WALLACE ASSET MANAGEMENT, LLC v. USA
Filing
30
REDACTED MEMORANDUM OPINION AND ORDER denying plaintiff's motions for a temporary restraining order and for a preliminary injunction. Signed by Judge Lydia Kay Griggsby. (lh) Copy to parties.
In the United States Court of Federal Claims
BID PROTEST
No. 15-1527C
Filed Under Seal: January 13, 2016
Reissued for Publication: April 20, 2016*
WALLACE ASSET MANAGEMENT,
LLC,
Plaintiff,
v.
THE UNITED STATES,
Defendant,
v.
BLM COMPANIES, LLC,
Defendant-Intervenor.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
The Tucker Act, 28 U.S.C. § 1491(b)(1);
28 U.S.C. § 1491(b)(2); Post-Award Bid
Protest; Motion for a Temporary
Restraining Order; Motion for a
Preliminary Injunction; RCFC 65.
James Stephen DelSordo, Counsel of Record, Argus Legal, LLC, Manassas, VA, for
plaintiff.
Agatha Koprowski, Trial Attorney, Douglas Mickle, Jr., Assistant Director, Robert E.
Kirschman, Jr., Director, Benjamin C. Mizer, Principal Deputy Assistant Attorney General,
Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington,
DC, for defendant.
Douglas Paul Hibshman, Counsel of Record, Fox Rothschild, LLP, Washington, DC, for
defendant-intervenor.
*
This Memorandum Opinion and Order was originally filed under seal on January 13, 2016 (docket entry
20), pursuant to the protective order entered in this action on December 17, 2015 (docket entry 11). The
parties were given an opportunity to advise the Court of their views with respect to what information, if any,
should be redacted under the terms of the protective order. The parties filed a joint status report on February
5, 2016 (docket entry 24) proposing certain redactions which the Court has adopted. Accordingly, the Court
is reissuing its Opinion and Order dated January 13, 2016, with the agreed redactions indicated by three
consecutive asterisks within brackets ([***]).
MEMORANDUM OPINION AND ORDER
DENYING PLAINTIFF’S MOTIONS FOR A TEMPORARY
RESTRAINING ORDER AND FOR A PRELIMINARY INJUNCTION
GRIGGSBY, Judge
I.
INTRODUCTION
Plaintiff, Wallace Asset Management, LLC, brought this post-award bid protest matter
challenging the decision of the United States Department of Housing and Urban Development to
award five contracts to provide field service management services to BLM Companies, LLC.
Wallace has filed motions for a temporary restraining order and for a preliminary injunction
requesting that the Court enjoin BLM from commencing performance under the contracts. For the
reasons set forth below, the Court DENIES Wallace’s motions for a temporary restraining order
and for a preliminary injunction.
II.
FACTUAL AND PROCEDURAL BACKGROUND1
A. Factual Background
The relevant facts in this case are not in dispute. Plaintiff, Wallace Asset Management, LLC
(“Wallace”), is a disappointed offeror in connection with the award of several government contracts
to provide field service management (“FSM”) services for the United States Department of Housing
and Urban Development (“HUD”). See generally Compl. Wallace has brought this bid protest
action challenging HUD’s August 27, 2015 and September 28, 2015 decisions to award these
contracts to BLM Companies, LLC (“BLM”). A374-75. In this action, Wallace seeks to, among
other things, enjoin BLM from commencing performance under the subject contracts until this
matter is resolved. See Pl. Mot. for TRO at 1-2; Pl. Mot. at 2.
The facts recited in this Memorandum Opinion and Order are taken from plaintiff’s complaint (Compl. at
__”); plaintiff’s motion for a temporary restraining order (“Pl. Mot. for TRO at _”); plaintiff’s motion for a
preliminary injunction (“Pl. Mot. at __”); plaintiff’s memorandum in support of its motion for a preliminary
injunction (“Pl. Mem. at __”); defendant’s response and opposition to plaintiff’s motion for a temporary
restraining order (“Def. Resp. at __”); defendant’s appendix to its response (“A__” or “Def. Appendix”); and
plaintiff’s reply in support of its motion for a temporary restraining order (“Pl. Reply at __”). Except where
otherwise noted, the facts cited herein are undisputed.
1
2
1.
The Request For Proposals
The Federal Housing Administration (“FHA”), a division of HUD, “insures approved
lenders against the risk of loss on mortgages obtained with FHA financing.” A99. If there is a
default on a mortgage, the mortgage lender may reclaim the property, file a claim for insurance
benefits, and convey the property to HUD. Id. HUD manages the conveyed property for eventual
sale. Id. HUD contracts for the maintenance of these properties via FSM contracts. Id.
Contractors performing FSM contracts “provide property maintenance and preservation services,”
including “inspecting the property, securing the property, performing cosmetic
enhancements/repairs, and providing on-going maintenance.” A102.
On May 22, 2014, HUD issued Request for Proposals No. DU204SA-13-R-0004 (“RFP”) to
provide FSM services in eight different geographic areas located across the United States. A72;
A84; A258. Under the terms of the RFP, HUD would award one indefinite-delivery, indefinitequantity contract, consisting of one base year and four option years, in each of the eight geographic
areas. A72; A87; A396.
Wallace and BLM both submitted proposals for FSM contracts in five of the eight
geographic areas covered by the RFP. A284; A292; A320; A325; A334. Namely, Wallace and
BLM submitted proposals in area 1D, encompassing Utah, Colorado, New Mexico, and Northern
Texas; area 1P, encompassing Michigan; area 3P, encompassing Maine, Vermont, New York, New
Hampshire, Rhode Island, New Jersey, Massachusetts, and Connecticut; area 4P encompassing
Ohio; and area 5P, encompassing West Virginia, Virginia, Delaware, Maryland, and the District of
Columbia. Id.; A373-75. In addition, BLM submitted proposals for FSM contracts in the
remaining three areas not at issue in this case. See A286; A288; A290. Several other contractors
also submitted proposals in response to the RFP. A284; A286; A288; A290; A292; A320; A325;
A334.
The RFP provided that the government would conduct the solicitation using a Performance
Price Trade-Off (“PPT”) methodology. A248. Under the RFP, technical approach would be
evaluated on a pass/fail basis. Id. If an offeror’s proposal was deemed technically acceptable, HUD
would then evaluate offerors’ past/present performance and price. Id. The RFP provided that the
past/present performance and price factors were of equal value. Id.
3
a.
Technical Approach
With respect to the technical approach factor under the RFP, HUD rated the proposals
submitted by Wallace and BLM as technically acceptable. A292; A295; A320; A325; A334. And
so, both proposals advanced to the next round of the evaluation. Id.
b.
Past/Present Performance
With respect to the past/present performance factor, the RFP required that offerors submit
information about their past or present performance on other contracts for field management
services. A11-12; A374. Alternatively, in the event that an offeror did not have any relevant past
contract experience, the RFP provided that:
Offerors or joint venture partners that either have no prior contracts or do not possess
relevant corporate Past/Present Performance, but have key personnel with relevant
past performance while employed by another company(s), may demonstrate the
performance of such key personnel by submitting the names, letter of commitment and
summary sheets for three of the most recent and relevant contracts under which such
key personnel performed the same role currently being proposed on the instant
acquisition.
A12.
Wallace addressed the past/present performance factor in each of its proposals by
identifying three past efforts related to FSM services and also proposing at least five key personnel
who worked for other FSM contractors. A341-3; A367-70. HUD determined that the three past
efforts identified by Wallace were not relevant and, thus, rated Wallace as neutral/unknown
confidence. A296; A317; A321; A326; A335; A341. Specifically, HUD determined that the first
effort was not relevant because Wallace failed to provide the volume of properties that Wallace
managed under the contract. A341; A367; A369. HUD also found that the two other efforts cited
by Wallace “did not meet the scope of work requirement of the solicitation.” A367; A369. In
addition, HUD determined that Wallace had failed to specify which key personnel with relevant
experience would be committed to a particular contract area. A380. And so, HUD concluded that
the past/present performance of the five key personnel was also not relevant and rated Wallace’s
proposal with respect to this factor as neutral/unknown confidence. A296; A317; A321; A326;
A335; A341; A380.
BLM addressed the past/present performance factor in its proposal by submitting three past
subcontracting efforts. A264-66. For each of the five areas at issue, HUD determined BLM had
“successfully performed most of the scope of this solicitation through 3 efforts as a subcontractor on
4
3 FSM contracts with superior ratings throughout the service period in the areas of Quality of
Product, Schedule, Cost, Business Relations, and Management of Key Personnel.” Id. And so,
HUD rated BLM’s proposal with respect to the past/present performance factor as good/significant
confidence. A296; A316; A321; A326; A335.
c.
Price
Lastly, with respect to the price factor, Wallace’s proposed price was higher than BLM’s
proposed price for each of the five FSM contracts in dispute. A295; A292; A320; A325; A334. For
area 1D, BLM’s proposed price was $112,969,979.00, whereas Wallace’s proposed price was
$192,453,895.00. A295. For area 1P, BLM’s proposed price was $73,262,899.00, and Wallace’s
proposed price was $86,762,390.00. A334. For area 3P, BLM’s proposed price was
$46,622,975.00. A292; A316. Wallace’s proposed price was $58,525,100.00. Id. For area 4P,
BLM’s proposed price was $61,375,629.00, whereas Wallace’s proposed price was $91,030,480.00.
A320-21. For area 5P, BLM’s proposed price was $83,733,750.00, and Wallace’s proposed price
was $124,707,630.00. A325.
In addition, for the contracts for areas 1D, 3P, 4P, and 5P, at least one other offeror–other
than BLM–had a technically acceptable, lower-priced proposal than Wallace, and received a
good/significant confidence rating for the past/present performance factor. A292; A295-96; A31617; A320-21; A325-26; A334-35.
2.
Award Of The Contracts
On August 6, 2015, HUD’s Source Selection Authority issued Source Selection Decisions
for the contracts for areas 1D and 3P, recommending that HUD award these contracts to BLM.
A294-98; A315-18. In its Source Selection Decision for the contract for area 1D, HUD’s Source
Selection Decision provides that:
The TEP [Technical Evaluation Panel] is proposing award to candidate, BLM
Companies, LLC, with the highest confidence rating and the second lowest contract
cost of $112,969,979.00. BLM Companies, LLC’s Present/Past Performance involved
the same scope, magnitude and complexity of work required in the solicitation
resulting in a rating of Good/Significant Confidence. BLM Companies, LLC’s overall
quality of services, scheduling, cost, business relations and management of key
personnel was rated excellent. BLM Companies, LLC’s Technical Approach was
rated Acceptable, which illustrates their abilities to manage, maintain, and/or preserve
HUD-owned properties. The TEP believes that the verified past performance of BLM
Companies, LLC with a good confidence rating is worth a higher price than the
5
unknown confidence of [***] at a lower price. There is reasonable expectation that
BLM Companies, LLC can successfully perform the services and the price differences
is not worth the risk of awarding to [***] where no confidence rating could be
reasonably assigned.
A297. With respect to the contract for area 3P, HUD’s Source Selection Decision provides
that:
The TEP is proposing award to candidate, BLM Companies, LLC, with an Acceptable
Technical Approach and Good/Significant Confidence rating and the third lowest
contract cost of acceptable offerors at a cost of $46,622,975. BLM Companies, LLC’s
overall past performance in the quality of service, scheduling, cost, business relations
and management of key personnel is rated good. BLM Companies, LLC’s
performance involved the scope, magnitude and complexity required in the solicitation
and based on this opinion, the offeror was rated “Good/Significant Confidence”
overall. The TEP believes that the verified past performance of BLM Companies,
LLC with a good confidence rating, is worth a higher price than the unknown
confidence of [***] and [***] at a lower price. There is reasonable expectation that
BLM Companies, LLC can successfully perform the services and the price difference
is not worth the risk of awarding to [***] or [***], where no confidence rating could
be reasonably assigned.
A317.
On August 26, 2015, HUD’s Source Selection Authority issued Source Selection Decisions
for the contracts for areas 4P and 5P, recommending that HUD award these contracts to BLM.
A319-23; A324-28. With respect to the contract for area 4P, HUD’s Source Selection Decision
provides that:
The TEP is proposing award to candidate, BLM Companies, LLC, with an Acceptable
Technical Approach and Good/Significant Confidence rating and at a cost of
$$61,375,629.00 [sic]. BLM Companies, LLC’s overall past performance in the
quality of service, scheduling, cost, business relations and management of key
personnel is rated good. BLM Companies, LLC’s performance involved the scope,
magnitude and complexity required in the solicitation and based on this opinion, the
offeror was rated “Good/Significant Confidence” overall. The TEP believes that the
verified past performance of BLM Companies, LLC with a good confidence rating, is
worth a higher price than the unknown confidence of [***] at a lower price. There is
reasonable expectation that BLM Companies, LLC can successfully perform the
services and the price difference is not worth the risk of awarding to [***] where no
confidence rating could be reasonably assigned.
A322. With respect to the contract for area 5P, HUD’s Source Selection Decision provides
that:
6
The TEP is proposing award to candidate, BLM Companies, LLC, with an Acceptable
Technical Approach and Good/Significant Confidence rating and at a cost of
$83,733,750.00. BLM Companies, LLC’s overall past performance in the quality of
service, scheduling, cost, business relations and management of key personnel is rated
good. BLM Companies, LLC’s performance involved the scope, magnitude and
complexity required in the solicitation and based on this opinion, the offeror was rated
“Good/Significant Confidence” overall. The TEP believes that the verified past
performance of BLM Companies, LLC with a good confidence rating, is worth a
higher price than the unknown confidence of [***] at a lower price. There is
reasonable expectation that BLM Companies, LLC can successfully perform the
services and the price difference is not worth the risk of awarding to [***] where no
confidence rating could be reasonably assigned.
A327.
Finally, on September 15, 2015, HUD’s Source Selection Authority issued a Source
Selection Decision for the contract for area 1P, also recommending that HUD award this contract to
BLM. A333-36. In its Source Selection Decision for the contract for area 1P, HUD’s Source
Selection Decision provides that:
The TEP is proposing award to candidate BLM Companies, LLC with an Acceptable
Technical Approach, Good/Significant Confidence rating and at a cost of
$73, 262,899.00 [sic]. BLM Companies, LLC’s overall past performance in the
quality of service, scheduling, cost, business relations and management of key
personnel is rated good. BLM Companies, LLC’s performance involved the scope,
magnitude, and the complexity required in the solicitation and based on this opinion,
the offeror was rated “Good/Significant Confidence” overall. BLM Companies, LLC
has a good history in servicing and managing REO properties as a subcontractor. The
TEP believes that the verified past performance of BLM Companies, LLC with a good
confidence rating is worth a higher price than the unknown confidence of [***] at a
lower price. There is reasonable expectation that BLM Companies, LLC can
successfully perform the services and the price difference is not worth the risk of
awarding to [***] where no confidence rating could be reasonably assigned.
A335-36.
On August 27, 2015, HUD awarded the FSM contract for area 3P to BLM.2 A374-75.
Subsequently, on September 28, 2015, HUD awarded the FSM contracts for areas 1D, 1P, 4P, and
5P to BLM. A375.
2
HUD previously awarded the FSM contracts for all eight of the geographical areas addressed under the RFP
on September 30, 2014. A374. The agency subsequently took corrective action by reevaluating the
proposals and making new source selection decisions. Id.
7
The contracts at issue have a “Start-Up” phase, a “Ramp-Up” phase, and a final phase,
wherein the transition period ends and the awardee assumes all new inventory under the contract.
A149-51. BLM is currently performing in the “Ramp-Up” phase of the contract. Def. Resp. at 20.
BLM was scheduled to begin assuming new inventory under the contract on January 1, 2016.
Status Report, Dec. 31, 2015. On December 31, 2015, defendant filed a status report informing the
Court that HUD voluntarily stayed BLM’s performance until January 31, 2016 and extended the
incumbent contracts until that time. Id. The government states that this additional time is needed
for BLM to complete transition on the contracts. Id.
3.
Wallace’s GAO Bid Protests
On October 14, 2014, Wallace filed a protest before the United States Government
Accountability Office (“GAO”) challenging a prior decision by HUD to award the FSM contract for
area 3P to BLM. A374. HUD subsequently informed the GAO that the agency intended to take
corrective action with respect to the award of the FSM contract for area 3P, and the GAO dismissed
the protest. A374.
On September 10, 2015, Wallace filed another protest at the GAO challenging HUD’s
August 27, 2015 decision to award the FSM contract for area 3P to BLM. A374-75. In that protest,
Wallace argued that BLM was not qualified or eligible to receive the contract award and that HUD
improperly rated the past performance factor in Wallace’s proposal. A375. Following HUD’s
decision to award FSM contracts for areas 1D, 1P, 4P, and 5P to BLM, Wallace filed a
supplemental protest before the GAO challenging HUD’s award decision for area 5P based upon
the same or similar grounds as its prior bid protests. A375.
The GAO dismissed Wallace’s protests on December 9, 2015. A396-98. In the dismissal
decision, the GAO held that Wallace was not an interested party with respect to 3P and 5P because
“there is no reasonable likelihood that Wallace would be next in line for award of either of the
protested contracts.” A396. In this regard, the GAO found that “it is reasonable to conclude that at
least one, and very likely several, offerors would have been considered for award ahead of
Wallace.” A397. With respect to Wallace’s challenge of its rating for the past/present performance
factor, the GAO further held that “while Wallace argues that it should have received a
good/significant confidence rating based on an assessment of its key personnel experience under the
past/present performance factor, our review does not support such a conclusion.” Id. And so, the
GAO dismissed the protest. A396-98.
8
4.
Organizational Conflict Of Interest
Lastly, the RFP for the subject FSM contracts prohibits contractors from performing preconveyance work on FHA Single Family Insured properties. A125. Wallace alleges that BLM
performed pre-conveyance work in Pennsylvania and New Jersey. Compl. at 6. HUD conducted an
investigation into whether BLM had performed pre-conveyance work in any of the performance
areas. A371. In connection with that investigation, HUD sought information from BLM and
consulted with HUD employees regarding any pre-conveyance work done by BLM in the areas it
received contracts. Id. HUD ultimately determined BLM had not performed pre-conveyance work
in any areas in which BLM received FSM awards, including Pennsylvania and New Jersey. Id.
B. Procedural Background
Wallace filed its complaint in this matter on December 15, 2015. See generally Compl. On
that same day, Wallace filed motions for a temporary restraining order and for a preliminary
injunction. See generally Pl. Mot for TRO; Pl. Mot. In both motions for emergency injunctive
relief, Wallace requests that the Court enjoin BLM from commencing performance under the
contracts. Id.
On December 16, 2015, BLM filed a motion to intervene. Mot. to Intervene. On December
17, 2015, the Court issued a Scheduling Order setting forth the briefing schedule for plaintiff’s
motions for emergency injunctive relief and granting BLM’s motion to intervene. Order, Dec. 17,
2015. On the same day, the Court issued a Protective Order. See Protective Order. On December
18, 2015, the government filed its response and opposition to Wallace’s motion for a temporary
restraining order. See generally Def. Resp. The government attached to its response a number of
documents, including BLM’s Technical Evaluation Panel Report, HUD’s Source Selection Decision
Document for each performance area, and the GAO’s December 9, 2015 bid protest decision. See
generally Def. Appendix. On December 21, 2015, Wallace filed a reply in support of its motion for
a temporary restraining order. See generally Pl. Reply.
On December 23, 2015, the Court held a telephonic hearing to discuss Wallace’s motions
for emergency injunctive relief. During that hearing, the Court issued an oral decision denying
Wallace’s motions for a temporary restraining order and for a preliminary injunction. The Court’s
rationale for denying Wallace’s motions is set forth below.
9
III.
JURISDICTION AND LEGAL STANDARDS
A. Bid Protest Jurisdiction
The Tucker Act grants the United States Court of Federal Claims jurisdiction over bid
protests brought by “an interested party objecting to a solicitation by a Federal agency for bids or
proposals for a proposed contract or to a proposed award or the award of a contract or any alleged
violation of statute or regulation in connection with a procurement or a proposed procurement.” 28
U.S.C. § 1491(b)(1) (2012). The United States Court of Appeals for the Federal Circuit has applied
the Competition in Contracting Act’s definition of interested party in the context of bid protest
matters, which defines the term “interested party” to mean an “actual or prospective bidder or
offeror whose direct economic interest would be affected by the award of the contract or failure to
award the contract.” Am. Fed. of Gov. Employees, AFL-CIO v. United States, 258 F.3d 1294, 1302
(Fed. Cir. 2001).
In bid protest cases, this Court reviews agency actions under the “arbitrary and capricious”
standard. See 28 U.S.C. § 1491(b)(4) (adopting the standard of review set forth in the
Administrative Procedure Act). And so, under the Administrative Procedure Act standard, an
award may be set aside if “(1) the procurement official’s decision lacked a rational basis; or (2) the
procurement procedure involved a violation of regulation or procedure.” Banknote Corp. of Am.,
Inc. v. United States, 365 F.3d 1345, 1351 (Fed. Cir. 2004) (quoting Impresa Construzioni Geom.
Domenico Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001)). The United States Court
of Appeals for the Federal Circuit has explained that:
When a challenge is brought on the first ground, the test is whether the contracting
agency provided a coherent and reasonable explanation of its exercise of discretion,
and the disappointed bidder bears a “heavy burden” of showing that the award decision
had no rational basis. When a challenge is brought on the second ground, the
disappointed bidder must show a clear and prejudicial violation of applicable statutes
or regulations.
Id.
In reviewing an agency’s procurement decision, the Court should recognize that the
agency’s decision is entitled to a “presumption of regularity.” Citizens to Pres. Overton Park, Inc.
v. Volpe, 401 U.S. 402, 415 (1971), overruled on other grounds by Califano v. Sanders, 430 U.S. 99
(1977) (citations omitted). In addition, the Court should not substitute its judgment for that of the
agency. Cincom Sys., Inc. v. United States, 37 Fed. Cl. 663, 672 (1997). And so, “[t]he protestor
10
must show, by a preponderance of the evidence, that the agency’s actions were either without a
reasonable basis or in violation of applicable procurement law.” Info. Tech. & Applications Corp.
v. United States, 51 Fed. Cl. 340, 346 (2001), aff’d, 316 F.3d 1312 (Fed. Cir. 2003); see Gentex
Corp. v. United States, 58 Fed. Cl. 634, 648 (2003).
This standard “is highly deferential.” Advanced Data Concepts, Inc. v. United States, 216
F.3d 1054, 1058 (Fed. Cir. 2000) (citing Bowman Transp., Inc. v. Ark.-Best Freight Sys., Inc., 419
U.S. 281, 285 (1974)). As long as there is “a reasonable basis for the agency’s action, the court
should stay its hand even though it might, as an original proposition, have reached a different
conclusion . . . .” Honeywell, Inc. v. United States, 870 F.2d 644, 648 (Fed. Cir. 1989). But, if “the
agency entirely fail[s] to consider an important aspect of the problem [or] offer[s] an explanation for
its decision that runs counter to the evidence before the agency,” then the resulting action lacks a
rational basis and, therefore, is defined as “arbitrary and capricious.” Ala. Aircraft Indus., Inc.Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle Mfrs.
Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)) (internal quotation marks omitted).
B. Preliminary Injunctions And Temporary Restraining Orders, RCFC 65
The Tucker Act authorizes this Court to “award any relief that the court considers proper,
including . . . injunctive relief.” 28 U.S.C. § 1491(b)(2); see Rule 65 of the Rules of the United
States Court of Federal Claims (“RCFC”). However, “a preliminary injunction is an extraordinary
and drastic remedy, one that should not be granted unless the movant, by a clear showing, carries
the burden of persuasion.” Mazurek v. Armstrong, 520 U.S. 968, 972 (1997) (emphasis omitted)
(citation omitted); Intel Corp. v. ULSI Sys. Tech., Inc., 995 F.2d 1566, 1568 (Fed. Cir. 1993) (The
award of “a preliminary injunction is a drastic and extraordinary remedy that is not to be routinely
granted.”). A temporary restraining order is similarly an “extraordinary and drastic remedy”. Jones
Automation, Inc. v. United States, 92 Fed. Cl. 368, 370 (2010) (citations omitted).
In deciding whether to grant emergency injunctive relief, the United States Court of Appeals
for the Federal Circuit has directed that the Court consider: (1) whether the plaintiff is likely to
succeed on the merits of the case; (2) whether the plaintiff will suffer irreparable harm if the Court
withholds injunctive relief; (3) whether the balance of hardships to the respective parties favors the
grant of injunctive relief; and (4) whether it is in the public interest to grant injunctive relief.
PGBA, LLC v. United States, 389 F.3d 1219, 1228-29 (Fed. Cir. 2004); FMC Corp. v. United
States, 3 F.3d 424, 427 (Fed. Cir. 1993); OAO Corp. v. United States, 49 Fed. Cl. 478, 480 (2001);
11
Cincom Sys., Inc. v. United States, 37 Fed. Cl. 266, 268 (1997) (To obtain a temporary restraining
order, the plaintiff must show the following: (1) it will suffer irreparable injury unless the temporary
restraining order issues; (2) the threatened injury to the moving party outweighs any damage to the
opposing party; (3) the temporary restraining order, if issued, will not be adverse to the public
interest; and (4) a substantial likelihood exists that the moving party will prevail on the merits.).
“Although the factors are not applied mechanically, a movant must establish the existence of
both of the first two factors to be entitled to a preliminary injunction.” Altana Pharma AG v. Teva
Pharm. USA, Inc., 566 F.3d 999, 1005 (Fed. Cir. 2009) (citing Amazon.com, Inc. v.
Barnesandnoble.com, Inc., 239 F.3d 1343, 1350 (Fed. Cir. 2001)). In addition, “[n]o one factor,
taken individually, is necessarily dispositive,” and “the weakness of the showing regarding one
factor may be overborne by the strength of the others.” FMC Corp., 3 F.3d at 427. But, “the
absence of an adequate showing with regard to any one factor may be sufficient, given the weight or
lack of it assigned to the other factors, to justify the denial” of a motion for a preliminary injunction
or for a temporary restraining order. Id.
IV.
ANALYSIS
In its motions for a temporary restraining order and for a preliminary injunction, Wallace
requests that the Court enjoin BLM’s performance under the FSM contracts until the resolution of
this matter. See generally Pl. Mot. for TRO; Pl. Mot. In this regard, Wallace argues that HUD’s
decision to award these contracts to BLM was unreasonable because HUD improperly evaluated the
past/present performance factor for the proposals submitted by Wallace and BLM. See generally
Pl. Mot. for TRO; Pl. Mot.; Pl. Memo. Wallace also argues that the Court should set aside HUD’s
award decision because BLM has an organizational conflict of interest and BLM is unqualified to
perform the FSM contracts. Id.
The government opposes Wallace’s motions and argues that Wallace has not met its heavy
burden to show that it is entitled to emergency injunctive relief. See generally Def. Resp.
Specifically, the government argues that HUD acted reasonably in awarding the subject contracts to
BLM and that the factors that the Court must consider in weighing a motion for emergency
injunctive relief weigh against granting Wallace’s motions. See generally Def. Resp. For the
reasons discussed below, the undisputed facts in this matter show that Wallace has not established
that it is entitled to emergency injunctive relief. And so, the Court must deny Wallace’s motions.
RCFC 65.
12
A. Wallace Has Not Shown That It Is Entitled To Injunctive Relief
It is well established that temporary restraining orders and preliminary injunctions are
extraordinary and drastic remedies that should not be granted unless the movant, by a clear
showing, carries the burden of persuasion. Mazurek, 520 U.S. at 972 (emphasis omitted) (citation
omitted); Intel Corp., 995 F.2d at 1568 (The award of “a preliminary injunction is a drastic and
extraordinary remedy that is not to be routinely granted.”); see also Jones Automation, 92 Fed. Cl.
at 370 (2010) (holding that a temporary restraining order is an “extraordinary and drastic remedy”)
(citations omitted).
When deciding whether to grant such emergency injunctive relief, the United States Court of
Appeals for the Federal Circuit has held that this Court must consider four factors: (1) whether the
plaintiff is likely to succeed on the merits of the case; (2) whether the plaintiff will suffer irreparable
harm if the Court withholds injunctive relief; (3) whether the balance of hardships to the respective
parties favors the grant of injunctive relief; and (4) whether it is in the public interest to grant
injunctive relief. PGBA, LLC v. United States, 389 F.3d 1219, 1228-29 (Fed. Cir. 2004); FMC
Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993); OAO Corp., 49 Fed. Cl. at 480; Cincom
Sys., Inc., 37 Fed. Cl. at 268 (applying the same four-factor test when determining whether to grant
a motion for a temporary restraining order).
A movant must establish the existence of both of the first two factors to be entitled to
injunctive relief. Altana Pharma AG, 566 F.3d at 1005 (citing Amazon.com, Inc., 239 F.3d at
1350). In addition, “[n]o one factor, taken individually, is necessarily dispositive,” and “the
weakness of the showing regarding one factor may be overborne by the strength of the others.”
FMC Corp., 3 F.3d at 427. But, “the absence of an adequate showing with regard to any one factor
may be sufficient, given the weight or lack of it assigned to the other factors, to justify the denial”
of a motion for injunctive relief. Id. For the reasons discussed below, Wallace has not met its
burden to establish that it is entitled to emergency injunctive relief in this bid protest matter.
1.
The Undisputed Facts Suggests That Wallace Is Not An Interested Party
As an initial matter, the record currently before the Court calls into question whether
Wallace is an interested party with standing to pursue its claims. In this regard, it is well settled
that, under the Tucker Act, only an “interested party” has standing to object to the award of a
contract. 28 U.S.C. § 1491(b)(1). The United States Court of Appeals for the Federal Circuit has
defined the term “interested party” to mean an “actual or prospective bidder or offeror whose direct
13
economic interest would be affected by the award of the contract or failure to award the contract.”
Am. Fed. of Gov. Employees, AFL-CIO, 258 F.3d at 1302. And so, to have standing here, Wallace
must show that its direct economic interest was affected by the award of the FSM contracts. Id.
In this case, it is undisputed that, for four of the five contracts at issue, Wallace would not
have been the next offeror in line for award if BLM were disqualified from receiving the contract
awards. A284; A292; A320-21; A325-26. In this regard, the record currently before the Court
shows that, with respect to the FSM contracts for areas 1D, 3P, 4P, and 5P, there was at least one
lower-priced, technically acceptable offer−other than BLM’s offer−that received a higher rating for
the past/present performance factor than Wallace. A284; A292; A320-21; A325-26.
Specifically, with respect to the FSM contract for area 1D, there were fifteen technically
acceptable offers, other than BLM, that proposed a lower price than Wallace, including one offer
with a good/significant confidence rating for the past/present performance factor. A295-96. For the
FSM contract for area 3P, there were six technically-acceptable offers, other than BLM, that
proposed a lower price than Wallace, including one offer with a good/significant confidence rating
for the past/present performance factor. A316-17; A397. For the FSM contract for area 4P, there
were eleven technically-acceptable offers, other than BLM, that proposed a lower price than
Wallace, including one with a good/significant confidence rating for the past/present performance
factor. A320-21. For the FSM contract for area 5P, there were ten technically-acceptable offers,
other than BLM, that proposed a lower price than Wallace, including two offers that received a
good/significant confidence rating for the past/present performance factor. A325-26; A397. Given
this, the record evidence suggests that Wallace would not have been awarded these four contracts if
the award to BLM were to be set aside. And so, Wallace does not have a direct economic interest
that was affected by the award of these four contracts to BLM. Am. Fed. of Gov. Employees, AFLCIO, 258 F.3d at 1302.
In the reply brief in support of its motions for emergency injunctive relief, Wallace argues,
without any support from the record, that it “should have been rated Excellent/High Confidence or
at least Good/Significant Confidence” for the past/present performance factor. Pl. Reply at 9.
Wallace further argues that such a rating “would have put [Wallace] ahead of all other offerors in
area 4P who were rated Fair and the appropriate Excellent rating would have placed [Wallace]
ahead of the other offerors in the other Areas described in the Record (Areas 1D, 3P, and 5P).” Id.
But, Wallace does not dispute the salient fact that at least one other offeror proposed an offer that
14
was superior to Wallace’s offer with respect to four of the five FSM contracts in dispute. Id. And
so, Wallace has not persuaded the Court it is an interested party with standing to challenge HUD’s
award decisions with respect to these four contracts. See Am. Fed. of Gov. Employees, AFL-CIO,
258 F.3d at 1302.
2.
Wallace Has Not Demonstrated Irreparable Harm
The matter of whether Wallace has standing to bring its claims with respect to four of the
five FSM contracts at issue in this case, alone, is not fully dispositive of Wallace’s request for
emergency relief. Nonetheless, for the reasons discussed below, the factors that the Court must
weigh when considering whether to grant Wallace’s motions for emergency injunctive relief weigh
against granting Wallace’s motions.
First, with respect to whether Wallace will be irreparably harmed if the Court does not grant
the request for injunctive relief, this Court has held that “denial of a fair opportunity to compete”
under a solicitation “and loss of financial benefit from a lawful procurement process” may
constitute irreparable harm. See, e.g., BCPeabody Constr. Servs., Inc. v. United States, 112 Fed. Cl.
502, 514 (2013). But, in terms of the injunctive relief that Wallace seeks here–namely, that BLM
be enjoined from commencing performance–Wallace’s position would be the same regardless of
whether the Court grants or denies this request. Wallace is not the incumbent contractor under any
of the subject FSM contracts. Compl. at 6-8. And so, it is without dispute that Wallace’s position
with respect to the performance of these contracts would be the same regardless of whether the
Court enjoins BLM from starting performance.
Nonetheless, even if the Court were to find that Wallace will suffer irreparable harm here,
the record currently before the Court shows that Wallace is not likely to succeed upon the merits of
its claims.
3.
Wallace Is Unlikely To Succeed Upon The Merits Of Its Claims
a.
Wallace’s Past/Present Performance Rating
The record before the Court does not support Wallace’s claim that HUD underrated its
past/present performance factor and overrated BLM’s past/present performance factor. In this
regard, there is no dispute that Wallace received a rating of neutral/unknown confidence for the
past/present performance factor. A341. It is also undisputed that Wallace identified three past
efforts and proposed at least five key personnel who worked for other field service management
contractors to satisfy the past/present performance factor. A341-3. The record before the Court
15
demonstrates that HUD determined that these past efforts were not relevant. A341. And so, HUD
rated Wallace’s past/present performance factor as neutral/unknown confidence. A296; A317;
A321; A326; A335; A341.
In regards to Wallace’s challenge to this rating, the record shows that HUD determined that
the personnel proposed by Wallace were not relevant, because Wallace submitted offers for
contracts in five different geographic areas, but failed to specify which key personnel with relevant
experience would be committed to a particular contract area. A380. Wallace does not dispute the
fact that it did not specify which members of its key personnel would be committed to the
geographic areas specified in the contracts. Id. And so, the undisputed record evidence currently
before the Court shows that there was a rational basis for the government’s decision to rate
Wallace’s past/present performance factor as neutral/unknown confidence.
b.
BLM’s Past/Present Performance Rating
Wallace’s claim that HUD overrated BLM’s past/present performance is also contradicted
by the record before the Court. It is without dispute that BLM submitted three past/present
performance efforts in which it provided FSM services as a subcontractor. A265. The record
before the Court also shows that, based upon this information, HUD determined that BLM “has
shown a good history of performance, as well as the capability to manage a project of this
magnitude.” See, e.g., A285. Wallace points to no evidence in the record to show that the agency’s
determination regarding BLM’s past/present performance was improper. See generally Pl. Reply.
Given this, HUD’s decision to rate BLM’s past/present performance factor as good/significant
confidence appears reasonable, and Wallace is unlikely to succeed upon the merits of this claim.
c.
Organizational Conflict of Interest
Wallace’s claim that BLM has an unresolved organizational conflict of interest, and that
HUD failed to properly investigate the alleged conflict, is also contradicted by the current record
evidence. The United States Court of Appeals for the Federal Circuit has held that the Federal
Acquisition Regulation only obligates an agency to conduct an organizational conflict of interest
analysis for significant conflicts. PAI Corp. v. United States, 614 F.3d 1347, 1352 (Fed. Cir. 2010)
(holding that agencies are only required to document “significant potential conflicts”); FAR
9.504(a)(2). In addition, contracting officers are given broad discretion in determining whether the
potential conflict of interest is significant. Id.
16
The parties agree that the RFP for the subject contracts prohibits contractors from
performing pre-conveyance work on FHA Single Family Insured properties. A125. Wallace
maintains that BLM has provided such pre-conveyance work in two of the areas for which it has
been awarded contracts. Compl. at 6. To support this allegation, Wallace has provided the Court
with an affidavit from its President, Kevin Wallace, which states that:
While WAM was preparing its proposal in response to the Solicitation I was
approached by Brent Martin, the owner of BLM Companies, LLC (“BLM”) offering
to provide me with inspection services on Bank owned homes in Eastern Pennsylvania.
In our discussion, Mr. Martin stated that he provided inspection services for the
incumbent HUD FSM contractor Innotion Enterprises, Inc. as well as two other
companies one named Safeguard and the other called Sentinel Field Services.
I have personal knowledge that Safeguard provides pre-conveyance services in
Pennsylvania for homes mortgaged by Freddie Mae [sic] and Fannie Mac [sic] which
are not HUD’s Federal Housing Administration (“FHA”). The services described as
creating a conflict interest in the Solicitation. Sentinal was doing Freddie Mac and
other pre-conveyance work in Pennsylvania.
Pl. Reply at 9-10.
The record currently before the Court shows that HUD conducted a reasonable investigation
into whether BLM had performed pre-conveyance work and that the agency did not find any
evidence that BLM performed pre-conveyance work in any of the areas for which BLM had been
awarded a contract. A371. Specifically, in a memorandum for the file dated October 9, 2015, Craig
Karnes, the Principal Administrative Contracting Officer, states that he sought information about
BLM’s potential pre-conveyance work in area 3P from BLM and also consulted HUD employees
regarding the existence of any pre-conveyance work in any of the other areas for which BLM had
been awarded a contract. A371; A377. HUD concluded that there was no evidence to indicate that
BLM performed any past or present pre-conveyance work that would give rise to an organizational
conflict of interest. A371. And so, the record currently before the Court shows that HUD
appropriately investigated the alleged organizational conflict involving BLM and reasonably
concluded that there was no evidence to indicate the existence of a significant organizational
conflict of interest with respect to BLM.
d.
Wallace’s Challenge Of BLM’s Qualifications
Lastly, Wallace’s final challenge to HUD’s award decisions–that BLM was not qualified to
be awarded the subject contracts–is also unsupported by the record. As previously mentioned, the
record before the Court shows that HUD appropriately rated the past/present performance factor
17
with respect to the proposals submitted by BLM and that HUD reasonably rated this factor as
good/significant confidence. A264-66. Wallace, nonetheless, alleges that BLM is unqualified to
perform the subject contracts because BLM relies too heavily upon a large business subcontractor.
Compl. at 7. But, Wallace provides no evidence to support this allegation. Id. Given this, Wallace
has not met its burden to show that it has a substantial likelihood of success upon the merits of this
claim.
In sum, Wallace has not met its burden to show that it is substantially likely to succeed upon
the merits in this case. For this reason, the Court must deny Wallace’s request for emergency
injunctive relief.
4.
The Remaining Factors Weigh Against Granting Injunctive Relief
The remaining factors that the Court considers when weighing whether to grant a motion for
a temporary restraining order or for a preliminary injunction also weigh against granting Wallace’s
motions.
First, with respect to the balance of the hardships for Wallace and the government if the
Court were to grant injunctive relief, any harm that Wallace would suffer as a result of the loss of its
motions is outweighed by the harm to the government, and to BLM, if the Court were to enjoin
BLM’s performance. See PGBA, 389 F.3d at 1229 (in considering a motion for a preliminary
injunction, the Court balances the harm the movant would suffer without preliminary relief, against
the harm that preliminary relief would inflict on the non-movant); Akal Sec., Inc. v. United States,
87 Fed. Cl. 311, 320 (2009) (“Generally, if the balance tips in favor of defendant, a preliminary
injunction is not appropriate.”); Reilly's Wholesale Produce v. United States, 73 Fed. Cl. 705, 71516 (2006). According to the government, BLM has begun the “Ramp-Up” phase of the contracts.
Def. Resp. at 20. BLM has spent significant resources–approximately $600,000 by the end of the
year according to the government–in this phase. Pl. Memo. at 20. The government also advises
that it will incur an additional cost of approximately $79,927 per day if BLM is enjoined from
commencing performance. Def. Memo. at 20.
On the other hand, Wallace is not currently performing under any of the contracts. Compl.
at 6-8; see also Status Report, Dec. 31, 2015. And so, as discussed above, Wallace’s position
remains the same regardless of whether the Court allows BLM to begin performance or enjoins
18
BLM from commencing performance. Compl. at 6-8. Given this, the hardship resulting from a stay
of BLM’s performance would be significant for the government and for BLM.
In addition, the public interest is best served by denying the requested injunctive relief. In
this regard, the public has an interest in ensuring that the homes HUD maintains are safe and do not
pose health or safety concerns for the public. Ensuring that the FSM contracts can proceed as
scheduled will promote this important public interest.
And so, for all of the above reasons, denial of Wallace’s motion for a temporary restraining
order is warranted.3 Because the Court considers the same factors discussed above when
considering Wallace’s motion for a preliminary injunction, the Court also denies Wallace’s motion
for a preliminary injunction.
V.
CONCLUSION
In sum, Wallace has not met its heavy burden to show that it is entitled to a temporary
restraining order or to a preliminary injunction. First, Wallace does not appear to have standing to
challenge the contract awards for four of the five contracts in dispute in this matter. In addition,
even if the Court were to accept that Wallace would suffer irreparable harm if the Court were to
deny its motions, Wallace has failed to demonstrate that it is likely to succeed upon the merits of its
claims. In this regard, the record currently before the Court shows that HUD conducted a
reasonable evaluation of the past/present performance factor for the offers submitted by Wallace
and BLM. The record also shows that HUD appropriately investigated the potential organizational
conflict of interest involving BLM, and that BLM is qualified to perform the subject contracts.
Lastly, the public interest in ensuring that the properties maintained by HUD are safe for the public
is best served by denying Wallace’s motion.
For these reasons, the Court will not interfere with this procurement by enjoining BLM’s
performance under the contracts. And so, the Court denies Wallace’s motion for a temporary
restraining order.
Because the arguments in Wallace’s motion for a preliminary injunction are identical to
those raised in its motion for a temporary restraining order, and the legal standards that the Court
3
Because Wallace has not established that it is entitled to a temporary restraining order or to a preliminary
injunction, the Court does not reach the question of the amount of bond.
19
must apply in deciding the two motions are the same, the Court also denies Wallace’s motion for a
preliminary injunction.
Some of the information contained in this Memorandum Opinion and Order may be
considered protected information subject to the Protective Order entered in this matter on December
17, 2015. This Memorandum Opinion and Order shall therefore be filed under seal. The parties
shall review the Memorandum Opinion and Order to determine whether, in their view, any
information should be redacted in accordance with the terms of the Protective Order prior to
publication.
The Court hereby ORDERS that the parties FILE a joint status report, on or before Friday,
February 5, 2016, identifying the information, if any, that they contend should be redacted in this
Memorandum Opinion and Order, together with an explanation of the basis for each proposed
redaction.
IT IS SO ORDERED.
s/ Lydia Kay Griggsby
LYDIA KAY GRIGGSBY
Judge
20
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?