KANSAS CITY POWER & LIGHT CO. v. USA
Filing
213
UNREPORTED ORDER granting 195 Motion to Compel. Plaintiff is directed to serve its amended responses on defendant by no later than March 12, 2020. Signed by Chief Judge Margaret M. Sweeney. (jhk)
In the United States Court of Federal Claims
No. 15-348C
(Filed: February 27, 2020)
NOT FOR PUBLICATION
*************************************
KANSAS CITY POWER & LIGHT CO., *
*
Plaintiff,
*
*
v.
*
*
THE UNITED STATES,
*
*
Defendant.
*
*************************************
RCFC 37; Motion to Compel;
Interrogatories
ORDER
On November 18, 2019, defendant moved to compel Kansas City Power & Light Co.
(“KCP&L”) to provide complete responses to Interrogatory Nos. 11 and 13 pursuant to Rule 37
of the Rules of the United States Court of Federal Claims (“RCFC”).1 Defendant argues that
KCP&L made unsupported objections to each interrogatory and failed to provide complete
answers. Defendant’s motion to compel is now ripe for adjudication, and the court grants the
motion.
I. BACKGROUND
KCP&L was contracted to provide electrical service to the United States General
Services Administration (“GSA”) at the Hardesty Federal Complex in Kansas City, Missouri.
Pursuant to that contract, the GSA was required to
indemnify, save harmless and defend [KCP&L] against all claims, demands, cost
or expense, for loss, damage or injury to persons or property, in any manner
directly or indirectly connected with, or growing out of the distribution or use of
the electric service by the [GSA] at or on the [GSA’s] side of the point of
delivery.
Compl. Ex. 6 at 22.
On August 10, 2006, David Eubank, a GSA employee, was injured and subsequently died
1
Defendant also moved to compel a response to Interrogatory No. 14, but, as explained
below, defendant withdrew that request.
after coming into contact with electrical equipment—specifically switch 6530—in Hardesty
Federal Complex building 13. Mr. Eubank’s widow subsequently sued KCP&L for damages and
then reached a settlement with KCP&L. The GSA refused to defend KCP&L during that lawsuit
or indemnify KCP&L for its litigation expenses or settlement costs. KCP&L alleges in this suit
that defendant breached its contractual obligation to provide indemnification. The parties are
now engaged in discovery; among its discovery requests, defendant served KCP&L with
Interrogatory Nos. 11 and 13.
A. Interrogatory No. 11
In Interrogatory No. 11, defendant requests that KCP&L
identify, in detail, all bases, legal and factual, for KCP&L’s belief, if any, that the
Government—including but not limited to the United States General Services
Administration—was engaged in “the distribution or use of electric service,” as
described in paragraph 4.12, at the time of Mr. Eubank’s accident on August 10,
2006.
Def.’s Feb. 21, 2020 Status Report (“Status Report”) Ex. A at 1. KCP&L answered that
interrogatory by stating that it
defines “electric service” as [the term] is defined by the applicable Tariff as the
“availability of electric power and energy at the point of delivery.” KCP&L
supplied the Government with electrical service under the terms of the Area-Wide
Public Utility Contract and the General Rules and Regulations Applying to
Electrical Service . . . .
Id. (citations omitted). And KCP&L then stated:
Fact #1: The “point of delivery” is the pothead, since that is where the
Government’s installation met KCP&L’s conductors/equipment (KCP&L’s
underground feeder lines).
....
Fact #2: Electric power and energy were available at the point of delivery
(“electrical service” was being provided), and that electric power and energy was
flowing beyond the point of delivery (the pothead) to the Government’s electrical
equipment at the time of the accident. KCP&L’s responsibility for the quality of
service and operation of its facilities ended at the point of delivery (the pothead),
and the flow of electrical power and energy past that point was the Government’s
use or distribution of “electric service”.
Id. at 2-3. KCP&L concluded its response by reiterating that “the flow and presence of electrical
power and energy extended beyond the point of delivery where electric service was supplied into
the Government’s electrical equipment, and this constituted the Government’s ‘use’ or
-2-
‘distribution’ of electrical service.” Id. at 4.
B. Interrogatory No. 13
In Interrogatory No. 13, defendant requests that KCP&L
[d]escribe in detail the history of and circumstances surrounding KCP&L’s operation of
switch 6530 in the Hardesty Federal Complex, including the identity of the entity or
individual(s) . . . that opened switch 6530 prior to Mr. Eubank’s accident, along with any
facts that support this identification; to the extent that your response states that KCP&L
was not responsible for switch 6530 being open at the time of Mr. Eubank’s accident,
please identify all facts relied on by KCP&L to support this response.
Id. KCP&L responded that the government constructed building 13 in 1941, KCP&L was not
involved in configuring or engineering the building, the GSA bought the complex (including the
equipment) in 1960, the government is responsible for maintaining and operating the equipment
(or hiring someone to do so), the contract reflects that the government would do its own
switching, and KCP&L would perform such switching upon request. Id. at 4-5. KCP&L then
discussed events surrounding the accident in 2006 and stated that it “has no records reflecting
who opened the switch prior to . . . June 29, 2006, and has no records that KCP&L opened it, or
regarding the identity of the person who was the last to open it before or after June 29, 2006.”
Id. at 5.
II. PROCEDURAL HISTORY
Defendant originally moved to compel responses to Interrogatory Nos. 11, 13, and 14
based on challenges to KCP&L’s objections and substantive answers. In its response to the
motion to compel, KCP&L withdrew its objections to each of those interrogatories because it
wanted the focus to be on the substance of its answers. Defendant then withdrew its request to
compel a complete answer to Interrogatory No. 14. The court subsequently directed the parties
to confer in an attempt to resolve the discovery dispute without further court involvement. On
February 21, 2020, defendant filed a status report in which it stated that KCP&L provided
amended responses, set forth above, that remain inadequate.
III. LEGAL STANDARD
It is “axiomatic that a trial court has broad discretion to fashion discovery orders[.]”
White Mountain Apache Tribe of Ariz. v. United States, 4 Cl. Ct. 575, 583 (1984); see
also Schism v. United States, 316 F.3d 1259, 1300 (Fed. Cir. 2002) (en banc) (“A trial court ‘has
wide discretion in setting the limits of discovery.’” (quoting Moore v. Armour Pharm. Co., 927
F.2d 1194, 1197 (11th Cir. 1991))). Although discovery rules “are to be accorded a broad and
liberal treatment,” Hickman v. Taylor, 329 U.S. 495, 507 (1947), the court must, “[i]n deciding
either to compel or quash discovery, . . . balance potentially conflicting goals,” Evergreen
Trading, LLC ex rel. Nussdorf v. United States, 80 Fed. Cl. 122, 126 (2007). Thus, “discovery,
like all matters of procedure, has ultimate and necessary boundaries.” Hickman, 329 U.S. at 507.
-3-
When a party is dissatisfied with the responses to its discovery requests, the party may
seek an order from the court compelling a more satisfactory response. Specifically, under RCFC
37, when a party fails to fulfill its discovery obligations, the “party seeking discovery may move
for an order compelling an answer, designation, production, or inspection.” RCFC 37(a)(3)(B).
A motion to compel is appropriate when a party “fails to answer an interrogatory under RCFC 33
. . . .” RCFC 37(a)(3)(B)(iii). And “an evasive or incomplete . . . response must be treated as a
failure to . . . respond.” RCFC 37(a)(4).
“In order to succeed on a motion to compel discovery, a party must first prove that it
sought discovery from its opponent.” Petrucelli v. Bohringer & Ratzinger, 46 F.3d 1298, 1310
(3d Cir. 1995). Additionally, an RCFC 37 motion “must include a certification that the movant
has in good faith conferred or attempted to confer . . . .” RCFC 37(a)(1). Like its Federal. Rules
of Civil Procedure counterpart, RCFC 37 “does not set forth what must be included in the
moving party’s certification except to indicate that the document must declare that the movant
has ‘in good faith conferred or attempted to confer’ . . . .” Shuffle Master, Inc. v. Progressive
Games, Inc., 170 F.R.D. 166, 171 (D. Nev. 1996). Conferment, in turn, requires that the movant
“personally engage in two-way communication with the nonresponding party to meaningfully
discuss each contested discovery dispute in a genuine effort to avoid judicial intervention.” Id.
IV. ANALYSIS
A. Interrogatory No. 11
Defendant first argues that KCP&L’s answer to Interrogatory No. 11 is deficient because
it provides no legal or factual basis for its statement that “the flow and presence of electrical
power and energy extended beyond the point of delivery where electric service was supplied into
the Government’s electrical equipment, and this constituted the Government’s ‘use’ or
‘distribution’ of electrical service.” Status Report 2 (quoting Status Report Ex. A at 4). KCP&L
maintains that it did so by stating that “the indemnity agreement is triggered by ‘loss, damage, or
injury’ resulting from any electricity beyond the point of delivery and that all electricity beyond
the point of delivery constitutes distribution or use.” KCP&L Resp. Br. 4.
KCP&L’s answer to Interrogatory No. 11 is incomplete. In relevant part, KCP&L merely
makes the conclusory statement that “the flow of electrical power past [the point of delivery] was
the Government’s use or distribution of the ‘electric service.’” Status Report Ex. A at 3. With
its response, KCP&L fails to explain the factual and legal basis for its belief that electricity
beyond the point of delivery constitutes distribution or use. KCP&L must remedy the
incomplete answer by stating the basis for its belief.
B. Interrogatory No. 13
Defendant also argues that KCP&L’s answer to Interrogatory No. 13 is incomplete
because KCP&L (1) provides no information about its operation of the switch prior to June 29,
2006, and (2) suggests that it has policies or practices related to when it will operate the switch
but failed to provide information on those policies/practices. KCP&L counters that defendant
failed to satisfy the meet-and-confer requirements because defendant’s counsel did not attempt to
-4-
amicably resolve the issues prior to filing its motion to compel.2
KCP&L’s meet-and-confer argument is a threshold procedural consideration because a
party must make a good faith effort to confer with the opposing party before filing a motion to
compel. See RCFC 37(a)(1). KCP&L’s argument here is mooted by the fact that, after briefing
was completed, the parties were directed to confer regarding their discovery dispute and
seemingly did so on January 21, 2020. See Status Report 1. On the merits, KCP&L makes no
argument that has not been waived, see supra note 2 (explaining KCP&L waived its arguments
concerning objections), and its answer to Interrogatory No. 13 is substantively incomplete. First,
KCP&L has not addressed its operation of the switch prior to June 29, 2006, despite defendant
requesting such information. Second, KCP&L fails to explain its policies and procedures with
respect to operating the switch even though the underlying contract and deposition testimony
reflect that KCP&L contemplated such operations. Indeed, KCP&L acknowledged in its answer
that it “would perform switching upon request or assist the customer with switching upon
request,” Status Report Ex. A at 5, and a KCP&L employee indicated that employees operated
the switch in the past, see id. Ex. B (Joyce Dep.) (responding “no” when asked if he felt like he
needed permission from the GSA to “either open or close the switches”). KCP&L, therefore,
seemingly had policies related to the switch that are not discussed in its interrogatory response
despite defendant requesting that information. KCP&L must rectify its incomplete response to
Interrogatory No. 13 by providing information on its (1) operation of switch 6530 prior to June
29, 2006, and (2) policies with respect to the operation of switch 6530.
V. CONCLUSION
In light of the above, the court GRANTS defendant’s motion to compel KCP&L to
provide additional information in response to Interrogatory Nos. 11 and 13. KCP&L is directed
to complete its answer to Interrogatory No. 11 by explaining the factual and legal basis for its
belief that electricity beyond the point of delivery constitutes distribution or use. Additionally,
KCP&L is directed to supplement its answer to Interrogatory No. 13 by providing information
on its (1) operation of switch 6530 prior to June 29, 2006, and (2) policies with respect to the
operation of switch 6530. The court further DIRECTS KCP&L to serve its amended responses
on defendant by no later than March 12, 2020.
IT IS SO ORDERED.
s/ Margaret M. Sweeney
MARGARET M. SWEENEY
Chief Judge
KCP&L also argues that defendant’s revisions to Interrogatory No. 13 “did nothing to
remedy the overbroad, vague, and ambiguous or burdensome nature of the request, or respond to
KCP&L’s objections on those grounds.” KCP&L Resp. Br. 7. But KCP&L stated that it was
waiving those objections. Id. at 1 (“[KCP&L] withdraws all objections so the parties and Court
can focus on [the] substance of the answers.”).