REMINGTON ARMS COMPANY, LLC v. USA
Filing
62
REPORTED OPINION. Plaintiff's motion to supplement the administrative record GRANTED; Plaintiff's motion for judgment on the administrative record Granted in Part and Denied in Part. Case REMANDED. Defendant shall file aStatus Report by 4/25/2016. Signed by Judge Nancy B. Firestone. (dpk) Copy to parties.
In the United States Court of Federal Claims
No. 15-1425C
(Filed: March 30, 2016)*
*OPINION ORIGINALLY FILED UNDER SEAL ON MARCH 25, 2016
REMINGTON ARMS CO., LLC,
Plaintiff,
v.
THE UNITED STATES,
Defendant.
and
COLT DEFENSE, LLC,
Defendant-Intervenor
and
FN AMERICA, LLC,
Defendant-Intervenor
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Bid Protest; Responsibility
Determination; FAR § 9.104-1;
Bankruptcy; Injunctive Relief Granted
Walter Brad English, with whom were J. Andrew Watson, III, Kevin C. Gray, Jon
D. Levin, and Emily J. Chancey, Huntsville, AL, for plaintiff.
Igor Helman, Civil Division, U.S. Department of Justice, Washington, DC, with
whom were Benjamin C. Mizer, Principal Deputy Assistant Attorney General, and Robert
E. Kirschman, Jr., Director, and Douglas K. Mickle, Assistant Director, for defendant.
Frank A. March, US Army Legal Services Agency, and Casey P. Nix, US Army
RDECOM-ARDEC, of counsel.
John E. McCarthy, Jr., with whom was Robert J. Sneckenberg, for defendantintervenor Colt Defense, LLC.
William A. Wozniak, with whom was Anthony H. Anikeeff, of counsel, Tysons,
VA, for defendant-intervenor FN America, LLC.
OPINION
FIRESTONE, Senior Judge
Pending before the court in this post-award bid protest are cross-motions for
judgment on the administrative record filed under Rule 52.1 of the Rules of the United
States Court of Federal Claims (“RCFC”) by plaintiff, Remington Arms Company, LLC
(“Remington”); the defendant, the United States; defendant-intervenor, Colt Defense
LLC (“Colt”), and defendant-intervenor FN America, LLC (“FN”). Remington
challenges the government’s decision to award one of two Indefinite Quantity Indefinite
Award (“IDIQ”) contracts for producing M4 and M4A1 carbines to defendant-intervenor
Colt. The other contract was awarded to FN America, LLC. Also pending before the
court is Remington’s motion to supplement the administrative record.
Remington’s bid protest is focused on whether the contracting officer’s (“CO”)
decision to award a contract to Colt while Colt was still in bankruptcy and was labeled
“high” risk by the Defense Contract Management Agency (“DCMA”) was arbitrary,
capricious, and an abuse of discretion. The DCMA based its high risk rating on fact that
Colt had recently filed for Chapter 11 bankruptcy protection and the fact that Colt’s
liabilities far exceeded its assets. The DCMA was uncertain whether Colt would have
enough working capital to fulfill the contract. Further, at the time of the award, Colt did
not have a long-term lease for the facility in which it intended to manufacture the M4s.
According to Remington, the CO failed to properly evaluate the DCMA report or
evidence she reviewed from the bankruptcy proceeding. Remington relies on evidence
from the bankruptcy proceeding to show that, at the time of award, Colt faced possible
2
liquidation and that Colt’s manufacturing facility lease was set to expire. Remington
argues that the CO’s responsibility determination under FAR § 9.104 is unsupported and
was thus arbitrary and capricious.1 Remington further argues that the government’s
technical evaluation of Colt’s proposal was arbitrary, capricious, or an abuse of discretion
because the technical evaluation did not take into account the possibility that Colt would
lose its lease. Remington is seeking an injunction requiring the government to either set
aside the award to Colt or to redo Colt’s responsibility determination. In the interim
Remington asks that no additional task orders be awarded to Colt.2
The government and Colt argue in response that the CO’s award decision and
responsibility determination are both rational and supported by the record. The
government and Colt also argue that even if Remington is correct with regard to the CO’s
responsibility determination or technical evaluation that Remington was not “prejudiced”
1
Under FAR § 9.104-1, to be determined responsible a prospective contractor must:
(a) have adequate financial resources to perform the contract, or the ability to obtain
them;
(b) be able to comply with the delivery or performance schedule;
(c) have a satisfactory performance record;
(d) have a satisfactory record of integrity;
(e) have the necessary organization to perform the work;
(f) have the necessary production, and technical equipment, and facilities; and
(g) be otherwise qualified and eligible to receive an award under applicable laws.
With regard to resources necessary to perform the contract under FAR § 9.104-1(f), the CO must
ensure that there is evidence that the contractor has a commitment for the necessary facilities.
See FAR § 9.104-3. A final responsibility determination is required before the contract may be
signed. FAR § 9.105-1. A pre-award survey by the DCMA is authorized where the CO needs
additional information to make a responsibility determination. FAR § 9.106.
2
Pursuant to the contract, the two awardees must compete with each other for each task order
beyond the first minimum order.
3
by any error because the government never guaranteed it would award two contracts.
With respect to Remington’s motion to supplement, the government has agreed to add to
the record the bankruptcy documents the CO expressly states she reviewed and
considered, but opposes the inclusion of the other documents from the bankruptcy that
Remington has identified. The government has also asked that several other documents,
including a declaration from the CO, be added to the record.
For the reasons discussed below, Remington’s motion to supplement the
administrative record is GRANTED. Remington’s motion judgment on the
administrative record is GRANTED IN PART AND DENIED IN PART. The case is
REMANDED for re-evaluation consistent with this opinion. Further, the government is
enjoined from awarding additional task orders to Colt until a new responsibility
determination based on the most up-to-date financial information is complete and
submitted to the court.3
I.
MOTION TO SUPPLEMENT THE ADMINISTRATIVE RECORD
In deciding a bid protest, the court’s review is ordinarily limited to the
procurement record existing at the time of the decision. Axiom v. United States, 564
F.3d 1374, 1379 (Fed. Cir. 2009) (citing Camp v. Pitts, 411 U.S. 138, 142 (1973)). The
Federal Circuit has held that supplementation is proper where “the omission of extra-
3
The CO issued her responsibility determination in September of 2015. The court understands
that on January 12, 2016, the bankruptcy court approved Colt’s reorganization plan thus allowing
Colt to exit Chapter 11 bankruptcy proceedings. However, as discussed below, Colt’s
reorganization plan details the significant risks the company still faces. Because the CO has not
yet adequately evaluated Colt’s present risk factors, the case is not moot.
4
record evidence precludes effective judicial review.’” Id. (citing Murakami v. United
States, 46 Fed .Cl. 731, 735 (2000)). In the context of a case involving a parallel
bankruptcy proceeding, this court has held that it “does not need every document in the
[bankruptcy docket], only those documents relevant to the decision that is properly before
the court.” Eskridge Research Corp. v. United States, No. 10-50C, 2010 WL 1837799, at
*3 (Fed. Cl. May 3, 2010) (citing Pers. Watercraft Indus. Ass’n v. Dep’t of Commerce,
48 F.3d 540, 546 n.4 (D.C. Cir. 1995)).
Remington argues that because the CO has admitted that she reviewed bankruptcy
court documents while making her responsibility determination, the court needs to review
the bankruptcy documents relevant to Colt’s financial status and lease arrangement at the
time of award before any additional task orders are issued. The government seeks to add
to the record the documents from the bankruptcy proceeding the CO, Jacyln Dayda
references in her affidavit. The government also seeks to add to the record Ms. Dayda’s
affidavit. In a telephonic conference held on January 8, 2016, the court agreed that the
record would need to be supplemented with documents from the bankruptcy proceeding
but reserved ruling on which documents until briefing was complete. See January 8,
2016 Order, ECF No. 37. The government now seeks to add the following documents to
the administrative record:
(1)
Declaration of Nikhil Menon [Menon Decl.] in Support of Debtors’
Motion, Pursuant To 11 U.S.C. §§ 105, 363, And 365, And Fed. R.
Bankr. P. 2002, 6004, 6006, 9008 and 9014 . . . , In re Colt Holding Co.,
No. 15-11296-LSS (Bankr. D. Del. Aug. 17, 2015), Dkt. No. 348;
(2)
Declaration of Keith Maib [Maib Decl.] In Support of the Debtors'
Motion for Entry of an Order Approving Key Employee Incentive Plan
5
(KEIP), In re Colt Holding Co., No. 15-11296-LSS (Bankr. D. Del.
Aug. 20, 2015) Dkt. No. 361;
(3)
Statement of Financial Affairs for Colt Security LLC, In re Colt
Holding Co., No. 15-11296-LSS (Bankr. D. Del. Aug. 25, 2015), Dkt.
No. 392;
(4)
Notice of (I) Proposed Sale of Substantially All of the Debtors' Assets
Free and Clear of Liens, Claims, and Encumbrances, (II) Auction and
(III) Sale Hearing Thereof, In re Colt Holding Co., No. 15-11296-LSS
(Bankr. D. Del. Sept. 9, 2015), Dkt. No. 453 (indicating an anticipated
Sale Hearing on October 26, 2015);
(5)
The “Hot Off The Press” internal publication and
(6)
The Declaration of Jacalyn B. Dyda, contracting officer
Gov’t MJAR 42-44. As noted, Remington agrees to the government’s proposed additions
to the record and has identified approximately twenty-five additional documents from the
bankruptcy docket that it wishes to also add to record. See Appendix A to Pl. MJAR
(“Pl.’s App’x”).
The court has reviewed the documents presented by both sides and concludes that
the documents the government has identified and the additional documents Remington
has identified from the bankruptcy docket are needed for effective judicial review.
Remington has identified bankruptcy documents that show that Colt did not have a plan
of reorganization in place at the time the CO signed her responsibility determination.
Remington also has identified documents to show that Colt’s relationship with its
creditors, including Colt’s landlord at the facility where it intended to manufacture M4s
under the contract, were not resolved at the time the CO signed her responsibility
determination. Regardless of whether the CO reviewed each document, they were
6
available to her at the time she made her responsibility determination and she claims to
have reviewed the bankruptcy court record. In such circumstances, the court finds that
the documents identified by both parties are necessary for effective judicial review and
are thus properly before the court and will be added to the record. Consequently, the
motions of both parties are GRANTED.
II.
FACTUAL BACKGROUND
A.
The Solicitation
On December 5, 2014, the Army issued Solicitation No. W15QKN-15-R-001 (the
“Solicitation”) seeking offerors for up to two contracts to provide M4 and M4A1 carbines
to the United States military. AR 593. The Army expected the awardees to be able to
produce and deliver between 2,000 and 6,000 M4/M4A1 carbines per month. AR 645. If
two companies were awarded the contract, “subsequent delivery orders will be competed
based on best value between the awardees.” AR 35-36. The solicitation also provided
that the proposals most advantageous to the Army would be selected utilizing the “Best
Value Trade-Off” procedures. AR 593. The Solicitation set forth four evaluation factors:
Production Capability, Past Performance, Small Business Participation, and Price. AR
700. Under the terms of the Solicitation, the factors were listed “in descending order of
importance,” with Production Capability identified as the most important factor, followed
by Past Performance, Price, and Small Business Participation as the least important
factor. Id.
7
The Production Capability factor is the only factor at issue in this protest.4 The
evaluation of Production Capability was further divided into three subfactors,
Manufacturing Plan, Key Tooling and Equipment, and Quality Control, with the
Manufacturing Plan identified as the most important subfactor. Id. The overall
Production Capability factor included an evaluation of an offeror’s risk of nonperformance, and set a range of five possible ratings: Outstanding, Good, Acceptable,
Marginal and Unacceptable. AR 701. “Outstanding” and “Good” proposals reflected
“very low” and “low” risk, respectively, while “Marginal” and “Unacceptable” proposals
reflected high risk. With regard to the “Manufacturing Plan,” offerors would be
evaluated on their proposed manufacturing facilities, including the “adequacy of the
proposed production facility layout to accommodate a minimum production rate of 2,000
and a maximum production rate of 6,000 [M4s] per month,” as well as the “adequacy and
capacity of the available weapon and ammunition storage facilities,” and the adequacy of
proposed schedules. AR 702. Evaluation under “Key Tooling and Equipment” would
focus on the “capability of the key tooling and equipment that w[ould] be used to produce
the M4[s]” as well as the “adequacy of the proposed critical subcontractor support” for
certain M4 components, such as barrels, bolts, and receivers. Id. Finally, under “Quality
Management” the Army would assess the adequacy of the various quality management
systems, including whether the systems were compliant with ISO9001 standards, and
4
Remington initially challenged the government’s evaluation of the past performance factor in
Colt’s proposal as well, but agreed at oral argument that this objection was not well-founded.
Therefore, the court will not further consider Remington’s objections to Colt’s past performance
evaluation.
8
whether the offeror had processes for inspecting, identifying, and preventing nonconforming products. AR 702-03.
The Army received six offers, including offers from Colt, Remington, and FN.
See AR 739-1478 (Colt’s proposal), 1479-1933 (FN’s proposal), 1934-2344
(Remington’s proposal). Colt was the original developer and owner and licensor of the
intellectual property for the M4 that was included in the solicitation’s Technical Data
Package (“TDP”). AR 2, 13.5
On July 22, 2015, the Source Selection Authority (“SSA”) approved a competitive
range that included only FN, Colt, and Remington. AR 3006-24. After discussions with
the CO about their proposals, each offeror was given the opportunity to submit a final
revision to its proposal. Colt and FN each responded that their proposals, which they had
amended with responses to the agency’s evaluation notices, were their final proposals.
AR 3097, AR 3263. Remington, in addition to incorporating its responses to the
evaluation notices, submitted a revised proposal which included an increased price on
August 18, 2015. AR 3273, AR 3274-98.
The proposals were evaluated and incorporated into the Source Selection
Evaluation Board (“SSEB”) Final Report. See AR 3300-86. Colt received an
“Outstanding” rating for the Production Capability factor, including “Outstanding”
ratings for the Manufacturing Plan and Key Tooling and Equipment sub-factors, and a
5
Under the terms of the solicitation other potential bidders would be provided the TDP and
would pay a royalty fee of five percent “if the item is manufactured by an entity other than Colt”
or its licensees. AR 20.
9
“Good” for the Quality Control sub-factor. AR 3317. Overall, Colt was listed as having
seven “Significant Strengths” and twelve “Strengths” in its Production Capability
proposal. Id. The evaluation for this factor noted Colt’s “extensive 20-plus year
background producing the Army’s M4 carbine” as well as the fact that a [xxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx]. AR 3318. Colt’s position as the “owner
and licensee of all non-Government owned M4[] technology and[] technical data”
allowed Colt’s proposal to “convey[] a deep knowledge of M4 production covering
virtually every aspect of the process.” Id. The risk of unsuccessful performance was
rated as “very low.” AR 3317.6
Remington received a “Good” rating for the Production Capability factor, with
“Good” ratings for all three sub-factors. AR 3336. The report listed Remington as
having two “Significant Strengths” and fifteen “Strengths.” Despite “Remington’s recent
2014 experience in producing up to 600 M4-type [R4A3] firearms daily for an
international military customer,” Remington did not have a “hot” production line that
would enable the Government to waive the FAT requirement. Id. Remington’s risk of
unsuccessful performance was rated as “low.” Id.
6
FN received an “Outstanding” rating for the Production Capability factor and had seven
“Significant Strengths” and eleven “Strengths.” AR 3327. The report noted that FN is
“currently producing US Army M4[] Carbines under Government contracts [xxxxxxx].” Id.
FN’s risk of unsuccessful performance was rated “very low.” Id.
10
For the Past Performance factor, both Colt and Remington received a rating of
“Satisfactory Confidence,” and FN received a higher “Substantial Confidence” rating.
AR 3347, 3367. The total evaluated price for Colt’s proposal placed just slightly over
$206 million. AR 3372. The total evaluated price for FN was at almost $219 million,
AR 3374, and the total evaluated price for Remington was almost $230 million, AR
3376.
B.
Colt’s Bankruptcy and the CO’s Responsibility Determination
On June 14, 2015, Colt filed for Chapter 11 bankruptcy protection. Pl.’s App’x
A1-50. According to Keith Maib, Colt’s Chief Restructuring Officer, Colt was suffering
“from an over-leveraged capital structure that has resulted in ongoing liquidity
constraints.” Id. at A209. Mr. Maib stated that during “the second half of 2014 the
Company continued to experience slow sales across all of its core business channels.” Id.
at A210. Colt also had a significant debt burden. Colt was a borrower under a $72.9
million term loan, a $35 million revolving loan and $250 million in 8.75% Senior Notes
maturing in 2017 (the “Senior Notes”). Id. at A209. The Senior Notes required annual
interest payments of $22 million, and were set to mature in 2017. Id. at A212. In Colt’s
Schedules of Assets and Liabilities, as amended, Colt identified owning only $5,027,406
in assets, while having aggregate liabilities of $384,839,567. See id. at A54. Colt
acknowledged in many of its filings and sworn statements submitted to the Bankruptcy
Court that it had been forced to borrow substantial amounts of money in the years
preceding the submission of its proposal for this contract, was highly leveraged and
facing severe liquidity issues. See, e.g. id. at A209, A226-27. As a result of the liquidity
11
problem combined with the high level of debt, Mr. Maib concluded that Colt “will not
survive protracted chapter 11 litigation and delay,” and determined that the “only other
alternative” to an expedited reorganization “is chapter 7 liquidation,” which would,
among other things, “curtail the critical delivery of weapons to military and law
enforcement agencies . . . .” Id. at A208. In this connection, Colt also was exploring the
viability of a bankruptcy 363 sale, in which a new owner would take over Colt’s assets.
This provision of the bankruptcy code envisions more money for creditors where a buyer
is willing to pay a premium to take over the bankrupt company without any debt. See 11
U.S.C. § 363.
In addition to Colt’s debt and liquidity problems, Colt’s lease on the West
Hartford facility, where Colt manufactured the bulk of its products and where it proposed
to manufacture the M4s if awarded the instant contract, was in jeopardy. The lease,
which was between Colt and the building’s owner, NPA Hartford, LLC (“NPA”), was set
to expire on October 25, 2015. Id. at A209-10. NPA was partially owned by Colt’s
equity sponsor, Sciens Capitol Management, LLC (“Sciens”), and during the bankruptcy
litigation, some of Colt’s creditors accused Sciens of using its ownership of NPA to
refuse extensions and modifications of the lease unless Sciens maintained its controlling
interest in Colt. Id. at A1567-A1568, A1652-A1653. According to a motion filed by the
creditors the loss of the lease would have meant Colt’s destruction: “Sciens was
threatening the [creditors] with the termination of the lease, and by extension, the
destruction of [Colt], if [the creditors] did not accept their proposed exchange offer that
left Sciens in control.” Id. at A294. The Agency entered into discussions on July 28,
12
2015, approximately six weeks after the Petition Date. AR 3436, 3044, 3142, 3203. As
of the date of the Notice of Award in September of 2015, the dispute regarding the
Facility Lease was ongoing. Pl.’s App’x A2307-A2327
As part of its evaluation, the Army directed the DCMA to conduct a pre-award
survey. See FAR § 9.106. The DCMA conducted a financial evaluation of each of the
three offerors in the competitive range, including Colt. The DCMA found Remington’s
and FN’s financial conditions to be satisfactory. AR 3481, 3506. However, the DCMA
issued a report on September 9, 2015, finding Colt’s “overall financial condition to be
unsatisfactory.” AR 3422. The DCMA found that as of July 5, 2015, Colt’s current
liabilities exceeded its current assets by $332.9 million. AR 3423. According to the
DCMA, this “working capital deficit” left Colt without assets sufficient to meet its thencurrent operational needs. Id. Further, the DCMA noted that Colt’s net profit margin
was -53% as of July 5, 2015 (up from -59.5% for fiscal year 2014). AR 3424.
Consequently, the DCMA concluded that Colt’s “overall financial risk [was] HIGH.”
AR 3422.
After receiving the DCMA report, the CO sent Colt the following list of questions
addressing Colt’s bankruptcy and the status of its lease negotiations:
I.
How will the entity Colt Defense, LLC change after a
363 sale, should one occur? Specifically:
1. Will it operate independently or even semiindependently from the other “Colt entities” or
from a new parent company?
2. What will be the extent of financial resources
available [related to contract]?
13
a.
b.
c.
What period of operation will these resources
cover?
What are Colt’s available lines of credit?
How would you characterize Colt’s working
capital?
3. Would the answers to the above questions be
different if it were a restructuring vs. a 363 sale? If
so, how and to what extent?
II.
Will the command and control structure, corporate
policies, procedures, and employees (corporate
experience) differ after if Colt is restructured? If so, to
what extent?
III. Lease Negotiations
1. What is the status of the ongoing lease
negotiations between Colt and the landlord of its
current facilities? In the event a new lease cannot
be renegotiated, how and to what extent, would
this affect Colt’s ability to produce?
2. What are Colt’s plans, if any, to relocate the
manufacturing line in the event the current lease
does not get renewed? How would this impact the
ability to perform on a potential M4 contract
award?
AR 3621. In her responsibility determination, the CO stated that on September 10, 2015,
she discussed the DCMA report with Colt’s management and asked them about the
possibility of a “material change in the entity ‘Colt Defense, LLC’ due to the anticipated
363 sale (either in corporate structure, management, premises, facilities or personel).”
AR 3613. According to the CO, in that conversation:
Colt assured the Government that part of the “core sale value
of Colt” was its relationship with the Government, including
current contracts and any anticipated future awards. As stated
in the [Reorganization Plan], Colt is very close to finalizing a
restructuring agreement (the Term Sheet) with the Board and
the Senior Noteholders, which would alleviate the need for a
14
Section 363 sale and would leave Colt in a positive cash
position with deleveraged debt. However, if that agreement is
not finalized by the Bankruptcy Court by September 30,
2015, it would be necessary to proceed with the Section 363
sale. But Colt emphasized that its intentions, whether through
reorganization or the Section 363 sale process, did not include
relocation of its manufacturing or other facilities or change in
senior management or workforce personnel. Colt did say that
if the Section 363 sale was consummated, any potential
changes with regards to personnel or facilities would depend
on the Buyer, and would require approval of the Bankruptcy
Court.
Id. Based on this conversation, the CO found that notwithstanding the negative
information in the DCMA report, Colt “does indeed possess the financial resources to
perform under the current contract, or will have the ability to obtain those resources.” Id.
The CO explained that the “DCMA report was based on information submitted before
Colt had submitted its bankruptcy petition” and so the DMCA report was out of date. AR
3614. The CO also noted that “Colt’s financial status is now being closely monitored by
the Bankruptcy Court.” Id.
With respect to Colt’s manufacturing facilities, the CO found that:
Colt currently has the production, construction, and technical
equipment and facilities for the manufacture of the M4A1
Carbines that are more than adequate to meet this
requirement. As of 09/22/2015 Colt is still in bankruptcy and
the proceedings were still pending. There was no decision
made by the landlord, NPA Hartford, LLC as to renewal of
the lease for the West Hartford facility; however, the current
lease has been extended to November 26, 2015. During the
teleconference with Colt management on 10 September 2015,
Colt reiterated that they had no intention of moving their
plant or hiring new people and they were very confident in
getting approval of their restructuring plan in a matter of
days.
15
Moreover, even if the restructuring plan is not approved and
Colt must be sold, multiple other parties have already
expressed an interest in purchasing Colt along with its
technical equipment and facilities. This is evidenced by the
United States Bankruptcy Court documents which indicate
the sale is due to take place in October, 2015 and instruments
have been filed by Offerors regarding their intent to bid.
In the event Colt were to relocate under a new entity the
schedule might be affected. The time it would take to obtain
facilities, install equipment, hire or relocate personnel, obtain
the necessary Preaward surveys and approvals of a new site
might adversely impact the schedule. Colt would be required
to pass First Article in time to meet the delivery schedule
which must begin within 365 days after award. However, as
of 09/18/2015 Colt is operating as debtor-in-possession in
Hartford, CT and has a reorganization plan (the Term Sheet)
that is due to be finalized 30 September 2015. The plan does
not include relocating Colt to any site other than the current
facility. Further, during my teleconference with Colt
leadership on 10 September 2015, they expressed to me that it
was very unlikely that a relocation would occur.
In light of the above, I have deemed Colt to have the
necessary production, construction, and technical equipment
and facilities, or the ability to obtain them.
AR 3619.
On September 23, 2015, the CO signed the Determination, finding that Colt was a
“Responsible Contractor.” AR 3620; see Dyda Decl. ¶ 8. On the basis of the SSEB final
report, the Source Selection Advisory Council (“SSAC” or “advisory council”), on
September 24, 2015, evaluated the proposals and recommended that the contracts be
awarded to Colt and FN, determining that they represented the best value to the
Government. AR 3400. The next day, the SSAC issued the Source Selection Decision
Document for the solicitation. AR 3401-12. The SSAC determined that there was “no
16
justification for the Government to pay Remington’s price premium of 11.5% over Colt’s
or 5.1% over FN’s” proposals. AR 3411. On September 25, 2015, Colt and FN were
selected to receive the contracts. AR 3636, 3722. Remington was informed that it was
not selected for an award. AR 3808-09. To date, two task orders for the minimum
required amounts of $10,000 each have been issued to FN and Colt. See AR 3637-3720
(Colt), AR 3723-3806 (FN).
After filing and then withdrawing a protest with the Government Accountability
Office, Remington filed this protest on November 24, 2015. On January 12, 2016, the
bankruptcy court approved Colt’s reorganization plan. The parties completed briefing on
their cross-motions on February 19, 2016. Oral argument was held on February 26, 2016.
III.
APPLICABLE STANDARDS
A.
Standard of Review for Bid Protests
This Court has jurisdiction to review post-award bid protests pursuant to the
Tucker Act, 28 U.S.C. § 1491(b). See Impresa Construzioni Geom. Domenico Garufi v.
United States, 238 F.3d 1324, 1330 (Fed. Cir. 2001). The court reviews the agency’s
decision pursuant to the standards set forth in the Administrative Procedures Act
(“APA”), 5 U.S.C. § 706. 28 U.S.C. § 1491(b)(4); see also Impresa, 238 F.3d at 1333
(noting that “the 1996 amendments to the Tucker Act require that [courts] apply the APA
standard of review”). Under 5 U.S.C. § 706(2), a court “shall . . . set aside agency action,
findings, and conclusions found to be . . . arbitrary, capricious, an abuse of discretion, or
otherwise not in accordance with law.” The Federal Circuit has stated that in a bid
protest, the court must determine whether “the government acted without rational basis or
17
contrary to law when evaluating the bids and awarding the contract.” Bannum, Inc. v.
United States, 404 F.3d 1346, 1351 (Fed. Cir. 2005). In this context, a “disappointed
bidder faces a heavy burden of showing that the award decision had no rational basis.”
Centech Group v. United States, 554 F.3d 1029, 1037 (Fed. Cir. 2009) (quoting Impresa,
238 F.3d at 1332-33). Agency action is irrational if the agency “entirely failed to
consider an important aspect of the problem, offered an explanation for its decision that
runs counter to the evidence before the agency, or is so implausible that it could not be
ascribed to a difference in view or the product of agency expertise.” Alabama Aircraft
Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir. 2009) (quoting
Motor Vehicle Mfrs. Ass’n of U.S. v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43
(1983)). With respect to responsibility determinations in particular, the Federal Circuit
has explained that “contracting officers are ‘generally given wide discretion’ in making
responsibility determinations and in determining the amount of information that is
required to make a responsibility determination.” Impresa, 238 F.3d at 1334-35. The
Federal Circuit has further stated that responsibility determinations are “complicated
business judgments” and that the court will not second guess them where there is
supporting evidence. Bender Shipbuilding & Repair Co. v. United States, 297 F.3d 1358,
1362 (Fed. Cir. 2002).
B.
Prejudice and Standing
The court will first address the government’s argument that Remington was not
prejudiced because there was no guarantee that the contract would be awarded to two
18
bidders, and Remington is not challenging the award of the contract to FN.7 In order to
prevail in a post-award bid protest, the protestor “must first show that it was prejudiced
by a significant error in the procurement process.” Labatt Food Serv., Inc. v. United
States, 577 F.3d 1375, 1378 (Fed. Cir. 2009) (quoting JWK Int’l Corp. v. United States,
279 F.3d 985, 988 (Fed. Cir. 2002)). A party is “prejudiced when it can show that but for
the error, it would have had a substantial chance of securing the contract.” Id. (citing
Bannum, 404 F.3d at 1358). In evaluating prejudice to the unsuccessful offeror, the court
must “make factual findings from the record evidence as if it were conducting a trial on
the record.” Bannum, 404 F.3d at 1354; see id. at 1357 (explaining that the “trial court’s
factual determination on prejudice . . . is entitled to review for clear error”).
According to the government, because FN’s proposal was superior to Remington’s
in a number of respects, Remington could not show it would have been awarded a second
contract in Colt’s place even if Colt had been eliminated. The government further argues
that because the Solicitation was for an IDIQ contract that contemplated the two
awardees competing for work orders beyond the minimum order, Remington cannot
demonstrate prejudice even if it were awarded a contract because FN, which had
submitted a lower price, would likely receive the subsequent orders.
7
Though the government presented the prejudice issue as a secondary argument, the court is
obliged to address it first because an argument that a party was not prejudiced is an attack on that
party’s standing, thus implicating the court’s jurisdiction. See Info. Tech. & Applications Corp.
v. United States, 316 F.3d 1312, 1319 (Fed. Cir. 2003) (finding that “because the question of
prejudice goes directly to the question of standing, the prejudice issue must be reached before
addressing the merits.”)
19
The court disagrees with the government, and finds that Remington has
demonstrated that it had a “substantial chance” of securing the contract absent the alleged
error in the procurement process. In this case, the competitive range was limited to three
bidders—Remington, Colt, and FN—and two of the three bidders were awarded the
contract. The Federal Circuit has found that a protestor had standing where, as here, the
protestor finished directly behind the awardee in the evaluation. See Galen Med. Assocs.
Inc. v. United States, 369 F.3d 1324, 1331 (Fed. Cir. 2004). This case is therefore
distinguishable from Linc Government Services v. United States, 96 Fed. Cl. 672 (2010),
upon which the government relies. In Linc, the court found that a protestor would lack
standing if there would still be six offerors more highly rated than the protestor but for
the alleged error. Id. at 722-23. By contrast, in this case, only FN and Remington would
have remained in the competitive range had Colt been eliminated.
Though the government is correct that the solicitation did not explicitly guarantee
that two contracts would be awarded, the agency’s intent to award two contracts is
evident from the structure of the contract (for example, the solicitation contemplated that
two awardees would compete with each other for subsequent orders), and the fact that
two contracts were in fact awarded. If the court accepted the government’s argument, a
protestor’s burden would rise from showing a substantial chance success to showing a
near certainty receiving the award, a standard the Federal Circuit has explicitly rejected.
Data Gen. Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed. Cir. 1996) (finding that a protestor
need not show it would have been awarded the contract but for the alleged error because
“[s]uch a rule would make it virtually impossible for a protester ever to prevail . . . .”).
20
The court also disagrees with the government’s assertion that Remington was not
prejudiced even if it had a substantial chance of being awarded a contract because there
was no guarantee that it would receive any delivery orders beyond the minimum $10,000
order. As an initial matter, the government does not cite any case law supporting its
implication that a $10,000 order would be insufficient to support standing. Further, the
Federal Circuit has stated that the prejudice inquiry is focused on whether the protestor
had a “substantial chance of securing the contract,” Lebatt, 577 F.3d at 1379 (emphasis
added), not subsequent delivery orders.8 This court declines the government’s invitation
to add additional requirements to the threshold issue of standing beyond what the Federal
Circuit has prescribed.9 The court therefore concludes that Remington has established
standing.
IV.
DISCUSSION
A.
The CO’s Responsibility Determination is not Supported by the
Record.
It is well-settled that a contract may be awarded to only responsible offerors. 48
C.F.R. § 9.103(a); see Bender Shipbuilding, 297 F.3d at 1361. Thus, before awarding
any contract, the CO must “make[] an affirmative determination of responsibility.”
Bender Shipbuilding, 297 F.3d at 1361 (quoting 48 C.F.R. § 9.103(b)). The fact that Colt
8
Remington asserts that the government’s argument would “preclude a post award protest any
time the contract at issue is a multiple award IDIQ.” Remington Reply 25.
9
Further, the government’s assertion that FN would have filled all of the delivery orders had FN
and Remington been awarded the contract appears to be in tension with the government’s
argument against Remington’s request for an injunction. In objecting to any grant of injunctive
relief, the government argues that it would be harmed if only FN were able to fill the agency’s
orders.
21
was in bankruptcy is not determinative in this case. As Remington acknowledges, the
Federal Circuit found in Bender Shipbuilding that the pendency of a bankruptcy
proceeding does not preclude a responsibility finding. Remington argues, however, that
this case is distinguishable from others where the responsibility determination was
upheld, primarily because at the time the responsibility determination was made it was
not certain whether Colt would be reorganized, sold, or even liquidated. Colt’s lease
arrangement, and thus production capability, was also uncertain. Remington argues that
the CO failed to adequately address how Colt could be responsible in such circumstance.
Remington concludes that the CO therefore had no rational basis for concluding that Colt
could perform the contract.
The government and Colt argue that the CO carefully considered Colt’s financial
status and did not ignore negative information and that the CO rationally determined
based on the information she received from Colt’s management and from the bankruptcy
filings that Colt was financially capable and would have access to the facilities it needed
to perform the contract.
For the reasons that follow, the court finds that the CO’s finding that Colt had the
necessary production capability to perform the contract at the time she made her
responsibility determination is not supported by the record. First, the court finds that the
CO’s stated reasons for disregarding the DCMA report were insufficient in light of the
bankruptcy court record before the CO. The CO stated that the DCMA report was based
on old information, and that she had discussed Colt’s current situation with Colt’s
management. See AR 3614. In explaining why she diverged from the DCMA report, the
22
CO noted that “Colt’s financial status is now being closely monitored by the Bankruptcy
Court.” Id. But the fact that Colt’s status was monitored does not mean that the
bankruptcy court would or could ensure Colt’s continued viability, which the record in
the bankruptcy court demonstrates was highly in doubt at the time of the responsibility
determination. Nor does the CO explain how any more recent data would have altered
the DCMA’s conclusion based upon supposedly out of date information.
During the CO’s September 10, 2015 call with Colt’s management, Colt
represented to the CO that it was “very close” to reaching agreement on a restructuring
plan that would allow it to exit bankruptcy. AR 3613. Colt cautioned that such a deal
would have to be consummated by September 30, 2015. Id. The CO signed the
responsibility determination on September 23, 2015, thirteen days after that telephone
conversation. AR 3620. By this time, the deadline for finding a 363 buyer had expired,
no buyer had come forward, and no restructuring deal was in place. See Pl.’s App’x
A2219; A2517.10 Indeed, at that time the parties to the bankruptcy case were embroiled
in litigation. Id. at A2301-A2327. The CO states that she reviewed all of the filings in
the Bankruptcy Case. Dyda Decl. ¶ 3.a. Thus, she knew, or should have known, that the
bankruptcy outcome was uncertain. In light of these facts, the court finds that it was not
10
As of the date of the Responsibility Determination, approximately six weeks after the filing of
the declaration upon which the CO relied, Sciens, the one buyer, had withdrawn it bid. Id. at
A2516. Colt had a deadline of September 21, 2015 to find a replacement for Sciens. Id. at
A2219. That deadline had passed and no replacement had been identified. Ultimately, the sale
process failed because Colt did not receive a qualified offer. See id. at A2517. While the sale
process had not yet formally collapsed on September 23, 2015, the proceedings in the
Bankruptcy Case as of that date made clear that it had stalled. Colt was then faced the protracted
Chapter 11 proceedings that Mr. Maib had described as unsustainable.
23
reasonable for the CO to rely only on Colt’s representations to support her conclusion
that Colt was financially able to perform the contract. The self-serving comments from
Colt’s own employees were not consistent with the facts identified in the bankruptcy
court records.
In addition, and equally importantly, the CO’s conclusions regarding Colt’s ability
to manufacture M4s at its West Hartford facility are also unsupported. The lease on the
Hartford facility was unresolved and the subject of litigation at the time she issued her
responsibility determination. Though Colt informed the CO that it intended to stay in the
facility, the bankruptcy record shows that that decision did not appear to be within Colt’s
control. The CO’s determination did not mention the fact that Colt’s creditors had
accused Colt's landlord of using control over the West Hartford Facility as a means of
maximizing its claims in the bankruptcy case and that Colt’s ability to stay at the facility
was uncertain. See Pl.’s App’x A1652-53.
It is for these reasons that the government and Colt’s reliance on Bender
Shipbuilding to support their contention that Colt's bankruptcy did not bar a
responsibility finding is misplaced. The facts of this case differ sharply from Bender
Shipbuilding, in which the Federal Circuit found that the CO’s responsibility
determination was based on ample evidence in the record to show that the company was
financially able to perform. In Bender Shipbuilding, the CO relied upon a DCMA report
finding that the awardee “has satisfactorily demonstrated the requisite financial
capabilities necessary for performance.” Bender Shipbuilding, 297 F.3d at 1361. The
CO also considered the fact that the awardee’s parent company had guaranteed the
24
awardee’s performance, and reports and surveys stating that the awardee would acquire
the necessary capital from the parent company’s sale of another subsidiary. Id. at 1362.
In this case, Colt could not give the CO any comparable assurances. Instead, the CO
relied on Colt’s stated expectations of how and when the bankruptcy proceedings would
be resolved without undertaking an investigation into the reasonableness of those
expectations. Under these circumstances, the court finds that the CO’s decision to take
Colt’s word that the lease situation would shortly be resolved and that Colt would emerge
largely intact from bankruptcy, when those statements were largely contradicted by
Colt’s filings in the bankruptcy case, was arbitrary and capricious. See Alabama Aircraft,
586 F.3d at 1375 (agency action is arbitrary and capricious when the agency “offered an
explanation for its decision that runs counter to the evidence before the agency . . . .”).
Colt has argued that because it has now exited bankruptcy, and has entered into a
long-term lease for the West Hartford facility, the case is moot. However, Remington’s
protest was not limited to the fact that Colt was in bankruptcy, but challenged the CO’s
evaluation of the precarious financial situation that led Colt to file for bankruptcy in the
first place. Though Colt has emerged from bankruptcy, the Disclosure Statement
attached to its Second Amended Joint Plan for Reorganization contains approximately
thirty pages of acknowledged risks to Colt’s creditors, including substantial indebtedness.
Pl.’s App’x 2600-2631. The CO has not yet evaluated these risks, and as such the court
has determined that the case is not moot. Nor does the fact that the army has placed an
initial order with Colt render the case moot, because the agency anticipates issuing
25
additional task orders in the future. See Furniture by Thurston v. United States, 103 Fed.
Cl. 505, 515 (2012).
B.
Colt’s Technical Evaluation was Not Arbitrary, Capricious, or an
Abuse of Discretion.
Remington also argues that the agency’s technical evaluation of Colt was
arbitrary, capricious, and an abuse of discretion because the Army failed to take into
account Colt’s financial status and the precarious nature of the West Hartford facility
lease. The government argues that the technical evaluation was properly performed by
technical specialists and that they properly limited their evaluation to a review of Colt’s
manufacturing capabilities as proposed in Colt’s bid.
The court agrees with the government and finds that Colt’s financial status and
lease issues are properly considered as part of the responsibility determination and should
not be evaluated as part of a technical evaluation. The agency’s technical evaluation
under the Production Capability factor and the Key Tooling and Equipment subfactor was
properly focused on technical matters such as “the Offeror’s proposed assembly line,”
“weapon and ammunition storage facilities,” and “[l]ong lead items,” and sub-factors
such as “the capability of the key tooling and equipment.” AR 3308-09. In contrast,
financial considerations such as whether Colt would still have access to its proposed
manufacturing location are properly evaluated as part of the CO’s responsibility
determination. The solicitation plainly states that the Production Capability subfactors
were to be based on the “proposed production facility” and did not include an evaluation
of the availability of that facility. AR 3307-09. The Army was limited to these criteria
26
and could not judge Colt’s technical proposal based on other criteria. See FAR §
15.305(a) (proposals are to be evaluated “solely on the factors and subfactors specified in
the solicitation”). Consequently, Remington’s motion for judgment on the administrative
record with regard to the government’s technical evaluation must be rejected.
V.
INJUNCTIVE RELIEF
Having concluded that the government’s responsibility determination cannot be
sustained, the court now turns to whether injunctive relief is appropriate and, if so, the
scope of such relief. This court “may award any relief that the court considers proper,
including declaratory and injunctive relief except that any monetary relief shall be limited
to bid preparation and proposal costs.” 28 U.S.C. § 1491(b)(2). In deciding whether to
grant permanent injunctive relief, a court considers whether: “(1) the plaintiff has
succeeded on the merits, (2) the plaintiff will suffer irreparable harm if the court
withholds injunctive relief, (3) the balance of hardships to the respective parties favors
the grant of injunctive relief, and (4) the public interest is served by a grant of injunctive
relief.” Centech Grp., Inc. v. United States, 554 F.3d 1029, 1037 (Fed. Cir. 2009) (citing
PGBA, LLC v. United States, 389 F.3d 1219, 1228-29 (Fed. Cir. 2004)). In this case, the
plaintiffs have succeeded on the merits. Therefore, the court must consider whether they
will suffer irreparable harm if the court withholds injunctive relief, whether the balance
of hardships to the respective parties favors the grant of injunctive relief, and whether the
public interest is served by a grant of injunctive relief.
After considering the equities of the parties, the court concludes that the equities
balance in favor of issuing an injunction. Remington has established that it has been
27
irreparably harmed by the government’s failure to prepare a supported responsibility
determination. “When assessing irreparable injury, ‘[t]he relevant inquiry . . . is whether
plaintiff has an adequate remedy in the absence of an injunction.’” PGBA, LLC v.
United States, 57 Fed. Cl. 655, 664 (2003) (quoting Magellan Corp. v. United States,
27 Fed. Cl. 446, 447 (1993)). The government does not suggest alternative remedies for
the plaintiff and courts have found that the “loss of potential work and profits from a
government contract constitutes irreparable harm.” Springfield Parcel C, LLC v. United
States, 124 Fed. Cl. 163, 194 (2015) (citations omitted). The record shows that, but for
the responsibility determination, Remington would have a substantial chance at the award
as the one of three offerors to make the competitive range. This court has found
irreparable injury in similar circumstances. See KWR Constr., Inc. v. United States, 124
Fed. Cl. 345, 362-63 (2015); Caddell Constr. Co. v. United States, 111 Fed. Cl. 49, 11516 (2013); CW Gov’t Travel, Inc. v. United States, 110 Fed. Cl. 462, 495 (2013).
The record further shows that the government has indicated that it will not be
harmed by a limited injunction to allow for a proper responsibility evaluation because FN
is capable of fulfilling the government’s needs. Dyda Decl. ¶ 9 (“If Colt was found not
responsible or otherwise eliminate from competing for the award, the whole contract
production could be absorbed by FN . . . .”). Thus, the court finds that the government
will not be prejudiced by a limited injunction. The court further finds that the public
interest supports injunctive relief as well. Where, as here, the government has awarded a
contract to a party in bankruptcy without fully analyzing its ability to perform, the public
28
interest is served in either ensuring that Colt can produce the M4s or that another
company be awarded a second contract if necessary.
The court will therefore enjoin the government from awarding any new task orders
to Colt for 30 days or until the agency has performed a new responsibility determination
that addresses Colt’s current financial status and submitted that new determination, and
award decision, if appropriate, to the court. This approach is similar to the
recommendation of the Defense Contract Audit Agency (“DCAA”) in Bender
Shipbuilding, 297 F.3d at 1361. In that case, the DCAA found that the awardee, despite
filing for Chapter 11 bankruptcy, “had sufficient financial capability to perform the base
year, but recommended that another survey be made at the end of the base year before
awarding a contract for any of the option years.” Id. The court finds that this option best
balances the interests of the parties and the public and is most likely to result in a speedy
resolution of this matter.
VI.
CONCLUSION
For the reasons stated above, Remington’s motion to supplement the
administrative record is GRANTED. Remington’s motion judgment on the
administrative record is GRANTED IN PART AND DENIED IN PART. The case is
REMANDED for re-evaluation consistent with this opinion. Further, the government is
enjoined from awarding additional task orders to Colt until a new responsibility
determination based on the most up-to-date financial information is complete and
submitted to the court. The government shall submit a status report on Monday, April
25, 2016 updating the court on its revised responsibility determination.
29
IT IS SO ORDERED.
s/Nancy B. Firestone
NANCY B. FIRESTONE
Senior Judge
30
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?