DELL FEDERAL SYSTEMS, L.P. v. USA
Filing
140
REPORTED OPINION on Cross-Motions for Judgment on the Administrative Record. Signed by Judge Thomas C. Wheeler. (gb) Copy to parties.
In the United States Court of Federal Claims
Nos. 17-465C, 17-473C
(Filed Under Seal: July 3, 2017)
(Reissued for Publication: July 13, 2017)1
***************************************
*
*
DELL FEDERAL SYSTEMS, L.P., and
*
BLUE TECH INC.,
*
*
*
Plaintiffs,
*
and
*
*
IRON BOW TECHNOLOGIES, LLC, et al., *
*
*
Plaintiff-Intervenors, *
*
v.
*
*
THE UNITED STATES,
*
*
*
Defendant,
*
and
*
*
*
ALPHASIX CORP., et al.,
*
Defendant-Intervenors. *
*
*
************************************** *
Bid Protest Challenging Agency
Corrective Action; Multiple Award
IDIQ Contracts; Proposal Discussions
Contrasted With Clarifications; Effect
of Blue & Gold Fleet; Declaratory and
Injunctive Relief.
Michael F. Mason, with whom were C. Peter Dungan, Christine Reynolds, and Thomas
A. Pettit, Hogan Lovells US LLP, Washington, D.C., for Plaintiff Dell Federal Systems,
L.P.;
Michael J. Anstett, with whom were James J. McCullough, Neaha P. Raol, and Brendan
C. McNamara, Fried, Frank, Harris, Shriver & Jacobson LLP, Washington, D.C., for
Plaintiff Blue Tech Inc.;
The Court issued this decision under seal on July 3, 2017, and invited the parties to submit proposed
redactions of any proprietary, confidential, or other protected information on or before July 10, 2017.
None of the parties proposed any redactions. Thus, the Court reissues the opinion in full.
1
Joseph E. Ashman, Trial Attorney, with whom were Chad A. Readler, Acting Assistant
Attorney General, Robert E. Kirschman, Jr., Director, and Martin F. Hockey, Jr., Deputy
Director, Commercial Litigation Branch, Civil Division, Department of Justice,
Washington, D.C., for Defendant;
Jerry Alfonso Miles, Deale Services, LLC, Rockville, Maryland, for Plaintiff-Intervenor
Govsmart, Inc.;
Maria L. Panichelli, with whom was Robert G. Ruggieri, Cohen, Seglias, Pallas, Greenhall
& Furman, P.C., Philadelphia, Pennsylvania, for Plaintiff-Intervenor Ideal Systems
Solutions, Inc.;
Thomas K. David, with whom were Kenneth D. Brody and Katherine A. David, David,
Brody & Dondershine, LLP, Reston, Virginia, for Plaintiff-Intervenor NCS Technologies,
Inc.;
Joseph P. Hornyak, with whom were Elizabeth N. Jochum and Rodney M. Perry, Holland
& Knight LLP, Tysons, Virginia, for Plaintiff-Intervenor Red River Computer Co., Inc.;
Anthony J. Marchese, with whom were Carol L. O’Riordan, Pamela J. Bethel, and Taimur
Rabbani, O’Riordan Bethel Law Firm, LLP, Washington, D.C., for Defendant-Intervenor
Alphasix Corp.;
Daniel R. Forman, with whom were Jonathan M. Baker, Elizabeth A. Buehler, and Nkechi
A. Kanu, Crowell & Moring LLP, Washington, D.C., for Defendant-Intervenor HPI
Federal, LLC;
David M. Nadler, with whom were David Y. Yang, Adrien C. Pickard, and Philip E.
Beshara, Blank Rome LLP, Washington, D.C., for Defendant-Intervenor CDW
Government LLC;
Gerald H. Werfel, with whom was Ian A. Cronogue, Baker, Cronogue, Tolle & Werfel,
LLP, McLean, Virginia, for Defendant-Intervenor Insight Public Sector, Inc.;
Anne B. Perry, with whom were Matthew W. Turetzky, and Keeley A. McCarty, Sheppard
Mullin Richter & Hampton LLP, Washington, D.C., for Defendant-Intervenor Sterling
Computers Corp.
2
OPINION AND ORDER
WHEELER, Judge.
Plaintiffs brought this bid protest to challenge the Department of the Army’s
decision to take corrective action after multiple previous protests had been filed at the
Government Accountability Office (“GAO”). The underlying solicitation sought to
procure commercial off-the-shelf computer hardware through indefinite-delivery,
indefinite quantity contracts with the Army. Fifty-eight offerors submitted proposals, and
the Army found only nine of those proposals to be technically acceptable. The Army
awarded contracts to each of the nine technically acceptable offerors.
Twenty-one of the unsuccessful offerors filed protests at the GAO. The protesters
mainly alleged that the solicitation contained several ambiguities causing the offerors to
submit technically unacceptable proposals. The protesters argued that they could have
corrected the flaws in their proposals if the Army had requested clarifications or engaged
in discussions with offerors.
After analyzing the GAO protests, the Army determined that the GAO protests
represented a significant litigation risk. The Army’s counsel found that Department of
Defense Federal Acquisition Regulation Supplement (“DFARS”) § 215.306(c), in
conjunction with a recent GAO decision, In re Science Applications International Corp.,
B-413501.2, 2016 WL 6892429 (Nov. 9, 2016), meant that the Army was obligated to
conduct discussions with offerors unless it had a reasonable basis for forgoing such
discussions. The Army thought it possible that the GAO could find the Army lacked a
reasonable basis to forgo discussions, and therefore it decided to implement corrective
action by reopening the procurement, conducting discussions with virtually all of the
offerors, and allowing offerors to resubmit proposals with new pricing. Complicating
matters, the Army had disclosed the prices of the nine contract awardees.
Plaintiffs and Plaintiff Intervenors (the “Protesters”)—six of the original contract
awardees—now challenge the Army’s corrective action. They argue that it was arbitrary
and capricious for the Army to decide that corrective action was appropriate in this case.
They further challenge the scope of the Army’s corrective action, as well as the Army’s
decision to release their winning proposal prices. Those receiving contracts rightly
complain that they would be at a significant competitive disadvantage in having to compete
again for contracts they had rightly won in the first instance. They seek a permanent
injunction that would forbid the Army from implementing the corrective action. Five of
the previously unsuccessful offerors have joined this suit as Defendant-Intervenors. They,
along with the Government, defend the Army’s corrective action as a reasonable response
to a reasonable assessment of litigation risk.
3
Most of the parties have submitted cross-motions for judgment on the administrative
record. The Court heard oral argument on the cross-motions on June 14, 2017. After
considering the parties’ arguments, the Court finds that the Army’s contemplated
corrective action is not narrowly targeted to address the procurement defects the Army has
identified. While discussions would have been permissible before the Army announced its
contract awards, the Army elected to make awards without discussions. The administrative
record reflects the consequences of that decision: many offerors made minor errors filling
out the Army-provided spreadsheets and submitted technically unacceptable proposals as
a result. These consequences are relatively minor, and the Court finds that clarifications
and reevaluation would suffice to remedy them. On the other hand, discussions paired with
re-solicitation would represent a blunderbuss approach to corrective action that neither the
record nor the law supports. There is no reason to reopen the competition and invite new
proposals, particularly where the Army’s requirements have not changed. Therefore, the
Court GRANTS Plaintiffs’ and Plaintiff-Intervenors’ motions for judgment on the
administrative record. The Court similarly grants their motions for a permanent injunction
barring the Army’s proposed corrective action. Defendant’s and Defendant-Intervenors’
motions are DENIED. As the Court will explain, the Army surely can formulate some
acceptable form of corrective action short of engaging in full-blown discussions and
requesting a new round of proposals. The simple use of clarifications and reevaluation of
proposals would cause many of the unacceptable proposals to become acceptable, and
thereby eligible for award.
Background
A.
The Army’s Solicitation
The Army, acting through the Army Contracting Command at Rock Island, Illinois,
issued Solicitation W52P1J-15-R-0122 on May 3, 2016. AR Tab 17 at 153.2 The
solicitation would begin a new iteration of the Army Desktop Mobile and Computing
program, known as ADMC-3. See id. at 155. The Solicitation sought indefinite-delivery,
indefinite-quantity contracts for “commercial-off-the-shelf (COTS) desktop computers,
integrated desktop computers, workstations, electronic display, notebooks, tablet
computers, slate, thin client, ultra-thin client, printers, multifunction devices and
warranty.” Id. The awardees would perform by filling firm fixed-price delivery orders.
Id. The Army guaranteed that it would place a minimum of $10,000 in delivery orders
with each awardee, which would “require each successful offeror to provide 1-2 laptops,
tablets or peripherals to be determined at the time of award.” Id. at 156. Still, the Army
2
References to “AR Tab __” refer to tabs in the administrative record. All page numbers given use the
pagination of the administrative record rather than that of individual documents within the record.
Furthermore, the Solicitation was amended ten times in ways that are not relevant to this case. For ease of
reference, the Court cites the first version (AR Tab 17).
4
contemplated ordering far more equipment under the contract, and the contract’s total
estimated value is $5 billion. Id. at 155; AR Tab 69 at 4324.
Offerors were evaluated based on “an integrated assessment of three evaluation
factors:” Technical Approach, Past Performance, and Price. AR Tab 17 at 199. Factor 1
(Technical Approach) was divided into two subfactors: Equipment Submission Form and
Business Process Form. Id. To be considered for an award, the solicitation required an
“acceptable” rating for the Technical Approach (including both subfactors) and Past
Performance factors. Id.
The solicitation directed offerors to submit their proposals in four “volumes:”
Technical Approach, Past Performance, Price, and Contracts/Business. Id. at 195.
Offerors were required to complete Army-provided Excel spreadsheets for the Equipment
Submission form and Business Process Form subfactors as part of Volume 1. Id. For both
subfactor spreadsheets, the solicitation instructed offerors to “complete all cell entries and
the information provided shall demonstrate that the minimum requirements outlined in the
Statement of Work (SOW) are met or exceeded.” Id. at 196. The instructions also stated
that “an incomplete or blank entry will indicate that the proposed item does NOT meet the
minimum requirements.” Id.
The Army intended to award “at least eight” contracts to the offerors who submitted
the lowest-priced technically acceptable proposals, but reserved the right to make “as
many, or as few, awards as deemed appropriate.” Id. at 155. The awards would be divided
into two categories: those reserved for small business, and those available through full and
open competition. Id. at 198. For the first category, the Army intended to “select the five
lowest priced Small Business Offerors for award, provided that five responsible small
business proposals [were] found to be acceptable in all non-price factors.” Id. For the full
and open competition category, the Army intended to award three contracts to the nonsmall-business offerors who submitted the lowest-priced technically acceptable proposals.
Id.
Finally, the solicitation stated that the Army “intend[ed] to award without
conducting discussions with Offerors.” Id. at 193.3 However, “the Government
reserve[ed] the right to conduct discussions and to permit Offerors to revise proposals if
determined necessary by the Contracting Officer.” Id. Further, if the Army chose to open
discussions, “all proposals, to include small business proposals previously removed for
unacceptability . . . [would] be included,” after which the Army would reevaluate proposals
in accordance with the solicitation. Id. at 198. The Army similarly noted that it could,
“solely at its discretion, enter into clarifications or communication as needed” with offerors
as part of the evaluation process. Id. at 193.
The procurement concept of making award without discussions, even for a large dollar procurement, is
not unreasonable when considering that the agency was acquiring commercial off-the-shelf equipment.
3
5
B.
The Army’s Evaluation and Award Decisions
All proposals from offerors were due by August 4, 2016. AR Tab 31 at 392. Fiftyeight offerors had submitted proposals by that date (fifty-two from small businesses and
six from large businesses). AR Tab 69 at 4327. The Army found that three of the fiftyeight proposals did not comply with the solicitation’s requirements, so the Army only
evaluated the remaining fifty-five proposals. Id. The Source Selection Evaluation Board
(“SSEB”) evaluated all offerors under the first factor (Technical Approach), and did not
evaluate offerors’ proposals under the other two factors if the offeror was rated
unacceptable for the first factor. See id. at 4329–30, 4334–40. The SSEB rated only nine
proposals acceptable under factor one, and rated each of these nine proposals acceptable
under the other two factors. Id.
In a briefing for the Source Selection Authority on the evaluation results, the SSEB
addressed the possibility of discussions and recommended that the Army not conduct them.
Id. at 4347. Specifically, the SSEB reasoned:
1)
We do not have a meaningful reason to open discussions
2)
Opening discussions would significantly delay award of
ADMC-3 because:
Past performance team would have to evaluate and write
past performance reports for 46 remaining offerors
All evaluation teams would have to evaluate final
proposal revisions after discussions are opened
3)
Based on the prices and items being offered, opening
discussions would not result in a greater variety of laptops,
desktops, etc.
Id. at 4348. Therefore, the Army did not conduct discussions, and it awarded contracts to
the nine technically acceptable offerors on February 16, 2017 (it notified the unsuccessful
offerors on the same date). See AR Tabs 75–84. The Army’s letters to the unsuccessful
offerors disclosed the nine awardees’ total proposed prices. AR Tab 84.
C.
The GAO Protests and the Army’s Corrective Action
Twenty-one of the unsuccessful offerors filed protests with the GAO between
February 21 and March 9, 2017 challenging the Army’s award decisions. See AR Tabs
85–105. The GAO protesters primarily alleged that clerical errors and other
misunderstandings concerning the Equipment Submission Form spreadsheet had led them
6
to submit technically unacceptable proposals. Several protesters also argued that the Army
should have engaged in discussions with offerors to resolve these spreadsheet-related
misunderstandings. In response to the protests, the Army instructed the nine awardees to
stop work under their contracts on February 22, 2017. AR Tab 106.
On March 21, 2017, the Army advised the GAO that it planned to take corrective
action in response to the twenty-one protests. AR Tab 107a. The Army announced that it
would open discussions with all remaining offerors, request final proposal revisions with
revised pricing, and issue new award decisions. Id. The Army documented its reasons for
taking corrective action in a Memorandum for Record (“MFR”) dated March 22, 2017.
AR Tab 110b. The MFR mainly quotes a previous memorandum prepared by George
Farley, an Army Attorney-Advisor. Id. Mr. Farley explained the possible impact of
DFARS § 215.306(c) on the pending GAO protests. Id. at 5832. That section states, “for
acquisitions with an estimated value of $100 million or more, contracting officers should
conduct discussions.” Mr. Farley noted that while no GAO decision had overturned an
agency decision not to conduct discussions in a procurement valued over $100 million,
“the GAO will review these cases to ensure the agency’s rationale for not holding
discussions is reasonable.” Id. at 5832.
Through the lens of a hypothetical GAO review, Mr. Farley found that the Army’s
grounds for not conducting discussions likely were unreasonable. First, he found that the
agency’s desire for convenience in not evaluating and writing past performance reports for
the forty-six remaining offerors did not pass muster. Id. at 5833–34. He noted that “[b]eing
convenient or providing an efficiency to the Agency is rarely, if ever, a reasonable rationale
for the Agency to not comply with a provision of law.” Id. at 5834. He further found the
Army’s “no greater variety of laptops, desktops, etc.” reason unavailing:
This stand-alone statement, which does not specifically
address the more advantageous pricing of the majority of the
unacceptable offerors’ proposals, is the Agency’s best
argument for not opening discussions. But, in order to
determine reasonableness, we must look at the totality of the
circumstances. Therefore, we must weigh the reasonableness
of this statement, along with the RFP language that the Agency
intended to award without Discussions, against the issues
raised regarding unreasonable behavior by the 20 protesters.
As summarized above, these issues lend themselves to showing
that the spreadsheet errors could have easily and quickly been
resolved. Additional issues raised impart either an ambiguity
in the requirements or the Government’s instructions how to
fill out the spreadsheet. A couple of these issues are:
7
a.
The hard-line issue regarding Hard-Drive versus SolidState Drives;
b.
Stating that an upgrade must be an increase in capability
but then stating that selection of an item in a drop-down is
acceptable when there are items in the dropdown that are not
upgrades to a base model.
These specific issues are detrimentally supported by the
Agency’s own evaluation when it states that the fifth (5th) most
common reason that proposals were found Technically
Unacceptable was “the offeror proposed items that did not
meet the minimum requirements” of the Agency. Given that
the language for the first two (2) reasons is that “the offeror
selected ‘NA’ instead of filling in a required field” and the
“offeror provided an incomplete or blank entry which
indicates” the item does not meet our requirements, the logical
conclusion is that the first two (2) reasons were merely
compliance issues with filling out the form rather than a
deficiency in the item proposed.
Id. He concluded that, because of these issues, there was “significant litigation risk in
defending these [GAO] protests.” Id. Mr. Farley then suggested a possible course for
corrective action:
If the Agency were to take corrective action based on the
litigation risk, we would be able to resolve all issues alleged in
these protests and make a new award decision that is simply
based on price alone. . . . By only allowing revisions to areas
previously determined as deficiencies and allowing Offerors to
change price the evaluation would be a reassurance that the
Offerors changed the spreadsheet in accordance with our
evaluation notice. Allowing Offerors to change price would
also benefit the Agency by getting offers that are a better value
to the Government.
RECOMMENDATION: Due to the significant litigation risk,
the ambiguities in the spreadsheet and SOW, and a matter of
policy to do what is right, I recommend that we take limited
corrective action to resolve the issues with Offerors’ Technical
Proposals.”
8
Id. at 5835. The Army MFR adopts Mr. Farley’s position, and does not give further reasons
for the Army’s corrective action.
On March 23, 2017, the GAO dismissed all twenty-one protests as academic in
response to the Army’s notice of corrective action. AR Tab 110c at 5836–37. The next
day, the Army sent letters to the fifty-five evaluated offerors. See AR Tab 112. In the
letters, the Army advised technically unacceptable offerors of the deficiencies in their
original proposals and instructed them to submit their “best and final” proposals. See, e.g.,
id. at 6013. To the previous awardees, the Army stated, “If you make changes to areas of
your technical proposal that have already been found acceptable, you are at risk of being
found technically unacceptable.” See, e.g., id. at 5861. In all of its letters, the Army further
added, “For the Price proposal, you are authorized to change your prices to your best and
final prices.” Id.
D.
The Original Awardees’ Current Protest
Dell Federal Systems, L.P. filed this bid protest challenging the Army’s corrective
action on March 31, 2017. The protest seeks a declaratory judgment that the corrective
action is unlawful, as well as a permanent injunction barring the corrective action. See
Dell Compl. at 8, Dkt. No. 1. Blue Tech Inc. brought a related protest, and the Court
consolidated the two protests on April 3, 2017. Dkt. No. 29. The Government notified the
Court on the same date that the Army would voluntarily stay its corrective action for the
duration of this protest. Dkt. No. 22. Five other original awardees—Iron Bow
Technologies, LLC, Govsmart, Inc., Ideal System Solutions, Inc., NCS Technologies, Inc.,
and Red River Computer Company, Inc.—have joined this case as plaintiff-intervenors.
Similarly, six of the losing offerors have joined this case as defendant-intervenors:
Alphasix Corp., HPI Federal, LLC, CDW Government LLC, Insight Public Sector, Inc.,
Integration Technology Groups, Inc., and Sterling Computers Corp.
The Government and all but one of the defendant-intervenors (Integration
Technology Groups) filed motions for judgment on the administrative record on May 3,
2017. The plaintiffs and all but one of the plaintiff-intervenors (Iron Bow Technologies)
filed cross-motions on May 17, 2017. The parties completed briefing on May 31, 2017,
and the Court heard oral argument on the cross-motions on June 14, 2017.
Discussion
A.
Jurisdiction and Standard of Review
The Tucker Act grants this Court subject matter jurisdiction over bid protests. 28
U.S.C. § 1491(b)(1) (2012). The protesters also have standing to challenge the Army’s
proposed corrective action despite their status as current contract awardees, as a protest of
corrective action “is in the nature of a pre-award claim.” Sheridan Corp. v. United States,
9
95 Fed. Cl. 141, 148 (2010) (quoting IMS Servs., Inc. v. United States, 32 Fed. Cl. 388,
398 (1994)).
In a bid protest, the Court reviews agency decisions—including decisions pertaining
to corrective action—pursuant to the standards set out in the Administrative Procedure Act
(“APA”). 28 U.S.C. § 1491(b)(4) (2012); 5 U.S.C. § 706 (2012). Under the APA, this
Court shall set aside an agency action if it is “arbitrary, capricious, an abuse of discretion,
or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A) (2012); see Banknote
Corp. of Am., Inc. v. United States, 365 F.3d 1345, 1350–51 (Fed. Cir. 2004). An agency’s
decision does not violate the APA if the agency “provided a coherent and reasonable
explanation of its exercise of discretion.” Impresa Construzioni Geom. Domenico Garufi
v. United States, 238 F.3d 1324, 1332–33 (Fed. Cir. 2001).
This standard is the same when a Court must consider an agency’s corrective action.
“Contracting officers are provided broad discretion to take corrective action where the
agency determines that such action is necessary to ensure fair and impartial competition.”
Sheridan, 95 Fed. Cl. at 151 (citation omitted). Therefore, in cases involving corrective
action, “the agency’s corrective action must be rationally related to the defect to be
corrected.” Id. (citation omitted). The evidence in the record must show that the agency
(1) identified a defect in the procurement, and (2) considered the ways in which its
corrective action would remedy the defect. See id. The Court’s review is deferential to
the agency as long as the agency has rationally explained its corrective action decision. Id.
(citing Advanced Data Concepts, Inc. v. United States, 216 F.3d 1054, 1057–58 (Fed. Cir.
2000). Finally, even if the agency acted without a rational basis, the Court cannot grant
relief unless the agency’s action prejudiced the protester. Bannum, Inc. v. United States,
404 F.3d 1346, 1351 (Fed. Cir. 2005).
B.
The Army’s Contemplated Corrective Action is not Rationally Related to
Defects in the Procurement
The parties’ dispute encompasses both elements of the corrective action analysis.
First, the parties dispute the existence of a procurement defect in need of correction. Next,
the parties disagree as to the appropriate scope of the Army’s corrective action. The Court
will address each of the parties’ arguments in turn.
1.
The Army Rationally Identified Procurement Defects
The Government and Defendant-Intervenors have pointed to two defects in the
Army’s procurement. First, they argue that the Equipment Submission Form spreadsheet
the offerors were required to submit with their proposals contained latent ambiguities.
Second, they argue that DFARS § 215.306(c) required the Army to conduct discussions
unless it reasonably concluded that discussions were unnecessary. According to this view,
the Army’s decision not to conduct discussions had no reasonable basis in the record, so
10
the failure to conduct discussions was itself a defect. The Protesters argue that any claims
predicated upon these alleged defects were waived after the close of the bidding process,
so it was irrational for the Army to decide to take corrective action to remedy the defects.
In the alternative, they argue that there were no defects in the procurement that could serve
as the basis for corrective action.
a.
The Timeliness of the GAO Protests has no Bearing on the
Rationality of the Army’s Decision to Take Corrective Action
As a threshold matter, the Protesters maintain that any claims the GAO protesters
might have made about the Army’s failure to conduct discussions and ambiguities in the
solicitation were waived under Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308
(Fed. Cir. 2007). Pursuant to Blue & Gold Fleet, “a party who has the opportunity to object
to the terms of a government solicitation containing a patent error and fails to do so prior
to the close of the bidding process waives its ability to raise the same objection” after the
close of the bidding process. Id. at 1313. This waiver rule ensures that protesters do not
sit on their rights and thereby force more expensive litigation after the agency has closed
the bidding process. Id. at 1314 (citation omitted). The protesters here argue that if the
GAO protesters’ claims were waived, then it was irrational for the Army to conclude that
it faced litigation risk from the GAO protests, and therefore also irrational to institute
corrective action.
The Court disagrees. Even if the GAO protesters had waived their claims under
Blue & Gold Fleet—a question the Court need not address—it still would be reasonable
for the Army to decide to institute corrective action. While the MFR did cite litigation risk
as a reason for instituting corrective action, that litigation risk did not stand alone. Rather,
the MFR predicates its litigation risk assessment on two apparent procurement defects: (1)
common errors offerors made when completing their Equipment Submission Forms, and
(2) the Army’s decision to forgo discussions. Therefore, it is important conceptually to
separate the litigation risk assessment from the procurement defects that caused the risk.
Litigation risk itself is not a procurement defect that can be the predicate for corrective
action. Rather, when agency counsel acknowledges litigation risk in a bid protest, he
acknowledges that the procurement may have contained defects. When the agency takes
corrective action in response to its counsel’s assessment, the agency’s corrective action
targets these defects rather than any legal liability. Therefore, it is reasonable for an agency
to take corrective action to remedy procurement defects even where the agency may have
faced no litigation risk because it may have won a protest on procedural grounds.
Both the Federal Acquisition Regulation (“FAR”) and applicable case law support
this view. FAR § 1.602-2(b) requires contracting officers to ensure “that contractors
receive impartial, fair, and equitable treatment.” Similarly, as this Court noted in Sheridan,
contracting officers are vested with broad discretion to take corrective action when doing
so would ensure fair and impartial competition. 95 Fed. Cl. at 151. Neither the FAR nor
11
any other law limits the contracting officer’s discretion to decide to take corrective action
when confronted with a procurement defect, even where a protest founded upon that defect
might be untimely.
Furthermore, the GAO has found that contracting officers have discretion to take
corrective action in a situation similar to the case at bar:
[I]t is not necessary for an agency to conclude that the protest
is certain to be sustained before it may take corrective action;
rather, where the agency has reasonable concern that there
were errors in the procurement, we view it as within the
agency’s discretion to take corrective action even if the protest
could be denied.
In re Integrated Sci. Sols., Inc., B-406025, 2012 WL 362186, at *2 (Jan. 17, 2012). The
GAO’s approach is especially prudent where a protest could be denied as untimely under
Blue & Gold Fleet. The Blue & Gold Fleet waiver rule protects agencies from expensive
litigation; it is not meant to deter agency action that would remedy procurement defects. It
would therefore be illogical to allow the Protesters here to use this waiver rule as a club to
prevent the Army from addressing errors it has discovered in its procurement. Thus, the
Court finds that the timeliness or untimeliness of the GAO protests alone does not render
the Army’s corrective action irrational.
b.
The Army Rationally Determined That Spreadsheet
Ambiguities and the Failure to Conduct Discussions Were
Procurement Defects
It stands to reason that an agency cannot take action to correct a procurement if the
procurement is not defective. See Sheridan, 95 Fed. Cl. at 151. Here, the Army (through
agency counsel) identified two procurement defects in its MFR: (1) ambiguities in the
spreadsheets that offerors were required to submit as part of their proposals, and (2) the
Army’s failure to conduct discussions (or adequately consider the reasonableness of
conducting discussions).
First, it was rational for the Army to find defects in the ambiguous spreadsheets. In
the MFR, Mr. Farley identified “a couple” examples of spreadsheet ambiguities. See AR
Tab 110b at 5834. He also noted that the Army had recognized offerors’ common failure
to fill out certain parts of the Equipment Submission Form correctly. Id. As set out in full
above, he identified two representative examples of ambiguity: (a) “The hard-line issue
regarding Hard-Drive versus Solid-State Drives”; and (b) “Stating that an upgrade must be
an increase in capability but then stating that selection of an item in a drop-down is
acceptable when there are items in the dropdown that are not upgrades to a base model.”
12
Id. He found that these mistakes were not substantive, but merely “compliance issues with
filling out the form.”
At oral argument, the Government discussed the “hard line issue” the MFR cites as
an example. See Oral Arg Tr. at 65–67, Dkt. No. 135 (June 14, 2017). This issue can be
seen in AR Tab 18 (performance notebook sheet). A slightly thicker black line appears
between the top three rows of the “operating system” column and the bottom three rows.
This circumstance could have led offerors to believe that the top three line items relate to
the hard disk drive component, whereas the bottom three line items relate to the solid state
disk drive. As the Government notes, “if an offeror was to propose a hard disk drive, it
would reasonably understand the spreadsheet’s instructions to mean that the offeror did not
have to complete rows 27 and 28 and could simply select ‘NA.’” This was not the case, as
the Army expected offerors to fill in all line items. The hard line issue misled an
astonishing nineteen offerors, who were then found technically unacceptable. See Def.
Demonstrative 2. Therefore, it was rational for the Army to conclude that spreadsheet
ambiguities such as the hard line issue represented a procurement defect. Put simply, the
Army’s spreadsheet confused offerors and led many of them to input their line item
responses incorrectly. As a result, the Army found many offerors technically unacceptable.
The Court also finds that the Army reasonably considered its failure to conduct
discussions to be a procurement defect. The MFR devotes the bulk of its analysis to this
issue. See AR Tab 110b at 5832–34. The argument starts with DFARS § 215.306(c),
which states, “for acquisitions with an estimated value of $100 million or more, contracting
officers should conduct discussions.” The MFR then discusses In re Science Applications
International Corp., B-413501.2, 2016 WL 6892429 (Nov. 9, 2016) (“SAIC”), a recent
GAO case that interprets DFARS § 215.306(c). In SAIC, the GAO found that the
regulation means “discussions are the expected course of action in DoD procurements
valued over $100 million, but that agencies retain the discretion not to conduct discussions
if the particular circumstances of the procurement dictate that making an award without
discussions is appropriate.” Id. at *8. Therefore, the GAO reviewed the record to
determine whether, “given the particular circumstances of this procurement, . . . there was
a reasonable basis for the agency’s decision not to conduct discussions.” Id. This was the
correct standard of review in spite of the agency’s statement in the solicitation that it
intended to award a contract without conducting discussions. Id. In the end, the GAO
examined the reasonableness of the agency’s decision to forgo discussions using three
factors: (1) whether there were deficiencies in the protester’s proposal, (2) whether “the
awardee’s proposal was evaluated as being technically superior to the other proposals,”
and (3) whether “the awardee’s price was reasonable.” Id. at *9. The solicitation met these
criteria, so the agency’s decision to forgo discussions in SAIC was reasonable. Id.
The MFR addresses SAIC warily, noting, “Because the SAIC case has now
incorporated a means for the GAO to give greater scrutiny to the reasonableness of the
Agency’s decision to not open discussions, we must also look at the underlying rationale,
13
and not just give automatic deference to the contracting officer’s decision.” AR Tab 110b
at 5833. The MFR then turns to the reasons the Army (through the SSEB) gave for not
conducting discussions—the effort involved in evaluating forty-six more proposals, as well
as the fact that there would be no greater variety of computer equipment—and finds them
wanting. First, the MFR states, “Being convenient or providing an efficiency to the Agency
is rarely, if ever, a reasonable rationale for the Agency to not comply with a provision of
law. Therefore, the first reason annotated for not conducting Discussions is not
reasonable.” Id. at 5834. The MFR also notes that the “totality of the circumstances”
showed that the Army’s “no greater variety of laptops, desktops, etc.” reason was better,
but predicted that this reason might not withstand scrutiny given the ease with which the
offerors could have revised their proposals. Id. Therefore, the MFR identified the failure
to conduct discussions as a procurement defect.
The Court finds the MFR’s interpretation of DFARS § 215.306(c) and SAIC
reasonable. Here, it is important to note that the Court does not review an agency’s legal
conclusions about potential procurement defects de novo, as would an appellate tribunal.
Rather, the Court’s role is to review agency decisions for their rationality. Therefore, the
Court finds that it was rational for the Army to find that it may have failed the
reasonableness test articulated in SAIC when it decided to forgo discussions. The Court
finds that the Army’s reasons for forgoing discussions, which are only articulated on one
slide in a PowerPoint presentation, are threadbare and conclusory. It is true that here, as in
SAIC, the Army announced that it would not conduct discussions. However, when
confronted by a situation in which the majority of the offerors appear to have been
disqualified because of minor spreadsheet errors, one would expect the Army to explain its
reasoning a bit more. After all, had the Army conducted discussions before it awarded its
nine contracts, several of the lower-priced offerors may have revised their proposals and
been found technically acceptable. Therefore, it was rational for the MFR to find that the
Army’s failure to conduct discussions constituted a procurement defect.
In sum, the Army rationally identified two procurement defects: (1) ambiguities in
the Equipment Submission Form, and (2) the Army’s failure to hold discussions.
2.
The Army’s Contemplated Corrective Action is Overbroad
Even where an agency has rationally identified defects in its procurement, its
corrective action “must narrowly target the defects it is intended to remedy.” Amazon Web
Servs., Inc. v. United States, 113 Fed. Cl. 102, 115 (2013) (citing Sheridan, 95 Fed. Cl. at
153). For example, in Amazon, the GAO found two defects. Id. at 115–16. The first defect
was a “price evaluation error” that only affected one part of the procurement. Id. at 115.
Therefore, the agency should have simply reevaluated the proposals rather than opening
discussions and soliciting final proposal revisions. Id. For the second defect, the GAO
found that the agency had impermissibly waived one of the solicitation’s material terms.
Id. at 116. Instead of targeting its corrective action to the affected portion of offerors’
14
proposals, the agency impermissibly “elected to use [the defect] as an opportunity to amend
other aspects of the solicitation.” Id. (citation omitted).
This case differs from Amazon in that the defects here are not mere evaluation
errors. Still, the same overbreadth principle applies: an agency cannot use relatively minor
defects to justify the full-scale opening of discussions and allowing revisions to proposals
that do not relate to the defects. Here, the Army attempted to craft corrective action that
addressed both defects (the ambiguous spreadsheet and the failure to conduct discussions).
It opened discussions with all fifty-five remaining offerors and allowed wholesale proposal
revisions as long as those revisions responded to the Army’s Evaluation Notices (“ENs”).
See, e.g., AR Tab 112 at 5960. Those ENs targeted errors not only on the Equipment
Submission Form, but also on the Business Process Form. See, e.g., id. at 5914. The Army
also allowed offerors to revise their final prices in any way they desired. The broad scope
of the corrective action is puzzling because the Army’s requirements had not changed, and
the contracting officer did not amend the Solicitation when it opened discussions (as the
agency had done in Amazon). In sum, the Army opened discussions in which all remaining
offerors, no matter how egregiously they had erred in their initial proposals, simply
received a second chance at submitting compliant proposals under an unchanged
solicitation.
If the Army wished to comply with the GAO’s SAIC decision, it would have been
reasonable for the Army to conduct open-ended discussions before it awarded its contracts.
However, now that the contracts have been awarded, any damage caused by not holding
discussions—including the disqualification of several offerors as a result of clerical
errors—has been done. The question now is whether holding post-award discussions is a
rational remedy for failing to hold pre-award discussions, and the Court finds that this
conclusion does not follow. After all, constructing a henhouse gate is not an appropriate
remedy after the fox has done its work—one instead needs new chickens.
With that heavy-handed analogy in mind, there is a more narrowly targeted postaward solution that the Army entirely failed to consider: clarifications and reevaluation.
After the agency has received proposals, it may engage in clarification exchanges with
offerors pursuant to FAR § 15.306(a). These clarifications “are limited exchanges,
between the Government and offerors, that may occur when award without discussions is
contemplated.” 48 C.F.R. § 15.306(a)(1). Furthermore, “[i]f award will be made without
conducting discussions, offerors may be given the opportunity to clarify certain aspects of
proposals . . . or to resolve minor or clerical errors.” Id. § 15.306(a)(2). Though they
address minor or clerical errors, clarifications can result in substantive changes to an
offeror’s proposal; for example, “clarifications by one offeror could lead to an increase in
its past performance score or perhaps tilt the award in its favor.” Info. Tech. & Appl. Corp.
v. United States, 316 F.3d 1312, 1323 (Fed. Cir. 2003) (citation omitted). Still,
clarifications “are not to be used to cure proposal deficiencies or material omissions,
materially alter the technical or cost elements of the proposal, or otherwise revise the
15
proposal.” JWK Int’l Corp. v. United States, 52 Fed. Cl. 650, 661 (2002), aff’d, 56 F.
App’x 474 (Fed. Cir. 2003) (quoting Charleston Marine Containers, Inc., B-283393, 1999
WL 101556884, at *4 (Nov. 8, 1999)). Thus, the general rule is that clarifications are
appropriate for correcting non-material or clerical errors. More substantive exchanges
require discussions.
Griffy’s Landscape Maintenance LLC v. United States, 46 Fed. Cl. 257 (2000) aptly
illustrates the purpose and proper use of clarifications. In Griffy’s Landscape, the Court
addressed a negotiated procurement in which a bidder’s “insurance point of contact
information” was missing from its proposal. Id. at 257. Therefore, the Army evaluated
the bidder negatively under the past performance factor. Id. The Army did not hold
discussions with offerors, but simply awarded the contract to a different bidder, even
though that bidder had submitted a much higher price. Id. at 258. The Court found that
the Army had a “duty to inquire” about the absence of this point of contact information,
noting that “the government should not be deprived of the best possible contract because
of a contractor’s clerical error.” Id. at 259–60. Faced with such a minor omission, the
Army’s decision not to seek clarification from the bidder was irrational. Id. at 261. In
reaching its conclusion, the Court distinguished GAO decisions such as Charleston Marine,
finding that in such cases “the contractors both failed to submit important information and
submitted incorrect or non-responsive information. There was no indication this was due
to a clerical error. There is a world of difference between material deficiencies and a lost
name and number.” Id. The Court concluded, “The government’s obligation is clear and
simple. If it suspects a clerical error, it must ask.” Id. at 261.
Though Griffy’s Landscape did not analyze clarifications as a means of corrective
action, the Court finds that the principles articulated in that case are relevant here. As in
Griffy’s Landscape, the Court finds that many of the losing offerors in this procurement
made minor or clerical errors that fall within the purview of FAR § 15.306(a).4 Many of
the offerors here did not make material mistakes; rather, they filled out a confusing Excel
spreadsheet incorrectly. Mistakenly omitting information from a spreadsheet in this way
is akin to the bidder’s omission of minor point-of-contact information in Griffy’s
Landscape. Furthermore, as in Griffy’s Landscape, the Army had notice that a clerical
error had likely occurred. In Griffy’s Landscape, the Army had previously contracted with
the bidder, so it should have known that the bidder had compliant insurance information.
Id. at 260. Similarly, the Army here knew that ambiguities in its spreadsheet had likely
caused offerors to make clerical errors. Indeed, the MFR itself acknowledges the “logical
conclusion” that offerors were disqualified because of “mere[] compliance issues with
filling out the form rather than a deficiency in the item proposed.” If this language does
Courts have since maintained that the holding in Griffy’s Landscape should be limited to clerical errors.
See, e.g., C.W. Over & Sons, Inc. v. United States, 54 Fed. Cl. 514, 521 n.10 (2002). In citing Griffy’s
Landscape here, the Court does not disturb their conclusion, as the errors many of the offerors made here
were clerical.
4
16
not suggest the Army knew that offerors had made clerical errors, it is difficult to see what
would.
As such, it was irrational for the Army not to seek clarification from all offerors it
knew had been directly affected by the ambiguities it had identified in its own spreadsheet.
Doing so would not have given all offerors the chance to make their proposals technically
acceptable—there are several offerors who made more wide-reaching errors—but it would
have given the offerors who justifiably thought they were proposing compliant equipment
the chance to show that they were in fact proposing compliant equipment. The Army then
could have reevaluated the offerors’ proposals instead of resoliciting new proposals.
In sum, it was irrational for the Army to fail to consider clarifications and
reevaluation of proposals as a more natural expedient for the minor clerical errors it had
identified. The Army instead opened wide-reaching discussions with all remaining
offerors and allowed all offerors to submit modified proposals with new prices, despite
having disclosed the awardees’ winning prices.5 This is manifestly overbroad; in fact, it is
akin to killing an ant with a sledgehammer when a rolled-up newspaper would have
sufficed. Therefore, the Court finds that the Army’s corrective action is not rationally
related to any procurement defects.
C.
The Army’s Action Prejudiced the Protesters
A court cannot grant relief in a bid protest unless the agency’s unlawful action has
prejudiced the protesters. See Bannum, 404 F.3d at 1351. In pre-award protests and,
consequently, in protests challenging corrective action, a protester establishes prejudice by
showing “a non-trivial competitive injury which can be addressed by judicial relief.”
Square One Armoring Serv., Inc. v. United States, 123 Fed. Cl. 309, 320 (2015) (quoting
Sys. Appl. & Techs., Inc. v. United States, 691 F.3d 1374, 1382 (Fed. Cir. 2012)). Here,
the Army’s overbroad corrective action constitutes a non-trivial competitive injury because
it substantially decreases the chance each of the Protesters otherwise has of receiving an
award. Had the agency followed the more logical step and engaged in clarification
exchanges, the Protesters would have had a greater likelihood of receiving contract awards
because their initial proposals were compliant and all but one of their proposed prices were
in the lower half of the fifty-five offers. See Def. Demonstrative 1 (highlighting awardees’
5
Disclosure of the awardees’ winning prices here was lawful. See Wildflower Int’l, Ltd. v. United States,
105 Fed. Cl. 362, 391 (2012). Allowing wholesale price revisions without any record support was not.
Neither the MFR nor the rest of the administrative record provide support for allowing price revisions. The
MFR states merely that “[a]llowing Offerors to change price would also benefit the Agency by getting
offers that are a better value to the Government.” While true, this statement on its face does not provide a
rational basis for soliciting new prices. See, e.g., WHR Grp., Inc. v. United States, 115 Fed. Cl. 386, 398
(2014) (“[T]he contracting officer’s bald assertions in the notes to file will not suffice because the agency
failed to examine the relevant data and articulate a coherent and reasonable explanation for their decision.”)
(citation omitted).
17
prices amid all proposed prices). As it is, the Army’s round of discussions opens the door
for all offerors to revise their proposals and prices such that they become more competitive.
The Court is capable of fashioning relief to address this competitive injury. Therefore, the
Protesters have established prejudice.
D.
The Protesters are Entitled to Relief
The Protesters seek both declaratory relief and a permanent injunction on the
Army’s corrective action. The Court may award “any relief that [it] considers proper,
including declaratory and injunctive relief.” 28 U.S.C. § 1491(b)(2). First, the Court
grants declaratory relief for the reasons stated above. The Court finds the Army’s
contemplated corrective action manifestly overbroad, and therefore irrational and
unlawful.
Second, the Court grants the Protesters’ request for a permanent injunction. A court
may grant injunctive relief if “(1) the plaintiff has succeeded on the merits, (2) the plaintiff
will suffer irreparable harm if the court withholds injunctive relief, (3) the balance of
hardships to the respective parties favors the grant of injunctive relief, and (4) the public
interest is served by a grant of injunctive relief.” Centech Grp., Inc. v. United States, 554
F.3d 1029, 1037 (Fed. Cir. 2009) (citation omitted). Here, the Protesters have succeeded
on the merits. Second, the Court finds that the Protesters would suffer irreparable harm if
the court withholds injunctive relief. The Protesters would be forced to recompete
wholesale for contracts they have already won. Further, as in Sheridan, discussions would
also force the Protesters to bid against their own prices. See 95 Fed. Cl. at 155.
The Court also finds that the balance of hardships favors the Protesters here. The
Government would suffer some hardship if it decided to engage in more limited
clarification exchanges, as this would require more effort on top of the effort already
expended in drafting its ENs. Still, in fashioning its clarification questions, the
Government would be free to look to offerors who stand a realistic chance of receiving an
award after clarifications; in other words, the Army would not need to review every single
proposal anew, as it would if it followed its current corrective action plan.6 In contrast, the
Protesters would face an elevated risk of losing their awards if the Army were to conduct
discussions. Thus, the balance of hardships favors the Protesters.
Finally, the public interest favors granting injunctive relief here. Corrective action
is something the judicial system should and does encourage. Still, allowing an agency to
respond disproportionately to minor procurement errors harms the integrity of the
procurement system because it introduces an unfair and unanticipated additional layer of
competition to a procurement. Agencies have broad discretion to institute corrective
6
Moreover, counsel for the Government indicated at oral argument that it would be “a very easy fix” to
craft more narrowly-targeted corrective action if the Court were to find the Army’s current corrective action
plan too broad. See Oral Arg. Tr. at 74.
18
action, but offerors should be secure in the knowledge that any corrective action an agency
implements will narrowly target the procurement defects the agency has identified.
Finally, enjoining the Army’s current corrective action plan does not mean the Army
cannot pursue more reasonable corrective action within the boundaries described above.
Therefore, granting a permanent injunction is in the public interest in this case.
Conclusion
Plaintiffs and Plaintiff-Intervenors’ cross-motions for judgment on the
administrative record are GRANTED. Defendant and Defendant-Intervenors’ motions for
judgment on the administrative record are DENIED. Having found that the prerequisites
for entering a permanent injunction are satisfied, the Court hereby permanently ENJOINS
Defendant from conducting its proposed corrective action. The Clerk is directed to enter
judgment for Plaintiffs and Plaintiff-Intervenors.
IT IS SO ORDERED.
s/Thomas C. Wheeler
THOMAS C. WHEELER
Judge
19
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?