MICHAEL ROTH & ASSOCIATES v. USA
Filing
22
UNREPORTED ORDER granting 15 Motion to Produce; on 15 MOTION to Produce Documents and Deponents, and for Extension of Time to Take Discovery Concerning Late Produced Information filed by MICHAEL ROTH & ASSOCIATES. Signed by Judge Victor J. Wolski. (sl) Copy to parties.
In the United States Court of Federal Claims
No. 13-626C
(Filed October 14, 2014)
NOT FOR PUBLICATION
* * * * * * * * * * * * * * * * * * *
*
*
MICHAEL ROTH & ASSOCIATES,
*
ARCHITECTS & PLANNERS, INC., *
*
Plaintiff,
*
*
v.
*
*
THE UNITED STATES,
*
*
Defendant.
*
*
* * * * * * * * * * * * * * * * * * *
ORDER
Pending before the Court is the plaintiff’s motion to enlarge the period of
time in which to conduct discovery, for the purpose of deposing Mr. Eric Miller. For
the reasons discussed below, the Court concludes, with some reluctance, that the
deposition should be allowed.
This case concerns work performed under a task order issued by the
Department of Veterans Affairs (VA). See App. to Def.’s Resp. to Pl.’s Mot. (DA) at
A16–A26. Under this task order the plaintiff, Michael Roth & Assocs., Architects &
Planners, Inc. (MRA) was to design an expansion and renovation of cardiology
facilities at a VA hospital in St. Louis, Missouri. Compl. ¶ 3. The project MRA
designed included an electrophysiology (EP) lab and two cardiac catheter (cath)
labs. Pl.’s Mot. for Prod. of Docs. & Deponents (Pl.’s Mot.) at 1; DA at A24. The
plaintiff seeks an equitable adjustment of its fees under the task order, contending
that increases in the scope of work, which resulted in the designed project exceeding
the construction budget ceiling, entitle MRA to an increase in fees. Compl. ¶¶ 10–
21.
Plaintiff served its initial discovery requests on defendant in March of this
year. This included requests for, among other things, the production of “[a]ll
documents related to cost projections concerning alternative bids requested by the
United States, and received by the United States”; “[a]ll documents concerning the
awarding of bids concerning the subject contract”; “[a]ll documents reflecting the
actual cost of the Project”; and “[a]ll contracts entered into between the general
contractor . . . [or] with subcontractors of the Project.” Pl.’s Mot. at 1–2. Defendant
objected that the requests were “vague and ambiguous,” “incomplete and
unintelligible,” and “broad and unduly burdensome.” DA at A79. Defendant also
objected that “documents reflecting the actual cost” of the project were irrelevant
but nonetheless agreed to produce the contract for construction of the facility and
modifications to that contract. See id. at 80–81.
More than one contract was involved, however, unbeknownst to defendant’s
counsel at the time documents were initially produced. When plaintiff’s counsel
reviewed documents produced in early July, he learned that the contract with J.W.
Fuller Construction, LLC, see DA at A27–28 --- which was among the documents
produced --- concerned only the EP lab, and emails suggested that the cath labs
were to have been constructed under separate contracts with Philips Healthcare, see
id. at A84. On July 9, 2014 plaintiff’s counsel notified defendant’s counsel that he
had not received the Philips contracts. Id. The following week, on July 14,
plaintiff’s counsel followed up with another email indicating that he wanted to
discuss these contracts with Clifford Farrell, the contracting officer’s technical
representative, during a planned July 18, 2014 deposition. See DA at A85–87; Ex. 2
to Pl.’s Mot. (Pl.’s Ex. 2) at 1–3. Defendant’s counsel responded that same day,
stating that the government would produce the Philips contracts “to the extent they
exist” once they are located. Pl.’s Ex. 2 at 1; DA at A85. Defendant’s counsel also
stated, “[i]f you are reluctant to conduct the depositions in the absence of the
documents that plaintiff now requests [the Philips contracts], then I suggest that
Mr. Farrell’s . . . deposition[] be postponed until the parties agree that document
discovery is complete.” Pl.’s Ex. 2 at 1; DA at A85. Plaintiff did not agree to
postpone the deposition and it occurred as scheduled. On July 28, 2014, the
government produced copies of the Philips contracts. See Pl.’s Mot. at 3; Def.’s Resp.
to Pl.’s Mot. (Def.’s Opp’n) at 6; DA at A88.
On August 14, 2014, eight days before the close of discovery, plaintiff
requested that Eric Miller be deposed and that Mr. Farrell be deposed again. Ex. 6
to Pl.’s Mot. (Pl.’s Ex. 6) at 1. Mister Farrell’s deposition was requested on the
ground that plaintiff had additional questions after learning in subsequent
depositions that Mr. Farrell was the VA employee with the most knowledge
concerning the Philips contracts. Pl.’s Mot. at 3. Mister Miller is apparently the
head nurse at the cardiology unit of the St. Louis VA hospital. Def’s Opp’n at 6.
After reviewing documents previously produced by the government, plaintiff found
that Mr. Miller was included in an email string in which information relating to the
construction of EP and cath labs was requested from Philips employees. Pl.’s Supp’l
Mem. at 2 & Ex. 1. Due to scheduling difficulties (with just four days left of the fact
discovery period) as well as doubts that the depositions could lead to relevant
-2-
evidence, defendant’s counsel on August 18 declined the request to schedule the two
depositions. Pl.’s Ex. 6 at 1. On August 20, 2014, plaintiff filed a motion for
production of documents and deponents and for an extension of the time period for
discovery.
After a hearing on these issues on September 22, 2014, the Court granted the
plaintiff leave to depose Mr. Farrell by written questions, but denied MRA’s motion
to compel the government to produce bid documents. Order (Sept. 22, 2014), ECF
No. 19. The Court also requested that the parties submit supplemental memoranda
on the issue of Mr. Miller’s deposition, which is the matter presently under
consideration. Id.
The Court admits to some difficulty in understanding MRA’s legal theory,
and hence its justification for deposing Mr. Miller. The plaintiff seems to contend
that when the VA amended the task order to request the design of facilities that
would cost no more than $2.945 million to build, the agency knew that the facilities
would in actuality cost at least 50 percent more than the purported ceiling.
According to MRA, this means that the fee to which it agreed was based on a project
of a smaller scope, and should be adjusted upwards. See Compl. ¶¶ 4, 11, 14, 17–22.
The deposition of Mr. Miller is sought because at Mr. Farrell’s request he initiated
communications with Philips, the eventual contractor for the cath labs portion of
the project, before the amendment issued. See Pl.’s Supp’l Mem. at 2 & Ex. 1. The
plaintiff presumes that Mr. Miller possessed at that time knowledge that the VA
believed the project to be larger than the plaintiff was told. Id. at 4.
The government opposes extending the fact discovery period for a deposition
of Mr. Miller. It argues that the referenced “email thread has nothing to do with
having Philips build the cath labs.” Def.’s Resp. to Pl’s Supp’l Mem. at 7.
Defendant contends that MRA has failed to show that Mr. Miller possesses any
relevant knowledge, id. at 8–9, and that a deposition would “unnecessarily take”
him “away from [his] work at an understaffed medical center.” Def.’s Opp’n at 9.
Under Rule 26(b)(1), “[p]arties may obtain discovery regarding any
nonprivileged matter that is relevant to any party’s claim or defense.” Rules of the
United States Court of Federal Claims (RCFC) 26(b)(1). To the extent that
plaintiff’s claim rests on the notion that the VA had requested design work of a
greater scope than the construction ceiling suggested, the Court supposes that Mr.
Miller’s deposition may have some relevance. Although the desire to depose Mr.
Miller was not communicated to government counsel until August 14, the request
was made prior to the discovery cut-off. Under the circumstances this request was
timely, as the size of the Philips contracts was not discovered prior to July 18, 2014,
and the contracts were produced on July 28, 2014 (pursuant to a document request
made in March).
-3-
The Court is mindful that Mr. Miller is apparently a health professional, not
a procurement official, and expects that the plaintiff will endeavor to inconvenience
his regular duties as little as possible. Moreover, the government is strongly of the
opinion that this deposition cannot be relevant, and thus cannot justify the costs of
an additional trip of its counsel to St. Louis. See Def.’s Opp’n at 9. While the Court
does not find that defendant has demonstrated that the expense of Mr. Miller’s
deposition outweighs its likely benefit, see RCFC 26(b)(2)(C)(iii), if defendant’s
counsel wishes to participate in the deposition by videoconferencing, MRA shall
accommodate those wishes.
As described above, the plaintiff’s motion to enlarge the time period for fact
discovery, for the purpose of deposing Mr. Miller, is GRANTED. The plaintiff shall
have thirty days from the date of this order, or until November 13, 2014, to take
this deposition and conduct (if necessary and within reason) any follow-up
discovery. The remaining deadlines from the September 22, 2014 order are
unchanged.
IT IS SO ORDERED.
s/ Victor J. Wolski
VICTOR J. WOLSKI
Judge
-4-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?