METROPOWER INC v. GSC CONSTRUCTION INC et al
Filing
30
ORDER denying (27) Motion to Vacate and granting (29) Motion for Judgment as a Matter of Law in case 4:18-cv-00001-CDL; denying (22) Motion to Vacate and granting (24) Motion for Judgment as a Matter of Law in case 4:18-cv-00035-CDL. Ordered by US DISTRICT JUDGE CLAY D. LAND on 7/18/2019 (tlf).
IN THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF GEORGIA
COLUMBUS DIVISION
UNITED STATES FOR THE USE AND
BENEFIT OF METROPOWER, INC.
D/B/A COLUMBUS POWER,
Claimant,
*
*
*
vs.
*
DARWIN NATIONAL ASSURANCE
COMPANY D/B/A ALLIED WORLD
INSURANCE COMPANY and GSC
CONSTRUCTION, INC.,
*
CASE NOS.
4:18-CV-1 (CDL)
4:18-CV-35 (CDL)
*
*
Respondents.
*
O R D E R
MetroPower, Inc. brought two Miller Act actions against GSC
Construction,
Inc.
and
its
performance
bond
surety,
Darwin
National Assurance Company d/b/a Allied World Insurance Company.
Both actions are based on construction projects performed at
Fort Benning, Georgia.
The first project was the construction
of Buildings 2944 and 2945, and that project is the subject of
Case No. 4:18-cv-1. The second project was the construction of
Building 972, and that project is the subject of Case No. 4:18cv-35.
The parties agreed that both actions should be stayed
pending arbitration, and the Court granted the parties’ motions
to stay.
both
The arbitrator conducted a consolidated hearing on
matters,
testimony.
receiving
documentary
evidence
and
hearing
The arbitrator issued a written award concluding
that the weight of the evidence supports MetroPower’s position
with regard to both projects.
The arbitrator awarded MetroPower
$56,678.00 against GSC and Allied on the Building 972 project
and $68,691.00 against GSC and Allied on the Buildings 2944/2945
project.
Arbitrator Award 6, 10, ECF No. 25-1 in 4:18-cv-1 &
ECF No. 21-1 in 4:18-cv-35.
Both awards are against GSC and
Allied jointly and severally.
GSC
and
Allied
filed
motions
to
vacate
the
arbitration
award (ECF No. 27 in 4:18-cv-1 & ECF No. 22 in 4:18-cv-35).
MetroPower filed motions to confirm the arbitration award and
for entry of judgment in accordance with the arbitration award
(ECF No. 29 in 4:18-cv-1 & ECF No. 24 in 4:18-cv-35).
discussed below, the Court denies the motions
As
to vacate and
grants the motions to confirm.
DISCUSSION
Both subcontracts at issue here state that they are subject
to
arbitration
pursuant
to
the
Georgia
Arbitration
Code,
O.C.G.A. §§ 9-9-1 to 9-9-18, and the parties agree that the
Georgia Arbitration Code is the governing statute.
See Am.
Compl. Attach. 1, Subcontract § 16.1(d), ECF No. 14-1 in 4:18cv-1; Am. Compl. Attach. 1, Subcontract § 16.1(d), ECF No. 7-1
in 4:18-cv-35.
Under the Georgia Arbitration Code, the “court
shall confirm an award upon application of a party made within
one year after its delivery to him, unless the award is vacated
2
or modified by the court as provided in this part.”
§ 9-9-12.
trial
O.C.G.A.
The Code “places strict limits on the scope of a
court’s
review
of
an
arbitrator’s
subsequent review by an appellate court.”
award
and
on
any
Brookfield Country
Club, Inc. v. St. James-Brookfield, LLC, 683 S.E.2d 40, 43 (Ga.
Ct. App. 2009).
The Code provides five exclusive grounds for
vacating an arbitration award based on the application of a
party who participated in the arbitration.
13(b).
and
See O.C.G.A. § 9-9-
As the parties challenging the arbitration award, GSC
Allied
have
the
burden
“to
come
forward
with
evidence
establishing the existence of one of the . . . statutory grounds
for vacating the award.”
Greene v. Hundley, 468 S.E.2d 350, 353
n. 24 (Ga. 1996).
Here, GSC and Allied rely upon one ground for vacating the
award:
the
“arbitrator’s
O.C.G.A. § 9-9-13(b)(5).
law,
GSC
evident
and
and
Plumbing,
Allied
[arbitrator]
647
that
disregard
of
the
law.”
To establish manifest disregard of the
must
intentional.”
Inc.,
manifest
establish
ABCO
S.E.2d
disregard
Builders,
574,
incorrectly
575
interprets
Inc.
(Ga.
the
that
v.
is
“both
Progressive
2007).
“An
law
not
has
manifestly disregarded it. It has simply made a legal mistake.
To manifestly disregard the law, one must be conscious of the
law
and
deliberately
Shearson Lehman
ignore
it.”
Id.
(quoting
Montes
v.
Bros., Inc., 128 F.3d 1456, 1461 (11th Cir.
3
1997)).
“Therefore, to prove that a manifest disregard of the
law has occurred, a party wishing to have an arbitration award
vacated must provide evidence of record that, not only was the
correct
law
communicated
to
an
arbitrator,
but
that
the
arbitrator intentionally and knowingly chose to ignore that law
despite the fact that it was correct.”
Id.
“[T]his showing is
an extremely difficult one to make[.]”
Id.
A reviewing “court
is prohibited from weighing the evidence submitted before the
arbitrator, regardless of whether the court believes there to be
sufficient
award.”
evidence,
or
even
any
evidence,
to
support
the
Greene, 468 S.E.2d at 354.
GSC
and
Allied
assert
that
the
arbitrator
manifestly
disregarded the law in two ways: (1) when he concluded that
MetroPower’s Miller Act payment bond claims were filed within
one year of MetroPower’s last work on the subcontracts and (2)
when he based the arbitration award on change orders that GSC
and Allied argue were unsigned.
According to GSC and Allied,
the “only credible evidence” before the arbitrator established
that the work was completed more than one year and one day
before
MetroPower
filed
its
Miller
Act
claims
and
that
the
change orders “largely were not signed by GSC or approved by the
Army.”
Resp’t’s Mot. to Vacate 10, ECF No. 27 in 4:18-cv-1.
Thus, GSC and Allied challenge the sufficiency of the evidence
4
supporting the arbitrator’s award.1
the
arbitration
award.
That is not enough to vacate
Instead,
“there
must
be
concrete
evidence of [the arbitrator’s] intent [purposefully to disregard
the law] either in the findings of the arbitrator, if he or she
chooses
to
make
such
findings,
arbitration hearing.”
Here,
the
arbitrator’s
or
in
the
transcript
of
the
ABCO Builders, Inc., 647 S.E.2d at 576.
written
intent to disregard the law.
findings
do
not
evidence
an
Based on the Court’s review, the
record does not contain a transcript of the arbitration hearing,
and the parties did not point to anything else in the record
that indicates the intent of the arbitrator in reaching the
conclusion he did.
that
the
In the absence of “viable concrete evidence
[arbitrator]
purposefully
intended
to
disregard
applicable law,” it would be error to vacate the arbitrator’s
award.
Id. (affirming court of appeals’ decision to reverse the
ruling of a superior court vacating an arbitration award because
there was no evidence of a manifest disregard of the law).
The
Court thus concludes that GSC and Allied did not meet their
burden of presenting evidence to establish a basis for vacating
the arbitrator’s award.
1
Even if the Court were permitted to weigh the evidence and determine
whether MetroPower’s evidence supports the arbitrator’s award—which
the Court is not permitted to do—the Court could not do so based on
the present record because the parties did not point to a transcript
of the arbitration hearing or any of the documentary evidence that was
presented to the arbitrator.
5
CONCLUSION
For the reasons set forth above, the Court denies GSC and
Allied’s motions to vacate (ECF No. 27 in 4:18-cv-1 & ECF No. 22
in
4:18-cv-35).
confirm
the
The
arbitration
Court
grants
award
and
MetroPower’s
for
entry
of
motions
to
judgment
in
accordance with the arbitration award (ECF No. 29 in 4:18-cv-1 &
ECF No. 24 in 4:18-cv-35).
The Clerk is directed to enter
judgments in favor of MetroPower and against GSC and Allied,
jointly and severally, in the amount of $56,678.00 in 4:18-cv-35
and $68,691.00 in 4:18-cv-1.
IT IS SO ORDERED, this 18th day of July, 2019.
S/Clay D. Land
CLAY D. LAND
CHIEF U.S. DISTRICT COURT JUDGE
MIDDLE DISTRICT OF GEORGIA
6
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?