MobilPref SpA v. Coastal Construction of South Florida, Inc. et al
Filing
88
FINAL JUDGMENT in favor of Coastal Construction of South Florida, Inc. on Complaint and in favor of MobilPref SpA on Counterclaim; FINDINGS OF FACT AND CONCLUSIONS OF LAW.The action is now CLOSED. Signed by Magistrate Judge Edwin G. Torres o n 3/1/2017. (EGT) NOTICE: If there are sealed documents in this case, they may be unsealed after 1 year or as directed by Court Order, unless they have been designated to be permanently sealed. See Local Rule 5.4 and Administrative Order 2014-69.
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF FLORIDA
Case No. 13-24582-Civ-TORRES
MOBILPREF, SpA.,
Plaintiff,
v.
COASTAL CONSTRUCTION OF
SOUTH FLORIDA, INC. d/b/a
COASTAL CONDOMINIUMS, a
Florida corporation,
and ITAL KITCHEN
INTERNATIONAL, INC. a/k/a
CAPITOL HOLDING, a Florida
Corporation.
Defendants.
________________________________/
COASTAL CONSTRUCTION OF
SOUTH FLORIDA, INC. d/b/a COASTAL
CONDOMINIUMS,
Counter-Plaintiff,
v.
MOBILPREF, SpA.,
Counter-Defendant.
________________________________/
FINDINGS OF FACT AND CONCLUSIONS OF LAW;
FINAL JUDGMENT ON ALL CLAIMS
This case came before the Court for non-jury trial on October 26-29, 2015,
and January 13, 2016.
The parties later filed proposed findings of fact and
conclusions of law for the Court’s consideration. The Court’s review of the greater
weight of the evidence in the case requires the entry of Judgment for Plaintiff in
Part and for Counter-claimant in Part.
This Court’s Findings of Fact and
Conclusions of Law follow, as well as the Court’s resulting Final Judgment.
I. FINDINGS OF FACT1
A.
Procedural History
Mobilpref, SpA. (“Mobilpref”) commenced this action on January 7, 2014, in
a two-count complaint seeking damages for breach of contract and account stated.
[D.E. 4]. Mobilpref seeks 240,443.43 euros, approximately $336,620.80 based on
the exchange rate it claims was in effect at the time of the project, for the
manufacture and sale of kitchen, closet and related materials it delivered without
complete payment. The complaint sought contractual damages from Ital Kitchen
International, Inc., a/k/a Capitol Holding (“Ital”) and Coastal Construction of South
Florida, Inc. d/b/a Coastal Condominiums (“Coastal”).
The materials were
purchased by Coastal for installation in the St. Regis hotel project in Bal Harbour,
Florida (“the Project”).
On January 29, 2014, Coastal filed its initial answer and affirmative
defenses. [D.E. 10].
On May 16, 2014, Coastal filed an amended answer,
affirmative defenses and counterclaim. In its answer, Coastal admits it did not pay
Mobilpref the full contract price but alleges that Mobilpref breached the Parties’
agreements by improperly shipping goods, delivering non-conforming goods, and
All references to the trial transcript (“T”) include the Volume number, page and
line(s), i.e., T.I-1:1. The Court’s Findings of Fact are also included in the Court’s
Conclusions of Law, which are found in the section that follows.
1
failing to deliver all the goods that were ordered. Coastal demands judgment in its
favor on Mobilpref’s complaint.
As for its counterclaim, Coastal admits it has no financial loss arising from
Mobilpref’s alleged breaches; rather, the counterclaim seeks damages for
Mobilpref’s breach of contract, fraud, fraud in the inducement, negligent
misrepresentation, and unjust enrichment, all under the auspices of an assignment
received from its surety (Liberty Mutual).
Coastal demands damages of
$1,151,385.91. [D.E. 23].
Mobilpref dismissed Ital from the case on May 18, 2015, [D.E. 55]. After
discovery and motion practice, the complaint and counterclaim went to trial before
the Court (as the parties had contractually waived their respective rights to a jury
trial). This case came up for non-jury trial before the Court on October 26-29,
2015, and concluded on January 13, 2016.
After an opportunity to review the
transcript of the trial, the parties submitted their proposed findings of fact and
conclusions of law for the Court’s consideration. As the Court found that neither
party’s proposed findings could be adopted without material modification, the
Court prepared its own findings after thoroughly reviewing the available transcript
and the documents submitted in evidence.
B.
The Project
This case arose from the construction of the St. Regis Hotel in Bal Harbour,
Florida.
St. Regis was a high-end luxury hotel and condominium project for
Starwood, a hotel and resort conglomerate (“Starwood” or “owner”). Coastal was
selected by Starwood to serve as general contractor for the construction of a multimillion dollar hotel and residential complex across from the Bal Harbour Shops.
Bill Ford was a vice-president of Coastal and designated as Coastal’s
corporate project executive in charge of the Project. Ford had overall responsibility
for all aspects of the Project. Ford was Coastal’s primary contact with Starwood as
well as with Coastal’s many subcontractors on the Project. Coastal had between
60-80 subcontractors on site at any given stage of the Project.
Coastal’s scope of work included custom-made kitchens and closets for
residential condominium units having sale prices exceeding $1,000,000. Starwood
requested that Coastal obtain a bid from Italkitchen International, Inc. (“Ital”),
along with several other cabinet subcontractors, for the cabinet supply and
installation that would utilize high-end Italian-made materials. The subcontract
required the manufacture, delivery, fabrication and installation of cabinets and
closets for the residences. DX 2.
For that purpose, Coastal selected Ital for the project. On October 22, 2008,
Coastal entered into a written subcontract with Ital for $13,625,000 to provide and
install the custom kitchens and closets. DX 2.
Liberty Mutual Insurance Company (“Liberty Mutual”) provided payment
and performance bonds for Ital on the Project as required by the subcontract.
Liberty Mutual assured Ital’s performance of the work and payment of its
subcontractors and suppliers. DX 19.
The initial subcontract included cabinets for 268 units. T.II-277:22-25. This
subcontract included kitchenware that which Starwood planned to provide with the
units. But, due to the deterioration of the real estate market, Starwood decided not
to finish 50 units. Coastal also removed the kitchenware from the subcontract,
thereby reducing the number of units to 218 and the subcontract price to
$9,414,061.79. DX 3. Ultimately, through other revisions, there were 216 units
which were to receive kitchens and closets under the Ital subcontract. T.II-290:1-4.
C.
Mobilpref Contract & Commencement of Work
To satisfy its obligations to Coastal, Ital contacted an Italian company,
Mobilpref, to manufacture and deliver the kitchen and closet component parts to
Miami, Florida. Ital and Mobilpref had worked together on other projects before.
This arrangement contemplated that, after delivery, Ital was obligated to affix the
necessary hardware, assemble the component parts, and install the completed
assembled cabinets in each unit in the Project. The price of the original order for
the goods purchased and ordered by Ital was 1,787,797.89 Euros. DX 26.
Under its contract Mobilpref agreed to receive the orders and technical
drawings from Ital and produce the goods in accordance with those drawings and
orders. Mobilpref was also required to prepare the goods for shipment to Miami.
Ital (and later Coastal) made all arrangements for shipment and paid directly for
all shipping and delivery to the Ital warehouse in Miami, Florida. T.I-9:1-10.
Mobilpref’s proformas and invoices set forth the terms of purchase and
include an “Ex Works” clause. PX 21, 26. The “Ex Works” clause means that the
producer, MobilPref, is responsible for the manufacture of the goods. All shipping,
assembly, installation and related matters are the responsibility of the customer
(here, Ital and later Coastal). T.I-15-16.
Coastal planned for Ital to begin receiving Mobilpref’s materials in the fall of
2010, as required by the Project’s overall schedule. The cabinets came with various
options to be chosen by the ultimate unit purchaser or Starwood. There were seven
selections of hardwoods, including exotics, for the kitchens and the closets. If the
units were not sold by a certain date, Starwood would make the selections for the
unsold units in order to maintain the schedule. The plan contemplated that the
cabinets would be installed as the work moved up in the building, in a sequential
fashion.
Specifically, the luxury-priced kitchens and closets were made up of a great
number of parts and components, with the complexity multiplied by the number of
unit owner selections in the kitchens and the closets. With 216 units, 7 possible
kitchen veneer selections in two finish selections (matte and high gloss), and 7
closet selections in two finishes, the permutations and combinations for that many
units were extensive. The unit purchasers were to be given an option of seven (7)
different species of exotic woods to choose from, in either a gloss or matte finish.
Thus, there were fourteen (14) possible combinations available to the purchasers.
Further, different parts of the closets were made of different types of
materials as well. The higher end “showy” part of the kitchen and closets that
were visible, i.e., doors, panels, etc., had to be veneer-faced, medium density
fiberboard (an engineered wood product) with the veneer finish as specified by the
unit purchaser. All of the different component parts had to be coordinated for
every kitchen and closet component to match.
The “boxes” for the kitchens and closets were all to be made of melamine,
i.e., an engineered wood product. This is a generic material but comes in different
finishes that had to be coordinated with the unit selections. The boxes formed the
backbone of the cabinets to which the veneered products were applied to give the
impression of a solid wood cabinet. However, some of the melamine materials had
to have veneer applied to maintain the illusion of a solid wood product.
Needless to say, this was a complex order. The full cabinet installation was
estimated to take approximately eight (8) months, with an initial completion date
in the summer of 2011. And this complex order was essential. The kitchen and
closet cabinets had to be installed before Starwood could close on the condo units
with the required certificates of occupancy.
Coastal provided Ital with its initial unit wood selections by June 2010,
anticipating that Ital would then commence the manufacturing and delivery
process. For that purpose, Ital received a deposit of $3,000,000 under its
subcontract with Coastal. T.II-293-2:6.
D.
Ital’s Failure to Perform Leads to Delayed Production
By September 2010, Coastal was expecting to see initial cabinets and
materials arriving at the Project site. Ford had anticipated the typical lead time
on such an order was 90 days from material selection to arrival of first materials.
T.II-297:23-25, 298:1-2. That did not happen, however. Coastal raised its concerns
with Ital, who assured Coastal that its work was proceeding as planned. In truth,
however, Ital at that point in time was encountering financial hardships that were
interfering with Ital’s work on this Project. Ital was thus not making the required
payments to Mobilpref to begin manufacture and delivery of the cabinets.
For its part Starwood also grew concerned that Ital was not performing. Its
project executive suggested a visit to Italy to meet directly with representatives of
Ital and Ital’s supplier (which Coastal later learned to be Mobilpref). A visit to
Ancona, Italy – where Mobilpref was based – was planned for September 2010 at
which time Coastal could verify the manufacture of the cabinet materials.
Starwood wanted to verify that Ital had secured the veneer raw product for
fabrication of the materials selected. Ford was thus tasked to go to Italy to meet
with Ital’s supplier – Mobilpref – to see the progress being made toward the
delivery of the cabinet components he had been told were being manufactured
there.
That first visit to Ancona, Italy took place that September. In attendance for
Coastal were Dan Whiteman (Coastal’s president), who testified, Donald
Whiteman, an assistant superintendent on the Project, and Ford.
Starwood’s
project manager, Fordsman, attended as the owner’s representative. Ital’s
principal, Ted Planton, also made the trip. This delegation met with Giancarlo
Pierdicca, Mobilpref’s owner, and Gerry Talozzi, who testified at trial as
Mobilpref’s corporate representative.
Talozzi played a central role.
Talozzi
testified that he represented several Italian companies, including Mobilpref, under
what he described as an “agency” relationship where he would promote a
company’s business and try to sell their materials outside of Italy. At the time of
the Project, Talozzi had worked with Mobilpref on about 15 other projects. T.I-
7:21-24.
As he was the primary Mobilpref representative who spoke English,
Talozzi was the sole point of contact for Coastal and acted as Mobilpref’s agent in
its work on the project.
Again, the purpose of the meeting was to confirm that Mobilpref had the
capacity and the commitment to produce the cabinets for Ital and the Project. The
attendees learned that Mobilpref was a “melamine” shop and only had the
equipment to manufacture the “boxes” portion of the kitchens and closets, not the
high-end veneered parts (the panels, doors and other visible component parts).
Mobilpref subcontracted out the veneered wooden panels and door components of
the kitchens and closets to GFL, another Italian cabinet company based near
Ancona.
Thus, the component parts of the kitchens and closets to be shipped to the
Project were going to be the combination of the materials manufactured at
Mobilpref’s factory, GFL’s factory and, later on, two other veneer shops at different
locations, which were then to be shipped separately in shipping containers to Ital
in Miami. Mobilpref represented that it had the systems in place to coordinate all
of these material sources and parts and components so that the materials arrived
in such a way that they could be assembled either in the Project or at Ital’s
warehouse.
Talozzi touted, in particular, Mobilpref’s use of a flat-packing process to
make it easier to assemble the component parts once they arrived at the project.
Talozzi explained how the packaging would be set up by unit for the kitchens, by
unit for the closets, and they would be sent in “flat packs,” which would be
identified on each package what they were for.
Coastal and Starwood’s representatives were disappointed, however, that
they did not see evidence of manufacturing of St. Regis components while they
toured the Mobilpref factory. They were expecting to see fabricated panels,
fabricated doors, or some type of finishing work in process, but they saw none of
that.
They thus left the meeting in Italy still concerned that Ital and Mobilpref
would not be able to deliver despite the subcontractors’ assurances. They had
reason to be concerned given that Mobilpref itself was relying on its own suppliers
to deliver complete kitchen and cabinet components. And Coastal learned on that
trip that Mobilpref’s factory only produced the melamine boxes that, without the
remaining components, would not satisfy Coastal’s needs.
By that point in time (September 2010), Coastal had already made deposits
to Ital under the subcontract. Coastal had no intention of making any further
payments to Ital until their product started arriving at Ital’s local warehouse in
Miami. By the time Coastal and Starwood returned to Miami, materials had still
not been shipped.
In October or November 2010, Platon from Ital claimed to Ford that the first
container was on its way. Ford went to Ital’s warehouse in Miami when Platon
told him that a shipment for the Project had come in, but when Ford arrived he
found only cabinet parts for another project. No St. Regis product was evident.
Ford by this point was fully aware of Ital’s failure to perform, which was
consistent with Starwood’s growing concern that Ital’s financial condition was
jeopardizing the project. After Ford confronted Ital about its failure to perform,
Platon put Ford in touch with Talozzi, who told Ford that Mobilpref had not yet
received its payment to begin shipping materials. T.III-359:9-15.
For its part, Mobilpref insisted on payment of $1,500,000 before it would
commence production of the materials for the Project.
Talozzi claimed that a
deposit payment of $200,000 was still due and owing. At the same time, Mobilpref
and Ital refused to disclose to Coastal the precise terms of their deal, i.e., the total
value of the materials that Ital had ordered from Mobilpref and the exact list of the
pieces to be supplied by Mobilpref. Ford was told, instead, that if Coastal paid the
$1,500,000, Coastal would receive the ordered materials.
By this point, both Coastal and Mobilpref were thus fully aware that Ital’s
financial
problems
was
hampering
its
performance
under
the
contract.
Accordingly, Coastal put Ital’s performance bond surety, Liberty Mutual, on notice
of a possible claim based on the issues it was having with Ital. T.IV-589:12-20.
Coastal’s knowledge that Ital would likely breach its contract was not enough for it
to cancel it and retain a replacement cabinet subcontractor. But this was not a
viable option, as Ford explained, because shop drawing submittals, material
selections, and measurements had already been prepared and would likely have to
be redone. Ford decided that, as a result, Coastal would have to find some solution
with Ital.
Mobilpref.
That solution required Coastal to step in and deal directly with
E.
The Tri-Party Agreement – December 20, 2010
Ultimately, on December 20, 2010, Coastal, Ital and Mobilpref entered into a
“Tri-Party Agreement” under which Coastal was to make the $1,500,000 in
payments directly to Mobilpref in order to receive all of the kitchen and closet
materials from Mobilpref (with a resulting credit against the balance of Ital’s
subcontract). PX 1; DX 4.
Ford’s intent was that, if Coastal fronted the $1,500,000 to Mobilpref for the
kitchen and closet materials, Ital would at least be able to complete its own scope
of work under the contract – receiving, sorting and assembling the delivered
materials for installation at the St. Regis project.
Based upon Ital’s and
Mobilpref’s assurances, Ford hoped that all of the dates for the shipment and
delivery of the materials per the Tri-Party Agreement were achievable.
The Tri-Party Agreement provides that Coastal was to receive all of the
materials (which at the time included 204 kitchens and 202 closets) for payment of
$1,500,000 and that Mobilpref would look only to Ital for any balance remaining
due for production of all the materials:
Whereas, Mobilpref has a separate Agreement with Ital to
manufacture and delivery [sic] the cabinets to Ital for fabrication and
installation, and
Whereas, the Subcontract Agreement between Coastal and Ital
provides for payment of materials only upon their delivery and storage
in Miami, Florida, and
Whereas, Mobilpref and Ital have jointly requested that certain
advance payments be made directly to Mobilpref for the above
cabinets, and wish to keep the terms and details of their separate
agreement confidential between their organizations, and
Whereas Mobilpref has agreed to remain open and in full production of
the cabinets without any interruption of manufacturing during the
Christmas and New Year Holiday Season, and
Whereas time is of the essence is assuring the timely completion of the
Project, and
Whereas Coastal, in exchange for the acceptance of this Agreement by
Ital and Mobilpref is prepared to make certain advance payments
provided certain conditions of manufacture and delivery are met, the
following represents the terms of this Agreement:
1. Ital and Mobilpref agree that Coastal shall only be responsible to
make payments to Mobilpref for the payments outlined below and
that any further payments that may now be or become due to
Mobilpref in excess of the following will be made solely by Ital, and
Coastal shall have no responsibility now or in the future for any
such payments.
2. Coastal agrees to make direct payments to Mobilpref by wire
transfer in the following amounts, with a simultaneous
acknowledgement by Ital that any such payment is an equal
reduction in the balance of the Subcontract amount between
Coastal and Ital, based upon confirmation of the fulfilment of the
agreed upon manufacture and shipping dates of the components
outlined herein . . . .
PX 1 at 1-2.
The balance of Item 2 of the Tri-Party Agreement specified five total
payments for a total of $1,500,000, with the final payment due after shipment of all
materials by February 28, 2011. This condition was consistent with the overall
scheduled completion date for the kitchens in July-August 2011 and the closets by
September-October. T.III-375:20-25. Hence, all parties to the Tri-Party Agreement
agreed that “time was of the essence.”
While the Tri-Party Agreement expressly referenced the existence of an
undisclosed balance that Ital would still owe Mobilpref, Coastal was not privy to
that information. Only Ital and Mobilpref knew that amount. Ford never saw the
original pro forma before Coastal entered into the Tri-Party Agreement.
But
Coastal entered into the Agreement anyway with the intent and expectation that
Ital and Mobilpref would perform their obligations under the Agreement and Ital’s
subcontract. T.I-15-16.
F.
Problems and Delays in Early Installation
With the Tri-Party Agreement in place, Coastal began making its first
installment payments directly to Mobilpref, which in turn started shipping
containers of materials from Italy in January 2011. T.III-376:15-25. But as the
containers for the kitchens started to arrive at Ital’s warehouse, they were not
being timely assembled by Ital personnel.
Under the Ital contract, Ital was
responsible for assembling the offloaded materials and preparing them for
installation at the project location. But that did not happen, in part due to the
manner in which Mobilpref began sending the materials. Mobilpref did not ship
closet-specific flat-packs as Coastal expected; instead, Mobilpref’s initial shipments
were organized by the type of component part, i.e., a series of end panels for
multiple units and not by unit. But the underlying contract documents ultimately
placed the responsibility of assembling the shipped materials at Ital’s doorstep.
Ital could not do so.
The problems evident in the early part of 2011 led Coastal to begin taking
over management of the Ital subcontract. Coastal began directing the operations at
the Ital warehouse facility in Miami and on the Project’s jobsite. Coastal installed
its own staff at the warehouse and hired Tom Driscoll Installations, Inc. to manage
Ital’s entire scope of work. Coastal’s in-house financial staff also took over all
payments for Ital’s vendors, suppliers, staff and overhead. Driscoll started working
on the Project in approximately the second week of February 2011. T.IV- 681:2022. Coastal could no longer afford to let Ital languish while the work on the project
got delayed.
But Ital’s failure to properly assemble the units created even further delays,
especially for the closet installations.
Ital (and then Coastal) had to sort the
materials at Ital’s warehouse to locate the different component parts (which in
many instances came on separate containers) to accumulate the product needed for
a single unit. To compound matters, Talozzi admitted that the veneered doors
were packaged separately from the other materials by Mobilpref’s veneer shop
subcontractor, GFL. And GFL did not flat-pack the doors in the way that Talozzi
had claimed. Moreover, the parts were either poorly labeled or not labeled at all,
which made it difficult to efficiently assemble the parts for installation of a closet
in a unit.
Upon arrival at the site, Driscoll familiarized himself with the current status
by reviewing the status of the installations in the units at the Project. Driscoll
testified that during the first two months he was on site (February and March
2011), the work focused on installation of the kitchen “boxes” in the units that
would ultimately receive the veneer door panels and other necessary veneer
component parts. Driscoll testified that in early February, he was trying to get the
“kitchen program up and running” and the next step would be to start the closet
program. T.IV-689:10-15. But the closet program was hindered because there was
“simply not enough material there.” T.IV-689:1-4.
G.
Amendment 1 to Tri-Party Agreement – April 2011
By mid-March 2011, Coastal had just made a large payment of $500,000 to
Mobilpref and had only one payment of $250,000 remaining to Mobilpref under the
Tri-Party Agreement. Yet, despite the shipment of materials that were received to
date, the quantities did not add up because many more materials were necessary
for completion, especially for the closets. Ford wanted to find out what was going
on before Coastal made the last $250,000 payment.
Talozzi travelled to Miami from Italy in March 2011 to meet with Coastal on
that issue. Ford picked Talozzi up at his hotel en route to dinner with Whiteman
and Platon. On the drive, Talozzi told Ford for the first time that Coastal would
have to pay Mobilpref an additional 590,000 Euros before Mobilpref could ship the
remaining materials. T.I-27:4-7, 28:1-13. Ford was not happy.
When Ford confronted Platon of Ital about this problem, Platon conceded
that the $1,500,000 in payments would not be enough. And while Talozzi and
Platon agreed that Coastal was supposed to receive the balance of the product for
the units for the $1,500,000 required by the Tri-party Agreement, Ital claimed it
did not have the funds to pay the rest of the order.
After that meeting, on March 30, 2011, Ford sent an email to Platon and
Talozzi (PX 6):
As agreed today we are making the final $250,000 payment on the
original Tri-Party Agreement based on manufacturing progress to
date. In order for Coastal to make the additional payments requested
beyond this amount the Tri-party Agreement will need an
extension/amendment to incorporate these additional payments
Coastal has been asked to make on Ital’s behalf. We will prepare and
forward this amendment in the next few days.
I would also note that an additional order has since been placed to
Mobilpref in the amount of $38,890 for the 6,500 puck lights, and per
Ital’s request we are paying this amount as well, and will include it
with the $250,000 payment wired today.
Talozzi responded to Ford’s email on April 5, 2011, confirming that
Mobilpref had “received the last wire for $250,000 US Dollars as per the original
Tri-Party Agreement.” He also attached a schedule to his email, which reflected
Mobilpref’s receipt of full payment on the original Tri-Party Agreement, as well as
the additional $38,000 for the puck lights referenced in Ford’s initial email, but
which also reflected a 608,563 euros balance on Mobilpref’s original pro forma with
Ital – the balance of the original order.
In connection with the “extension/amendment” which Ford said would be
necessary before Coastal would pay more money, Ford (now with Driscoll) went on
a second trip to Mobilpref’s factory in Ancona, Italy. The purpose of this second
trip was to ensure that if additional monies were paid then Coastal would in fact
get all of the materials needed to complete the Project. T.III-389:9-19.
In Italy, Ford met with Talozzi and developed what would become
Amendment No. 1 to the Tri-Party Agreement (hereinafter “Amendment 1”). PX 2;
DX 5. Amendment 1 provided that Coastal would make the remaining payments
due to Mobilpref, addressed modifications to the cabinets and related products to
be provided by Mobilpref, and added a few new products to be purchased.
Amendment 1 also included a retainage provision of 160,000 Euros to the payment
terms as an incentive for Mobilpref’s timely performance of its contractual
obligations.
Specifically, Amendment 1 provides, in relevant part:
(1) It is agreed that the total outstanding amount to be paid on the
Current Order (the Balance) for the items generally described herein
is 590.000,00 Euros, to be adjusted per the exchange rate in effect at
the times the remaining payments are made.
(2) Payments for the Balance are to be made as follows:
A. Coastal will wire transfer to Mobilpref $300,000.00 within 3 days
of shipment of 2 additional containers (containers 22 and 23).
B. Coastal will wire transfer to Mobilpref an additional amount of
$333,000.00 within 3 days of shipment of all remaining parts required
to complete the Current Order.
C. The balance remaining will be withheld as Retainage to be paid by
Coastal to Mobilpref within 45 days of delivery to Miami, Florida of
the final shipment(s). Within this 45 day period Ital and Coastal will
confirm that all parts were properly manufactured and delivered or
shall provide a list to Mobilpref of any parts that may be defective or
missing, which parts shall be furnished or replaced by Mobilpref and
delivered to the shipper. Two times the value (as reasonably
determined among the parties) of any such parts, if any, that have not
been received in Ital's warehouse within this 90 day period shall be
withheld from the final payment of the Retainage, which amount, if
any, shall be paid within 14 days of receipt of these parts.
PX 2 (emphasis added).
Coastal entered into this modification of the Tri-party agreement despite
grave misgivings about the status of Mobilpref’s production. For instance, Talozzi
took Driscoll to GFL’s location, where Driscoll was hoping to see what raw
materials GFL had on hand for the veneer work. The answer was, not much.
Based on what Driscoll saw at GFL, he had the impression that GFL had just
started production that morning. Further, Driscoll determined that the original
Ital order of 204 kitchens and 202 closets was short and that in fact 216 units were
needed. This is why Amendment 1 specifically referenced 204 kitchens/202 closets,
because the intent was to submit an additional order to Mobilpref for the
additional 12 units. T.III-395:18-25, 396:1-9.
Nevertheless, Amendment 1 was finalized and Ford left Italy.
Driscoll
stayed behind to try to pin down the materials that had been shipped and what
remained to be shipped, in the hope that he could rectify the existing inability to
fully complete any single unit due to lack of parts. Ford left Italy thinking that
finally the situation was in hand (albeit, at the price of an additional 590,000
Euros). Indeed, Mobilpref was bound to complete all its work on the original order
after Amendment 1. T.I-32:10-12.
With Amendment 1 in place, Coastal made the initial payment ($300,000)
and started receiving additional containers. As the additional containers arrived,
however, Coastal continued to find problems with the manner in which the
materials were shipped, as well as missing components particularly relating to the
veneer components. But Driscoll realized in his trip to Italy that delays with the
veneer products were inevitable given how they were being processed by
Mobilpref’s suppliers.
Specifically, Driscoll learned that matte finished veneer
products would be shipped from Mobilpref’s location, while the high-gloss veneer
shop (250 miles away) would be loading and shipping its products from that
location. T.IV-705:1-25.
As Driscoll feared, as of April 2011 there was still not enough product to
finish any single unit in the project. The continuing issues Coastal was having led
to Talozzi and Gianfranco Pierdicca traveling to Miami.
During that trip,
Mobilpref made further assurances that it would timely complete its work required
by Amendment 1.
Coastal then made the second payment of $333,000 under
Amendment 1.
But, at this point Mobilpref had clearly and expressly been placed on notice
that these continued shipment problems could lead to Coastal charging back
monies from Mobilpref, both through Driscoll’s communications with Ital and
Mobilpref, as well as what was in effect a “demand” from Ford that Mobilpref cure
its failure to timely perform. DX 28.
H.
Third Trip to Italy and Amendment 2 to Tri-Party Agreement
During Ford and Driscoll’s trip to Italy in April 2011 to work on Amendment
1, Driscoll discovered that the original pro forma between Ital and Mobilpref was
missing 12 units of materials. Driscoll went to Italy to develop that order in May
2011, as well as inspect the status of production of the materials previously
ordered. When he arrived, he observed that Mobilpref was still in the midst of
producing those materials. He also reiterated to Mobilpref how difficult it had
been to complete a unit based on the manner in which the goods were shipped and
the delays in producing all the necessary parts.
Driscoll’s May 2011 visit led to the creation of Amendment 2, DX 32, which
followed Mobilpref’s pro forma for additional parts that were ordered to complete
the project. Mobilpref’s initial price for the pro forma was 287,000 euros. Driscoll
reviewed the pro forma and removed some items, particularly attic stock, to bring
the price down to 155,000 euros. Talozzi eventually agreed to 165,000 euros price
(or about $226,000). That order and price was memorialized in Amendment 2.
Talozzi and Mobilpref denied the existence of any such formal Amendment
to the original contract, in part because an executed copy of the agreement signed
by all parties (not just Ford from Coastal) was not introduced into evidence. But
the great weight of the evidence admitted at trial proved otherwise.
Talozzi’s
testimony in this respect was not credible, while Ford’s testimony on the subject
was entirely credible.
In addition to that credibility finding, written evidence of the parties’
agreement to enter into Amendment 2 also is found in the record.
Talozzi
communicated in writing with Ford and others after the Italy trip that he had
received the final version of the Amendment and submitted it to Mobilpref. DX 33.
Talozzi later confirmed in writing work had begun on manufacturing the ordered
materials and, later, receipt of the wire of the final payment of those materials. DX
43.
Coastal ultimately paid Mobilpref the 165,000 euros (in two installments) for
all the materials ordered and incorporated into Amendment 2. T.I-92:7-12. Such
payments were received and acknowledged by Mobilpref.
Therefore, the great
weight of the evidence supports the existence of an enforceable agreement in this
respect.
I.
Mobilpref’s Completion of Contract and Claim for Payment
During the summer 2011, shipments continued but so too were Coastal’s
difficulties in completing the units. At trial, Talozzi admitted that by June 2011
there were still kitchen cabinets from the original order that had not yet shipped.
T.I-126:2-22.
The delays in delivery of all the required components led Coastal to set up a
“cabinet-making shop” in the garage of the Project. That effort involved bringing in
machinery, procuring materials locally, including exotic veneer materials, to
produce the parts that they were not receiving from Mobilpref because of an
upcoming deadline for the Temporary Certificate of Occupancy (TCO) for the
Project. Driscoll provided samples of all of the seven different wood species to
South Florida supply houses to prepare the proper tints necessary to finish the
veneered components. This effort also provided Coastal a means to re-finish nonmatching materials that Mobilpref had provided.
By August 11, 2011, Dan Whiteman again got involved and emailed Talozzi
after Coastal received notice that Container #35 was being shipped, inquiring as to
whether a) Container #35 was the last container and; b) whether it completed the
order. DX 35. Talozzi’s responded five days later that there were still parts that
were missing and that an additional container would be required after August.
Ford confirmed that container #35 did not include all the components
necessary to complete the order. It was at this time that Ford approved only
100,000 euros to be paid of the 165,000 euros due under Amendment 2.
On September 13, 2011, Ital sent Talozzi a detailed breakdown of all of the
missing doors and panels still needed to finish the job. Per the three agreements,
all of the materials had been purchased by Coastal, some arguably multiple times.
It was a large list of about 800 veneered door panels for the kitchens. Talozzi
admitted that he received the list. T.I-141:25, 142:1. These door panels were not
necessarily additional materials that Coastal was ordering for the first time in
September. They were panels that were included in the original order and its
amendments.
But some portion of that order may have included new or
replacement materials that were required to finish the job. But the Court cannot
find without speculating what percentage were new versus what percentage were
items missing from the original order.
By September 20, 2011, Talozzi was emailing Ford and advising that “the
only material left to be shipped are the 2 custom units secondary closets S-110 and
S-1201. We are shipping these with the remaining attic stock required – wood
panels pre-finished which are coming ready too. . . . Gianfranco [Pierdicca] will be
the best person indicated to come and assist you on sorting out all the missing. Let
me try to get this organized and then I will let you know.” DX 43.
On September 21, 2011, Coastal initiated and approved the wire for the final
65,000 Euros ($89,114.90) and paid Mobilpref in full for Amendment 2 to the TriParty Agreement. Ford conceded that Coastal received all the materials for the
extra units under Amendment No. 2. From his point of view, the only open
payment issue was the retainage left on the 590,000 Euros in Amendment 1, which
was approximately 130,000 – 135,000 euros.
This amount was not disbursed
because Coastal had not yet received everything it had ordered.2
While Talozzi testified that the retainage on Amendment No. 1 was “around
160,000 euros,” Ford testified that he calculated it somewhere 130,000-135,000
euros based upon an exchange rate of the time.
2
In September and October, Coastal continued to demand that all the
remaining doors and parts be delivered. But as of November 1, 2011, kitchens and
closets were still incomplete due to a lot of parts and pieces missing. Some units
were getting punched out, others getting completed, and others getting ready for
unit owner walk-throughs for those closings. But some units were only partially
completed and some units were missing a lot of parts.
On November 1, 2011, Ford emailed Platon (and copied Talozzi) advising
that Coastal was going to have to procure the doors locally, as “Mobilpref is going
to be too late. . . . As you know, we have to be 100% done by the middle of the
month.” DX 54. Two days later on November 3, 2011, Talozzi was still asking
whether the material that Coastal is waiting on has to be shipped “finished or
unpolished.” DX 53. Clearly, Talozzi’s response revealed that the missing doors
were not arriving any time soon. Coastal then decided to procure the doors locally.
Later, on December 20, 2011, Talozzi emailed Ford asking “will the doors we
made be useful for you at this point. Can we ship them at all?” DX 57. By that
point, Coastal was installing the substitute doors that it manufactured locally.
After some time passed, on October 11, 2012, Mobilpref sent Coastal a
demand letter seeking 160,000 euros.
Coastal refused.
Mobilpref filed suit in
January 2014, nearly three years later. Mobilpref’s breach of contract claim at
trial was based on Coastal’s failure to pay: (1) 160,000 Euros due for the retainage
amount held back under Amendment 1; and (2) the balance of 80,243.43 Euros due
for the additional orders related to the 15 additional units and “extra orders” that
Coastal made in the fall of 2011. Based on the agreed exchange rate at the time of
the construction of the Project, the total unpaid balance due, according to
Mobilpref, is $336,340.80.
J.
Coastal’s Claim Against Ital’s Surety
At the conclusion of the Project, Coastal submitted a claim to Ital’s Surety,
Liberty Mutual, for $1,900,000.00 seeking damages allegedly caused by Ital’s nonperformance of its contractual obligations. Coastal ultimately settled its surety
claim and received $1,700,000.00. T.III-526:1-18; T.V-961-62; DX 14. By making
payment of the Ital claim to Coastal, Liberty Mutual became the owner of any
claim that Coastal had against Ital or any of Ital’s subcontractors who contributed
to that claim, i.e. Mobilpref. Liberty Mutual then assigned its rights against Ital
and those subcontractors back to Coastal. DX 18.
As Liberty Mutual’s assignee of Coastal’s claim against Ital, Coastal is the
current holder of the rights to sue for subrogation arising from the payment of the
claim against Ital, which includes the right to seek damages for contribution on
Ital’s behalf.
K.
Coastal’s Claim Against Mobilpref
Coastal concedes that Mobilpref performed the lion’s share of Ital’s
subcontract, which required it to produce the materials for the kitchen and closet
cabinets
for
the
Project.
But
Coastal
alleges
that
Mobilpref
“poorly”
performed that obligation, which materially contributed to Ital’s own default of its
subcontract with Coastal.
Coastal allocated $1,151,385.913 of the original
$1,900,000 performance bond claim to issues proximately caused by Mobilpref’s
breach of its agreements with Coastal on the Project.
II. CONCLUSIONS OF LAW
A.
Mobilpref’s Breach of Contract Claim
The pleadings in the case require the Court to determine whether Coastal or
Mobilpref (or both) breached the parties’ agreements, as set forth in the Tri-Party
Agreement and its two amendments.
We turn first to Mobilpref’s complaint.
Mobilpref takes the position that it fully performed by supplying all the materials
ordered, while Coastal failed to make full payment. Mobilpref seeks damages in
the case based on a breach of contract claim governed by Florida law.4
“Under Florida law, a breach of contract arises when there exists (1) ‘a valid
contract’; (2) a ‘material breach’ of that contract; and (3) resulting ‘damages.’”
Energy Smart Industry, LLC, v. Morning Views Hotels—Beverly Hills, LLC, 660 F.
App’x 859, 862 (11th Cir. 2016) (quoting Beck v. Lazard Freres & Co., LLC, 175
F.3d 913, 914 (11th Cir. 1999)); Havens v. Coast Florida, P.A., 117 So. 3d 1179,
1181 (Fla. 2d DCA 2013) (same).
There is no dispute that Mobilpref proved that it originally entered into a
valid contract for the sale of goods with Coastal, the Tri-Party Agreement. That
DX 61 identified $1,208,884.09 in claimed damages; however, at trial Coastal
reduced that amount by the amount of the Drawer Hardware costs ($57,498.18)
and dropped that portion of the claim, leaving the revised claim of $1,151,385.91.
4 Mobilpref also pleaded an account stated claim in the original complaint but did
not press that theory of recovery, separate from the underlying contract claim,
either in the pretrial stipulation or in its post-trial submission.
3
agreement
required
payment
from
Coastal
in
exchange
for
Mobilpref
manufacturing and shipping materials ordered by Ital. Timely compliance was a
material term of that agreement, as the parties agreed upon a time is of the
essence provision.
It is also undisputed that the Tri-Party Agreement was supplemented and
modified by Amendment 1, which required additional payments from Coastal in
exchange for Mobilpref’s completion of its obligations under the original
agreement, plus additional product ordered by Coastal.
That modification also
expressly included a timely condition precedent to final payment that required
timely and complete performance by Mobilpref.
The greater weight of the evidence also showed that Mobilpref and Coastal
entered into a second modification of the Tri-Party Agreement’s – Amendment 2 –
that constituted an additional order for more materials and parts necessary to
complete the project. Amendment 2 constituted a purchase agreement for specific
materials that Coastal ordered (and agrees that it received) in addition to those
encompassed by the original agreement or Amendment 1.
While Mobilpref
disputes that it agreed to provide the totality of the materials listed on the
itemized list attached to Amendment 2 as part of the contract, the Court finds that
Mobilpref did in fact agree to satisfy that order and for amount – 165,000 euros (or
about $226,000 based on the currency rate at the time).
The crux of the dispute centers on whether Coastal breached these written
agreements in failing to make the final payment to Mobilpref.
The evidence
reflects that Coastal paid Mobilpref $1,500,000 under the Tri-Party Agreement,
plus $633,000 under Amendment 1. Coastal also paid $226,000 for the parts and
material ordered through Amendment 2.
Altogether, Coastal made direct
payments to Mobilpref (separate and apart from any funds originally disbursed to
Ital at the inception of the project) in the amount of $2,359,000.
But Mobilpref still alleges Coastal breached by not making full payment for
all the materials shipped under these agreements. Specifically, Mobilpref seeks (1)
160,000 Euros remaining due under Amendment 1 for the retainage amount held
back by Coastal; and (2) the balance of 80,243.43 Euros due for the additional
orders related to the 15 additional units and “extra orders” that Coastal made in
the fall of 2011.
Coastal argues in response that it did not breach the agreements – Mobilpref
did. Mobilpref’s breach of its agreements for timely and complete performance
excused Coastal from further performance, i.e., disbursing the retainage amount
set aside by Amendment 1.
The retainage amount is created and governed by Paragraph 2(c) of
Amendment 1:
The remaining balance will be withheld as Retainage to be paid by
Coastal to Mobilpref within 45 days of delivery to Miami, Florida of the
final shipment(s). Within this 45 day period Ital and Coastal will
confirm that all parts were properly manufactured and delivered or
shall provide a list to Mobilpref of any parts that may be defective or
missing, which parts shall be furnished or replaced by Mobilpref and
delivered to the shipper.
Two times the value (as reasonably
determined among the parties) of any such parts, if any, that have not
been received in Ital’s warehouse within the 90 day period shall be
withheld from the final payment of the Retainage, which amount, if
any, shall be paid within 14 days of receipt of these parts.
This provision calls into question whether Mobilpref did, in fact, deliver all
of the materials required by the original Tri-Party Agreement and its two
amendments. On this issue, the circumstances surrounding the September 13,
2011, Ital door order and the events that followed are telling. Coastal laid the
predicate at trial and elicited from both Talozzi and Ford the procedures that
Mobilpref and Coastal used for “extras” on the Project. Coastal would provide an
order, Mobilpref would prepare a pro forma for review with pricing, Coastal would
review the order and if acceptable, Mobilpref would provide an invoice for payment
to Coastal and require payment before the materials were shipped.
While Talozzi claimed that the Ital door order constituted “extra” materials,
the parties’ course of performance for extras was never put into place for the door
order. Ford testified that the door order was in fact a “list” of all the missing parts
and pieces that Coastal needed to finish the Project. The email from Gustavo
Aristia at Ital to Talozzi transmitting the door order simply states: “Please find
attached the doors & panels orders needed to complete the job.”
There is no
correspondence or communications between the parties, from that September 13th
Ital email through the last email between Ford and Talozzi on December 20, 2011,
that contain any indication from Talozzi that he considered the door order to be an
order for extra materials. To the contrary, the communications during this time
period show Coastal’s urgent need to obtain the missing materials as quickly as
possible for their efforts to finish units that were rapidly approaching closing dates.
It is also telling that during this time period, Talozzi made no mention of any
monies due from Coastal relative to the door order. Instead, the only reference to
monies owed during this time period occurred on September 15, 2011, where
Talozzi advised Ford that, “[d]uring the next weeks, I would like to start [to]
discuss with you the 150,000.00 euro as retainage.” DX 44.5
There is no mention of any additional billing for the door order. Indeed,
Talozzi confirmed on cross-examination that the doors were in fact never shipped
nor ever invoiced. T.II-195, 206.
The record contains further support for that
conclusion: On October 26, 2011, Ford emailed Talozzi and said:
I understand you have approximately 800 kitchen doors that will be
ready to ship 1st week of November, based on an order sent from Ital
several weeks ago. I will need to air freight these doors in order to
complete the units for turnover to the Owner which is scheduled for
mid-November.
Please confirm whether this is correct and advise of any requirements
you may have in order to release these doors for shipment.
DX 50.
Talozzi did not respond to Ford’s email with any requirements that
Mobilpref had in order to release the doors for shipment. Mobilpref never sent
Coastal a pro forma for the door order. Despite promising that the doors would be
available the “first [week] of November,” Talozzi was still asking Ford whether the
doors should be shipped “finished or unpolished” on November 3rd, further
indicating that the order was still not complete. DX 55.
Of course Ford had already told Talozzi the day before in an email, “These
units are supposed to be 100% DONE by 11/11 so obviously the dates outlined
Further support for this fact is found in the demand letter sent by Mobilpref’s
Italian counsel to Coastal, which demanded immediate payment of “160,000 Euros”
owed following Mobilpref’s completion of its work. PX 20.
5
below will not work. Can you please set these doors up for an immediate shipment
and we will take care of the finishing over here.”
DX 56.
Ford had already
answered the question that Talozzi asked the next day and then Talozzi never
contacted Ford against until December 20, 2011.
The weight of the evidence shows that on November 3rd, with imminent
closing dates, Mobilpref had not performed with respect to these missing items. As
a result, Coastal mitigated its own exposure for delay damages to Starwood if the
project was not completed in time to close on units in November and December
2011. Coastal did so by cancelling the Mobilpref shipment and retaining a new
source of supply for the same doors.
Accordingly, the weight of the evidence persuasively shows that Mobilpref
failed to timely ship the material in the manner that had been promised back in
September 2010, starting with Mobilpref’s failure to ship all of the materials by
February 28, 2011, all the way up to November 2011. The weight of the evidence
also points to the fact that Mobilpref had never delivered these doors before.
Mobilpref’s failure to provide the doors in a timely fashion means that the
predicate for final payment of the retainage amount in paragraph 2(c) was never
triggered.
Mobilpref is not, therefore, entitled to any retainage because, after
being given notice more than 45 days earlier of materials not accepted or delivered,
it failed to replace those missing materials within the time period required. And
because the contract provided for a type of liquidated damages that Coastal could
impose, in the form of twice the value of the materials at issue, the net amount
relating to these particular materials would rise to the level of the $160,000
retainage.
Accordingly, the Court finds that the retainage amount constitutes the
“damage” amount that Amendment 1 contemplated.
Coastal was contractually
entitle to retain that amount as compensation for Mobilpref’s own breach based on
its inability to deliver all the components necessary to fully complete the project.
Coastal retained a substitute source of supply and relied in part on the retainage
amount for this purpose.
For its part, Mobilpref takes the position that all goods were shipped and
accepted by Mobilpref, thus negating any argument that payment was excused
under the Uniform Commercial Code. Mobilpref argues that Coastal failed to carry
its burden of proving that it rejected any of Mobilpref’s goods, and, instead
accepted and used all of the goods. See Fla. Stat. § 672.607 (“the buyer must pay at
the contract rate for any goods accepted,” and “[a]cceptance of goods by the buyer
precludes rejection of the goods accepted and if made with knowledge of a
nonconformity cannot be revoked because of it unless the acceptance was on the
reasonable assumption that the nonconformity would be seasonably cured. . . .”);
see, e.g., In re Holistic Serv. Corp., 29 B.R. 509, 512 (S.D. Fla. Bkrtcy. 1983) (debtor
accepted goods shipped by creditor where evidence established that goods were
delivered, debtor had opportunity to inspect and debtor failed to notify creditor of
any defect within reasonable time, and only raised objections after litigation arose).
The problem is that due to the nature of the project, as confirmed by the
parties in their written agreements and their course of performance, Coastal was
not in a position to put non-conforming materials back on a container to Italy, have
Mobilpref inspect those materials on arrival, and wait for a new container with
new materials to come back to Florida. Instead, the parties agreed in paragraph
2(c) of Amendment 1 as to how missing materials would be handled once Mobilpref
gave notice that it had completed its performance and supplied all the materials
due under the parties’ agreements.
The record also shows that Coastal did, in fact, provide timely notice of its
general dissatisfaction of the manner in which Mobilpref shipped its goods, as well
as particularly identified materials that were non-conforming and needed to be
cured. The most relevant instance of Coastal’s rejection was Ital’s kitchen door
order.
And Mobilpref agrees that it received that notification and the list of
materials identified by Coastal. Yet Mobilpref also conceded at trial that it did not
provide timely replacement materials. As Talozzi testified, the doors were never
shipped.
Hence, Mobilpref’s reliance on the UCC as support for its claim for damages
does not help because Coastal did in fact show that Mobilpref did not fully perform
under its agreements based on missing or defective materials, which were then not
timely cured after notice.
And contrary to Mobilpref’s claim that Coastal’s
acceptance and use of the shipped materials negate its defenses to payment, these
particular goods – the kitchen doors – were never used in the project by Mobilpref’s
own admission. That relieves Coastal of its obligation to make payment for those
materials. Cf. B.P Dev. & Mgmt. Corp. v. P. Lafer Enters., Inc., 538 So. 2d 1379
(Fla. 5th DCA 1989) (“Once goods are accepted, the buyer must pay at the contract
rate for any goods accepted.”).
In this important respect, the Court credits the testimony of Coastal’s
witnesses over Talozzi because their version of events surrounding the final
shipment of materials were more credible and more verifiable based upon the
written documentation submitted in evidence. Talozzi, however, was not credible
when it came to explaining what gave rise to the door completion order and the
reasons why that order instead constituted a “new” order.
Had Talozzi’s testimony been more reliable, Mobilpref would have been able
to show through him or an expert that the doors at issue were precisely the ones
included in the original pro forma, that they were the ones shipped on particular
dates well before September, and that the September Order represented something
very different.
That showing was never made.
Mobilpref relied on a global
approach to the issue that relied in great deal on Talozzi’s own credibility in terms
of his claim that Mobilpref shipped all the materials that were required by the
original order. Because the Court was forced to reach that same conclusion largely
based on the credibility of Talozzi’s testimony, as opposed to a meticulous tracking
of the materials at issue, the Court could not reach the same conclusion simply
because Talozzi was not, in fact, credible on this point.
Further, as the emails discussed above amply demonstrate, there is a steady
stream of communication between Coastal and Mobilpref from March 2011 to the
end where Coastal is unambiguously giving Mobilpref notice of all of the problems,
i.e., lack of flat-packing packaging as was promised by Talozzi in Italy, missing
materials, non-uniformity of materials, shipments that arrived but did not contain
what was supposed to be in them, etc. While Coastal paid Mobilpref $2,133,000 for
the materials (plus $226,000 for the 12 extra units and miscellaneous items
ordered in Amendment 2), there is ample evidence before the Court that Coastal
did not get all that it paid for. Mobilpref did not fully perform. And in failing to
fully perform, it breached the Tri-Party Agreement and Amendment 1 on which it
relies for its claim for payment.
Accordingly, the Court finds that Mobilpref has failed to satisfy its burden to
show that Coastal breached and failed to perform with respect to the retainage
amount.
Mobilpref also failed to satisfy its burden to show that any additional orders
or materials were ordered by Coastal for which payment is due. This conclusion is
based on the same analysis as set forth above. But this finding is also due to one
additional reason that was not really addressed by the parties. The door order that
Mobilpref references, to the extent it was in fact a “new” order (contrary to the
Court’s finding to the contrary above), was made by Ital, which was still acting at
this stage as the original subcontractor on the project that retained Mobilpref as
the supplier.
Arguably, if the September Order was a new Order, Ital is
responsible in the first instance for payment, either on a breach of contract, breach
of account stated, or promissory estoppel theory.6
It is notable here that Mobilpref dismissed Ital from the case on May 18, 2015.
[D.E. 55].
6
Arguably, Ital was then acting on behalf of Coastal when it made that Order.
Thus Coastal would have been responsible for payment if it had accepted delivery
of materials ordered by its subcontractor for use at in the project, either under an
agency theory or an unjust enrichment theory. But, where the record shows that
the goods at issue were never delivered (as admitted by Mobilpref) Coastal shares
no legal responsibility for payment even if the doors at issue constituted a “new”
order that was not already encompassed by the Tri-Party Agreement or its
amendments.
In this circumstance, to the extent Mobilpref has any right to
recover reliance damages of any kind, Mobilpref’s claim can be raised only against
Ital, not Coastal.
In short, for all these reasons Mobilpref has failed to carry its burden to
show entitlement on a breach of contract claim against Coastal for either the
retainage amount or the separate $112,340.80 that it claims were the cost of
additional materials ordered by Coastal. Mobilpref is thus entitled to no damages
on its complaint. The Court finds in Coastal’s favor on the complaint. Judgment
shall be entered in Coastal’s favor.
B.
Coastal Counterclaim as Assignee of Liberty Mutual
Coastal counterclaimed against Mobilpref in its answer as assignee of all
claims owed by Mobilpref to Liberty Mututal as surety for Ital’s contractual
obligations. Coastal’s claims are asserting subrogation rights that Liberty Mutual
has against Mobilpref due to Mobilpref’s contribution to Ital’s failure to perform
under the subcontract with Coastal.
As Coastal made clear in its post-trial
submission to the Court, “Coastal is not seeking damages from Mobilpref for
Coastal’s already paid claim, but rather Coastal is seeking recovery of Liberty
Mutual’s claims against Mobilpref that Coastal now owns as Liberty Mutual’s
assignee.” [D.E. 86-1 at 73].7
Turning then to the count of the counterclaim that Coastal seeks to
adjudicate after the trial, Count VI, Coastal contends that out of the $1,900,000
claim it submitted to Liberty Mutual, $1,151,385.91 was attributable to Mobilpref’s
own failures.
Liberty Mutual’s payment of $1,700,000 to Coastal on Ital’s
performance bond purportedly was due to these failures, for which Coastal, as
assignee of Liberty Mutual, seeks damages against Mobilpref. Specifically, the
counterclaim alleges that “as a direct and proximate result of Mobilfpref’s breaches
of its agreement with Ital, Ital suffered damages, which claims Liberty Mutual
became subrogated to upon making payment to Coastal on the performance bond
claim.” [D.E. 23 ¶38].
As to the nature of those breaches between Ital and Mobilpref, the
counterclaim alleges that “Mobilpref breached its agreement with Ital by failing to
timely deliver the materials, delivering the materials without proper labeling,
missing pieces, broken pieces and incomplete shipments[,] and overbilling Ital for
materials which were not shipped and delivered.” [D.E. 23 ¶37].
Coastal’s original counterclaim also included personal claims, separate and apart
from Coastal’s standing as assignee of Liberty Mutual’s subrogation rights, against
Mobilpref. Specifically, Mobilpref sued Mobilpref for breach of contract (Count I),
fraud (Count II), fraud in the inducement (Count III), negligent misrepresentation
(Count IV), and unjust enrichment (Count V). Based on Coastal’s stated position
post-trial, it is plainly clear that Coastal abandoned those personal claims against
Mobilpref. Judgment shall thus be entered against Coastal on those counts and no
further analysis of their merit (or lack thereof) is necessary.
7
1. Standing
Mobilpref’s first response to this claim is that it fails as a double recovery for
Coastal. Mobilpref argues that Coastal cannot receive a double recovery under the
election of remedies theory because the ultimate remedy it seeks here is the same
as the remedy it already obtained from Liberty Mutual. Hence, Coastal’s claim to
damages against Mobilpref has been satisfied and/or extinguished.
On this preliminary issue, Coastal’s claim in Count VI as assignee for
Liberty Mutual is on firm legal footing. When a surety is called upon to perform on
its suretyship obligation and does so, it becomes subrogated to the rights of its
principal (Ital) for any remedies or securities that would otherwise belong to the
principal. Continental Casualty Co. v. Ryan Incorporated Eastern, 974 So. 2d 368,
376-77 (Fla. 2008) (“Equitable subrogation has been defined as ‘the substitution of
one party for another whose debt the party pays, entitling the paying party to
rights, remedies, or securities that would otherwise belong to the debtor.’ . . . In the
context of a surety relationship, the key to equitable subrogation lies in the surety’s
right to indemnification. Because a surety who pays a judgment on behalf of its
principal is entitled to indemnification by its principal, it has the right to be
subrogated to any rights the principal has. . . .”).
In the context of a construction contract, a common form of equitable
subrogation well established in Florida and elsewhere is the surety’s claim, on
behalf of a contractor/principal, against subcontractors that defaulted on their own
obligations owed to the contractor.
See, e.g., Wilcon, Inc. v. Travelers Indem. Co.,
654 F.2d 976, 987 (5th Cir. 1981) (“When [the surety] completed the ... project upon
the default of the [principal] and pursuant to its bond obligations, [the surety]
became subrogated to all of the rights and remedies of the [principal] against
defaulting subcontractors.”); Travelers Indem. Co. v. Peacock Const. Co., 423 F.2d
1153, 1156 (5th Cir. 1970) (“[U]nder the most rudimentary principles the surety
succeeds to its principal's right to payment upon completion of the contract.”).
Here, Liberty Mutual, as Ital’s performance bond surety, paid $1,700,000 to
Coastal on Coastal’s performance bond claim. That undertaking as a performing
surety granted Liberty Mutual the broadest possible scope of subrogation, which
encompassed any remaining contract balances (of which there were none), as well
as the right to recoup the loss it was obligated to pay on Ital’s behalf to any
contributing wrongdoer.
Thus, contrary to Mobilpref’s position, Coastal is not
seeking to recover monies that it has already been paid, but rather asserts a claim
as the assignee of the party who possessed the right to seek damages from
Mobilpref prior to the assignment, Liberty Mutual.
2. Mobilpref’s Liability
Moving past that preliminary question, we proceed to adjudicate the rights
that Coastal is enforcing as assignee of Liberty Mutual. Coastal has asserted that
Mobilpref breached its contractual obligations to Ital by failing to timely and
properly deliver materials necessary for completion of Ital’s contract with Coastal.
Coastal’s claim fails, however, based upon its inability to meet its burden of proof
as to the elements of a breach of contract between Ital and Mobilpref.
For starters, it is important to remember what Ital’s claim against Mobilpref
is that Coastal is pressing as assignee of Liberty Mutual. Ital’s claim is alleged to
be a breach of contract by Mobilpref. The elements for such a claim are the same
as those that Mobilpref undertook: “Under Florida law, a breach of contract arises
when there exists (1) ‘a valid contract’; (2) a ‘material breach’ of that contract; and
(3) resulting ‘damages.’” Energy Smart, 660 F. App’x at 862 (quoting Beck, 175 F.3d
at 914).
As to the first element, the underlying contract between Ital and Mobilpref,
the evidence is surprisingly lacking. The Court’s review of the extensive record in
the case shows that any master contract between Ital and Mobilpref was never
admitted into evidence, nor was the detail included in Ital’s purchase order. The
record contains only the terms of the pro forma that Mobilpref prepared in
response to Ital’s order as well as the invoices and records of shipment that
Mobilpref delivered to Ital. PX 14, 21. The record evidence thus is missing critical
components of a traditional breach of contract claim – the precise terms of the
parties’ agreements to one another.
The testimony at trial, of course, supplied overwhelming evidence of the
existence of such a contract and Mobilpref’s performance under that arrangement.
But what was still lacking was any testimony from any Ital representative as to the
precise terms of that original arrangement, the parties’ understanding as to how
Mobilpref had agreed to perform its obligations to Ital, or even the manner in
which that performance was carried out. The witnesses who testified at trial were
only representatives of the parties themselves, Mobilpref and Coastal. But Ital
was completely absent from this trial.
As between Mobilpref and Coastal, of course, that would not be surprising.
But Coastal is standing in the shoes of Liberty Mutual, which is entitled to
equitable subrogation on behalf of Ital. Ital’s role is central to that equation. Yet
the Court heard zero testimony from Ital as to any of the issues personal to Ital.
That failure to have a complete record in this respect makes Coastal’s claim, on
Liberty Mutual’s behalf, that much more difficult.
But, at minimum Coastal clearly established that Mobilpref agreed to
manufacture and deliver materials for the St. Regis project. That much is clear.
Yet the record also shows that, with the exception of certain materials that were
addressed above with respect to Mobilpref’s own damage claim, Mobilpref delivered
the materials and components that Ital ordered for its contract with Coastal. So
failure to deliver at all cannot be a source of a finding of a breach or damages for
purposes of the counterclaim.
The record also contains evidence of Mobilpref’s agreements to perform set
forth in the Tri-Party Agreement and Amendment 1. But performance under those
agreements was also shown to have been completed, again but for certain doors
and other missing parts necessary to complete installation of the kitchens. And as
far as Amendment 2, there was no evidence that shipments of those additional
materials did not take place.
That leads us then to the question whether Mobilpref breached those
agreements in other ways. Specifically, Coastal presented evidence though its own
witnesses that Mobilpref delivered the materials in an untimely fashion and in a
manner that made it unnecessarily difficult to assemble and install the parts into
the St. Regis units. But there is a failure of proof in this aspect of the claim as
well. Coastal failed to designate an expert witness at trial to provide causation or
damage testimony. Instead, it sought to substantiate its damages through the lay
opinion testimony of Thomas Driscoll. At no time during his work on the Project or
in the three years after did Mr. Driscoll ever attempt to record the details of his
work or the work of others on the Project to allocate what work, materials or
services were attributed to some alleged fault of Mobilpref.
Indeed Mr. Driscoll admitted at trial that he performed his valuation opinion
of responsibility in 2015, years after the Mobilpref work was performed and well
after this litigation began. T.IV-773.
And Coastal’s counsel conceded that Mr.
Driscoll performed this after-the-fact allocation only after Mobilpref requested
discovery going to damages under the counterclaim. So the long and short of it is
that the evidence in this record is based on Coastal’s self-serving estimates and reallocations performed by one of its employees and admitted into evidence as lay
opinion testimony. To be sure, the Court, over Mobilpref’s objections, permitted
this testimony into evidence (along with the supporting third-party invoices and
receipts) but reserved the right to assess its weight as factfinder.
That assessment of the weight to attribute to this evidence proved to be
quite difficult. The Court extensively re-reviewed Mr. Driscoll’s testimony and the
materials that his testimony relied upon. Mr. Driscoll’s damage analysis assigned
specific costs of materials and services for dozens of suppliers, vendors,
independent contractors and employees of various companies involved in the
Project over an eighteen month period of time.
But the suppliers, vendors,
employees and contractors worked at widely varying times and at least two
different locations. It is not possible to fully credit Mr. Driscoll’s conclusions with
respect to the necessity of their work juxtaposed against Mobilpref’s performance
under its contract with Ital.
For example, Mr. Driscoll allocates 50% of each of his own invoices to
Mobilpref’s improper acts or omissions. Specifically, based on the summary, Mr.
Driscoll opines that every one of his invoices to Coastal were 50% attributable to
Mobilpref. DX 61. According to the summary and Mr. Driscoll’s testimony on his
invoices, over an eighteen month span there was never a day where his time was
either more or less than 50% attributable to Mobilpref; instead, his work on any
given day was always exactly 50% attributable to Mobilpref. But Mr. Driscoll did
not testify as to any of his specific invoices, and he never substantiated that what
he was doing on any specific day was attributable to Mobilpref. Perhaps that is
because Mr. Driscoll’s timesheets do not contain any description of what work he
did on a given day. Mr. Driscoll also did not keep a contemporaneous ledger of what
activities or costs were believed to be attributable to Mobilpref.
Thus Mr. Driscoll’s lay opinions are entitled to little weight because they are
not adequately supported in the record.
Mr. Driscoll’s allocation is not
substantiated by firsthand experience, is not entirely plausible, and lacks
trustworthiness given the manner in which he prepared his estimates.
The Court instead finds that, based on the testimony and evidence that was
introduced at trial, the necessity for Mr. Driscoll’s work at the project was due
mainly to Ital’s failure to perform the most essential tasks that it contracted to
perform.
Ital’s responsibility on such a large project had to have included the
retention of many employees to review, sort and distribute the component parts
that Mobilpref was delivering.
Ital was responsible under its agreement with
Coastal to “provide project management expertise in the coordination of this
[project]”; to “coordinate deliveries with the Project Schedule” and maintain “offsite
storage costs” for that purpose; to “furnish and install” all required cabinetry for all
units; to “provide complete shop drawings that show all required installation
details”; to “provide all necessary adjustment of doors, hardware, cabinets, vanities,
etc. in order to offer a completed and satisfactory product to the Owner”; to “touchup damaged cabinets, as necessary, and to replace cabinets if damage cannot be
concealed or remediated” and “expedite delivery of products” for this purpose; and
to “provide sufficient manpower to properly perform required punchout work,
which includes supervision provided by [Ital] dedicated to this aspect of the
Project.” DX 2, Exh. A at 1-9.
The record instead showed very little evidence of what Ital’s own employees
were doing from the beginning of the project through its conclusion.
Isolated
snippets of testimony reveal an Ital employee trying to complete a task. But the
record also shows that Coastal’s own workers, including Mr. Driscoll, were taking
on a greater and greater share of responsibility at Ital’s facility precisely because
Ital was not completing its scope of work on the project. Indeed given the size of
this contract and the scope of work involved, Ital would have been required to
amass a small army to undertake the type of work it agreed to perform. The record
at trial barely had evidence of a platoon, least of all an army.
So, faced with this record, it is just as equally plausible to find that the
majority of the work that Mr. Driscoll was required to perform to facilitate
completion of the Project on Coastal’s behalf was attributable directly to Ital’s
failure to perform.
After all, Mobilpref was only contractually responsible for
manufacturing goods and shipping them to Miami. Ital was in charge of what
would happen to those goods after they got there. Coastal was forced to retain Mr.
Driscoll to take on responsibilities that Ital had contractually agreed to perform.
Attributing 50% of that work to Mobilpref, the entity that delivered 40 shipping
containers’ worth of product under its contract, belies common sense and is not
supported by the record Coastal developed at trial.
And what is most telling is that the greatest “breach” of performance of any
portion of this contract occurred before Mobilpref delivered its first component.
Ital’s failure to initiate payment that Ital owed to Mobilpref at the early stage of
the project was a critical failure to perform that undermined the entire project.
After Ital entered into its contract with Coastal, at an initial cost to Coastal of
$3,000,000, it was tasked with preparing the order, submitting it to Mobilpref, and
depositing the initial monies with the subcontractor to initiate manufacture. Yet,
as Coastal’s own witnesses explained, Ital failed to do that, which failure lead to
months and months of delays. Only after the Tri-Party Agreement was signed and
Coastal fronted those initial monies to Mobilpref did Coastal begin to receive the
necessary goods.
Coastal had been expecting to see delivery commence in
September 2010. That did not occur. But the record shows convincingly that it
was not Mobilpref that failed to perform at this early stage, but rather Ital.
Compounding matters, Ital again failed to materially perform after
shipments began to arrive when, despite its original contract obligations that were
reincorporated into the Tri-party Agreement, Ital did not make the required
payments to Mobilpref that Ital had committed to.
This second round of non-
performance caused further delays in completing the shipments in March 2011,
and ultimately led to Amendment 1 of the Agreement and additional
disbursements of monies directly from Coastal to Mobilpref.
These multiple material breaches on Ital’s part played a recurring central
role in all the problems that followed. Because of the initial material delay in
starting production and the delivery of product, the kitchen/closet project was
severely prejudiced. The plan projected a completion date in the summer of 2011,
well in advance of the closing dates that would follow in the fall by which time
certificates of occupancy were due. Despite Coastal’s best efforts, the project never
really got back on firm ground in time to complete the units as scheduled.
Substantial work continued well into the late fall of 2011, even as closing dates
were imminent. This added a substantial amount of pressure to all the workers
and installers laboring on the project, which pressure undoubtedly resulted in a
slew of problems with each kitchen and cabinet installation. Though it may also be
accurate to state that individual shipment delays or packaging issues compounded
matters, the weight of the evidence shows that – for a project this large – it was
materially hampered by non-performance that occurred back in 2010, and then
again in the early part of 2011.
These contractual breaches were attributable
entirely to Ital. Yet, Mr. Driscoll’s analysis assumed that Ital and Mobilpref were
on equal footing for the many failures that led to the delays in completion. That
conclusion is simply not credible given the weight of the evidence.
The weight of the evidence also shows that, after Ital failed to perform
initially on its contractual obligations to Coastal, Coastal was well aware of that
breach.
But Coastal did not immediately replace Ital and find a substitute
contractor. Instead it sought to facilitate Ital’s performance. Ital’s representative
was thus asked to travel to Italy on Coastal’s first trip in September and be present
for Coastal’s inspection. Nevertheless, Coastal was again disappointed in Ital’s
performance when, a few months later, Ital’s promised delivery of the first
container turned out to be a ruse.
It was after these multiple failures to perform that Coastal agreed to enter
into direct negotiations with Mobilpref, which negotiations led to the Tri-party
Agreement. But Ital remained an essential party to the project. Ital signed the
Tri-Party Agreement. Ital did not enter into a new agreement with Coastal to
minimize its role. Instead Ital agreed to perform its share of the original contract if
Coastal made the $1,500,000 payment to Mobilpref (after having paid Ital
$3,000,000 months earlier). Coastal thus chose to maintain Ital as the principal
responsible party tasked with assembling the manufactured parts, sorting them,
and rejecting any goods that did not live up to specifications.
That essential
responsibility – the “project management expertise in the coordination of this Scope
of Work” – continued throughout the end of the project.
responsibility, not Mobilpref’s.
That was Ital’s
Yet, notwithstanding that critical role, there is no evidence from Ital or
Coastal that any specific goods were rejected for months after delivery ensued. Ital
did not give written notice to Mobilpref of any defective parts, nor did it place any
orders for substitute components until months later – September 2011. So for
months Mobilpref delivered components and the buyer – Ital/Coastal – accepted
them. But all the while Ital was failing in its obligation to sort and assemble the
delivered material in a manner that would facilitate their installation at the
project. It failed in its contractual obligation to timely reject any materials after
shipment to assure their replacement on schedule. After all Mobilpref did not have
its employees working at Ital’s facility, Ital did. Ital was responsible at all times
for adequately manning their facility with all the workers necessary to complete its
obligations for the project.
Indeed one of the responsibilities that Ital would have needed to perform in
the ordinary course of this project is refinishing work that may have been
necessary after product arrived from the manufacturer. That work may have been
due to imperfect manufacturing, but it could also have been necessary due to
failures in the installation process. Under paragraph 1.3.39 of the subcontract, Ital
was responsible for touching-up any damaged cabinets and to replace those
cabinets, if necessary, if such damage could not be remediated. DX 2, Exh. A at 5.
Yet, Mr. Driscoll’s lay opinion was that 100% of the $837,406.02 in refinishing costs
that Coastal incurred were attributable to Mobilpref, even though he did not attest
that he saw all of the material that was refinished or witness all of the refinishing
work as it occurred. He could not have seen firsthand that 100% of the refinishing
was attributable to Mobilpref. There is thus no record basis for us to determine
what percentage of the material needed refinishing because it arrived at the project
in a defective condition, versus what percentage needed refinishing because it was
damaged at some point during the sorting and/or installation process. If it was the
former, Mobilpref would be responsible. If it was the latter, Ital would be most
responsible.
But the Court cannot reach a definitive conclusion one way or the other
where the record contains no contemporaneous, product-based rejection of
delivered goods as they were being shipped. Instead the Court was presented with
global after-the-fact assessments of Coastal’s own employees that attributed every
single refinishing cost to Mobilpref. Faced with that take it or leave it choice, the
Court chooses to leave it. The evidence does not meaningfully allow for a reliable
finding that Mobilpref substantially contributed to a particular amount for
refinishing work that Coastal incurred at the project, and especially not for 100% of
all the refinishing that may have been required.
Other costs included in Coastal’s calculations meet a similar fate. Coastal
attributes $195,255 to Mobilpref for the overall $293,000 Coastal spent for
additional labor and distribution costs at the Ital facility, which represents 66% of
the total figure. Coastal argues that these additional costs were incurred as a
proximate result of Mobilpref’s failure to deliver and ship the product in the
manner in which it promised to do using pre-assembled flat packs that would
facilitate installation of the necessary parts at the project site.
The problem is that the Court was presented with zero evidence that
Mobilpref’s agreement with Ital encompassed a binding commitment to deliver the
product in any particular manner. We do not even have any testimony from an Ital
representative that could attest that Mobilpref agreed to deliver the materials in a
specific fashion so that Ital could then undertake its distribution and installation
responsibilities. The record also contains no definitive representations from which
we could find that Ital or Coastal relied to their detriment. After all, Coastal’s
employees confirmed at trial that they realized that product would be delivered
from multiple locations as Mobilpref was itself only manufacturing the melamine
components.
Without binding commitments from Mobilpref’s part that we can attribute as
a condition of Ital’s performance, it is not possible to find, as Coastal contends, that
66% of the added labor cost at Ital’s facility was attributable to Mobilpref. Nor can
we find that any particular percentage of the labor cost was attributable to
Mobilpref without a more specific showing that particular shipments or containers
failed to meet Mobilpref’s contractual obligations. We were presented with only a
broad-brush theory that Mobilpref failed to live up to Coastal’s expectations and,
therefore, 66% of the added cost that Coastal incurred at the Ital facility can be
linked to this disappointment.
That showing does not come close to Coastal meeting its burden to show
that Mobilpref’s non-performance was a proximate cause of Ital’s own failure to
perform under its contract with Coastal. Under Florida law to make such a finding
the Court would have to be presented with evidence that Mobilpref’s own non-
performance was a substantial factor in the equation. See, e.g., Cedar Hills Props.
Corp. v. Eastern Fed. Corp., 575 So. 2d 673, 678 (Fla. 1st DCA 1991) (citing 5
Corbin on Contracts § 999 (1964) (“To establish liability the plaintiff must show
that the defendant’s breach was a ‘substantial factor’ in causing the injury.”));
Tuttle/White Constructors, Inc. v. Montgomery Elevator Co., 385 So. 2d 98, 100
(Fla. 5th DCA 1980) (trial court erred in setting aside possible delay damages
against contractor due to other subcontractors’ role in contributing to breach where
evidence showed that only contractor’s delays were a substantial factor in causing
the injury). The evidence in this record does not allow for such a finding as against
Mobilpref, at least with respect to the vast majority of product it delivered.
The Court can find that with respect to some replacement doors and parts
ordered in September 2011, Mobilpref did not perform. But that fact was taken into
account in relation to Mobilpref’s demand for final payment of the retainage
amount and additional monies purportedly due for these orders. The Court has
sustained Coastal’s defense to that claim that the retainage amount need not be
disbursed given Mobilpref’s limited failures to perform. But the same cannot be
said with respect to the vast amount sought by Coastal, on Liberty Mutual’s behalf,
that requires the Court to find that Mobilpref materially failed to perform despite
shipping 40 containers of product over a ten-month period.
The weight of the
evidence in this case does not allow the Court to find that Mobilpref’s nonperformance was a substantial factor that contributed to Ital’s multiple and
repeated failures to perform under its subcontract with Ital. See also RDP Royal
Palm Hotel, L.P. v. Clark Const. Grp., Inc., 168 F. App’x 348, 354 (11th Cir. 2006)
(“The record shows that some delays were caused by [GC’s] subcontractors, but
those delays did not substantially postpone the eventual completion of the Resort.
Rather, the substantial delays which severely impacted the Resort's construction . .
. were all attributable to [developer] and not the fault of [GC’s] subcontractors.
Although [developer] asserts that the district court erroneously failed to apportion
the total delay among the contributing parties, we find no error because [developer]
has not established a reasonable basis for such apportionment nor shown that
apportionment was required.”) (emphasis added); Gesco, Inc. v. Edward L. Nezelek,
Inc., 414 So. 2d 535, 538 (Fla. 4th DCA 1982) (“Although the record demonstrates,
and the trial court found, that [GC] was responsible for some of the delay, the court
was nevertheless correct in concluding that [developer’s] evidence did not establish
a reasonable basis for apportioning responsibility for the total delay.”).
Finally, even if Coastal had shown that Mobilpref’s non-performance was a
substantial factor, Coastal would still have to prove an amount of damages that
could remedy an injury suffered as a proximate result of the breach.
E.g.,
Tuttle/White Constructors, 385 So. 2d at 100. And to do so Coastal would have to
show that the extent of those damages can be proven with reasonable certainty.
E.g., Nebula Glass Int'l, Inc. v. Reichhold, Inc., 454 F.3d 1203, 1212 (11th Cir.
2006) (“ ‘Under [Florida’s] certainty rule, which applies in both contract and tort
actions, recovery is denied where the fact of damages and the extent of damages
cannot be established within a reasonable degree of certainty.’ ”) (quoting Miller v.
Allstate Ins. Co., 573 So. 2d 24, 27-28 (Fla. 3d DCA 1990), and citing Restatement
(Second) of Contracts § 352 (1981); Restatement (Second) of Torts § 912 (1982)).
Coastal has failed to do that in this record.
The amount of damages
requested bears little connection to the actual amount of losses that could fairly be
attributably in fairness to Mobilpref. And assuming there was some level of loss
that Mobilpref substantially caused, the amount cannot be determined with any
degree of reasonable certainty because we have no way to connect the dots. The
shotgun showing that Coastal presented at trial is not a fair substitute for a
specific showing that particular items of damage or delay were substantially
caused by a particular defective component or a particular delay in its shipment.
Coastal would argue that given the volume of product delivered for this
project it would be practically impossible to make such a showing, even though any
reasonable person can see that Mobilpref failed in its duty to substantially perform.
But Coastal forgets that Mobilpref did substantially perform on its obligation to
manufacture product and ship that product to Florida. Ital was the installer and
the party responsible for project supervision over the entire operation. The great
bulk of the problems that Coastal identified at trial can be tied directly to Ital’s
breaches of its performance obligations. To add Mobilpref into that equation,
Coastal (as assignee of Liberty Mutual) has the burden of showing with some
reasonable degree of specificity that Mobilpref’s failures rose to the level of a
legally sanctionable breach of its contractual obligations. For the most part, it
simply could not accomplish that fundamental task.
In sum, Mobilpref did not perform ideally in many different ways.
It
contributed to delays in the project, made it difficult for the installer to perform
more efficiently, which compounded the installer’s ultimate failure to perform.
Troubled as it was, however, Mobilpref’s performance cannot be found to have
substantially contributed to that failure. And any damages that Mobilpref may
have contributed to in particular cannot be identified with any reasonable degree of
certainty or confidence. The Court is left to speculate what that amount would be,
but a breach of contract remedy cannot be imposed on sheer speculation. The
weight of the evidence, therefore, shows that Liberty Mutual, as subrogee of its
principal Ital, is not entitled to any material contribution from Mobilpref for the
woefully deficient performance of its principal, Ital, on this project.
Accordingly, Coastal as assignee of Liberty Mutual is not entitled to any
damages on its counterclaim.
The Court finds in Mobilpref’s favor on the
counterclaim. Judgment shall be entered in Mobilpref’s favor.
***
III. CONCLUSION & FINAL JUDGMENT
Based upon the foregoing Findings of Fact and Conclusions of Law, it is
ORDERED and ADJUDGED that:
1.
Final Judgment is hereby entered in favor of Coastal Construction of
South Florida, Inc., and as against Mobilpref, SpA, as to all counts of the
complaint. Mobilpref, SpA shall take nothing on the complaint.
2.
Final Judgment is hereby entered in favor of Mobilpref, SpA. as to all
counts of the counterclaim, and as against Coastal Construction of South Florida,
Inc.
Coastal Construction of South Florida, Inc. shall take nothing on the
counterclaim.
3.
This case is now CLOSED.
DONE and ORDERED in Chambers in Miami, Florida, this 1st day of
March, 2017.
________________________________
EDWIN G. TORRES
United States Magistrate Judge
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?