims on the merits. The
corrective action only attempted to address the objections raised by the other two protestors at
GAO.
10
The doctrine of ripeness “prevent[s] the courts, through avoidance of premature adjudication,
from entangling themselves in abstract disagreements over administrative policies, and also to
protect the agencies from judicial interference until an administrative decision has been
formalized and its effects felt in a concrete way by the challenging parties.” Abbott Labs. v.
Gardner, 387 U.S. 136, 148–49 (1967), abrogated on other grounds by Califano v. Sanders, 430
U.S. 99 (1977). A two-part test determines whether a claim is ripe for judicial action:
(1) “whether the issues are fit for judicial decision—that is, whether there is a present case or
controversy between the parties” and (2) “whether there is sufficient risk of suffering immediate
hardship to warrant prompt adjudication—that is, whether withholding judicial decision would
work undue hardship on the parties.” Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573, 1580–81
(Fed. Cir. 1993). The first part of the test requires that the “agency action is final.” Tokyo Kikai
Seisakusho, Ltd. v. United States, 529 F.3d 1352, 1362 (Fed. Cir. 2008).
15
that the plaintiff had not “pled any facts to suggest that [the agency was] not properly performing
the technical re-evaluation”); Textron, Inc. v. United States, 74 Fed. Cl. 277, 288–89 (2006);
ManTech Telecomms. & Info. Sys. Corp. v. United States, 49 Fed. Cl. 57, 65 n.13 (2001), aff’d,
30 F. App’x 995 (Fed. Cir. 2002) (per curiam).11
B.
Plaintiff Has Standing to Assert Claims Relating to CLINs 17, 23, 28, 29, 30, 32,
and 33
To establish standing, plaintiff must show that it is an “actual or prospective bidder[] or
offeror[] whose direct economic interest would be affected by the award of the contract or by
failure to award the contract.”12 Info. Tech. & Applications Corp. v. United States, 316 F.3d
1312, 1319 (Fed. Cir. 2003) (alterations in original) (quoting Am. Fed’n of Gov’t Emps. v. United
States, 258 F.3d 1294, 1302 (Fed. Cir. 2001)). A showing of “direct economic interest” requires
the plaintiff to demonstrate that “any alleged errors caused prejudice.” Global Computer Enters.,
Inc. v. United States, 88 Fed. Cl. 350, 401 (2009). “In post-award bid protests, the court ‘looks
twice at prejudice, first weighing prejudice as it pertains to standing, and then more thoroughly
weighing prejudice to determine whether plaintiff shall be afforded relief.’” Magnum Opus
Techs., Inc., 94 Fed. Cl. at 530 (quoting A & D Fire Prot. Inc. v. United States, 72 Fed. Cl. 126,
131 n.4 (2006)). “[I]n a post-award bid protest, before reaching the merits of the parties’ dispute,
the court conducts only a ‘limited review’ of the plaintiff’s allegations and the administrative
record for the ‘minimum requisite evidence necessary for plaintiff to demonstrate prejudice and
therefore standing.’” Id. at 530 n.12 (quoting Night Vision Corp. v. United States, 68 Fed. Cl.
368, 392 & n.23 (2005)). “This threshold determination of standing should ‘require [ ] only that
a protestor be (1) either a bidder or proposer that has been prevented from bidding or proposing
due to some infraction other than the terms of the solicitation itself; or (2) either a bidder or
proposer who would be in contention absent the unreasonable procurement decision or violation
of applicable procurement regulations.’” Id. (alteration in original) (quoting Textron, Inc., 74
Fed. Cl. at 285). “The second, more searching prejudice inquiry relating to the merits requires
assessing whether the plaintiff has established a ‘substantial chance’ it would have received the
contract after ‘review of the contract award or bid evaluation process to determine what might
have occurred if the government had not erred.’” Id. at 530 (citations omitted) (quoting Rex
Serv. Corp. v. United States, 448 F.3d 1305, 1308 (Fed. Cir. 2006); Weeks Marine, Inc. v. United
States, 79 Fed. Cl. 22, 35 (2007), aff’d in relevant part, 575 F.3d 1352 (Fed. Cir. 2009)).
11
Defendant essentially argues that plaintiff should have waited until the corrective action was
completed and then filed a new bid protest or supplemental pleadings. Although the Court finds
that plaintiff need not have done so, the Court notes that a court may sometimes look to
supplemental pleadings to determine whether jurisdiction exists. See Ford Motor Co. v. United
States, No. 2011-1134, 2012 WL 3241005, at *5 (Fed. Cir. Aug. 10, 2012) (“Consistent with
Rockwell International [v. United States, 549 U.S. 457 (2007)], this court has not hesitated to
consider post-complaint developments when the case warrants.”).
12
“The standing issue in this case is framed by 28 U.S.C. § 1491(b)(1), which [the Federal
Circuit] ha[s] found imposes more stringent standing requirements than Article III.” Weeks
Marine, Inc. v. United States, 575 F.3d 1352, 1359 (Fed. Cir. 2009).
16
Here, defendant and defendant-intervenor Siller argue that plaintiff lacks standing to
assert claims relating to CLINs 17, 23, 28, 29, 30, 32, and 33. They primarily rely on plaintiff’s
failure to meaningfully compare its proposal to the other proposals also not selected for the
contested CLINs. See Def.’s Mots. & Opp’n 26–28; Def.-Intervenor Siller’s Opp’n to Croman’s
Mot. for J. on Administrative R. & Cross-Mot. for J. on Administrative R. (“Def.-Intervenor
Siller’s Mot. & Opp’n”) 9–10, 18 (docket entry 41, June 6, 2012); see also Def.’s Reply & Mot.
7–10; Def.-Intervenor Siller’s Reply in Opp’n to Croman’s Mot. for J. on Administrative R. & in
Supp. of Its Cross-Mot. for J. on Administrative R. (“Def.-Intervenor Siller’s Reply”) 2–4
(docket entry 58, July 3, 2012).
Based on the Court’s review of plaintiff’s allegations and the administrative record, the
Court is persuaded that plaintiff has made a sufficient showing of prejudice to have standing to
assert all of its claims relating to CLINs 17, 23, 28, 29, 30, 32, and 33. Plaintiff would have been
in contention absent the alleged unreasonable procurement decisions and violations of applicable
procurement regulations. The Court is persuaded by the fact that plaintiff proposed relatively
low total prices for its helicopters; plaintiff’s proposal received exceptional ratings for the
safety/risk, past performance, and organizational experience factors; plaintiff’s helicopters met
the minimum payload requirement for all the contested CLINs; and plaintiff has alleged
numerous errors in the evaluations and best-value tradeoff determinations.13 See Pl.’s Mot. 6, 13
& n.19, 14 & n.20, 18, 33–36; Pl.’s Resp. 9. Accordingly, the Court DENIES defendant’s
motion to dismiss plaintiff’s protest for lack of standing.14 See, e.g., GTA Containers, Inc. v.
United States, 103 Fed. Cl. 194, 201 (2012).
C.
Defendant’s Motion to Dismiss Plaintiff’s Challenge to the Recent Solicitation for
Four Helicopters, RFP 12-9025, for Lack of Standing Is Moot Because Plaintiff’s
Counsel Stated at Oral Argument that Plaintiff Does Not Challenge RFP 12-9025
In its supplemental brief, plaintiff points to RFP 12-9025 as evidence that the
cancellation of the four CLINs in RFP 11-9001—the solicitation at issue—was improper. See
Pl.’s Supplemental Br. 2. Plaintiff seeks in that brief to enjoin RFP 12-9025. Id. at 5. However,
plaintiff has not protested RFP 12-9025, a point plaintiff’s counsel made clear at oral argument.
See Hr’g Tr. at 13:21–22, Croman Corp. v. United States, No. 12-75C (Fed. Cl. July 16, 2012)
(hereinafter “July 16, 2012 Hr’g Tr.”) (“[W]e’re not challenging the later solicitation at all.”)
(docket entry 68, Aug. 10, 2012). Accordingly, the Court DENIES on grounds of mootness
defendant’s motion to dismiss for lack of standing with respect to RFP 12-9025. See Def.’s
Mots. & Opp’n 28.
13
The Court rejects defendant’s argument that plaintiff failed to sufficiently address standing in
its opening brief and thus waived the issue. See Def.’s Mots. & Opp’n 26.
14
However, as discussed infra in examining the merits, for some of plaintiff’s allegations, the
Court finds that plaintiff has not established it had a substantial chance to secure a contract
absent the alleged errors. See USfalcon, Inc. v. United States, 92 Fed. Cl. 436, 450 (2010)
(“[E]ven though the question of prejudice involves the same test and a factual analysis in both
contexts, the answers might differ due to the procedural posture.”); see also Linc Gov’t Servs.,
LLC v. United States, 96 Fed. Cl. 672, 697–99 (2010).
17
D.
The Court Rejects Defendant’s Argument that Plaintiff Waived or Abandoned Its
Claims
In Blue & Gold Fleet, L.P. v. United States, the Federal Circuit recognized “a waiver rule
against parties challenging the terms of a government solicitation.” 492 F.3d 1308, 1314 (Fed.
Cir. 2007). Here, defendant argues that plaintiff has waived its claims regarding CLINs 17, 23,
28, 29, 30, 32, and 33 because the solicitation disclosed that performance requirements were a
minimum and that technical factors, when combined, were significantly more important than
price. Def.’s Mots. & Opp’n 29–32; Def.’s Reply & Mot. 10–12.
The Court rejects this argument because, as will become apparent below, plaintiff’s
objections are not to the terms of the solicitation, but to the agency’s evaluations and best-value
tradeoff determinations. See Pl.’s Resp. 9–12.
Defendant also argues that plaintiff has abandoned its challenge to the cancellation of
CLINs 21, 22, 27, and 34 because it did not sufficiently address this claim in plaintiff’s
supplemental brief in support of its motion for judgment on the administrative record. See Def.’s
Mots. & Opp’n 32–34; Def.’s Reply & Mot. 13–15. The Court rejects this argument because, as
is evident in plaintiff’s supplemental brief in support of its motion for judgment on the
administrative record, plaintiff continues to challenge the Forest Service’s decision to cancel four
CLINs. See Pl.’s Supplemental Br. 2–3.
E.
Standard for Review of Bid Protests
In a bid protest action, the court will set aside agency action if it is “arbitrary, capricious,
an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); see 28
U.S.C. § 1491(b)(4); Banknote Corp. of Am. Inc. v. United States, 365 F.3d 1345, 1350 (Fed. Cir.
2004). The protestor will succeed when “(1) the procurement official’s decision lacked a
rational basis; or (2) the procurement procedure involved a violation of regulation or procedure.”
Banknote Corp. of Am., 365 F.3d at 1351 (quoting Impresa Construzioni Geom. Domenico
Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001)) (internal quotation marks
omitted). The protestor must show that the agency failed to provide a “coherent and reasonable
explanation of its exercise of discretion” or that there was a “clear and prejudicial violation of
applicable statutes or regulations.” Id. (quoting Impresa Construzioni Geom. Domenico Garufi,
238 F.3d at 1332–33) (internal quotation marks omitted).
The protestor’s burden becomes more difficult as the degree of discretion vested in the
contracting officer becomes greater. DynCorp Int’l LLC v. United States, 76 Fed. Cl. 528, 537
(2007). Negotiated procurements afford the contracting officer a “breadth of discretion”; “best
value” awards afford the contracting officer additional discretion. Id. Therefore, in a negotiated,
best-value procurement, the “protestor’s burden is especially heavy.” Id.
The disappointed offeror bears the burden to demonstrate an error sufficient to warrant
relief. Maint. Eng’rs v. United States, 50 Fed. Cl. 399, 413 (2001). Establishing prejudice at the
merits stage requires proving “that there was a substantial chance [the protestor] would have
received the contract award but for this error.” Alfa Laval Separation, Inc. v. United States, 175
F.3d 1365, 1367 (Fed. Cir. 1999) (quoting Statistica, Inc. v. Christopher, 102 F.3d 1577, 1582
18
(Fed. Cir. 1996)) (internal quotation marks omitted). De minimis errors in the procurement
process do not justify relief. Grumman Data Sys. Corp. v. Dalton, 88 F.3d 990, 1000 (Fed. Cir.
1996). But “multiple errors might cumulatively establish prejudice.” USfalcon, Inc. v. United
States, 92 Fed. Cl. 436, 450 (2010). “Prejudice is a question of fact.” Bannum, Inc. v. United
States, 404 F.3d 1346, 1353 (Fed. Cir. 2005) (citing Advanced Data Concepts, Inc. v. United
States, 216 F.3d 1054, 1057 (Fed. Cir. 2000)). “In a multiple-award contract, prejudice analysis
must take into account the impact of the error on all the awards, including whether the correction
of an error ‘might not only improve the protester’s evaluation, but diminish that of a current
awardee, or even eliminate that awardee from further consideration altogether.’” Afghan Am.
Army Servs. Corp. v. United States, 90 Fed. Cl. 341, 367 (2009) (quoting Serco Inc. v. United
States, 81 Fed. Cl. 463, 501 (2008)).
In reviewing cross-motions for judgment on the administrative record, the court must
determine “whether, given all the disputed and undisputed facts, a party has met its burden of proof
based on the evidence in the record.” A & D Fire Prot., 72 Fed. Cl. at 131. In a manner “akin to an
expedited trial on ‘the paper record,’” the court will make findings of fact where necessary. CHE
Consulting, Inc. v. United States, 78 Fed. Cl. 380, 387 (2007) (quoting A & D Fire Prot., 72 Fed. Cl.
at 131).
F.
Plaintiff’s Claims Regarding the Agency’s Evaluation of Proposals Are
Unavailing
“Evaluations may be conducted using any rating method or combination of methods,
including color or adjectival ratings, numerical weights, and ordinal rankings.” FAR 15.305(a).
“The rating method need not be disclosed in the solicitation.” FAR 15.304(d). Regardless of the
method used to evaluate proposals, evaluations must document the “relative strengths,
deficiencies, significant weaknesses, and risks” of the evaluated proposals. FAR 15.305(a).
When tradeoffs are performed, FAR requires that the source selection record include “[a]n
assessment of each offeror’s ability to accomplish the technical requirements” and “[a] summary,
matrix, or quantitative ranking, along with appropriate supporting narrative, of each technical
proposal using the evaluation factors.” FAR 15.305(a)(3).
1.
Plaintiff Has Not Demonstrated that the Rating Methods for the
Safety/Risk, Past Performance, and Organizational Experience Factors
Were Irrational or Contrary to Law
At bottom, plaintiff challenges the averaging of whole numbers to arrive at numerical
ratings carried out to multiple decimals because plaintiff claims this process led to numerical
ratings that were “falsely precise.” Pl.’s Mot. 26–33; Pl.’s Resp. 32–40. The Court finds that,
although the agency’s rating method may lead to false precision in some cases, see, e.g., Serco,
81 Fed. Cl. at 488, plaintiff has failed to demonstrate that the rating method the agency used
caused false precision in this case. Plaintiff has not shown that its proposal deserved a better
numerical rating for any of these three factors. Plaintiff also has not shown that the other
proposals deserved different numerical ratings from what they received. In short, plaintiff has
failed to demonstrate that the numerical ratings for these three factors did not accurately reflect
the actual differences in the proposals. See Dismas Charities, Inc. v. United States, 61 Fed. Cl.
191, 205 (2004) (“While the methodology used by [the agency] may be, at first glance, a bit
19
confusing to some, it is not irrational. [The plaintiff] has not met its burden of showing that the
evaluation of the proposals did not accurately reflect the actual differences in the proposals.”
(internal quotation marks omitted)).
Plaintiff’s allegation that the adjectival ratings were undefined is simply incorrect, see
Pl.’s Mot. 26–27, a fact that plaintiff appears to acknowledge in its response brief. See Pl.’s
Resp. 20, 22, 32 nn.28–29. The SSP defined the adjectival ratings. See AR Tab 3, at 24–25.
Additionally, plaintiff notes in passing that the TET Reevaluation narrative uses the term “Above
Acceptable,” but does not define this term. See Pl.’s Resp. 21 n.13. However, even plaintiff
concedes that all of the ratings were not required to be defined. See Pl.’s Mot. 28 n.40.
Lastly, the Court rejects plaintiff’s arguments in its response brief that amount to attempts
to turn an arguable lack of clarity in the administrative record as to how the factors were rated
into claims that the rating method was improper. See Pl.’s Resp. 38–40. For example, parts of
the administrative record describing what occurred in the evaluations and reevaluations suggest
that the OM assigned the numerical ratings for the safety/risk, past performance, and
organizational experience factors, despite the fact that it is clear from elsewhere in the
administrative record that the OM only assigned the numerical ratings for the overall technical
rating and aircraft performance factor based on formulae the agency created. The administrative
record shows that the TET assigned the adjectival and numerical ratings for safety/risk, past
performance, and organizational expert factors, and these numerical ratings were then entered
into the OM. The Court rejects plaintiff’s argument that it was improper for the TET to assign
numerical ratings in addition to assigning adjectival ratings.
2.
Plaintiff’s Claims Regarding the Rating Method for the Aircraft
Performance Factor Are Unavailing
Plaintiff argues that the numerical ratings carried out to multiple decimals for the aircraft
performance factor created a false sense of precision. Pl.’s Resp. 32–40. However, plaintiff has
not demonstrated that there was any false precision in this case.
For the first time in its response brief,15 plaintiff notes that the aircraft performance factor
was not assigned an adjectival rating by the TET. Pl.’s Resp. 34. The OM only assigned a
numerical rating for each aircraft proposed for each CLIN based on the number of pounds by
which the aircraft exceeded the minimum payload requirement and based on the capabilities of
the other helicopters proposed for the CLIN. Plaintiff argues that it was inconsistent with the
SSP not to assign an adjectival rating. However, plaintiff has not demonstrated that it was
prejudiced by the failure of the agency to do so. See CACI Field Servs., Inc. v. United States,
854 F.2d 464, 466 (Fed. Cir. 1988) (“[The plaintiff] chooses not to dispute the [trial] court’s
clear finding on lack of prejudice: ‘[The plaintiff] . . . failed to demonstrate that it was prejudiced
by any of the differences in relative importance between the RFP evaluation factors and the SSP
15
Because the Court rejects plaintiff’s arguments on the merits, the Court need not decide
whether plaintiff waived its claims regarding the evaluation of the aircraft performance factor
that were not raised until plaintiff’s response brief, as argued by defendant. See Def.’s Reply &
Mot. 23.
20
[Source Selection Plan] evaluation factors.’ That finding is supported by record evidence . . . .”
(fourth and fifth alterations in original) (quoting CACI Field Servs., Inc. v. United States, 13 Cl.
Ct. 718, 729 (1987)); see also USfalcon, 92 Fed. Cl. at 453 (discussing relationship between SSP
and evaluation method ultimately employed).
For the first time in its response brief, plaintiff also argues that the rating method for
evaluating the aircraft performance factor was improper because keys on charts containing the
proposals’ ratings indicated that numerical ratings of 3.1 to 5 for the aircraft performance factor
corresponded to adjectival ratings of marginal or unacceptable. See Pl.’s Resp. 33–34 (citing AR
Tab 3, at 24; AR Tab 67, at 15995–97, 16011, 16013, 16016, 16041, 16051). However,
defendant explains:
[T]he Forest Service simply spread the Aircraft Performance numerical ratings
over a 5-point scale instead of concentrating them within a 2-point scale, which
would have eliminated the application of “Marginal” and “Unacceptable”
descriptors to helicopters that met performance requirements. If the Forest
Service had scored Aircraft Performance on scale of 1-2.9, then it still would have
to differentiate between the helicopters’ performance capabilities in order to
qualitatively evaluate the Aircraft Performance factor, which the 2011 RFP
required. AR 280. For example, a helicopter that received the worst Aircraft
Performance rating on a 1-5 scale (5.0) still would receive the worst Aircraft
Performance rating on a 1-2.9 scale (2.9); only the number would change, not the
helicopter’s rating relative to the competition.
. . . . Here, the use of a more condensed scale for the Aircraft Performance factor
would not have improved Croman’s placement in that scale. Croman does not
argue that it would have, nor does it specify any way in which Croman,
specifically, was harmed by use of an improper scale.
Def.’s Reply & Mot. 26. The Court agrees with defendant’s assessment of the effect of this
alleged error. See also Seaborn Health Care, Inc. v. United States, 101 Fed. Cl. 42, 52 (2011)
(holding “that [the plaintiff] did not suffer any prejudice from the information provided in the
solicitation or from the weights actually used in the evaluation of proposals”).
3.
Plaintiff Has Not Demonstrated that It Was Prejudiced by the Agency’s
Alleged Failure to Sufficiently Document Strengths and Weaknesses or
that the Administrative Record Is Inadequate for Effective Judicial Review
Plaintiff has repeatedly argued that the administrative record is lacking in sufficient
documentation of strengths and weaknesses. See, e.g., Pl.’s Mot. 22, 24 n.16, 26; Pl.’s Resp. 15
n.7, 16 n.9, 18–22, 24 n.16, 40 n.38. The administrative record shows plaintiff’s total prices,
prices per pound, and adjectival and numerical ratings for technical factors and subfactors, as
well as the TET Reevaluation narrative. Plaintiff has not shown that it was prejudiced, even if
the agency fell short of what is required by FAR, or that the record is inadequate for effective
judicial review.
21
4.
The Agency Need Not Have Eliminated Defendant-Intervenor Siller’s
Proposal from Consideration for CLIN 23 Based on Price
The RFP stated that price proposals would be evaluated “to determine reasonableness and
to determine the demonstrated understanding of the level of effort needed to successfully
perform the services.” AR Tab 7, at 280. Price proposals were also to be evaluated using the
“Best Value” formula, which calculated the price per pound. Id.; see also FAR 15.404-1(a)(1)
(“The contracting officer is responsible for evaluating the reasonableness of the offered prices.”);
FAR 15.404-1(b)(2) (“The Government may use various price analysis techniques and
procedures to ensure a fair and reasonable price. Examples of such techniques include, but are
not limited to, the following: . . . Comparison of proposed prices received in response to the
solicitation. Normally, adequate price competition establishes a fair and reasonable price.”); AR
Tab 3, at 12 (“It is anticipated that adequate competition will result in reasonable prices. Past
acquisitions and market research indicated there are more than enough potential Offerors to
allow for adequate competition.”).
In the Revised Request for Source Selection Authority, the CO stated, “Overall price
reasonableness was determined based on comparison of two pricing factors[:] 1) prices proposed
for the base year and three one year option periods, and 2) evaluating the average cost per pound
for each aircraft as per the solicitation for the base year and three one year option periods.” AR
Tab 67, at 15999; see also id. (“The TET and the Contracting Officer reviewed all of the pricing
to determine price reasonableness . . . .”).
In response to CLIN 23, the agency received fewer proposals than it did for the other
CLINs requiring helicopters with medium-lift capabilities. See AR 67, at 16054. According to
defendant, that CLIN 23 required a helicopter with at least medium-lift capabilities that was
equipped with a tank, as opposed to a bucket, resulted in “a unique assortment of bids and . . . a
higher average price.” Def.’s Mots. & Opp’n 50. For this CLIN, plaintiff’s total price for an
aircraft was approximately [***] and defendant-intervenor Siller’s total price for an aircraft was
approximately [***].
Plaintiff concedes that “the Forest Service undertook . . . a review [of price] and, as a
result, rejected offers on certain line items.” Pl.’s Mot. 15–16. However, according to plaintiff,
the agency “improperly failed to do so with regard to Siller’s proposal on line item 23.” Id. at
16; see Pl.’s Resp. 24–32. Plaintiff argues that the agency should have eliminated defendantintervenor Siller’s helicopters proposed for CLIN 23 because defendant-intervenor Siller’s prices
were unreasonable. In support of its argument, plaintiff compares defendant-intervenor Siller’s
total price and daily availability rates to plaintiff’s total price and daily availability rates and total
prices and daily availability rates for awardee helicopters with medium-lift capabilities. See
Pl.’s Mot. 14–15, attach. 1. Plaintiff also argues that the agency’s failure to eliminate defendantintervenor Siller’s proposal was inconsistent with its decision to eliminate helicopters proposed
by Erickson because the money saved, calculated in dollars and percentages, would have been
greater in this instance. Pl.’s Mot. 16.
In addition to arguing that defendant-intervenor Siller’s price was unreasonable, plaintiff
argues that the price showed a lack of understanding of the level of effort needed to perform the
services required by CLIN 23. According to plaintiff, defendant-intervenor Siller failed to
22
appreciate that CLIN 23 only required a helicopter with medium-lift capabilities to “meet” the
performance requirements. Pl.’s Mot. 17.
Plaintiff’s argument that the agency was required to eliminate defendant-intervenor
Siller’s proposal in response to CLIN 23 suffers from four principal flaws. First, defendantintervenor Siller’s total price was for a helicopter with heavy-lift capabilities. Thus, the agency
received a helicopter with a payload that was much greater than the payload of helicopters with
medium-lift capabilities. The payload requirements in the solicitation were only minimums.
Second, as noted by defendant, the average proposed total price on CLIN 23 was approximately
[***]. See Def.’s Mots. & Opp’n 49 (citing AR Tab 67, at 16054). Although defendantintervenor Siller’s total price was approximately [***] higher than plaintiff’s total price,
defendant-intervenor Siller’s total price was only approximately [***] higher than the average
proposed total price on CLIN 23. Third, plaintiff’s argument fails to appreciate that defendantintervenor Siller’s price per pound was actually lower than plaintiff’s price per pound. Id. at 50.
Fourth, plaintiff’s analogy to the agency’s elimination of [***] helicopters is inapposite. When
the agency eliminated [***] proposed helicopters, it did so because similar performing
helicopters were available at a lesser cost to the agency. Plaintiff has not shown that any of its
helicopters were similar to the helicopter proposed by defendant-intervenor Siller.
Accordingly, the Court finds plaintiff’s claim that the agency was required to eliminate
defendant-intervenor Siller’s proposal responding to CLIN 23 from consideration to be
unavailing.
G.
Plaintiff Has Not Demonstrated that It Was Prejudiced by Alleged Errors in the
Agency’s Best-Value Tradeoff Determinations
The best-value process is described in FAR 15.101-1: “This process permits tradeoffs
among cost or price and non-cost factors and allows the Government to accept other than the
lowest priced proposal. The . . . rationale for tradeoffs must be documented in the file in
accordance with 15.406.” FAR 15.101(c). FAR 15.308 addresses the role of the SSA. First, the
SSA’s “decision shall be based on a comparative assessment of proposals against all source
selection criteria in the solicitation.” FAR 15.308. Second, the “decision shall represent the
SSA’s independent judgment.” Id. Third, the decision “shall be documented, and the
documentation shall include the rationale for any business judgments and tradeoffs made or
relied on by the SSA, including benefits associated with additional costs,” although any tradeoffs
need not be quantified. Id.
The court in Serco thoroughly explained the requirements of the regulations, creating “a
skeletal framework” of the inquiry. “First, the regulation requires the agency to make a business
judgment as to whether the higher price of an offer is worth the technical benefits its acceptance
will afford.” 81 Fed. Cl. at 496. An agency must “do more than simply parrot back the strengths
and weaknesses of the competing proposals—rather, the agency must dig deeper and determine
whether the relative strengths and weaknesses of the competing proposals are such that it is
worth paying a higher price.” Id. at 497. Second, “the agency need neither assign an exact
dollar value to the worth associated with the technical benefits of a contract nor otherwise
quantify the non-cost factors. But . . . logic suggests that as that magnitude [of the price
differential] increases, the relative benefits yielded by the higher-priced offer must also
23
increase.” Id. (citation omitted). Third, the agency must document its tradeoff analysis. Id.
“Conclusory statements, devoid of any substantive content, have been held to fall short of this
requirement, threatening to turn the tradeoff process into an empty exercise.” Id.
Here, plaintiff challenges the use of the OM by the agency and the sufficiency of
statements and explanations by the TET, CO, and SSA. The OM assigned “overall technical
ratings” based on the numerical ratings for the aircraft performance, safety/risk, past
performance, and organizational experience factors. The OM assigned the overall technical
ratings with weights set by the TET to reflect the level of importance of the technical factors.
The overall technical ratings were numerical ratings carried out to four decimals. The OM was
programmed by the TET to emphasize or prioritize the overall technical rating at [***] percent,
total price at [***] percent, and price per pound at [***] percent. The administrative record
includes explanations of how the OM worked, see AR Tab 67, at 16040, 16210, and statements
by the TET, CO, and SSA that the proposals selected by the OM represented the best value to the
agency. See AR Tab 67, at 16034–35; AR Tab 68, at 16213.
Even if the agency’s use of the OM and the statements and explanations by the TET, CO,
and SSA fell short of what is required by FAR 15.308, plaintiff has failed to establish that it was
prejudiced by the agency’s best-value tradeoff determinations. “Prejudice in the context of a
violation of FAR 15.308 requires that the protestor’s chances of receiving the contract be
increased” if the agency had complied with FAR. Info. Scis. Corp. v. United States, 73 Fed. Cl.
70, 121 (2006). The Court has four reasons for concluding that plaintiff has not shown
prejudice. First, as to CLIN 23, plaintiff has not demonstrated that any of the proposals should
have been eliminated from consideration based on price. Thus, plaintiff is required to show
increased chances of receiving CLIN 23 even if no proposals were eliminated from
consideration, which it has not done. Second, regarding all of the disputed CLINs, plaintiff has
failed to meaningfully compare its proposal with any of the other proposals not selected.
Plaintiff’s failure to do so is especially evident with respect to CLINs 17, 28, 29, 30, 32, and 33.
See Brooks Range Contract Servs., Inc. v. United States, 101 Fed. Cl. 699, 713 (2011) (finding
that the plaintiff had failed to establish prejudice to show standing in light of another proposal
not selected). Third, plaintiff has not established that the underlying evaluations were improper,
which in turn could have affected the best-value tradeoff determinations. See id. Fourth,
plaintiff has failed to demonstrate that this is a case in which plaintiff need not meaningfully
compare its proposal to other proposals not selected, as plaintiff’s counsel seemed to suggest at
oral argument. See generally July 16, 2012 Hr’g Tr. at 28:22–31:9, 76:11–21.
Accordingly, even if the agency failed to comply with FAR 15.308, plaintiff has failed to
show that it was prejudiced.
H.
Plaintiff Has Not Shown that the Cancellation of Four CLINs Was Irrational or
the Agency’s Reasons Were Pretextual
“[A]n agency’s cancellation decision must be supported by a ‘rational’ or ‘reasonable’
basis.” Madison Servs., Inc., 90 Fed. Cl. at 680. Here, four CLINs were cancelled due to,
among other reasons, budget constraints. See AR Tab 29, at 13408; see also AR Tab 67, at
15994. Thus, the agency had a rational basis for its action, notwithstanding plaintiff’s arguments
that simply amount to a mere disagreement with the wisdom of the agency’s decision. See Pl.’s
24
Mot. 4 n.5, 18; Pl.’s Supplemental Br. 2–6. To the extent plaintiff contends that the reasons for
the cancellation were pretextual, see Compl. ¶¶ 82–97, plaintiff has not met its burden of
providing clear and convincing evidence to demonstrate such. Def. Tech., Inc. v. United States,
99 Fed. Cl. 103, 126 (2011).
I.
Defendant’s Motion to Strike Is DENIED
Defendant moves to strike attachment 1 to plaintiff’s response brief and related portions
of plaintiff’s response brief. See Def.’s Reply & Mot. 35–37. Specifically, defendant moves to
strike a letter from the Forest Service informing plaintiff that it was unsuccessful in its proposal
responding to RFP 12-9025 and portions of plaintiff’s response brief relating to the letter. The
Court indicated at oral argument that it would deny defendant’s motion to strike. See July 16,
2012 Hr’g Tr. at 6:7–9.
For substantially the reasons set forth in the Court’s order denying plaintiff’s motion to
supplement the administrative record, see June 8, 2012 Order (docket entry 48), the Court
DENIES defendant’s motion to strike.
CONCLUSION
For the foregoing reasons, the Court DENIES plaintiff’s motion for judgment on the
administrative record; DENIES defendant’s motion to dismiss on grounds of mootness and lack
of standing; DENIES defendant’s motion to strike; and GRANTS defendant’s and defendantintervenor Siller’s cross-motions for judgment on the administrative record. The Clerk shall
enter judgment accordingly.
Some information contained herein may be considered protected information subject to
the protective order entered in this action on March 2, 2012 (docket entry 18). This Opinion and
Order shall therefore be filed under seal. The parties shall review the Opinion and Order to
determine whether, in their view, any information should be redacted in accordance with the
terms of the protective order prior to publication. The Court ORDERS that the parties shall file,
by Monday, August 27, 2012, a joint status report identifying the information, if any, they
contend should be redacted, together with an explanation of the basis for each proposed
redaction.
IT IS SO ORDERED.
s/ George W. Miller
GEORGE W. MILLER
Judge
25
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?