In the United States Court of Federal Claims
No. 21-1047C
Filed: June 30, 2021 1
(**SEALED**)
SIGNET TECHNOLOGIES, INC.,
DOING BUSINESS AS CONVERGINT
FEDERAL SOLUTIONS,
Plaintiff,
v.
THE UNITED STATES,
Defendant,
and
SECURITYHUNTER, INC.,
Intervenor-Defendant.
Ira Hoffman, Butzel Long, Washington, D.C., for Plaintiff.
Mikki Cottet, Senior Trial Counsel, Franklin E. White, Jr., Assistant Director, Martin F. Hockey,
Jr., Acting Director, Brian M. Boynton, Acting Assistant Attorney General, Commercial
Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for
Defendant.
James Y. Boland and Krista Nunez, Venable, LLP, Vienna, VA, for Intervenor-Defendant.
MEMORANDA OPINION AND ORDER
TAPP, Judge.
This bid protest considers whether the Social Security Administration (“SSA”) erred
when it established a vehicle for the purchase, maintenance, and installation of security system
This Order was originally filed under seal on June 16, 2021, (ECF No. 44). The Court provided
parties the opportunity to review this Opinion for any proprietary, confidential, or other protected
information and submit proposed redactions. The proposed redactions were filed June 30, 2021,
(ECF No. 48) and are accepted by the Court. Thus, the sealed and public versions of this Opinion
differ only to the extent of those redactions, the publication date, and this footnote.
1
equipment in its offices across the United States. On March 10, 2021, Plaintiff, SigNet
Technologies, Inc., doing business as Convergint Federal Solutions, (“SigNet”) 2, filed its
Complaint against Defendant, United States, acting by and through the SSA. (See Complaint
(“Compl.”), ECF No. 1). SigNet asserts that the SSA impermissibly established an agreement for
the purchase and installation of security equipment at SSA offices. (Id.). In turn, SigNet requests
declaratory injunctive relief providing that the SSA’s award lacks a rational basis and is
otherwise unreasonable, arbitrary and capricious, and contrary to applicable law and regulation.
(Id.). The awardee, Securityhunter, Inc. (“Securityhunter”), successfully intervened in this suit
on March 11, 2021. (ECF No. 10).
Before the Court are the parties’ Cross-Motions for Judgment on the Administrative
Record and Securityhunter’s Motion to Dismiss. For reasons articulated below, the Court
DENIES SigNet’s Motion for Judgment on the Administrative Record, (Pl.’s MJAR, ECF No.
25), GRANTS the United States’ Motion for Judgment on the Administrative Record, (Def.’s
MJAR, ECF No. 28), GRANTS Securityhunter’s Motion for Judgment on the Administrative
Record, (Int.-Def.’s MJAR, ECF No. 29), and DENIES Securityhunter’s Motion to Dismiss and
Motion to Strike, (id.).
I.
Background 3
A. The Solicitation
This post-award bid protest involves a challenge to the SSA’s decision to establish a
Blanket Purchase Agreement (“BPA”) with Securityhunter for the purchase and installation of
security equipment. On June 10, 2020, the United States issued a Request for Quotations4
(“RFQ”) seeking to establish a Physical Security Systems Standardization and Support Services
(“PS5”) BPA for “equipment, acquisition, installation and maintenance services to support
project management, site system design, installation, maintenance, inventory management,
miscellaneous work and repair of security equipment at [SSA] offices” at approximately 1,500
Throughout the United States’ and Intervenor-Defendant’s briefing, Plaintiff is referred to as
“Convergint.” The initial filing from Plaintiff refers to itself as “SigNet.” For uniformity, this
Opinion refers to Plaintiff as “SigNet.”
2
The Administrative Record, (ECF No. 24), is consecutively paginated, thus the Court will cite
to the record using “(AR __).” On May 24, 2021, the United States moved to amend the record
after it discovered errors preventing the parties from accessing a portion of the AR. (ECF No.
37). The Court granted the United States’ motion and accepted corrected attachment, which
replaced pages 453–678 of the Administrative Record. (ECF Nos. 37-1; 40). Any citations to that
portion of the record reflect citation to the corrected document.
3
4
Solicitation No. 28321320Q00000234.
2
locations nationwide. (Administrative Record (“AR”) 557). 5 In an effort to enhance its physical
security, the SSA sought to establish this BPA to provide “standardized video services including
video surveillance systems (VSS), intrusion detection systems (IDS), duress alarms, and physical
access control systems (PACS), and other physical security equipment installation, maintenance,
and support services” to all SSA offices. (AR 523).
The RFQ articulated multiple requirements, only some of which are relevant here. The
Statement of Work (“SOW”) explained that the BPA “intended to serve as a vehicle for the
purchase of all security system equipment and materials required for maintenance and
installations.” (AR Tab 23 at 1715 (“the SOW”)). The SOW outlined various requisite services,
including design, installation, maintenance, and physical security assessments, and noted Lenel 6
products as just one of many other branded systems currently in place at the SSA. (See AR Tab
23 at 1715–17).
The RFQ instructed offerors to submit their quotes in two separate volumes—Volume I
(Non-Price) and Volume II (Price). (AR 1701). In Volume I, offerors provided proposed
solutions, information, and specified materials consistent with the Corporate Experience, Past
Performance, and Technical Approach factors outlined in the RFQ. (See AR 1702–07). As part
of their Volume II quotes, offerors submitted “[c]omplete pricing tables found in Section
D/Attachment 3” of the RFQ, which included the mandatory “Pricing Schedule” template that
detailed the required labor, equipment, and maintenance line items. (AR 1708).
Importantly, the RFQ authorized the use of Contractor Teaming Arrangements (“CTAs”),
described and explained as follows:
A Schedule Contractor Teaming Arrangement (CTA) is an arrangement
between two or more Schedule Contractors to work together to meet agency
requirements. The CTA allows the Contractor to meet the government agency
needs by providing a total solution that combines the supplies and/or services
from the team members’ separate Schedule contracts. . . .
A CTA document is required for any proposed CTA under this BPA. A CTA
document is a written agreement between the team members detailing the
responsibilities of each team member during the BPA performance period. If
a CTA is proposed, the Contractor shall specifically identify the CTA as such
The SSA amended the RFQ six times, (AR 288–706, 2181–82), and responded to offeror’s
questions in amendments 3 and 5, (AR 382–391, 511–522, 2182). Unless otherwise indicated,
references to the solicitation are to amendment 5, (AR 453–678), which incorporates all prior
amendments to the RFQ. (See also AR 2758–83).
5
Lenel is the producer of some portion of the equipment and software required for performance
of the BPA; in order to sell, implement, and service Lenel security systems, a contractor must be
certified by Lenel as a Value Added Reseller (“VAR”). (Compl. at 12–16).
6
3
in its quotation. The Contractor’s CTA document must be complete and fully
executed between the parties. If a CTA is proposed, the Contractor shall
identify a Team Lead to be the main point of contact between the Government
and the CTA Team Members. The CTA Team Lead will be responsible for
all communication, ordering procedures, delivery requirements, invoicing
and payment, warranties and all other activities within the CTA “model”
document (See [AR 2980-82]). The Contractor’s CTA document must be
submitted to the government as part of its quotation in response to this RFQ.
Failure to provide a complete and fully executed CTA document in
accordance with this solicitation will result in no further consideration of the
Contractor’s quotation . . ..
(AR 2801–02). The RFQ pointed offerors to GSA’s website for further information regarding
this explanation. (See AR Tab 23 at 1700).
The RFQ then set forth the terms of the “quote format,” stating: “Quotes must set forth
full, accurate, and complete information as required by this RFQ. The government will rely on
such information in the award of the BPA.” (AR 2803 (emphasis added)).
The RFQ set forth the “evaluation factors” as follows:
The Government intends to establish a single-award BPA to the responsible
contractor whose quote, conforming to the RFQ, represents the best value to
the Government, considering both price and non-price factors. This may be
determined by using a trade-off process that allows us to consider award to
other than the lowest price Contractor or other than the highest technically
rated Contractor. For this solicitation, all non-price evaluation factors, when
combined, are significantly more important than price. The non-price factors
([1] Corporate Experience, [2] Past Performance, and [3] Technical
Approach) have equal weight/importance. SSAS intends to make an award
based on initial quotations.
(AR 2812 (italics in original; numbers in brackets added)).
The SSA was to evaluate the first non-price factor by assessing the relevance of an
offeror’s Corporate Experience, considering the extent to which the offeror’s maximum of three
“identified projects/contracts adequately demonstrate its experience in providing
supplies/services similar in size, scope, and complexity” to the requirements under the RFQ.
(Id.). The RFQ instructed offerors to include descriptions of at least one, but no more than three,
contracts/projects that “clearly and conclusively demonstrate the Contractor’s relevant
experience (similar in size, scope, and complexity)” to the RFQ’s requirements. (AR 2804). The
information that offerors were to provide for each contract/project for the evaluation of
Corporate Experience included the following:
A complete and full description of the services provided (in your role as either
the Prime Contractor, CTA member, or subcontractor) for each
contract/project. Specifically, describe the extent to which the work
4
performed under the cited/referenced contract/project is similar in size,
scope, and complexity to the requirements set forth in the Statement of Work
(SOW) and elsewhere in this solicitation.…
(AR 2805).
The RFQ notified offerors that submitted quotations be made as a CTA and include a
“complete” “CTA document,” addressing “each element in the CTA ‘model’. . ..” (AR 2810).
Providing guidance for evaluating CTAs for Corporate Experience, the RFQ stated:
Contractor Team Arrangements (CTA): SSA will evaluate Corporate
Experience and Past Performance of each party to the CTA only to the extent
that it relates to the work that each party will be responsible for under the
BPA. Previous experience and past performance of the CTA, operating as a
CTA (comprised of the same CTA members), is considered more relevant
than experience and past performance of the individual parties to the CTA,
as it represents experience and past performance of the team rather than that
of the individual players.
(AR 2813 (bold emphasis in original)).
For Past Performance, the RFQ explained that the evaluation would be a “subjective
assessment based on performance history on the contracts/projects cited in the ‘Corporate
Experience’ section of the Contractor’s quotation.” (AR 2806). The SSA was to evaluate the past
performance of the contractor’s identified projects/contracts based on information in the
quotation, responses to the Past Performance Questionnaires received from references, and
additional pertinent information relative to the offeror’s Contractor Performance Assessment
Reporting System. (AR 2813–14). This evaluation would be based on the quality of service,
timeliness of performance, and management of personnel/business relations. (AR 2814).
As to Technical Approach—the final non-Price factor—the RFQ stated in part as follows:
The Technical Approach section must thoroughly describe in narrative form
the solution proposed by the Contractor, and must be sufficiently specific,
detailed and complete to clearly and fully demonstrate the techniques and
procedures the Contractor will employ to meet all of the requirements of the
SOW….
(AR 2808). As part of its Technical Approach, the RFQ required each offeror to submit a
“staffing plan” proposing a “project team for the BPA, as well as the ability to deliver personnel
with the appropriate knowledge, experience and skills throughout the entire period of
performance, including options.” (Id.). The SSA should consider “specifics” of the technical
approach, and quotations must “clearly demonstrate an understanding of the government’s
requirements and provide a high likelihood for success to be eligible for award.” (AR 2814).
Turning to pricing, the RFQ indicated that the Agency “will perform a price analysis . . .
to evaluate the contractor’s submission for completeness, accuracy, and reasonableness.” (AR
2815). The SSA was to evaluate quotations for award purposes by adding the total price for the
5
performing a trade-off, consistent with how SSA identified that the
quotations would be evaluated in Solicitation Section E-6 Evaluation Criteria.
(AR 2595).
C. SigNet’s GAO Protest and Protective Order
On October 13, 2020, SigNet filed a protest 10 with the United States Government
Accountability Office (“GAO”) challenging the SSA’s award of the BPA to Securityhunter. (See
AR Tab 47 at 2610–20). The GAO entered an automatic stay under the Competition in
Contracting Act (CICA) and Securityhunter was instructed to suspend contract performance on
October 14, 2020. (Def.’s MJAR, Ex. 1 (“Brennan Decl.”)). On November 25, 2020, rather than
filing comments or supplemental protest grounds, SigNet filed a notice withdrawing its protest.
(See AR Tab 60 at 3231). The GAO closed the protest file that same day. (See AR Tab 61 at
3232). More than three months after voluntarily withdrawing its protest with the GAO, on March
10, 2021, SigNet filed its Complaint pursuant to 28 U.S.C. § 1491(b). (See Compl.).
II.
Analysis
A. Motion to Strike Complaint and Dismiss
The Court will first address Securityhunter’s Motion to Strike SigNet’s Complaint and
motion for outright dismissal. Securityhunter asserts two grounds for dismissing SigNet’s
Complaint—failure to state a claim for which relief can be granted and for lack of subject matter
jurisdiction. (See generally Int.-Def.’s MJAR).
The burden of establishing subject matter jurisdiction rests with the plaintiff, who must
do so by a preponderance of the evidence. Lujan v. Defenders of Wildlife, 504 U.S. 555, 561
(1992); Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988). When
faced with a motion to dismiss for lack of subject matter jurisdiction according to the RCFC
12(b)(1), the Court must assume that all undisputed facts alleged in the complaint are true and
draw all reasonable inferences in the plaintiff’s favor. Scheuer v. Rhodes, 416 U.S. 232, 236
(1974), overruled on other grounds by Davis v. Scherer, 468 U.S. 183 (1984); see also Henke v.
United States, 60 F.3d 795, 797 (Fed. Cir. 1995). In determining whether a plaintiff has met this
burden, courts may look “beyond the pleadings and ‘inquire into jurisdictional facts’ in order to
determine whether jurisdiction exists.” Lechliter v. United States, 70 Fed. Cl. 536, 543 (2006)
(quoting Rocovich v. United States, 933 F.2d 991, 993 (Fed. Cir. 1991)).
A protective order was issued during SigNet’s sojourn at the GAO. (ECF No. 18, Ex. A
(“GAO Protective Order”)). Securityhunter alleges that SigNet used protected materials obtained
during GAO proceedings in its Complaint before this Court—specifically Securityhunter’s
sealed bid proposal. (ECF No. 18; see also Int.-Def.’s MJAR at 10). Due to that alleged
violation, Securityhunter urges the Court to strike relevant portions of SigNet’s Complaint
10
GAO Docket No. B-419328.1.
8
pursuant to RCFC 12(f) and dismiss the Complaint for failure to state a claim. (Int.-Def.’s MJAR
at 11–16). The Court declines to do so.
Paragraphs 7 and 8 of the GAO-issued Protective Order state:
7. Within 60 days after the conclusion of the protest (including any requests
for reconsideration or entitlement, or claims for costs), each party admitted
to this protective order must destroy all protected material received pursuant
to this protest, including all electronically transmitted material and copies of
such material, with the exception of a single copy of a protected decision or
letter issued by our Office, and certify in writing to each other party that such
destruction has occurred or must return the protected information to the
parties from which the information was received . . .. Any individual retaining
material received under this protective order (except for the single copy of a
protected decision or letter issued by our Office) beyond the 60-day period
without the authorization of GAO or the prior written agreement of the party
that produced the material is in violation of this order. . . The terms of this
protective order (except those terms regarding the return or destruction of
protected material) shall apply indefinitely to the single copy of the protected
decision or letter issued by our Office that is retained by a party admitted
under this order.
8. Material to which parties gain access under this protective order is to be
used only for the subject protest proceedings, absent express prior
authorization from the GAO. Protected material obtained under this
protective order may be used, however, in a bid protest filed with the United
States Court of Federal Claims, without GAO’s prior authorization, provided
that the information is filed under seal with the Court, that the Court is
informed of GAO’s protective order, and that the Court is requested to issue
its own protective order to cover the protected material. In addition, GAO
must be notified no later than one business day after suit is filed with the
Court, regardless of whether protected information is used in the Court filing.
After the Court issues its own protective order, use of material protected
under the GAO protective order will be governed by the protective order
issued by the Court.
(GAO Protective Order ⁋⁋ 7–8).
A significant portion of SigNet’s Complaint is indeed related to Securityhunter’s
quotation and proposal. (See Compl. at 20–29). SigNet does not controvert that it retained
information garnered from the GAO protest; instead, SigNet contends that it was exempt from
the GAO’s 60-day retention cap because the protected documents were retained concerning this
bid protest. (ECF No. 20; see also Pl.’s Resp. 14–15).
On April 6, 2021, Securityhunter filed a notice with the GAO describing the alleged
violations of that protective order and requested a determination as to those violations. (Int.Def.’s MJAR at 10–11). In that request, “Securityhunter explained to the GAO that the
9
Complaint filed in this case relied extensively on portions of Securityhunter’s proposal that
counsel for SigNet was required to destroy no later than January 25, 2021, per Paragraph 7 of the
GAO’s protective order.” (Id. at 11). On May 6, 2021, the GAO apparently informed the parties
that it was “still reviewing the filings submitted by the parties” and that it would inform the
parties of its decision at a later date. (Id.). As far as the Court is aware, the GAO has not issued a
determination as to SigNet’s apparent violations.
The crux of Securityhunter’s argument for striking the Complaint, and ultimately
dismissal, is that SigNet’s use of information which it improperly retained from the earlier GAO
proceeding effectively rendered the protected material “fruit of the poisonous tree.” 11 RCFC
12(f) empowers the Court to “strike from a pleading . . . any redundant, immaterial, impertinent,
or scandalous matter” and states that the Court “may act . . . on its own.” Securityhunter alleges
that, should SigNet’s Complaint be stricken under this rule, the Complaint would fail to state a
claim for which relief could be granted pursuant to RCFC 12(b)(6).
The Court is apprehensive regarding its role, if any, in interpreting protective orders
issued by a different forum, particularly when that forum has the issue squarely before it and has
yet to rule. To do so could present significant and consequential procedural issues, running
counter to notions of judicial efficiency and restraint. Hypothetically, if the Court were to find
that a violation exists, thereby ruling in Securityhunter’s favor, but the GAO later found to the
contrary, what remedy could reconcile those inconsistent rulings? Short of reopening this protest
and starting anew, there are no other channels for relief. Without a ruling from the GAO, this
Court is unable to definitively rule that the information SigNet used in its Complaint was
improper and therefore should be stricken pursuant to RCFC 12(f). Since there has been no
ruling, and because this protest is denied on other grounds set forth below, the Court will not act
absent the GAO’s application of its own protective order. As such, Securityhunter’s Motion to
Strike is denied and SigNet’s Complaint will not be dismissed on these grounds.
Securityhunter next insists the Court dismiss SigNet’s Complaint pursuant to RCFC
12(b)(1) based on what it perceives as SigNet’s failure to comply with material requirements of
the RFQ. (Int.-Def.’s MJAR at 16–23). Securityhunter claims that, because SigNet apparently
failed to comply with the material requirements of the RFQ, it thus lacks standing to pursue
relief in this Court. (Id.).
Standing is a threshold issue that implicates the Court’s subject-matter jurisdiction.
Lujan, 504 U.S. at 560–61. And so, if a plaintiff cannot establish standing, the Court is without
jurisdiction to render a decision on the merits of a claim. Myers Investigative & Sec. Servs. v.
United States, 275 F.3d 1366, 1369–70 (Fed. Cir. 2002). The Court assumes well-pled
allegations of error to be true for purposes of the standing inquiry. Square One Armoring Serv.,
In context of criminal law, the exclusionary rule encompasses both the “primary evidence
obtained as a direct result of an illegal search or seizure” and, relevant here, “evidence later
discovered and found to be derivative of an illegality,” the so-called “‘fruit of the poisonous
tree.’” Utah v. Strieff, 136 S. Ct. 2056, 2061, (2016) (citing Segura v. United States, 104 S.Ct.
3380, (1984)). The Court draws parallels to this suit in that the protected materials used in
SigNet’s Complaint are allegedly derivative of the improper retention of materials.
11
10
Inc. v. United States, 123 Fed. Cl. 309, 323 (2015) (citing Digitalis Educ. Sols., Inc. v. United
States, 97 Fed. Cl. 89, 94 (2011), aff’d, 664 F.3d 1380 (Fed. Cir. 2012)). Under the Tucker Act,
the Court has jurisdiction over “an action by an interested party objecting . . . to an alleged
violation of a statute or regulation with a procurement or a proposed procurement.” 28 U.S.C. §
1491(b)(1). In evaluating who qualifies as an interested party with standing to bring a bid protest
claim, the Court looks to the definition of “interested party” provided in CICA. Myers, 275 F.3d
at 1370 (quoting Am. Fed’n of Gov’t Employees v. United States, 258 F.3d 1294, 1302 (Fed. Cir.
2001)); see 31 U.S.C. § 3551(2). And so, to have standing, a plaintiff must show that: “‘it [(1)] is
. . . an actual or prospective bidder and [(2)] . . . has a direct economic interest’ in the
procurement or proposed procurement.” Diaz v. United States, 853 F.3d 1355, 1358 (Fed. Cir.
2017) (alterations in original) (quoting Digitalis Educ. Sols., Inc. v. United States, 664 F.3d
1380, 1384 (Fed. Cir. 2012)); see also 31 U.S.C. § 3551(2).
While Securityhunter’s arguments to this point are well-reasoned, the Court cannot
ignore the United States’ determination (and concession) that SigNet’s quotation was compliant
with solicitation requirements. (Def.’s MJAR at 11 (“[t]he SSA received and evaluated three
quotes, including quotes from Convergint and Securityhunter, which were all determined to be
timely and compliant with the solicitation requirements) (citing AR 2065–66, 2067, 2182)). The
Court cannot reasonably defer to the agency’s discretion in its ultimate decision while ignoring
its ground-level determination that an offeror complied with the RFQ requirements. Because the
United States effectively concedes that SigNet’s quotation largely complied with the RFQ, the
Court will not dismiss SigNet’s Complaint for failure to establish standing.
Based on these findings, the Court denies Securityhunter’s Motion to Strike and Dismiss.
SigNet’s claims will be addressed on the merits.
B. Motions for Judgment on the Administrative Record
In bid protest cases, this Court reviews agency actions under the Administrative
Procedure Act’s “arbitrary and capricious” standard. See 28 U.S.C. § 1491(b)(4); 5 U.S.C. §
706(2)(A), (D). Under this standard, an “award may be set aside if either (1) the procurement
official’s decision lacked a rational basis; or (2) the procurement procedure involved a violation
of regulation or procedure.” Impresa Construzioni Geom. Domenico Garufi v. United States, 238
F.3d 1324, 1332 (Fed. Cir. 2001).
When a challenge is brought on the first ground like the instant case, the test is whether
“the contracting agency provided a coherent and reasonable explanation of its exercise of
discretion, and the disappointed bidder bears a ‘heavy burden’ of showing that the award
decision ‘had no rational basis.’” Id. at 1332–33 (internal citations omitted). In this regard,
“courts have recognized that contracting officers are ‘entitled to exercise discretion upon a broad
range of issues confronting them’ in the procurement process.” Id. at 1332. In addition, when
reviewing an agency’s procurement decision, the Court should recognize that the agency’s
decision is entitled to a “presumption of regularity.” Citizens to Preserve Overton Park, Inc. v.
Volpe, 401 U.S. 402, 415 (1971), overruled on other grounds by Califano v. Sanders, 430 U.S.
99 (1977). “The [C]ourt should not substitute its judgment for that of a procuring agency.”
Cincom Sys., Inc. v. United States, 37 Fed. Cl. 663, 672 (1997). And so, “[t]he protestor must
show, by a preponderance of the evidence, that the agency’s actions were either without a
11
reasonable basis or in violation of applicable procurement law.” Info. Tech. & Applics. Corp. v.
United States, 51 Fed. Cl. 340, 346 (2001), aff’d, 316 F.3d 1312 (Fed. Cir. 2003) (citation
omitted).
The Court’s standard of review “is highly deferential.” Advanced Data Concepts, Inc. v.
United States, 216 F.3d 1054, 1058 (Fed. Cir. 2000). If there is “a reasonable basis for the
agency’s action, the court should stay its hand even though it might, as an original proposition,
have reached a different conclusion.” Honeywell, Inc. v. United States, 870 F.2d 644, 648 (Fed.
Cir. 1989) (quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301 (D.C. Cir. 1971)).
Stated differently, “[the Court] will uphold a decision of less than ideal clarity if the agency’s
path may be reasonably discerned.” Bowman Transp., Inc. v. Arkansas-Best Freight Sys., Inc.,
419 U.S. 281, 286 (1974). However, if “the agency ‘entirely fail[s] to consider an important
aspect of the problem [or] offer[s] an explanation for its decision that runs counter to the
evidence before the agency,’” then the resulting action lacks a rational basis and, therefore, is
defined as “arbitrary and capricious.” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586
F.3d 1372, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto.
Ins. Co., 463 U.S. 29, 43 (1983)).
Unlike RCFC 56 summary judgment motions, “the existence of genuine issues of
material fact does not preclude judgment on the administrative record” under RCFC 52.1. Tech.
Sys., Inc. v. United States, 98 Fed. Cl. 228, 242 (2011); see also RCFC 56. Rather, the Court’s
inquiry is whether, “given all the disputed and undisputed facts, a party has met its burden of
proof based on the evidence in the record.” A&D Fire Prot., Inc. v. United States, 72 Fed. Cl.
126, 131 (2006) (citing Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed. Cir. 2005)).
In its Complaint and Motion for Judgment on the Administrative Record, SigNet
propounds two primary explanations why it believes the United States acted improperly: first,
Securityhunter’s quotation did not include a complete CTA document in violation of the RFQ;
and second, the SSA failed to conduct the evaluations fairly and consistently with the RFQ’s
evaluation scheme. Not unexpectedly, the United States and Securityhunter argue to the contrary
and separately move for judgment. The arguments will be addressed in turn.
1. Completeness of Securityhunter’s CTA
SigNet contends that the SSA should have disqualified Securityhunter from award
because its CTA was incomplete and thus “defective.” (Pl. MJAR at 33–34). Specifically, SigNet
indicates that Securityhunter’s CTA document did not adequately address the following elements
in the model CTA: Specific Team Activities, Terms of Arrangement, Team Ordering Procedures,
Responsibilities of Team Lead, Responsibilities of Team Members, Pricing, Delivery
Responsibility, Liabilities, and Legal Relationship. (Id.). As such, SigNet postulates that the SSA
violated the express terms of the RFQ when it continued to consider Securityhunter’s quotation.
(Id.). The United States argues that SigNet misapprehends the RFQ and that the RFQ did not
require a proposed CTA document to mirror the format of the model document. (Def.’s MJAR at
20). Securityhunter counters that its proposal did in fact satisfy each element of the CTA
requirements. (Int.-Def.’s MJAR at 23–32). The Court finds that Securityhunter’s quote
addressed all elements as required by the RFQ.
12
As the Federal Circuit has explained, “a proposal that fails to conform to the material
terms and conditions of the solicitation should be considered unacceptable and a contract award
based on such an unacceptable proposal violates the procurement statutes and regulations.” E.W.
Bliss Co. v. United States, 77 F.3d 445, 448 (Fed. Cir. 1996) (citation omitted); see also Centech
Grp., Inc. v. United States, 554 F.3d 1029, 1037 (Fed. Cir. 2009) (“To be acceptable, a proposal
must represent an offer to provide the exact thing called for in the request for proposals, so that
acceptance of the proposal will bind the contractor in accordance with the material terms and
conditions of the request for proposals.”).
As recited above, the RFQ set forth the requirements when an offeror’s quotation
proposed a CTA and provided a referential “model” CTA, (AR 496–97; 284–86). The model
required that the relevant document (1) “state the various types of activities that will be
incorporated into the team arrangement and who is the primary party responsible for the
particular activity,” (AR 284), (2) “define the whole course of the project,” (3) “specify the
duration, the players, the responsibilities, and the limitations of the various players,” (id.), (4)
outline and specify the duties of the designated team lead at each phase of the project specify and
describe the individual duties of the team member, (id.), (5) “state whether the team lead or each
team member is responsible for a particular part of the project, so that delivery responsibility is
clearly established,” (AR 285), and (6) “address each team member’s responsibilities and
performance requirements so that liability is clearly established[.]” (Id.).
Securityhunter’s CTA document explained that ETC’s sole responsibility as a team
member was “
.” (AR 824). The Court reiterates this to highlight that ETC’s role is quite narrow. In
its Response and Motion for Judgment on the Administrative Record, Securityhunter detailed
how its quote adequately addressed each element called into question by SigNet. (Int.-Def.’s
MJAR at 24–32). The Court addresses those elements below.
First, SigNet asserts that Securityhunter’s CTA document did not provide a “‘complete’
answer” to either the “Specific Team Activities” or the “Delivery Responsibility” elements in the
model CTA. (See Pl.’s MJAR at 16–17). Paragraph 9 of Securityhunter’s CTA document
identifies ETC’s “primary delivery responsibilities” as being limited to “
.” (AR Tab 21 at 824). Thus,
Securityhunter notes, (Int.-Def.’s MJAR at 24–25), ETC’s role in the CTA was accordingly
restricted to this very limited scope. Since the RFQ is only for a BPA, not any particular call
order, the SSA did not solicit proposals for any specific projects, thus there were no specific
tasks to describe at this early stage of the procurement. The level of detail describing the team
activities and delivery responsibilities for the BPA was consistent with both the nature of a BPA
and the proposed CTA relationship, where ETC’s responsibilities were limited to a specific,
narrow scope of work (
).
Thus, SigNet has not proved there are specific team activities or delivery responsibilities omitted
from Securityhunter’s CTA. Therefore, it has also failed to demonstrate that it was arbitrary or
an abuse of discretion for the SSA to accept Securityhunter’s CTA document.
Second, SigNet argues that Securityhunter’s CTA failed to provide “a ‘list [of] the
supplies/services and pricing’” per the “Team Ordering Procedures” element. (Pl.’s MJAR at 17–
19 (quoting AR Tab 9 at 284) (alteration in MJAR); see also Pl.’s MJAR at 19–20). This is
13
irrelevant that Securityhunter is not certified as a Lenel VAR because the RFQ did not require
the prime contractor to be certified as Lenel VAR.
Finally in its Lenel-related sally, SigNet argues that “[s]ince the access control systems
with Lenel as the main component represent approximately 30% of the overall SOW
requirements, and since ETC had
, it strains credulity to
believe that the Securityhunter CTA could service 1,500 facilities nationwide, plus U.S. overseas
territories, in accordance with the requirements of the SOW.” (Pl.’s MJAR at 34–35). Simply
put, this is not supported in the record. Even assuming that it were, SigNet fails to consider that
ETC (as the CTA team member) is not barred from hiring more Lenel-certified employees as
needed based on call orders issued under the BPA, and neither Securityhunter nor ETC are
prohibited from subcontracting work relating to the access control systems to subcontractors who
are certified Lenel technicians. Thus, the number of Lenel-certified employees is irrelevant, and
consideration of these facts would be speculative.
Within this argument, SigNet summarily states in a single-sentence paragraph that, “[the
SSA’s] evaluation of Securityhunter’s price leads ineluctably to the inference that the price
analysis was skewed in Securityhunter’s favor, to [SigNet’s] prejudice. (Pl.’s MJAR at 35)
Without offering some scintilla of support, it is unclear what SigNet wants the Court to do with
that argument. “Such naked claims, no matter how vigorous, fall far short of meeting the heavy
burden of demonstrating that the findings in question were the product of an irrational process
and hence were arbitrary and capricious.” Banknote Corp. of America, Inc. v. United States, 56
Fed. Cl. 377, 384 (2003), aff’d, 365 F.3d 1345 (Fed. Cir. 2004). Nonetheless, the Court reiterates
that the record demonstrates the SSA conducted the appropriate price analysis and reasonably
concluded that Securityhunter’s price was reasonable. (AR 2184–219).
While Lenel authorization is not required by the RFQ, Securityhunter has an effective
CTA with a Lenel authorized retailer, thereby negating SigNet’s apparent concerns. SigNet has
failed to persuade the Court that prejudice existed in the analysis of SigNet and Securityhunter’s
proposals. Based on the analysis above, the record demonstrates that the SSA conducted the
appropriate price analysis and rationally concluded that Securityhunter’s proposal was complete.
(AR 2184–219). As such, SigNet cannot prove that the SSA’s award was irrational, arbitrary and
capricious, or contrary to applicable law and regulation. Thus, the Court must enter judgment for
the United States and Securityhunter.
“Because proving success on the merits is a necessary element for a permanent
injunction.” Dell Fed. Sys., L.P. v. United States, 906 F.3d 982, 999 (Fed. Cir. 2018). Since
SigNet failed to establish success on the merits for the reasons set forth above, injunctive relief
would be likewise be inappropriate.
III.
Conclusion
For the reasons set forth above, the Court hereby DENIES SigNet’s Motion for Judgment
on the Administrative Record, (Pl.’s MJAR, ECF No. 25), GRANTS the United States’ Motion
for Judgment on the Administrative Record, (Def.’s MJAR, ECF No. 28), GRANTS
Securityhunter’s Motion for Judgment on the Administrative Record, (Int.-Def.’s MJAR, ECF
No. 29), and DENIES Securityhunter’s Motion to Dismiss and Motion to Strike, (id.).
18
The Clerk is directed to enter judgment in accord with this Opinion. Each side shall bear
its own costs. The parties shall file proposed redactions to this Opinion on or before July 1, 2021.
IT IS SO ORDERED.
s/
David A. Tapp
DAVID A. TAPP, Judge