Prime Investors & Developers, LLC v. Rockwood Specialties, LLC et al
Filing
36
ORDER granting 19 Motion to Remand to State Court. Closing Case. Signed by Judge Beth Bloom on 1/4/2017. (ail) NOTICE: If there are sealed documents in this case, they may be unsealed after 1 year or as directed by Court Order, unless they have been designated to be permanently sealed. See Local Rule 5.4 and Administrative Order 2014-69.
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF FLORIDA
Case No. 16-cv-62660-BLOOM/Valle
PRIME INVESTORS & DEVELOPERS, LLC
Plaintiff/Counter-Defendant,
v.
ROCKWOOD SPECIALTIES, LLC,
Defendant/Counter-Plaintiff
v.
KEY LARGO HOSPITALITY LAND TRUST
Counter-Defendant.
__________________________________/
ORDER ON MOTION FOR REMAND
THIS CAUSE is before the Court upon a Motion for Remand filed by
Plaintiff/Counter-Defendant Prime Investors & Developers, LLC (“Prime Investors”), ECF No.
[19] (“Motion for Remand”). These proceedings arise from an action originally filed by Prime
Investors in the Circuit Court of the Seventeenth Judicial Circuit in and for Broward County.
Prime Investors moves the Court to remand proceedings back to state court. Defendant/CounterPlaintiff Rockwood Specialties, LLC (“Rockwood”) opposes the Motion for Remand. For the
reasons that follow, the Court grants the Motion for Remand.
I.
BACKGROUND
On July 29, 2016, Prime Investors filed a Complaint for breach of contract against
Rockwood in the Seventeenth Judicial Circuit Court in and for Broward County, Florida. See
ECF No. [1-1], Exh. A. Prime Investors alleges that Rockwood breached a Subcontractor Base
Agreement (the “Agreement”) that the parties entered into on July 10, 2015, whereby Rockwood
Case No. 16-cv-62660-BLOOM/Valle
was to “supply and install finished carpentry, architectural woodwork, millwork and trim” for a
project relating to property in Key Largo, Florida. Id. at ¶¶ 8, 10. On September 13, 2016,
Rockwood filed an Answer, Affirmative Defenses and Counterclaim (the “Counterclaim”),
wherein Rockwood asserts its own claim for breach of contract against Prime Investors, and also
seeks to enforce a construction lien and recover on a quantum meruit claim against CounterDefendant Key Largo Hospitality Land Trust, Steven B. Greenfield, Trustee – the owner of the
subject property. ECF No. [1-1], Exh. B. On September 13, 2016, Rockwood propounded a
single request for admission relating to Prime Investor’s damages. See ECF No. [1] at ¶ 3.
Prime Investors responded on October 21, 2016, admitting that the amount in controversy
exceeds $75,000. ECF No. [1-1], Exh. C. Thereafter, on November 10, 2016, Rockwood
removed this matter to this Court pursuant to this Court’s diversity jurisdiction.
II.
ANALYSIS
Pursuant to 28 U.S.C. § 1332(a), a district court is vested with subject matter jurisdiction
when the parties are diverse and the amount in controversy “exceeds the sum or value of
$75,000, exclusive of interest and costs.”
There is no dispute here that the amount in
controversy exceeds the jurisdictional threshold; Prime Investors instead moves for remand on
the basis that removal was not timely effectuated. The time limit for removal is set forth in 28
U.S.C. § 1446(b), which provides in relevant part:
(1) The notice of removal of a civil action or proceeding shall be filed within 30
days after the receipt by the defendant, through service or otherwise, of a copy of
the initial pleading setting forth the claim for relief upon which such action or
proceeding is based, or within 30 days after the service of summons upon the
defendant if such initial pleading has then been filed in court and is not required
to be served on the defendant, whichever period is shorter.
....
(3) [I]f the case stated by the initial pleading is not removable, a notice of removal
may be filed within thirty days after receipt by the defendant, through service or
otherwise, of a copy of an amended pleading, motion, order or other paper from
2
Case No. 16-cv-62660-BLOOM/Valle
which it may first be ascertained that the case is one which is or has become
removable.
The parties are in disagreement as to what triggered the 30-day period during which
Rockwood had to remove the action. Prime Investors contends that the Complaint filed on July
29, 2016 triggered the 30-day removal period in that it sufficiently disclosed an amount in
controversy in excess of $75,000. Alternatively, Prime Investors argues that the 30-day removal
period was triggered, at the latest, by Rockwood’s Counterclaim filed on September 13, 2016,
wherein Rockwood alleges “damages for greater than the sum or value of $75,000 . . . .” ECF
No. [1-1], Exh. B at 4, ¶ 1. In response, Rockwood argues that the Complaint is not clear as to
the damages alleged by Prime Investors, and therefore directs the Court to Prime Investors’
October 21, 2016 response to Rockwood’s request for admission as the trigger for the 30-day
removal period. The removal, effectuated on November 10, 2016, would be timely only if the
October 21, 2016 date applies.
The Complaint, in its opening paragraph, states that “the amount in controversy exceeds
$15,000” – the threshold amount required to invoke the state court’s jurisdiction. ECF No. [1-1],
Exh. A at ¶ 1. At paragraph 10, the Complaint alleges Rockwood’s breach of the Agreement
(attached to the Complaint) by Rockwood’s failure, among other things, “to promptly correct
defective work resulting in delays to the Overall Project Schedule (‘OPS’)” and “to timely
deliver and install granite/solid surface countertops resulting in delays to the OPS.” Id. at ¶¶
10(a)-(b) (emphasis added).
With respect to the alleged delays in Rockwood’s work, the
Complaint, at paragraph 12, references a liquidated damages provision contained in the parties’
Agreement:
The Agreement contains a Liquidated damages provision. Rockwood agreed that
because delay damages resulting from its failure to “strictly comply” with the
OPS are difficult to ascertain, should Rockwood fail to timely complete all work,
3
Case No. 16-cv-62660-BLOOM/Valle
it must credit back to Plaintiff $1,000.00 for each and every day Rockwood is late
in completing the Work. Pursuant to the Agreement and because of Rockwood’s
substantial delays, Plaintiff is entitled to liquidated damages.
Id. at ¶ 12. The OPS referred to in paragraphs 10 and 12 of the Complaint is delineated in the
attached Agreement and indicates that the work to be performed by Rockwood was to be
completed by August 17, 2015, more than eleven months prior to Prime Investors’ filing of the
Complaint. See ECF No. [1-1] at 68.
Notwithstanding the above, Rockwood argues in conclusory fashion that the Complaint’s
“vague reference to a liquidated damage claim” was insufficient to trigger the 30-day removal
period. ECF No. [22] at 3. Importantly, however, Rockwood does not dispute that its work was
to be completed by August 17, 2015 pursuant to the OPS outlined in the Agreement, or that the
“substantial delays” alleged in paragraph 12 of the Complaint included more than 75 days
following August 17, 2015 – assertions raised in Prime Investors’ Motion to Remand.1 See ECF
No. [19] at 6. Rather, Rockwood relies on George v. Wells Fargo Bank, N.A., 2014 WL 61487
(S.D. Fla. Jan. 8, 2014). There, the plaintiffs sued their mortgage company for breach of contract
and intentional infliction of emotional distress after the mortgage company reneged on a
permanent loan modification that the parties had previously entered into. Id. at *1. The Court
found that the plaintiffs’ original complaint did not permit the defendant mortgage company to
determine that the amount in controversy exceeded $75,000 for purposes of removal because,
although it alleged specific amounts of money relating to the total purchase price of the subject
property, the down payment, and the loan amount, it “did not state that [the] [p]laintiffs sought to
recover the original loan amount or down payment[,] . . . . [and] nothing in the original
[c]omplaint [] show[ed] any relationship between the price of the home and the damages
sought.” Id. at *3. As the Court explained, “while the original complaint stated amounts of
1
Indeed, Rockwood addresses neither point in its Response to the Motion to Remand. See ECF No. [22].
4
Case No. 16-cv-62660-BLOOM/Valle
money (i.e., the down payment, the purchase price of house, etc.), it did not link those amounts
to any of the causes of action.” Id.
As the holding in George was predicated on the lack of a relationship between the
amounts stated and the causes of action asserted in the complaint, the Court finds it inapposite.
Here, unlike in George, the damages sought by Prime Investors are “clearly identified and []
linked” to the breach of contract claim asserted against Rockwood.
Id.
Specifically, the
Complaint alleges that Prime Investors is entitled to liquidated damages as a result of
Rockwood’s “substantial delays” with respect to the OPS. ECF No. [1-1], Exh. A at ¶ 12.
Furthermore, the Complaint identifies those delays as well as a specific term under the
Agreement regarding the calculation of the resulting damages. See id. at ¶¶ 10(a)-(b), 12.
Regarding the actual amount of damages, while the Court “will not speculate as to the
amount of damages and cannot expect the Defendant to have done so[] where the pleading itself
states only that the amount in controversy exceeds $15,000[,]” Lamberton v. Go Fit, LLC, 918 F.
Supp. 2d 1283, 1285 (S.D. Fla. 2013) (emphasis added), the initial pleading in this case clearly
states much more than that. The Complaint alleges specific “delays to the OPS” as a result of
Rockwood’s work, incorporates the parties’ Agreement – which, as mentioned, indicates that
Rockwood was to complete its work by August 17, 2015 – and references the Agreement’s
liquidated damage provision under which Prime Investors is entitled to “$1,000.00 for each and
every day Rockwood is late in completing the Work”.
The Complaint does not invite
speculation as to damages in this context given that it was filed well after 75 days had passed
since the August 17, 2015 deadline. ECF No. [1-1] at 14-68; ECF No. [1-1], Exh. A at ¶¶ 10(a)(b), 12; see also ECF No. [1-1], Exh. A at ¶¶ 11, 13 (alleging that Rockwood refused to correct
the defective work and that Prime Investors “continues to suffer damages”) (emphasis added); cf.
5
Case No. 16-cv-62660-BLOOM/Valle
Lamberton, 918 F. Supp. 2d at 1285 (finding that the complaint’s allegations that the plaintiff
suffered serious permanent physical injuries – including near complete blindness in one eye and
partial vision loss in the other eye – were insufficient without more to establish the jurisdictional
minimum). Thus, the Court finds that it is apparent on the face of the Complaint (and the
Agreement incorporated therein) that the amount in controversy exceeds the jurisdictional
requirement.
Accordingly, the 30-day removal period began upon service of the Complaint – not upon
Rockwood’s Counterclaim filed on September 13, 2016 or Prime Investors’ October 21, 2016
response to Rockwood’s request for admission. Rockwood’s notice of removal filed on
November 10, 2016 was therefore untimely.2
III.
CONCLUSION
For the foregoing reasons, it is ORDERED AND ADJUDGED that Prime Investor’s
Motion to Remand, ECF No. [19], is GRANTED. This case is REMANDED to the Circuit
Court of the Seventeenth Judicial Circuit in and for Broward County. The Clerk of Court is
directed to CLOSE this case. All pending motions in this matter are DENIED AS MOOT.
2
Prime Investors also moves for remand on the alternative basis that the Complaint does not sufficiently
allege the citizenship of Prime Investors and Rockwood, both of which are limited liability companies.
See generally Rolling Greens MHP, L.P. v. Comcast SCH Holdings L.L.C., 374 F.3d 1020, 1021 (11th
Cir. 2004) (“[T]he citizenship of an artificial, unincorporated entity generally depends on the citizenship
of all the members composing the organization.”) (citation omitted). The Court declines to address this
basis for remand, however, because the untimeliness of Rockwood’s notice of removal is dispositive. Cf.
South Beach Grp. Hotels, Inc. v. James River Ins. Co., 2016 WL 4157422, at *2 (S.D. Fla. Aug. 5, 2016)
(“[T]he Eleventh Circuit[] [has] instruct[ed] that, prior to remanding a case for lack of subject matter
jurisdiction upon the failure of a removing party to properly allege diversity, a district court must allow
the removing party an opportunity to cure the deficiency.”) (citing Corp. Mgmt. Advisors Inc. v. Artjen
Complexus, Inc., 561 F.3d 1294, 1297-98 (11th Cir. 2009)).
6
Case No. 16-cv-62660-BLOOM/Valle
DONE AND ORDERED in Miami, Florida, this 4th day of January, 2017.
_________________________________
BETH BLOOM
UNITED STATES DISTRICT JUDGE
Copies to:
Counsel of Record
7
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?