Llanten v. American Security Insurance Company
Filing
20
ORDER granting in part and denying in part 13 Defendant's Motion to Permit Entry onto Property. Signed by Magistrate Judge Julie S. Sneed on 3/10/2017. (LBL)
UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF FLORIDA
TAMPA DIVISION
NANCY LLANTEN,
Plaintiff,
v.
Case No: 8:16-cv-2835-T-35JSS
AMERICAN SECURITY INSURANCE
COMPANY,
Defendant.
___________________________________/
ORDER ON DEFENDANT’S MOTION TO PERMIT ENTRY ONTO PROPERTY
THIS MATTER is before the Court on Defendant’s Motion to Permit Entry onto Property
(“Motion”) (Dkt. 13), Plaintiff’s response in opposition (Dkt. 14), and Defendant’s reply (Dkt. 17).
For the reasons that follow, the Motion to Permit Entry onto Property is granted in part and denied
in part.
BACKGROUND
This case involves an insurance coverage dispute under an insurance policy issued to
Plaintiff by Defendant. (Dkt. 2.) Plaintiff alleges that her property covered by the policy was
physically damaged in June 2015. (Dkt. 2 ¶¶ 4–5.) After reporting the loss to Defendant,
Defendant inspected the property. (Dkt. 2 ¶ 7.) Thereafter, Defendant denied Plaintiff’s claim and
did not pay Plaintiff benefits under the policy. (Dkt. 2 ¶ 8.)
Plaintiff alleges that Defendant breached the policy by denying or undervaluing her claim,
and has suffered the following damages she alleges are recoverable under the policy: “the value of
her dwelling and all other structures, costs to stabilize the land and building and repair the
foundation, costs associated with debris removal, any consequential damages plus the applicable
interest rate, and all other elements of damages provided for in the Policy.” (Dkt. 2 ¶¶ 9–10.)
In its answer, Defendant admits that it issued Plaintiff a Residential Dwelling Certificate
and denied Plaintiff’s claim for a sinkhole loss at the property “following receipt of a Structural
Damage Assessment Report from Central Florida Testing Laboratories, which concluded that there
was no sinkhole loss at the Property.” (Dkt. 3 ¶¶ 4, 8.) As one of its affirmative defenses,
Defendant contends that the policy does not cover a sinkhole loss “where there has been no
structural damage to the Property as defined under Fla. Stat. § 727.706(k).” (Dkt. 3 ¶ 15.) To the
extent Plaintiff prevails on establishing a sinkhole loss, Defendant contends her damages are either
totally precluded or limited to certain categories. (Dkt. 3 ¶¶ 17–20.)
In the Motion, Defendant seeks an order compelling Plaintiff to allow Defendant entry onto
Plaintiff’s property in order for Defendant’s expert to perform an inspection and testing. Although
Defendant’s expert inspected the property during the insurance claims process before this lawsuit
was filed, since that time, Plaintiff served Defendant with Plaintiff’s expert’s report. Defendant
requests access to the property to perform the same testing as Plaintiff’s expert in order to rebut
Plaintiff’s expert’s findings and conclusions. Plaintiff opposes Defendant’s request, arguing that
an additional inspection would be duplicative of the previous inspection and unduly burdensome.
APPLICABLE STANDARDS
The court has broad discretion to compel or deny discovery. Josendis v. Wall to Wall
Residence Repairs, Inc., 662 F.3d 1292, 1306 (11th Cir. 2011). Parties may obtain discovery
regarding any non-privileged matter that is relevant to any party’s claim or defense and
proportional to the case’s needs. Fed. R. Civ. P. 26(b)(1). Nonetheless, the court must limit the
extent of discovery otherwise allowed if it determines that “the discovery sought is unreasonably
cumulative or duplicative, or can be obtained from some other source that is more convenient, less
burdensome, or less expensive.” Fed. R. Civ. P. 26(b)(2)(C)(i).
-2-
Federal Rule of Civil Procedure 34 provides that “[a] party may serve on any other party a
request within the scope of Rule 26(b) . . . to permit entry onto designated land or other property
possessed or controlled by the responding party, so that the requesting party may inspect, measure,
survey, photograph, test, or sample the property or any designated object or operation on it.” Fed.
R. Civ. P. 34(a)(2). Requests “must specify a reasonable time, place, and manner for the inspection
and for performing the related acts.” Fed. R. Civ. P. 34(b)(1)(B).
In accordance with Rule 26(b), a court evaluating a request to permit entry under Rule 34
will consider the relevance of the inspection and balance the value of the information sought with
the burden of the proposed intrusion. See N.Y. Ass’n for Retarded Children Inc. v. Carey, 706
F.2d 956, 961 (2d Cir. 1983); Murphy v. Cooper Tire & Rubber Co., No. 5:08cv40/RS/EMT, 2008
WL 3926715, at *3–4 (N.D. Fla. Aug. 21, 2008); Tesler v. Costa Crociere S.p.A., No. 08-60323CIV, 2008 WL 4371319, at *1 (S.D. Fla. Sept. 19, 2008).
ANALYSIS
In the Motion, Defendant seeks an order compelling Plaintiff to allow Defendant entry onto
Plaintiff’s property and its attorneys’ fees and costs incurred in bringing the Motion. (Dkt. 13 at
14.) Defendant explains that, during the insurance claims evaluation process and after an initial
inspection of Plaintiff’s property, Defendant retained Central Florida Testing Laboratories, Inc.
(“CFTL”) to determine whether there was structural damage to the dwelling at the Property as
defined in Fla. Stat. § 627.706.” (Dkt. 13 ¶ 2.) CFTL performed a structural damage assessment
of the property, and issued a report concluding that the dwelling at the property “had not
experienced ‘structural damage’ as that term is defined under Fla. Stat. § 627.706.” (Dkt. 13 ¶ 3.)
Defendant notified Plaintiff that her claim was denied based on CFTL’s determination that there
was no structural damage to her house, and, thus, no sinkhole loss as defined under Florida law
-3-
and the policy. (Dkt. 13 ¶ 4.) In December 2015, Plaintiff invoked, pursuant to Florida law, a
natural evaluation of the property by David Aponte, P.E., who concluded that there was no
structural damage to the dwelling, and, thus, no sinkhole loss. (Dkt. 13 ¶ 5.)
Plaintiff sued Defendant in state court in June 2016, after which the case was removed.
(Dkt. 13 ¶ 7.) Defendant contends that Plaintiff sues for the repair and remediation of an alleged
sinkhole loss, as defined under Florida law and the policy. (Dkt. 13 at 9.) The policy defines a
sinkhole loss as structural damage to the dwelling or foundation arising out of or caused by
sinkhole activity. (Dkt. 2 at 22 ¶¶ 9–10.) In the course of discovery, Plaintiff produced a structural
damage evaluation report, dated June 1, 2016, prepared by Florida Testing & Environmental, Inc.
(“FTE”). (Dkt. 13 ¶ 8.) FTE opined that there is a sinkhole loss at the property because there was
structural damage to the dwelling and sinkhole activity. (Dkt. 13 ¶ 11.)
Because Plaintiff claims, pursuant to the FTE report, that her dwelling has structural
damage caused by sinkhole activity, Defendant seeks entry onto the property to perform an
inspection and testing responsive to FTE’s findings and conclusions. Pursuant to Rule 34(a)(2),
Defendant served an inspection request on Plaintiff’s counsel in October 2016, requesting
Defendant’s access to the property to inspect the dwelling’s interior and exterior and to perform
boring tests on the dwelling’s exterior. (Dkt. 13-1.) Defendant states that the interior inspection
would be completed in four hours or less and the testing of the dwelling’s exterior would take
approximately eight to ten hours over a two-day period. (Dkt. 13-1.) Plaintiff served an objection
to Defendant’s inspection request, asserting that the request is unduly burdensome and seeks
duplicative evidence because no further inspection is required as CFTL has already concluded
there was no structural damage to the dwelling. (Dkt. 13-2.)
-4-
In the Motion, Defendant argues that, regardless of any pre-suit inspections, it is entitled
to inspect the subject property of this lawsuit; a four-hour interior inspection is not unduly
burdensome, especially in light of Plaintiff’s recent estimate of $71,000 in cosmetic damage to
thirteen of Plaintiff’s rooms; and fairness dictates that Defendant be permitted to perform testing
of whether there is evidence of sinkhole activity in order to rebut FTE’s conclusions. (Dkt. 13 ¶
19.)
In response to the Motion, Plaintiff first argues that Defendant’s inspection request is
unreasonable under Rule 34(b)(1)(B) because four hours is not sufficient time to perform visual
inspections and testing, and, nonetheless, “given the Defendant had allegedly gathered enough
data to deny the Plaintiff’s claim, four hours or more is an excessive and unduly burdensome
amount of time for the Plaintiff and her counsel to monitor the Defendant’s experts at the
Property.” (Dkt. 14 at 3.) The presence of Plaintiff’s counsel and experts at a four-plus hour
inspection, Plaintiff argues, is burdensome and expensive to Plaintiff. (Dkt. 14 at 4.) Second,
Plaintiff argues that another inspection is duplicative of Defendant’s first inspection and the testing
Defendant requests “would only be relevant to the Defendant’s defenses if the Property had
experienced ‘structural damage’ during the policy period,” which Defendant’s expert concluded
did not occur. (Dkt. 14 at 5.)
In reply, Defendant argues that the inspection would not be duplicative of its previous
inspection because “CFTL did not previously perform testing to determine whether sinkhole
activity existed at the Property because the issue of the existence of sinkhole activity was never
ripe until this lawsuit was filed and Plaintiff presented the FTE Report.”
(Dkt. 17 ¶ 2.)
Specifically, Defendant contends, because Plaintiff must establish a sinkhole loss under the policy,
which requires a showing of structural damage arising out of or caused by sinkhole activity,
-5-
discovery related to whether there was sinkhole activity at the property is relevant to Plaintiff’s
claims and Defendant’s defenses. (Dkt. 17 ¶ 3.) Further, Defendant contends that the exterior
testing is not unduly burdensome because FTE’s testing took the same amount of time as
Defendant proposes and Plaintiff has the option of whether or not to observe the testing. (Dkt. 17
¶ 4.)
While CFTL has inspected the property before, those inspections were conducted before
this lawsuit was filed. Although the basis of Plaintiff’s claim for coverage has not changed, the
posture of the parties has because, at the time of CFTL’s inspection, Defendant was assessing
Plaintiff’s insurance claim rather than, as now, conducting discovery regarding the parties’ claims
and defenses. Also, at the time of CFTL’s inspection, Defendant did not have FTE’s report, which
Defendant now seeks to rebut. Recognizing that the discovery rules are designed to “allow the
parties to develop fully and crystalize concise factual issues for trial,” and “are to be broadly and
liberally construed,” Burns v. Thiokol Chem. Corp., 483 F.2d 300, 304 (5th Cir. 1973),1 the Court
finds that Defendant’s inspection of the property is not unreasonably cumulative or duplicative.
See Fed. R. Civ. P. 26(b)(2)(C)(i).
Plaintiff argues that the four-hour interior inspection is burdensome, and the need for
Plaintiff’s counsel and expert to be present for the interior inspection and the much lengthier
exterior testing is costly. However, “[t]he mere fact that compliance with an inspection order will
cause great labor and expense or even considerable hardship and possibility of injury to the
business of the party from whom discovery is sought does not of itself require denial of the
motion.” Tesler, 2008 WL 4371319, at *1–2 (quoting 8A Wright, Miller & Marcus, Federal
Practice and Procedure: Civil 2d § 2214 (2d ed.1994)). Here, Defendant limits its request of the
1
In Bonner v. City of Pritchard, 661 F.2d 1206, 1209 (11th Cir. 1981) (en banc), the Eleventh Circuit adopted as
precedent the decisions the former Fifth Circuit rendered prior to October 1, 1981.
-6-
interior to four hours and its exterior testing is no more onerous than FTE’s. See Abreu v. Am. Sec.
Ins. Co., Case No. 8:15-cv-01180, ECF No. 14 (M.D. Fla. Dec. 9, 2015) (permitting a four-hour
inspection of property subject to a lawsuit regarding whether losses allegedly caused by a sinkhole
were compensable); Morejon v. Am. Sec. Ins. Co., Case No. 8:11-cv-02510-RAL-TGW, ECF 40
(M.D. Fla. Mar. 1, 2013) (permitting an inspection of property subject to a lawsuit regarding
whether losses allegedly caused by a sinkhole were compensable).
Accordingly, the Motion is granted. The parties shall confer and agree on a mutuallyagreeable date(s) and time(s) for CFTL to inspect and perform testing on the property. The
inspection and testing shall be completed within thirty days of this Order. The Motion, however,
is denied with respect to Defendant’s request for its fees and costs because Plaintiff’s objection to
the inspection was substantially justified. Fed. R. Civ. P. 37(a)(5)(A)(ii) (providing that, if a
motion to compel is granted, the court must not order payment of the movant’s reasonable expenses
if “the opposing party’s . . . objection was substantially justified”); Devaney v. Cont’l Am. Ins. Co.,
989 F.2d 1154, 1163 (11th Cir. 1993) (internal quotations omitted) (explaining that “an
individual’s discovery conduct should be found ‘substantially justified’ under Rule 37 if it is a
response to a genuine dispute, or if reasonable people could differ as to the appropriateness of the
contested action.”).
Accordingly, it is ORDERED that Defendant’s Motion to Permit Entry onto Property
(Dkt. 13) is GRANTED in part and DENIED in part.
DONE and ORDERED in Tampa, Florida, on March 10, 2017.
-7-
Copies furnished to:
Counsel of Record
-8-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.