Sabal Trail Transmission, LLC v. 9.669 Acres of Land, More or Less, in Polk County, Florida et al
Filing
49
ORDER granting 4 Plaintiff's Motion for Partial Summary Judgment; granting 6 Plaintiff's Motion for Preliminary Injunction. See Order for details. Signed by Judge Virginia M. Hernandez Covington on 5/11/2016. (DRW)
UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF FLORIDA
TAMPA DIVISION
SABAL TRAIL TRANSMISSION, LLC,
Plaintiff,
v.
Case No. 8:16-cv-640-T-33AEP
9.669 ACRES OF LAND IN
COUNTY FLORIDA, BENNER
CORPORATION, ET AL.
POLK
LAND
Defendants.
____________________________/
ORDER
This cause is before the Court on Plaintiff Sabal Trail
Transmission, LLC’s Motion for Partial Summary Judgment (Doc.
# 4) and the Motion for Preliminary Injunction for Immediate
Possession (Doc. # 6), both filed on March 18, 2016. For the
reasons discussed herein, the Court grants both Motions.
I.
Background
On
February
Commission
things,
2,
(“FERC”)
granted
to
2016,
the
issued
an
Sabal
Trail
Federal
order
a
Energy
which,
Regulatory
among
Certificate
of
other
Public
Convenience and Necessity (“FERC Certificate”) under the
Natural Gas Act, 15 U.S.C. § 717f. (Doc. # 1-4). The FERC
Certificate authorizes Sabal Trail to construct and operate
an interstate natural gas pipeline project. (Id.). Relying on
1
the FERC Certificate, Sabal Trail brought this case against
Benner Land Corporation and Dunham Concrete Co.,1 along with
a number of related cases, in order to take the easements
necessary to complete the pipeline project. (Doc. # 1).
Simultaneously with filing the Complaint, Sabal Trail
moved for entry of a partial summary judgment on the issue of
its
entitlement,
under
the
Natural
Gas
Act,
15
U.S.C.
§717f(h), to condemn the easements described, identified, and
depicted in Exhibit A to the Complaint (the “Easements”).
(Doc. # 4). In addition, Sabal Trail moved for the entry of
a preliminary injunction granting it immediate possession of
the Easements. (Doc. # 6).
Sabal Trail effected service on Benner Land Corporation
pursuant to Rule 71.1(d)(3)(A), Fed. R. Civ. P., on April 1,
2016. (Doc. # 18). Benner Land Corporation responded in
opposition to both pending Motions on April 18, 2016, (Doc.
## 28, 29), and answered the Complaint on April 21, 2016 (Doc.
# 32).
On May 10, 2016, the parties filed a Stipulation for
Immediate Possession, stating that Benner Land Corporation
1
Upon a motion by Sabal Trail, the Court dismissed Dunham
Concrete Co. as a defendant in this proceeding because it
was wrongfully joined. (Doc. # 25).
2
“stipulates to a partial summary judgment confirming [Sabal
Trail’s] right to condemn and immediate possession.” (Doc. #
45). Thereafter, on May 11, 2016, the Court held a hearing,
at which it heard oral arguments on the pending Motions. This
Court’s findings of fact and conclusions of law regarding the
Motion
for
Partial
Summary
Judgment
and
Motion
for
Preliminary Injunction are described below.
II.
FEDERAL POWER TO CONDEMN
A.
Findings of Fact
1.
Sabal Trail requests that this Court enter an order
of partial summary judgment establishing its right to condemn
certain easement rights.
2.
On February 2, 2016, the Federal Energy Regulation
Commission (“FERC”) issued an Order granting Sabal Trail a
Certificate
of
Public
Convenience
and
Necessity
(“FERC
Certificate”) that authorizes Sabal Trail to construct and
operate the Sabal Trail Project (the “Project”).
3.
In order to construct the Project in accordance
with the FERC Certificate, Sabal Trail must acquire easements
from the larger parcel described in Exhibit 1 to the Complaint
filed herein (“Owner’s Larger Parcel”), which is located
within the jurisdiction of this District Court.
3
4.
As part of the certification process, Sabal Trail
submitted and FERC approved “alignment sheets” showing the
final alignment of the Sabal Trail Project.
5.
Sabal Trail prepared the easements set forth in
Exhibit 2 to the Complaint (“Subject Easements”) to conform
with the FERC-approved alignment sheets.
6.
Sabal
Trail
was
unable
to
acquire
the
Subject
Easements by contract.
B.
Conclusions of Law
7.
Congress enacted the Natural Gas Act to impose
federal regulation through the Federal Energy Regulatory
Commission (“FERC”) upon the interstate transportation and
sale of natural gas for resale to the public for domestic,
commercial, industrial or any other use. As such, the Natural
Gas Act applies to Sabal Trail’s Project, which will be an
interstate natural gas pipeline. The pertinent section of the
Natural Gas Act provides as follows:
When any holder of a certificate of public
convenience and necessity cannot acquire by
contract, or is unable to agree with the owner of
property to the compensation to be paid for, the
necessary right-of-way to construct, operate, and
maintain a pipe line or pipe lines for the
transportation of natural gas, and the necessary
land or other property, in addition to right-ofway, for the location of compressor stations,
pressure apparatus, or other stations or equipment
necessary to the proper operation of such pipe line
4
or pipe lines, it may acquire the same by the
exercise of the right of eminent domain in the
district court of the United States for the
district in which such property may be located. .
. .
15 U.S.C. § 717f(h) (2016).
8.
A number of courts have held, and this Court agrees,
the Natural Gas Act authorizes a party to exercise the federal
power of eminent domain to acquire property necessary for an
interstate
natural
gas
pipeline
project
when:
(1)
the
plaintiff is the holder of a FERC Certificate authorizing a
project,
(2)
FERC
has
determined
that
the
property
is
necessary for the project, and (3) the plaintiff is unable to
acquire the property by contract. E.g., Columbia Gas Trans.,
LLC, v. 1.01 Acres, More or Less, in Penn Twp., York Cty.,
Pa., 768 F.3d 300, 304 (3d Cir. 2014); Columbia Gas Trans.,
LLC, v. 0.85 Acres, No. WDQ-14-2288, 2014 WL 4471541, at *3
(D. Md. Sept. 8, 2014); Transcon. Gas Pipe Line Co., LLC, v.
Permanent Easement Totaling 2.322 Acres, No. 3:14-cv-00400HEH, 2014 WL 4365476, at *4 (E.D. Va. Sept. 2, 2014).
9.
Under the pertinent section of the Natural Gas Act,
Sabal Trail meets each condition precedent to condemn the
Subject
Easements.
Sabal
Trail
holds
a
FERC
Certificate
authorizing the Project. FERC has determined that the Subject
Easements are necessary for the Project. And Sabal Trail has
5
been unable to acquire the Subject Easements by contract.
10.
Sabal Trail complied with its obligations under the
Natural Gas Act by attempting to acquire the Subject Easements
by contract.
No greater effort is required. See Maritimes &
Ne. Pipeline, LLC, v. Decoulos, 146 Fed. Appx. 495, 498 (1st
Cir. 2005), cert. denied, 546 U.S. 1138 (2006) (“Absent any
credible
authority
making
good
faith
negotiation
a
requirement precedent to the condemnation action . . . we
decline
the
invitation
to
create
one
in
this
case.”)
(citations omitted).
11.
attempt
Even if the NGA implicitly requires Sabal Trail to
to
negotiate
in
good
faith,
several
factors
illustrate that Sabal Trail has satisfied that requirement.
Sabal
Trail
submitted
the
declaration
of
a
Right-of-Way
Project Manager for the Sabal Trail Project, Brian Armitage.
(Doc. # 5 at ¶ 2). In the Declaration, Brian Armitage provided
the following statements of fact: (1) Sabal Trail hired
Florida-licensed real estate appraisers to determine the
value of each easement and sent offers to the landowners based
on those appraisals (Id. at ¶ 15-16); (2) Sabal Trail hired
land agents to negotiate with the landowners (Id. at ¶ 14);
and (3) as of the date of the Declaration, Sabal Trail
succeeded in negotiating purchase agreements with 1,248 of
6
the 1,582 landowners affected by the Project. (Id. at ¶ 11).
Finally, the appraised value of the easement on the subject
property in this case as of the date of the Declaration is
$1,458,900.00, and Sabal Trail extended a final offer of
$1,500,000.00. (Doc. # 5-3, as amended at the hearing). These
facts, taken together, show that Sabal Trail negotiated in
good faith.
12.
District
courts
have
limited
jurisdiction
in
Natural Gas Act condemnation actions. The condemnation action
“does not provide challengers with an additional forum to
attack the substance and validity of a FERC order. The
district court's function under the statute is not appellate
but, rather, to provide for enforcement.” Williams Nat. Gas
Co. v. Okla. City, 890 F.2d 255, 264 (10th Cir. 1989), cert.
denied, 497 U.S. 1003 (1990). “The District Court's sole
charge and authority is to evaluate the scope of the FERC
Certificate,
and
order
the
condemnation
of
property
in
accordance with that scope.” Steckman Ridge GP, LLC, v. An
Exclusive Nat. Gas Storage Easement Beneath 11.078 Acres,
More or Less, in Monroe Twp., et al., Nos. 08-168, et al.,
2008 WL 4346405, at *3 (W.D. Pa. Sept. 19, 2008) (citations
omitted); see also Columbia Gas Transmission Corp. v. An
Easement to Construct, Operate & Maintain a 24-Inch Pipeline,
7
No. 5:07CV04009, 2008 WL 2439889, at *2 (W.D. Va. June 9,
2008).
13.
Thus,
this
Court
finds
that
Sabal
Trail
is
authorized by the Natural Gas Act to exercise the power of
eminent domain and has the right to condemn the Subject
Easements identified in Exhibit A hereto and incorporated by
reference.
III. PRELIMINARY INJUNCTION AND POSSESSION
A.
Findings of Fact
14.
Sabal Trail also requests that the Court issue a
preliminary injunction granting it immediate possession of
the Subject Easements in order to begin pre-construction and
construction activities.
15.
The FERC Certificate authorizes the construction
and operation of the Project on its specified terms and
conditions. (FERC Certificate, ¶ 88, p. 28). FERC found the
Project
is
necessary,
its
“benefits
to
the
market
will
outweigh any adverse effects on other pipelines and their
captive
customers,
communities,”
and
and
“the
on
landowners
public
and
convenience
surrounding
and
necessity
requires approval of” the Project, as conditioned in the Order
granting certification. (Id.).
16.
The purpose of the Project is to provide additional
8
supplies of natural gas to Florida Power & Light Company and
Duke Energy Florida, LLC, for their power generation needs
and to the southeast region of the United States as a whole,
by making additional supplies and new energy infrastructure
available to support other regional power generators and the
growing demand for natural gas. Upon completion, the Sabal
Trail Project will be able to transport up to 1.1 billion
cubic feet of natural gas per day. (FEIS at p. 1-2 through 16; FERC Certificate at ¶ 4, p. 2).
17.
The Project involves the construction and operation
of approximately 516.2 miles of natural gas pipeline and
related
facilities.
facilities
will
(Doc.
consist
of
#
7
at
¶
11).
approximately
The
481.6
pipeline
miles
of
mainline pipeline in Alabama, Georgia, and Florida; 13.1
miles of lateral pipeline (the Hunters Creek Line) in Florida;
21.5 miles of lateral pipeline (the Citrus County Line) in
Florida; five new natural gas-fired compressor stations; and
appurtenant
facilities.
(Id.).
Sabal
Trail
also
will
construct and operate a facility in Osceola County, Florida,
referred to as the Central Florida Hub.
18.
The magnitude of the Project requires a complex
and coordinated construction process, with work activities
being performed in sequential phases. (Doc. # 7 at ¶ 13). The
9
Sabal Trail Project consists of five pipeline construction
spreads and three compressor station construction spreads (a
“spread” is a separate construction segment) across three
states.
(Id.).
The
construction
schedule
in
Florida
is
predicated upon construction of the new pipeline facilities
starting in particular places within the several spreads and
proceeding in a sequential manner. (Id. at ¶ 14). The process
is comparable to an assembly line, with specialized teams
following each other down the right of way, successively
performing tasks such as clearing, grading, ditching, pipestringing,
testing,
carefully
welding,
and
land
planned
coating,
pipe-laying,
restoration.
so
that
crews
(Id.).
and
backfilling,
Construction
equipment
is
proceed
sequentially along the right of way at a distance per day
dependent on topography, road and stream crossings, and other
factors. (Id.).
19.
Sabal Trail must begin construction on each spread
no later than June 21, 2016, in order to be completed by the
May 1, 2017, in-service date. (Doc. # 7 at ¶ 13). Sabal Trail
must take immediate possession in order to perform certain
pre-construction activities. (Id.).
20.
If
construction
begins
on
previously-acquired
parcels but a construction crew reaches a parcel that Sabal
10
Trail does not yet possess, Sabal Trail would have only two
options, both of which entail significant delays and costs:
Sabal Trail must either stop work on the Project altogether
until the necessary easements can be acquired or try to “move
around” the unresolved parcel, begin construction on the next
parcel, and return at such time as the necessary easement can
be obtained. (Doc. # 7 at ¶¶ 23-24).
21.
Temporarily stopping construction upon reaching an
unresolved parcel is not a tenable option, as it would delay
completion of the Project indefinitely and cause Sabal Trail
to miss the in-service date. (Id.). It also would result in
significant financial consequences, as Sabal Trail would be
liable to its contractors for delay costs resulting from work
stoppage
estimated
to
range
between
$20,333.00
and
$123,333.00 per day. (Id. at ¶ 23).
22.
efficient,
The
“move
linear
around”
workflow
option
and
delay
would
disrupt
completion
of
the
the
Project for at least as long as it takes to acquire the
necessary interests, thereby substantially increasing the
risk of missing the in-service date. Each such “move around”
is also very costly. (Id. at ¶ 24). Although move-around costs
are subject to various factors specific to each skipped area,
such as the size of the property and the nearest FERC-approved
11
access locations for the other accessible properties, such
costs will likely range between $18,000.00 to $130,000.00.
(Id.). If all of the construction crews are required to move
around a particular parcel, the cost for that single move
around would be approximately $720,000.00. (Id.).
23.
If Sabal Trail does not complete construction by
the May 1, 2017, in-service date, it will be unable to timely
transport
price-competitive
natural
gas
from
Alabama
to
Florida to help meet the growing demand for natural gas by
the electric generation, distribution, and end use markets in
Florida and the Southeast United States. (Doc. # 7 at ¶ 25).
B.
Conclusions of Law
24.
It is well established that granting immediate
possession of property through a preliminary injunction is
appropriate where a pipeline company holds a valid FERC
Certificate, a court has entered an order establishing the
pipeline company's right to condemn the necessary easements,
and the pipeline company has satisfied the standard for
injunctive relief. See, e.g., E. Tenn. Nat. Gas Co. v. Sage,
361 F.3d 808, 828 (4th Cir. 2004) (“Sage”), cert. denied, 543
U.S. 978 (2004); Alliance Pipeline, LP, v. 4.360 Acres of
Land, More or Less, in the S/2 of Sect. 29, Twp. N., Range 85
W., Renville Cty., N.D., 746 F.3d 362, 368-69 (8th Cir. 2014),
12
cert. denied, 135 S. Ct. 245 (2014); Columbia Gas Trans.,
LLC, 768 F.3d at 315-16.
25. In the Eleventh Circuit, as in other circuits, a
party satisfies the standard for injunctive relief and is
entitled to a preliminary injunction if it show[s]:
“(1) a substantial likelihood of success on the
merits; (2) that irreparable injury will be
suffered unless the injunction is issued; (3) the
threatened injury to the moving party outweighs
whatever damage the proposed injunction might cause
the non-moving party; and (4) if issued, the
injunction would not be adverse to the public
interest.”
Jysk Bed'N Linen v. Dutta-Roy, 810 F.3d 767, 774 (11th Cir.
2015) (citations omitted).
26.
By
granting
Sabal
Trail’s
Motion
for
Partial
Summary Judgment, this court has determined Sabal Trail has
the right to condemn the Subject Easements.
27.
Accordingly, there is a substantial likelihood that
Sabal Trail will prevail on the merits.
28.
Sabal Trail will suffer irreparable injury if the
requested preliminary injunction is not granted.
29.
The
irreparable
injury
that
would
be
suffered
includes significant additional construction costs due to
work
suspensions,
move-arounds,
and/or
specialty
crew
remobilization charges. Each disruption of the Project’s
orderly, linear workflow would force Sabal Trail to incur
13
such added construction costs that could not be recouped and
constitute irreparable injury. See N. Border Pipeline Co. v.
64.111 Acres of Land, More or Less, in Will Cty., Ill., 125
F. Supp. 2d 299, 301 (N.D. Ill 2000) (holding irreparable
harm would result from construction delays because increased
construction costs could not be recovered from defendants).
30.
Finally,
any
delay
in
granting
Sabal
Trail
possession of the Subject Easements will impede its ability
to provide the needed energy delivery services already and
conclusively deemed by FERC to be in the best interest of the
public.
31.
outweighs
The irreparable injury at stake for Sabal Trail
any
damage
the
proposed
injunction
may
cause
Defendant, which damage is reparable. As explained in Sage,
the damage to Defendant is simply loss of possession that
“would still be disturbed, albeit at a later time, if just
compensation was determined first.” 361 F.3d at 829; see also
Columbia
Gas
Trans.
Corp.
v.
An
Easement
to
Construct,
Operate, & Maintain a 24-inch Gas Trans. Pipeline Across
Props. in Greene Cty., Va., No. 3:07cv00028, 2007 WL 2220530,
at *4 (W.D. Va. July 31, 2007) (finding “the only ‘harm’ to
Defendants is that of compensation – an issue that will not
change depending on whether [the court] grant[s] or den[ies]
14
the injunction”). The relief that Sabal Trail seeks in the
form of immediate possession will not harm Defendant’s right
to compensation. Any damages to Defendant must and will be
remedied with money. Upon the grant of injunctive relief,
each landowner will still have the opportunity for a trial on
the
issue
of
monetary
compensation
and
this
right
to
compensation can be adequately secured by a bond. See ANR
Pipeline Co. v. Acres of Land, No. 03 C 50348, 2004 WL 421527,
at *1 (N.D. Ill. Feb. 24, 2004) (“There is no requirement
that the compensation be paid before possession is taken only
that
a
reasonable
and
adequate
provision
for
obtaining
compensation after the taking exists.”).
32.
In order to satisfy the requirement under Rule
65(c) of the Federal Rules of Civil Procedure that a movant
give security upon issuance of a preliminary injunction,
Sabal Trail has proposed to post a bond equal to two times
the appraised value of the Subject Easements. (Doc. # 6 at
3). This Court finds such security to be sufficient. See Sage,
361 F.3d at 824 (observing the financial strength of the gas
company and its parent corporation would enable payment if
the security fell short); Guardian Pipeline, LLC v. 950.80
Acres of Land, More or Less, in Kendall, McHenry, DeKalb, and
Will Ctys., Ill., 210 F. Supp. 2d 976, 979 (N.D. Ill. 2002)
15
(finding defendants could be “adequately protected by bond”
equal to the fee value of the affected land).
33.
Granting Sabal Trail immediate possession of the
Subject Easements in order to construct the Project in a
timely
manner
would
advance,
not
undermine,
the
public
interest. This conclusion is supported by the Natural Gas Act
and the FERC Certificate. “Congress passed the Natural Gas
Act and gave gas companies condemnation power to insure that
consumers would have access to an adequate supply of natural
gas at reasonable prices.” Sage, 361 F.3d at 830. Before
issuing a certificate of public convenience and necessity,
FERC must determine that the project at issue furthers the
goals of the Act and, thus, serves the public interest. See
Id. (observing “FERC conducted a careful analysis of the
[pipeline
promote
project]
these
and
determined
congressional
goals
that
and
the
serve
project
the
will
public
interest”).
34.
the
Here, FERC determined the “[P]roject's benefits to
market
will
outweigh
any
adverse
effects
on
other
pipelines and their captive customers, and on landowners and
surrounding communities . . . [and] the public convenience
and necessity requires approval of [the Project].” (FERC
Certificate, ¶ 88, p. 28). Those findings are conclusive and
16
binding on this Court and cannot be collaterally attacked.
See, e.g., E. Tenn. Nat. Gas, 2006 WL 1133874, at *13 (noting
the defendants could not ask the district court to “engage in
an appellate review of the propriety of [the FERC-approved]
project”).
35.
Further, supplying natural gas for the generation
of electricity and other energy needs advances the public
interest. See Sage, 361 F.3d at 830 (finding pipeline project
served public interest because it would make gas available to
consumers and electric power plants, as well as help local
communities to attract new business); E. Tenn. Nat. Gas, 2006
WL 1133874, at *14 (“[T]here is a substantial public interest
at stake in this case – the need to capture and supply as
much natural gas to the market as soon as possible.”). And
the Sabal Trail Project will not only provide increased
natural gas supplies to existing delivery points, but will
also involve the construction of the Central Florida Hub,
which will serve as a new natural gas trading point with the
potential for increased market competition that will result
in economic benefit to end users. (FEIS, § 1 Introduction,
1.1.1.2, p. 1-5).
36.
A delay of the Project’s in-service date would
cause injury to Sabal Trail’s customers, particularly Florida
17
Power & Light and Duke Energy Florida, as well as their
customers
–
the
numerous
citizens
and
businesses
that
purchase electric power. Such negative impacts on a gas
company’s customers and the public consumers they serve may
justify a preliminary injunction. Sage, 361 F.3d at 829
(finding
the
gas
company’s
“inability
to
satisfy
[its]
commitments would have negative impacts on its customers and
the consumers they serve”). This factor counsels in favor of
granting immediate possession.
37.
Additionally, the Project is expected to have a
positive economic impact on Florida’s economy. Sabal Trail
anticipates that the Project will provide approximately 4,077
temporary construction jobs, 360 permanent operational jobs,
and 977 indirect employment positions. (FEIS, § 3 Envtl.
Analysis,
Table
3.10-1,
p.
177).
Postponement
of
these
benefits is not in the public interest. See Sage, 361 F.3d at
829 (noting construction delays would cause harm by hindering
“economic development efforts”).
38.
In consideration of the foregoing factors, this
Court finds that Sabal Trail's request for a preliminary
injunction should be granted. The Court conditions the entry
preliminary injunction on Sabal Trail posting a security bond
in the amount of $2,917,800.00. That bond will “blunt” or
18
negate any potential claim of irreparable harm to Defendant.
Sage, 361 F.3d at 829.
Accordingly, it is
ORDERED, ADJUDGED, and DECREED:
1.
Plaintiff’s Motion for Partial Summary Judgment
(Doc. # 4) is GRANTED, and Sabal Trail has the right to
condemn the Subject Easements.
2.
Plaintiff’s Motion for Preliminary Injunction and
Immediate Possession (Doc. # 6) is GRANTED.
3. Upon Sabal Trail posting a proper security bond with
the Clerk of this Court in the amount of $2,917,800.00, the
following shall occur:
a.
Sabal Trail shall have immediate access to, and
possession of, the Easements described in Exhibit
A attached hereto and incorporated herein; and
b.
Sabal Trail may immediately begin pre-installation
activities so that construction-related activities
can commence by June 21, 2016, for the purposes of
constructing the Project’s pipelines and related
facilities at the Easements described in Exhibit A.
4.
All
pre-installation
and
construction-related
activities shall be consistent with the Easements acquired by
Sabal Trail and obligations agreed to by Sabal Trail as set
19
forth in Exhibit A, the FERC Certificate, and all other
required regulatory permits.
DONE and ORDERED in Tampa, Florida, this 11th day of
May, 2016.
20
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?