City of Dania Beach Florida et al v. U.S. Army Corps of Engineers
Filing
74
ORDER denying 53 Plaintiffs' Motion for Summary Judgment; granting 57 Defendant/Intervenor Broward County's Motion for Summary Judgment; granting 59 Defendant U.S. Army Corps of Engineers' Motion for Summary Judgment. Signed by Judge James I. Cohn on 7/22/2013. (npd)
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF FLORIDA
CASE NO. 12-60989-CIV-COHN/OTAZO-REYES
CITY OF DANIA BEACH, FLORIDA,
et al.,
Plaintiffs,
vs.
U.S. ARMY CORPS OF ENGINEERS,
Defendant,
and
BROWARD COUNTY, FLORIDA,
Intervenor/Defendant.
_____________________________________/
ORDER DENYING PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT; GRANTING
DEFENDANT U.S. ARMY CORPS OF ENGINEERS’ CROSS MOTION FOR
SUMMARY JUDGMENT; GRANTING DEFENDANT/INTERVENOR BROWARD
COUNTY’S CROSS MOTION FOR SUMMARY JUDGMENT
THIS CAUSE is before the Court upon Plaintiffs’ Motion for Summary Judgment
[DE 53] (“Plaintiffs’ Motion”), Defendant/Intervenor Broward County’s Cross-Motion for
Summary Judgment [DE 57] (“Broward County Motion”), and Defendant U.S. Army
Corps of Engineers’ Cross-Motion for Summary Judgment [DE 59] (“Corps Motion)
(collectively “Motions”). The Court has carefully considered the Motions, the replies
thereto, the administrative record1, and is otherwise fully advised in the premises.
1
On July 20, 2012, the Court granted Defendant U.S. Army Corps of
Engineers’ motion to file the record conventionally. See DE 35. All references to the
Administrative Record will be designated “AR” followed by the page number.
I. BACKGROUND
A. Procedural History.
Plaintiffs City of Dania Beach, Rae Sandler, and Grant Campbell (collectively
“Plaintiffs”) filed suit against Defendant U.S. Army Corps of Engineers (the “Corps”) on
May 23, 2012. Complaint [DE 1]. The Complaint challenged a permit the Corps issued
which allowed Defendant/Intervenor Broward County2 to fill approximately 8.87 acres of
wetlands and secondarily impact 39.17 acres of wetlands in order to expand Runway
9R/27L (“South Runway”) at the Fort Lauderdale-Hollywood International Airport (the
“Airport”). Id. ¶ 1. Plaintiffs contended that the Corps issued the permit without
considering the impact of increased noise levels on the health of residents in
neighborhoods in the City of Dania Beach, thus violating both the National
Environmental Policy Act (“NEPA”) and the Clean Water Act (“CWA”). Id. ¶ 2.
Plaintiffs further argued that the Corps authorized the permit for the South Runway
despite another practicable alternative, namely a north parallel runway (“North
Runway”), which would have resulted in less noise and environmental impacts. Id. ¶ 3.
On May 24, 2012, Plaintiffs filed a motion for preliminary injunction to enjoin
further construction of the South Runway while the Court considered Plaintiffs’
Complaint on the merits. See DE 4. The Court denied the motion for preliminary
injunction on July 6, 2012. See DE 30. Additionally, the Court found that Plaintiffs were
collaterally estopped from arguing that the North Runway alternative presents a
2
On June 6, 2012, Broward County moved to intervene. See DE 12. The
Court granted this motion on June 13, 2012, finding that Broward County was entitled to
intervene as a matter of right. See DE 17.
2
practicable alternative for the Airport’s expansion plans. See DE 30 at 14-15. On
August 20, 2012, Plaintiffs filed an Amended Complaint. See DE 41. In the Amended
Complaint, Plaintiffs seek a declaration from this Court that the permit issued by the
Corps violates NEPA, the CWA, and the Administrative Procedure Act (“APA”), to
vacate the Corps’ record of decision and the permit, and to enjoin the Corps and
Broward County (collectively “Defendants”) from any further construction of the South
Runway until it complies with NEPA, the CWA, and the APA. Am. Compl. at 17. The
parties have now filed cross motions for summary judgment.
B. Relevant Facts.
In 1994, expansion of runways at the Airport was proposed to accommodate
existing and projected demand. AR 05124-25. In 1996, the Federal Aviation
Administration (“FAA”) began NEPA review of the proposed expansion. Id. As the lead
agency, the FAA, coordinating with other federal, state, local, and tribal entities,
prepared an environmental impact statement (“EIS”) regarding the potential
environmental impacts of the proposed runway expansion project. AR 06128;
06331-33. The Corps participated in the EIS process, offering expertise on impacts to
wetlands and other matters within the Corps’ jurisdiction. See, e.g., AR 00011-12;
00013-20; 00041-44; 06239; 06308; 06311; 06322; 06331-33; 21671.
The City of Dania Beach provided studies to the FAA regarding aviation noise
and its potential health impacts. AR 17569-75. FAA responded to these comments,
along with many hundreds of others from Dania Beach and other parties. See AR
03799-4660; 04702-05031. After approximately thirteen years of ongoing
environmental review, the FAA released the final environmental impact statement
3
(“FEIS”) in June 2008 and thereafter the Record of Decision (“ROD”) in December
2008. AR 00048-6221; 06232-823. The City of Dania Beach challenged the ROD in
the Court of Appeals for the District of Columbia, arguing that the FAA’s determination
that the City’s preferred expansion option, Alternative C1, was impracticable was
arbitrary and capricious and that FAA should have selected a different runway
expansion alternative. The Court of Appeals upheld the FAA’s decision. City of Dania
Beach v. FAA, 628 F.3d 581 (D.C. Cir. 2010); AR 13198-226.
Broward County then applied for a permit to fill approximately 8.87 acres of
wetlands for the expansion of Runway 9R/27L at the Airport. AR 10822-13197. The
Corps provided the first public notice for the permit on March 1, 2011. AR 13365-89.
On March 29, 2011, in response to the first public notice, Plaintiffs’ counsel submitted to
the Corps a six page letter, AR 16834-39, and enclosed over three thousand pages of
materials. AR 13611-16833. Although the public comment period was scheduled to
close on March 31, 2011, the Corps extended the comment period for an additional two
weeks. AR 16885. During the extended public comment period, Plaintiffs’ counsel sent
another letter to the Corps, enclosing the same noise related articles and studies
previously provided to the FAA in January 2008, as well as a 2011 World Health
Organization report on noise (“WHO Report”). AR 17464-845.
The Corps directed these comments to the FAA who responded that noise
impacts were adequately analyzed using its accepted methodology, and would be
significantly mitigated through the ongoing noise abatement programs. AR 21330. On
May 31, 2011, the Corps issued a second public notice, AR 19488-524, and extended
the public comment period for an additional 30 days. AR 19494. In July 2011, the FAA
4
prepared a Written Re-Evaluation of the FEIS which again addressed noise impacts
and mitigation. AR 19934-20065. Plaintiffs did not challenge this Written
Re-Evaluation. The Corps then issued its Memorandum for Record/Environmental
Assessment (“MFR/EA”) in October 2011, AR 21664-737, and shortly thereafter, the
permit at issue here. AR 21745-89.
II. DISCUSSION
A. Legal Standards.
The Court may grant summary judgment “if the pleadings, the discovery and
disclosure materials on file, and any affidavits show that there is no genuine issue as to
any material fact and that the movant is entitled to judgment as a matter of law.” Fed.
R. Civ. P. 56(c). The movant “bears the initial responsibility of informing the district
court of the basis for its motion, and identifying those portions of [the record] which it
believes demonstrate the absence of a genuine issue of material fact.” Celotex Corp. v.
Catrett, 477 U.S. 317, 323 (1986). To discharge this burden, the movant must
demonstrate a lack of evidence supporting the nonmoving party’s case. Id. at 325.
After the movant has met its burden under Rule 56(c), the burden of production
shifts to the nonmoving party who “must do more than simply show that there is some
metaphysical doubt as to the material facts.” Matsushita Elec. Indus. Co. v. Zenith
Radio Corp., 475 U.S. 574, 586 (1986). The non-moving party “may not rely merely on
allegations or denials in its own pleading,” but instead must come forward with “specific
facts showing a genuine issue for trial.” Fed. R. Civ. P. 56(e); Matsushita, 475 U.S. at
587.
As long as the non-moving party has had an ample opportunity to conduct
5
discovery, it must come forward with affirmative evidence to support its claim.
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 257 (1986). “A mere ‘scintilla’ of
evidence supporting the opposing party’s position will not suffice; there must be enough
of a showing that the jury could reasonably find for that party.” Walker v. Darby, 911
F.2d 1573, 1577 (11th Cir. 1990). If the evidence advanced by the non-moving party “is
merely colorable, or is not significantly probative, summary judgment may be granted.”
Anderson, 477 U.S. at 249-50 (citations omitted).
NEPA, 42 U.S.C. §§ 4321-4370h, is “essentially a procedural statute that
requires federal agencies to inform themselves of the environmental effects of
proposed federal actions.” Fla. Keys Citizens Coal., Inc. v. U.S. Army Corps of Eng’rs,
374 F. Supp. 2d 1116, 1123 (S.D. Fla. 2005) (citing Sierra Club v. U.S. Army Corps of
Eng’rs, 295 F.3d 1209, 1214 (11th Cir. 2002)). When an agency proposes any “major
[f]ederal action[] significantly affecting the quality of the human environment,” NEPA
mandates the preparation of an EIS. 42 U.S.C. § 4332(2)(C). “Agencies are not
required to duplicate the work done by another federal agency which also has
jurisdiction over a project.” Sierra Club, 295 F.3d at 1215. When a project has both a
lead agency and cooperating agencies, a cooperating agency may adopt an EIS signed
by a lead agency, provided it conducts “an independent review of the statement” and
finds that its “comments and suggestions have been satisfied.” Id. (quoting 40 C.F.R. §
1506.3(c)).
“If, after the original EIS is prepared, the agency ‘makes substantial changes in
the proposed action that are relevant to environmental concerns,’ or if there are
‘significant new circumstances or information relevant to environmental concerns and
6
bearing on the proposed action or its impacts,’ the agency is required to prepare a
supplemental environmental impact statement (SEIS).” Id. (quoting 40 C.F.R. §
1502.9(c)(1)). The standard for determining when a SEIS is required is “essentially the
same” as the standard for determining when an EIS is required. Id. at 1215-16 (quoting
Envtl. Def. Fund v. Marsh, 651 F.2d 983, 991 (5th Cir. Unit A July 1981)).3 If “‘the
post-[original EIS] changes in the [project] will have a “significant” impact on the
environment that has not previously been covered by the [original] EIS,’” a supplement
is necessary. Id. at 1216 (quoting Nat'l Wildlife Fed'n v. Marsh, 721 F.2d 767, 782
(11th Cir. 1983)).
The CWA, 33 U.S.C. § 1251, et seq., “prohibits the discharge of pollutants,
including dredged spoil, into waters of the United States, except in compliance with
various sections of the CWA.” Fla. Keys Citizens Coal., Inc., 374 F. Supp. 2d at 1124.
Section 404(a) of the act authorizes the Secretary of the Army to issue permits for the
discharge of dredged or fill material into waters of the United States. 33 U.S.C. §
1344(a). “Waters of the United States” include wetlands. 33 C.F.R. § 328.3(a), (b).
“Challenges to agency action under NEPA are governed by the
arbitrary-and-capricious standard set forth in the Administrative Procedure Act, 5 U.S.C.
§ 706(2)(A).” Wildlaw v. U.S. Forest Serv., 471 F. Supp. 2d 1221, 1231 (M.D. Ala.
2007) (citing Marsh v. Or. Natural Res. Council, 490 U.S. 360, 375-76 (1989); N.
3
The decisions of the former United States Court of Appeals for the Fifth
Circuit decided before September 30, 1981, are binding precedent in the Eleventh
Circuit. Bonner v. City of Pritchard, 661 F.2d 1206, 1207 (11th Cir. 1981) (en banc).
7
Buckhead Civic Ass'n v. Skinner, 903 F.2d 1533, 1538 (11th Cir.1990)).4 The APA
requires that a reviewing court shall “hold unlawful and set aside agency action,
findings, and conclusions found to be . . . arbitrary, capricious, an abuse of discretion,
or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). The arbitrary and
capricious review standard is a “deferential one.” Wildlaw, 471 F. Supp. 2d at 1231
(citing Fund for Animals, Inc. v. Rice, 85 F.3d 535, 541 (11th Cir. 1996)). The court may
not substitute its own judgment for that of the agency. Id. (citing Motor Vehicle Mfrs.
Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983); Skinner, 903 F.2d at
1539)). The court must also “look beyond the scope of the decision itself to the relevant
factors that the agency considered . . . to ensure that the agency took a ‘hard look’ at
the environmental consequences of the proposed action.” Sierra Club, 295 F.3d at
1216 (citations omitted).
“An agency has met its ‘hard look’ requirement if it has examine[d] the relevant
data and articulate[d] a satisfactory explanation for its action including a rational
connection between the facts found and the choice made.” Id. (quoting Motor Vehicle
Mfrs. Ass’n, 463 U.S. at 43 (internal quotation marks omitted)). A court may overturn
an agency’s decision as arbitrary and capricious under “hard look” review only if: “(1)
the decision does not rely on the factors that Congress intended the agency to
consider; (2) the agency failed entirely to consider an important aspect of the problem;
(3) the agency offers an explanation which runs counter to the evidence; or (4) the
4
This standard also applies to challenges under the CWA. Sierra Club v.
U.S. Army Corps of Engr’s, 935 F. Supp. 1556, 1565 & n.10 (S.D. Ala.1996).
8
decision is so implausible that it cannot be the result of differing viewpoints or the result
of agency expertise.” Id. (citing Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43). The burden
of establishing that the decision was arbitrary and capricious falls upon the party
seeking to overturn the agency decision. Sierra Club, 935 F. Supp. at 1565; Citizens
for Smart Growth v. Peters, 716 F. Supp. 2d 1215, 1221 (S.D. Fla. 2010).
B. The Corps did not Violate NEPA.
Plaintiffs raise a number of arguments which they contend demonstrate that the
Corps violated NEPA. See Plaintiffs’ Motion at 10-22. Defendants dispute these
arguments and contend that the Corps complied with NEPA. For the reasons
discussed below, the Court agrees with Defendants that the Corps did not violate
NEPA. Accordingly, summary judgment is appropriate for Defendants on Plaintiffs’
NEPA claim.
1. The Corps Took a Hard Look at the Environmental Consequences of Issuing the
Permit.
Plaintiffs first argue that the Corps violated NEPA because it failed to take a hard
look at the public health effects of high noise levels that would be generated by the
runway expansion project. Plaintiffs’ Motion at 12. Plaintiffs contend that the WHO
Report was provided to the Corps, but it “never had any internal discussions regarding
the report or the public health issues raised in it.” Id. Thus, according to Plaintiffs,
because the Corps did not consider the WHO Report, it was arbitrary and capricious in
its NEPA compliance. Id. In opposition, Broward County argues that “the Corps
reasonably relied upon the FAA’s analysis of noise impacts.” Broward County Motion at
6. The Corps similarly argues that “as a coordinating agency with a relatively minor role
9
in the overall project, [it] properly defined the scope of its NEPA obligations, duly relied
upon the FAA’s aviation expertise, and fully analyzed the environmental impacts of their
actions.” Corps Motion at 9.5
“Review of NEPA claims is limited to procedural compliance with NEPA rather
than the substance of the decision.” Fla. Keys Citizens Coal., Inc., 374 F. Supp. 2d at
1144. The Court may not “call into question any reasonable agency methodologies
used in arriving at its conclusion.” Id. (quoting Protect Key West, Inc. v. Cheney, 795 F.
Supp. 1552, 1559 (S.D. Fla. 1992)). Because the permit was issued as part of an
airport capacity enhancement project, the Vision 100-Century of Aviation
Reauthorization Act (“Vision 100 Act”) impacts this analysis. The Vision 100 Act
requires that:
[t]he Secretary [of transportation, acting through the FAA] shall determine the
reasonable alternatives to an airport capacity enhancement project at a
congested airport or a project designated under subsection (b)(2). Any other
Federal agency, or State agency that is participating in a coordinated review
process under this section with respect to the project shall consider only those
alternatives to the project that the Secretary has determined are reasonable.
49 U.S.C. § 47171(k). The Vision 100 Act further provides that the FAA:
shall be the lead agency for . . . airport capacity enhancement projects at
congested airports and shall be responsible for defining the scope and content of
the environmental impact statement, consistent with regulations issued by the
Council on Environmental Quality. Any other Federal agency or State agency
that is participating in a coordinated environmental review process under this
section shall give substantial deference, to the extent consistent with applicable
law and policy, to the aviation expertise of the Federal Aviation Administration.
49 U.S.C. § 47171(h) (emphasis added).
5
Page references to the Corps Motion refers to the CM/ECF pagination.
10
a. The Corps’ Scope of Analysis was Appropriate.
Plaintiffs argue that the Corps failed to consider the public health effects of
increased aviation noise and “it improperly limited its scope of analysis to the direct
impacts of filling the wetlands.” Plaintiffs’ Motion at 12. Specifically, Plaintiffs argue
that the permit “is a necessary precondition to the South Runway’s extension,” thus the
Corps was required to examine all environmental impacts resulting from the issuance of
the permit. Id. at 13. According to the Corps, however, its “decision to focus its
environmental review on the effects of the permitted activity was entirely reasonable,
and is due deference.” Corps Motion at 10. Broward County also asserts that the
Corps’ scope of review was appropriate because it prepared its own independent
environmental assessment to address the direct, secondary, and cumulative impacts to
wetlands and participated in and incorporated the FAA’s FEIS related to noise-related
impacts. Broward County Motion at 10.
As this Court has previously held, the Corps, as a mere coordinating agency6 on
this airport expansion project, was required to defer to the FAA regarding all matters of
“aviation expertise” which includes impacts to residents from increased aviation noise.
See Fla. Keys Citizens Coal., Inc., 374 F. Supp. 2d at 1157 (finding that the Corps
could rely upon the judgment of other agencies with particular expertise related to
managing sensitive marine environments); Nat’l Mitigation Banking Ass’n v. U.S. Army
6
Plaintiffs reassert their argument that the Corps was not a cooperating
agency. Plaintiffs’ Motion at 19 (citing AR 00360). This argument once again misstates
the issue. Because the Corps and FAA executed a Memorandum of Understanding, it
is clear that the Corps was not the lead agency and aided the FAA in the preparation of
the EIS. Corps Motion at 8 & n.1; AR 00011-12. Indeed, the ROD reflects that the FAA
coordinated with agencies including the Corps. See, e.g., AR 06331-32.
11
Corps of Eng’rs, No. 06-cv-2820, 2007 WL 495245, at *22 (N.D. Ill. Feb. 14, 2007)
(noting that “[w]here multiple agencies are involved, a lead agency prepares an EIS and
a cooperating agency can adopt that EIS if it independently reviews the EIS and is
satisfied that its comments and suggestions are satisfied.”).7 “Although it specifies a
7
Plaintiffs assert that the Environmental Protection Agency, not the FAA, is
the expert on the “effects of noise on health.” Plaintiffs’ Motion at 18. As Broward
County points out, however, the statutory provision Plaintiffs rely upon for this
proposition, 42 U.S.C. § 4903(c)(2) provides that: “[w]ith respect to the Federal Aviation
Administration, section 44715 of Title 49 shall apply in lieu of this paragraph.” Broward
County’s Reply [DE 71] (“Broward County Reply”) at 5 (citing 42 U.S.C. § 4903(c)(2)).
Title 49 § 44715 states that:
To relieve and protect the public health and welfare from aircraft noise and sonic
boom, the Administrator of the Federal Aviation Administration, as he deems
necessary, shall prescribe-(i) standards to measure aircraft noise and sonic boom; and
(ii) regulations to control and abate aircraft noise and sonic boom.
49 U.S.C. § 44715(a). While the FAA must consult with the EPA to proscribe such
standards, it is apparent that Congress has given the FAA the ability to create aircraft
noise standards. The Integrated Noise Model that the FAA employed in this case is
one such standard. See AR 94874; FAA Order 1050.1E ¶ 14.2b (“All detailed noise
analyses must be performed using the most current version of the FAA's Integrated
Noise Model (INM), Heliport Noise Model (HNM), or Noise Integrated Routing System
(NIRS). Use of an equivalent methodology and computer model must receive prior
written approval from the FAA's Office of Environment and Energy.”); 14 C.F.R. §
150.9(b) (“The exposure of individuals to noise resulting from the operation of an airport
must be established in terms of yearly day-night average sound level (YDNL) calculated
in accordance with the specifications and methods prescribed under appendix A of this
part.”); U.S. Air Tour Ass'n v. FAA, 298 F.3d 997, 1008 (D.C. Cir. 2002) (“The INM is
‘the most widely used civilian software program for analyzing noise effects relating to
changes in airspace use.’”). Thus, the Court disagrees with Plaintiffs’ contention that
the Corps should not have relied upon the FAA’s analysis of noise impacts.
12
broad range of impacts which must be considered, NEPA does not expand the authority
of the Corps to either approve or disapprove activities outside waters of the United
States.” Environmental Quality; Procedures for Implementing the National
Environmental Policy Act (NEPA), 53 Fed. Reg. 3120, 3121 (Feb. 3, 1988) (to be
codified at 33 C.F.R. pt. 230, 325). Here, as the Corps pointed out in its MFR/EA, it
determined that its jurisdiction was “limited to the work in jurisdictional waters” because
the project was “under the purview of the FAA” and the Corps did not have “jurisdiction
to the uplands.” AR 21671. The Corps also determined that the capacity at the Airport
could increase even without issuance of the permit. Id.; see also AR 21745 (noting that
permit was being issued to fill 8.87 acres of wetlands and secondarily impact 39.17
acres of wetlands). The Corps’ decision to limit its review to the waters impacted by the
project should be accorded deference. Fla. Wildlife Fed’n v. U.S. Army Corps of
Engr’s, 401 F. Supp. 2d 1298, 1312 (S.D. Fla. 2005) (citing Marsh, 490 U.S. at 375-76).
Plaintiffs argue, however, that because the permit was necessary to complete
the South Runway, the Corps was obligated to analyze the effects of the entire project.8
Plaintiffs’ Motion at 12 (citing 33 C.F.R. pt. 325 app. B § 7(b)(2)(A) (“The district
engineer is considered to have control and responsibility for portions of the project
beyond the limits of Corps jurisdiction where the Federal involvement is sufficient to turn
an essentially private action into a Federal action. These are cases where the
8
Additionally, as the Corps points out, the U.S. Supreme Court has
rejected “but for” reasoning in the NEPA context. Defendant U.S. Army Corps of
Engineers’ Reply in Support of Cross Motion for Summary Judgment [DE 70] (“Corps
Reply”) at 4 (citing Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 767 (2004)); Corps
Motion at 13 (citing same).
13
environmental consequences of the larger project are essentially products of the Corps
permit action.”)). As noted above, the Corps’ determination that the capacity at the
airport would increase even without issuance of the permit should be accorded
deference. See AR 21671. Moreover, this argument misstates the issue. Where, as
here, the project was under the control of another federal agency, the Corps was
permitted to adopt the EIS of the lead agency. See 40 C.F.R. § 1506.3(a) (stating that
cooperating agency may adopt lead agency's EIS if it concludes that its NEPA
requirements have been satisfied); see also Sierra Club, 295 F.3d at 1215 (“Agencies
are not required to duplicate the work done by another federal agency which also has
jurisdiction over a project.”); Cal. Trout v. Schaefer, 58 F.3d 469, 474 (9th Cir. 1995)
(limiting scope of Corps review to effects of filling wetlands where another agency had
the responsibility of protecting fisheries); North Carolina v. City of Va. Beach, 951 F.2d
596, 605 (4th Cir. 1991) (holding that Federal Energy Regulatory Commission was not
required to perform NEPA review over portions of the project over which it did not have
jurisdiction where NEPA “requirements were previously satisfied by the Corps”); Nat’l
Mitigation Banking Ass’n, 2007 WL 495245, at *22 (“Whenever an agency has
prepared a broad EIS, and a subsequent statement or EA is then prepared regarding a
component of the larger project, the subsequent EA need only summarize the issues
discussed in the broader statement and incorporate discussions from that statement by
reference, concentrating instead on matters specific to the subsequent action.”). Thus,
the issue before this Court is whether the Corps conducted “an independent review of
the statement” and found that its “comments and suggestions have been satisfied.”
See Sierra Club, 295 F.3d at 1215 (quoting 40 C.F.R. § 1506.3(c)).
14
b. The Corps Properly Incorporated by Reference the FEIS.
Plaintiffs also argue that the Corps failed to satisfy its NEPA obligations by
incorporating by reference the FAA’s analysis because “the FAA itself never analyzed
or evaluated the impact of noise on the public health of residents.” Plaintiffs’ Motion at
15. In opposition, the Corps contends that its “reliance on FAA’s use of its existing
methodology was reasonable and is due considerable deference.” Corps Motion at 13.
The Corps argues that Plaintiffs essentially disagree with the methodology the FAA
employed to analyze the effect of noise. Id. at 14. Broward County also asserts that it
was appropriate for the Corps to incorporate the FAA’s FEIS on noise-related impacts
into its MFR/EA. Broward County Motion at 10.
Here, the administrative record establishes that noise impacts were considered
in the FEIS. See AR 01235-513; 05302-35; 05609-764; 06038-39; 06055. Moreover,
the administrative record reveals that the FAA received a comment regarding the
adverse health effects of airport noise which urged the FAA to revise the EIS to analyze
these concerns, but the FAA decided to apply its existing aviation noise methodology.
AR 04874. The FEIS notes that “the Integrated Noise Model (INM) and the associated
methodologies to assess aircraft noise impacts [ ] is the accepted industry methodology
for assessing noise impacts on the human environment.” Id. This Court cannot find
that the FAA was unreasonable in relying on its established methodology regarding
noise impacts. See City of Bridgeton v. FAA, 212 F.3d 448, 459 (8th Cir. 2000)
(declining to “second-guess the FAA’s noise level findings” because “[t]he agency, not a
reviewing court, is entrusted with the responsibility of considering the various modes of
scientific evaluation and theory and choosing the one appropriate for the given
15
circumstances.”) (citations and internal quotation marks omitted). Accordingly, it was
not arbitrary and capricious for the Corps to rely upon the FEIS’ discussion of the noise
impacts of the runway expansion.9
The Eleventh Circuit’s holding in Sierra Club v. United States Army Corps of
Engineers supports this result. In Sierra Club, the Court held that the Corps had met its
requirements under NEPA because:
First, it acted as a cooperating agency in the preparation of the 1994 EIS.
Second, it remained involved in the planning process throughout the
development of the mitigation plan and the other methods to avoid and minimize
the impact of the Parkway. Third, the Corps acted both efficiently and
consistently with NEPA regulations by incorporating the previous studies into its
current analysis. The 1997 EAs all incorporate portions of the 1993 biological
opinion and rely on the 1994 EIS, as well as the work done during the
partnership process. The initial 1997 EA, prepared January 6, 1997, extensively
referred to and relied upon the 1994 EIS and the 1993 biological opinion. Indeed,
the “reasonable and prudent measures” and “terms and conditions” detailed by
FWS in the 1993 biological opinion were incorporated verbatim, with notations
describing the changes being made to increase the mitigating effects.
Subsequent EAs in 1997 referred back to this January 6, 1997 EA and the 1994
EIS. Such reliance on a previous EIS is specifically authorized.
295 F.3d at 1220 (footnote omitted). Similarly, here, the Corps was a cooperating
agency in the preparation of FEIS. See, e.g., AR 00011-12; 00013-20; 00061; 05128.
Indeed, the Corps participated in the review process for the draft EIS. AR 00286. The
MFR/EA explicitly incorporates the FEIS by reference. AR 21644. The Corps also
9
Indeed, under the Vision 100 Act, the Corps was required to defer to the
FAA on matters of aviation expertise. See 49 U.S.C. § 47171(h). Accordingly, it was
reasonable for the Corps to refer the Plaintiffs’ concerns regarding noise impacts and
the WHO Report to the FAA. See Corps Motion at 15 (citing AR 21331-33). Moreover,
as Broward County points out, Plaintiffs never challenged the FAA’s noise methodology
with the FAA, even when they filed a lawsuit regarding the expansion project against
the FAA. See Broward County Motion at 8. Instead, Plaintiffs indirectly challenge the
FAA’s methodology by contesting the Corps’ issuance of the permit. See id.
16
forwarded comments it received regarding noise impacts to the FAA which the FAA in
turn addressed. See AR 21702 (“The applicant provided a summary of the chapters
where these public comments were previously addressed in the FEIS on 20 June 2011.
The applicant provided RAI responses on 14 June 2011. The applicant provided a
Written Re-evaIuation of the FFEIS (WR-FFEIS) and a response to the letter from
White and Case on behalf of the City of Dania Beach on 26 August 2011.”); 21330;
21331-33 (FAA’s Review of and Responses to the letters received by the USACE from
White and Case on Behalf of the City of Dania Beach, FL, dated March 29 and April 14,
2011). This record establishes that the Corps fulfilled its NEPA obligations.
Plaintiffs also argue that the Corps violated NEPA because they failed to analyze
or evaluate the impacts of increased noise from airplanes using the South Runway.
Plaintiffs’ Motion at 14. This argument ignores the fact that the Corps specifically
incorporated by reference the FEIS, the ROD, the Written-Revaluation, and written
correspondence with the FAA regarding noise studies Plaintiffs submitted. See AR
21664. As discussed above, the Court finds that the FAA adequately considered the
impact of noise from the runway expansion project using its standard methodology. It
was appropriate for the Corps, deferring to the aviation expertise of the FAA, to
incorporate this analysis into its MFR/EA.
c. Noise Mitigation Measures Nullified the Need for Further Environmental Review
of Noise Impacts.
Both Broward County and the Corps argue that the noise mitigation measures
incorporated into the ROD and Written Re-Evaluation alleviated the need for any further
review of noise impacts. Corps Motion at 16-17; Broward County Motion at 8-9. In
17
opposition, Plaintiffs contend that this argument is without merit because (1) the Corps
did not impose any noise mitigation conditions on its permit; (2) neither the Corps nor
the FAA determined that noise mitigation measures would prevent increased
cardiovascular disease and cognitive impairment in children; and (3) the noise
mitigation measures would not avoid all the public health risks described in the WHO
Report. Plaintiffs’ Consolidated Memorandum of Law in Opposition to Defendant U.S.
Army Corps of Engineers’ Cross-Motion for Summary Judgment (D.E. 59) and
Intervenor Defendant Broward County’s Cross-Motion for Summary Judgment (D.E. 57)
and in Support of Plaintiffs’ Motion for Summary Judgment (D.E. 53) [DE 66] (“Plaintiffs’
Reply”) at 18-21.
Under Eleventh Circuit precedent, “[w]hen mitigation measures compensate for
otherwise adverse environmental impacts, the threshold level of ‘significant impacts' is
not reached so no EIS is required.” C.A.R.E. Now, Inc. v. FAA, 844 F.2d 1569, 1575
(11th Cir. 1988). The mitigation measures, however, must be “a condition of agency
approval.” Sierra Club, 295 F.3d at 1220. Here, Plaintiffs argue that the Corps cannot
rely on any mitigation measures discussed in the FEIS, ROD, and Written-Reevaluation
because the Corps did not impose any noise mitigation conditions in its permit.
Plaintiffs’ Reply at 18. However, as the Corps points out, it “incorporated the FAA’s
analysis and decision, and so necessarily incorporated the portion of the FEIS that
discusses noise mitigation and indeed imposes mitigation measures as conditions
precedent to the project’s approval.” Corps Reply at 7. A review of the Administrative
Record indicates that the FEIS incorporates eight operational noise abatement and
mitigation measures and four land-use based mitigation measures. AR 05334-35.
18
Approval of the ROD is explicitly conditioned upon implementation of these mitigation
measures. AR 06334. Thus, it was reasonable for the Corps to rely upon the FAA’s
mandatory mitigation measures and no further environmental review was necessary.
See Hillsdale Envtl. Loss Prevention, Inc. v. U.S. Army Corps of Eng’rs, 702 F.3d 1156,
1172-73 (10th Cir. 2012) (holding that Corps reasonablely relied on mitigation
agreement entered by BNSF Railway Company and Kansas Department of Health and
the Environment to find no significant impact from dust emissions and that Corps
preparation of EIS was not necessary). To the extent Plaintiffs argue that the noise
mitigation plan will not avoid all the public health risks identified in the WHO Report, see
Plaintiffs’ Reply at 19-20, the Court finds that this is merely another attack on the FAA’s
chosen noise impact methodology, which the Court has extensively discussed–and
rejected–above.10
2. The Corps was not Required to Prepare a SEIS.
Plaintiffs also argue that the Corps violated NEPA by failing to prepare a SEIS
after it was provided the WHO Report. Plaintiffs’ Motion at 20. Plaintiffs contend that
the WHO Report was “a new authoritative analysis of the public health impacts of
noise.” Id. Defendants both argue that no SEIS was necessary because the WHO
Report did not present new information. Broward County Motion at 12; Corps Motion at
17. The Court agrees that the Corps’ decision not to prepare a SEIS was neither
10
Moreover, as Broward County points out in its reply, the WHO Report
acknowledges that “[n]oise annoyance is widely accepted as an end-point of
environmental noise on the exposed population.” Broward County Reply at 2 (citing AR
17684).
19
arbitrary nor capricious.
A SEIS should only be prepared when new circumstances “present a seriously
different picture of the environmental impact of the proposed project from what was
previously envisioned.” Fla. Keys Citizens Coal., Inc., 374 F. Supp. 2d at 1145
(citations and internal quotation marks omitted) (emphasis in original). Here, Plaintiffs
concede that they had previously submitted many of the individual studies discussed in
the WHO Report to the FAA. See Plaintiffs’ Motion at 21; AR 17464 (“These concerns
are not newly discovered. We raised these concerns as early as January 2009 when
we submitted a letter to the Federal Aviation Administration.”) Indeed, the FEIS reflects
that the FAA received a comment regarding the adverse health effects of airport noise
from Plaintiffs, but decided to apply its existing aviation noise methodology. AR 04874.
When the Plaintiffs brought the WHO Report to the Corps’ attention, the Corps in turn
provided it to the FAA who concluded that its existing methodology was sufficient. AR
21333. Thus, Plaintiffs have failed to demonstrate that the WHO Report constitutes
“significant new circumstances or information relevant to environmental concerns and
bearing on the proposed action or its impacts” sufficient to require a SEIS. See 40
C.F.R. § 1502.9(c)(1); Airport Cmtys. Coalition v. Graves, 280 F. Supp. 2d 1207,
1218-19 (W.D. Wash. 2003) (SEIS not necessary where the Corps considered
“environmental impacts and found them to be insignificant in light of various mitigation
measures that would be put in place.”). Because Plaintiffs have failed to establish that
the Corps was arbitrary and capricious in carrying out its obligations under NEPA, the
Court will grant summary judgment for Defendants on Plaintiffs’ NEPA claim.
20
C. The Corps did not Violate the CWA.
The parties also cross move for summary judgment on Plaintiffs’ CWA claim.
Plaintiffs contend that the Corps violated the CWA by (1) failing to consider the
potential for the project to affect public health and (2) affording the opportunity for
adequate public participation because neither of its notices “provided any information
as to likely secondary and cumulative health effects resulting from the proposed
activity.” Plaintiffs’ Motion at 22-24. Broward County argues that the Corps properly
relied on the FAA’s expertise regarding aviation noise impacts. Broward County Motion
at 14. Similarly, the Corps argues that it considered multiple factors beyond the harm
to wetlands in its environmental assessment, including conservation, economics,
aesthetics, general environmental concerns, historic properties, fish and wildlife values,
flood hazards, floodplain values, land use, navigation, water quality, safety, and the
need and welfare of the people. Corps Motion at 20 (citing AR 21714). The Corps also
contends that it complied with all public notice requirements and that there is no
evidence that the Corps hid any information from the public. Id. at 22-27.
First, the Court agrees with Defendants that the Corps adequately considered all
potential impacts related to the runway expansion project. Corps regulations state that:
The decision whether to issue a permit will be based on an evaluation of the
probable impacts, including cumulative impacts, of the proposed activity and its
intended use on the public interest. Evaluation of the probable impact which the
proposed activity may have on the public interest requires a careful weighing of
all those factors which become relevant in each particular case. The benefits
which reasonably may be expected to accrue from the proposal must be
balanced against its reasonably foreseeable detriments. The decision whether to
authorize a proposal, and if so, the conditions under which it will be allowed to
occur, are therefore determined by the outcome of this general balancing
21
process. That decision should reflect the national concern for both protection and
utilization of important resources. All factors which may be relevant to the
proposal must be considered including the cumulative effects thereof: among
those are conservation, economics, aesthetics, general environmental concerns,
wetlands, historic properties, fish and wildlife values, flood hazards, floodplain
values, land use, navigation, shore erosion and accretion, recreation, water
supply and conservation, water quality, energy needs, safety, food and fiber
production, mineral needs, considerations of property ownership and, in general,
the needs and welfare of the people.
33 C.F.R. § 320.4(a)(1). Moreover, the Corps may determine the specific weight to be
given each factor. 33 C.F.R. § 320.4(a)(3). Here, the administrative record establishes
that the Corps considered many potential impacts of the runway expansion project. AR
21714. Plaintiffs’ argument that the Corps did not adequately consider the public
interest because it failed to consider the runways’s impact on public health is merely a
variation of the argument that the Corps did not consider the WHO Report. See
Plaintiffs’ Motion at 22 . However, as discussed extensively above, the Corps properly
deferred to the FAA on matters of aviation expertise, including noise impacts.
Moreover, the Corps incorporated the FAA’s noise impact analysis, and all noise
mitigation measures, into its MFR/EA. AR 21664. Accordingly, based on this record,
the Corps was not arbitrary and capricious in determining that the permit was in the
public interest.
The record similarly does not support that the Corps violated the CWA’s public
participation requirements. See Plaintiffs’ Motion at 23 (citing 33 U.S.C. § 1344(a); 33
C.F.R. §§ 325.2(a), 325.3). Under Corps’ regulations,“[t]he notice must
[ ] include sufficient information to give a clear understanding of the nature and
magnitude of the activity to generate meaningful comment.” 33 C.F.R. § 325.3(a).
22
Here, the notices the Corps issued unequivocally did this, clearly describing the project
purpose and the nature of the work to be done through issuance of the permit. See AR
13366 (“The basic project purpose is to provide sufficient capacity for existing and
forecast demand at Fort Lauderdale-Hollywood International Airport (FLL). . . . The
applicant proposes to fill approximately 15.51 acres, and potentially secondarily impact
3.32 acres of freshwater and saltwater wetlands for the redevelopment and extension of
Runway 9R/27L at the Fort Lauderdale-Hollywood International Airport.”); 19488.
Corps’ regulations specifically contemplate that “[i]f a question develops with respect to
an activity for which another agency has responsibility and that other agency has not
responded to the public notice, the district engineer may request its comments.” 33
C.F.R. § 325.3(d). This is exactly what occurred here: when the Corps received the
Plaintiffs’ comments regarding the health effects of aviation noise, the Corps provided
the comments to the FAA for response. AR 17464-845; 21330. There is no evidence,
other than Plaintiffs’ bare assertion that the August 2011 letter the Corps received from
the FAA, AR 21331-34, was “[t]he Corps’ main justification in the ROD for refusing to
consider the public health impacts from increased noise.” Plaintiffs’ Motion at 24.11
11
Even if the Corps did rely on the August 2011 letter when issuing the
permit, this does not establish that the Corps violated the notice requirements. The
rationale of the August 2011 letter is the same as discussed in the FEIS which the
Corps incorporated into its MFR/EA and referenced in the notices. See Corps Reply at
10. Thus, the information contained in this letter would not represent “essential data
and the agency's rationale.” Nat’l Wildlife Fed’n v. Marsh, 568 F. Supp. 985, 994
(D.D.C. 1983). The Corps’ rationale for rejecting Plaintiffs’ comment was contained
within the administrative record long before the August 2011 letter. See id. (finding that
notice requirement was not met where evaluation which formed the basis for
Secretary’s decision was first introduced after public comment period concluded).
23
Instead, the Corps properly followed the procedure outlined in 33 C.F.R. § 325.3(d) to
seek the FAA’s comment.
Plaintiffs have failed to cite any authority for the proposition that the Corps was
required to modify the notice to raise previous public comments such as the Plaintiffs’
concerns regarding health impacts from aviation noise. See Broward County Reply at
9.12 Moreover, there is no evidence that the Corps in any way concealed information
regarding the health effects of aviation noise from the public. See Plaintiffs’ Motion at
24. Instead, both public notices provide a link to the FEIS which throughly analyzes
noise impacts. AR 13372; 19494. Thus, the Court cannot find that the Corps was
arbitrary and capricious in carrying out its obligations under the CWA. Accordingly, the
Court will grant summary judgment for Defendants on Plaintiffs’ CWA claim.
III. CONCLUSION
Based on a thorough review of the administrative record and the foregoing
analysis, the Court finds that Defendants are entitled to summary judgment.
Accordingly, it is ORDERED AND ADJUDGED as follows:
1.
Plaintiffs’ Motion for Summary Judgment [DE 53] is DENIED;
2.
Intervenor Defendant Broward County’s Cross-Motion for Summary Judgment
12
Essentially, Plaintiffs ask this Court to find that the Corps violated the
CWA because it did not apprise the public of comments Plaintiffs raised regarding the
health effects of airport noise. There is simply no evidence that the Corps failed to
provide “sufficient information to give a clear understanding of the nature and
magnitude of the activity to generate meaningful comment,” as required by 33 C.F.R. §
325.3(a) when Plaintiffs and many others did in fact comment. See Broward County
Reply at 10 (citing AR 15872-73; 15878; 15893-94; 16834; 17430; 17467).
24
[DE 57] is GRANTED;
3.
Defendant U.S. Army Corps of Engineers’ Cross-Motion for Summary Judgment
[DE 59] is GRANTED; and
4.
The Court will enter a separate final judgment.
DONE AND ORDERED in Chambers at Fort Lauderdale, Broward County,
Florida, this 22nd day of July, 2013.
Copies provided to counsel of record via CM/ECF.
25
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?