The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company
Filing
164
ORDER granting 129 Motion to Exclude Certain Opinion Testimony of Michael Harris. Harris is otherwise permitted to testify, including on his independent conclusions regarding containment delay. Signed by Magistrate Judge Benjamin W. Cheesbro on 01/13/2022. (jlh)
IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF GEORGIA
BRUNSWICK DIVISION
THE UNITED STATES OF AMERICA FOR
THE USE AND BENEFIT OF TSI TRISTATE PAINTING, LLC,
Plaintiff/Counter-Defendant,
CIVIL ACTION NO.: 2:16-cv-113
v.
FEDERAL INSURANCE COMPANY,
Defendant/Counter-Claimant.
ORDER
This matter is before the Court on Plaintiff Tri-State Painting, LLC’s Motion to Exclude
Certain Opinion Testimony of Michael Harris. Doc. 129. Defendant Federal Insurance
Company (“Federal”) filed a Response, and Plaintiff filed a Reply. Docs. 138, 147. On
November 15, 2021, the Court held a hearing on Plaintiff’s Motion to Exclude, at which counsel
for both Plaintiff and Federal appeared. Dkt. entry dated Oct. 12, 2021; Doc. 158. Following the
hearing, the parties submitted supplemental briefing on the matter. Docs. 161, 162.
For the following reasons, the Court GRANTS Plaintiff’s Motion to Exclude. Harris is
not permitted to offer expert testimony about the apportionment of responsibility for
containment-related delays using figures provided by Federal’s counsel (e.g., the Government is
responsible for 75% of the containment-related delays and the subcontractors, including Plaintiff
TSI, are responsible for the remaining 25%). This Order does not otherwise limit Harris’
testimony, and he is generally permitted to testify in accordance with the Federal Rules of
Evidence.
BACKGROUND
Plaintiff TSI sues Federal over a project at the Naval Submarine Base in Kings Bay,
Georgia. Doc. 1. Plaintiff worked as a subcontractor for the general contractor, Sauer, Inc. 1
Doc. 129-1 at 1–2. The project had a series of delays, and the parties dispute who is responsible
for the delays. Responsibility for the delays impacts the amount that may be owed under the
contract for work Plaintiff performed. The reasons included delays due to weather and
performance issues. Doc. 129-2 at 9–13. Additionally, significant delays arose from detection
of lead paint at the site, which had to be removed before the project could continue. The removal
of the lead paint also required use of a containment system. There were significant delays
related to the implementation and execution of the containment system. Id. These
“containment-related delays,” and Federal’s expert’s anticipated testimony on who bears
responsibility for them, are the focus of Plaintiff’s challenge in the instant Motion.
Federal hired Michael Harris, a civil engineer with Secretariat International, to perform a
delay analysis of the project. Id.; Doc. 129-2. Harris has an undergraduate degree in civil and
environmental engineering, as well as a juris doctorate, and has worked as a licensed engineer
for more than 30 years. 2 Doc. 138 at 1. Harris has previously testified as an expert in
arbitrations, boards of contract appeals, and state court proceedings. Id. Harris offers a
comprehensive report and set of opinions on the allocation of responsibility for delays during the
course of the project. Doc. 129-2. Harris’ opinions focus on determining allocation of
responsibility for the days of delay and, specifically, delays associated with TSI’s work. Id. at 9–
Federal represents Sauer Inc.’s interests in this litigation. For convenience, the Court treats
Federal and Sauer as interchangeable in this Order.
1
Plaintiff does not challenge Harris’ qualifications at this time. A summary of Harris’
qualifications is provided only as background. The Court makes no finding as to whether Harris is
qualified to offer any particular opinion.
2
2
12. Harris provided two reports assigning responsibility for project delays—his Independent
Report and Rebuttal Report. See generally id. Harris’ Independent Report involves an analysis
on the causes of various delays occurring during the project and who bears responsibility for
those delays—including responsibility for containment-related delays. Id. at 88–159. Harris’
Rebuttal Report offers similar opinions and also an analysis of Plaintiff’s expert’s opinions on
delays. Id. at 7, 26–58. In his Rebuttal Report, Harris reached conclusions about which delays
were TSI’s responsibility and for which delays TSI should be compensated. Id. at 14–17. In
sum, in both his Independent and Rebuttal Reports, Harris generally provides his expert opinions
on which party was responsible for which delays based on his own analysis of the project.
The parties disagree over one aspect of Harris’ opinions contained in his Reports. In the
Independent and Rebuttal Reports, Harris states Federal “has determined that delays related to
the containment should be apportioned so that NAVFAC bears 75% of the responsibility and
Sauer’s subcontractors bear the remaining 25%.” 3 Id. at 18; see also id. at 93, 95. Harris
explains he did not validate the 75/25 allocation figure for containment delays. Id. at 18. The
parties agree the 75/25 allocation figure was provided to Harris by Federal’s counsel and Harris
has not had any opportunity to determine the accuracy of the figure. Indeed, Federal
acknowledges it has not disclosed the basis for the 75/25 allocation figure to Plaintiff, instead
explaining only it intends to “prove [the figure] at trial.” Doc. 138 at 5. Nonetheless, Harris
NAVFAC is the United States Naval Facilities Engineering Command, which Sauer and TSI
performed work for at the Kings Bay Naval Submarine Base and which was ultimately responsible for
overseeing the project.
3
3
provides a new assessment of overall responsibility for all delays utilizing the 75/25 allocation
figure for containment-related delays. Doc. 129-2 at 18, 93, 95.
To be clear, the 75/25 allocation figure provided by Federal’s counsel is distinct from
Harris’ own, independent opinions about the parties’ responsibility for containment-related
delays. Harris initially determined Plaintiff TSI is responsible a number of days of delay. Id. at
94, 155. This determination was based on his experience and expertise and review of several
relevant aspects of the project. Id. at 101–154. Additionally, in his Rebuttal Report, Harris
addressed expert opinions by JS Held, Plaintiff’s expert, and revised his own opinions about
TSI’s responsibility for certain delays, including containment-related delays. Id. at 82. Harris
provides a robust analysis of the JS Held opinion. Id. at 13–15, 24–50. Harris explains how JS
Held’s conclusions and methodology influence his own analysis—even leading him to make
revisions to his initial opinion. Id. at 55–59. That is, Harris provided opinion based on his
expertise about the responsibility for containment-related delays at issue in this suit, both initially
and in consideration of JS Held’s opinions.
Despite forming his own opinions about containment-related delays, Harris also utilized
the 75/25 figure provided to him by Federal’s counsel. Id. at 83. Harris notes use of Federal’s
counsel’s figure resulted in removing 77 compensable delays from Plaintiff and results in
Plaintiff only having 64 compensable days. Id. Harris provides no reasoning for his adjustment,
other than reliance on the 75/25 figure. 4 Harris, in his Reports and testimony, was candid the
75/25 allocation was not the result of him applying his expertise to determine who was
responsible for the delays, but was simply given to him by Federal’s counsel, who informed him
Harris also utilized a figure assuming 50% NAVFAC containment responsibility and 25%
NAVFAC containment responsibility, which are also unsupported and are equally unreliable. Doc. 129-2
at 84–85. Unlike the 75/25 figure, there is no indication Federal relies on these other allocation figures.
4
4
they would prove this is the correct allocation at trial. Doc. 129-2 at 18; Doc. 129-3 at 4–5.
While Harris did explain how such responsibility for delay would impact his opinions, he does
not state the 75/25 figure is accurate or otherwise correct. Indeed, Harris states expressly he did
not “validate” the 75/25 figure. Id. at 18.
In its Motion, Plaintiff does not challenge Harris’ own, independent opinions on delay,
his revisions in light of the JS Held findings, or his ability to testify to these conclusions,
regardless of the type of delay or the allocation of responsibility. Instead, Plaintiff challenges
Harris’ opinions on delay responsibility that are based on the 75/25 figure for containmentrelated delays provided by Federal’s counsel. Id. at 2–87. Plaintiff contends Harris should not
be permitted to offer opinions about delay responsibility using a 75/25 containment-related delay
allocation figure, where that figure is merely unsupported supposition offered by Federal’s
counsel. Doc. 147.
DISCUSSION
I.
Federal Rule of Evidence 702 and Daubert
The United States Supreme Court’s holding in Daubert v. Merrell Dow Pharmaceutical,
Inc., 509 U.S. 579 (1993), and the text of Rule 702 require trial judges to serve as gatekeepers in
determining the admissibility of expert testimony; however, any decision regarding admissibility
is not a position on the strength or weight of the testimony. Fed. R. Evid. 702; Kumho Tire Co.
v. Carmichael, 526 U.S. 137, 141 (1999). In this Circuit, courts routinely look to three elements
to determine if an expert is qualified under Daubert and Rule 702. As the Eleventh Circuit Court
of Appeals has stated, the elements for consideration are whether:
(1) the expert is qualified to testify competently regarding the matters he intends
to address; (2) the methodology by which the expert reaches his conclusions is
sufficiently reliable as determined by the sort of inquiry mandated in Daubert;
and (3) the testimony assists the trier of fact, through the application of
5
scientifically, technical, or specialized expertise, to understand the evidence or
to determine a fact in issue.
United States v. Frazier, 387 F.3d 1244, 1260 (11th Cir. 2004) (citations omitted). “[A]lthough
there is some overlap among the inquiries into an expert’s qualifications, the reliability of his
proffered opinion and the helpfulness of that opinion, these are distinct concepts that courts and
litigants must take care not to conflate.” Quiet Tech. DC-8, Inc. v. Hurel-Dubois UK Ltd., 326
F.3d 1333, 1341 (11th Cir. 2003). The trial court has broad latitude in evaluating each of these
three factors.
As to reliability, courts look, when possible, to: (1) whether the expert’s theory can be
and has been tested; (2) whether the theory has been subjected to peer review and publication;
(3) the known or potential rate of error of the particular scientific technique; and (4) whether the
technique is generally accepted in the scientific community. Daubert, 509 U.S. at 593–94.
However, these factors are not exhaustive, and “a federal court should consider any additional
factors that may advance its Rule 702 analysis.” Quiet Tech., 326 F.3d at 1341. At all times in
this flexible inquiry, the court’s focus must be “solely on principles and methodology, not on the
conclusions that they generate.” Seamon v. Remington Arms Co., LLC, 813 F.3d 983, 988 (11th
Cir. 2016) (citation omitted).
Finally, as to the third Daubert factor, expert testimony is likely to assist the trier of fact
to the extent it “concern[s] matters beyond the understanding of the average lay person and
logically advance[s] a material aspect of the proponent’s case.” Kennedy v. Elec. Ins. Co., Case
No. 4:18cv148, 2019 WL 2090776, at *5 (S.D. Ga. May 13, 2019) (citing Daubert, 509 U.S. at
591); Frazier, 387 F.3d at 1262–63. Rule 702 permits experts to make conclusions based on
competing versions of the facts, but those conclusions must still assist the trier of fact by
explaining something that is “beyond the understanding of the average lay person.’” Jackson v.
6
Catanzariti, No. 6:12-CV-113, 2019 WL 2098991, at *10 (S.D. Ga. May 14, 2019) (citing
Frazier, 387 F.3d at 1262). Expert testimony generally will not help the trier of fact “when it
offers nothing more than what lawyers for the parties can argue in closing arguments.” Id.
(quoting Cook v. Sheriff of Monroe Cnty., 402 F.3d 1092, 1111 (11th Cir. 2005)). Such
testimony “is properly excluded when it is not needed to clarify facts and issues of common
understanding which jurors are able to comprehend for themselves.” Hibiscus Assocs. Ltd. v.
Bd. of Trs. of Policemen & Firemen Ret. Sys., 50 F.3d 908, 917 (11th Cir. 1995) (citations
omitted).
“The burden of laying the proper foundation for the admission of the expert testimony is
on the party offering the expert, and admissibility must be shown by a preponderance of the
evidence.” Allison v. McGhan Med. Corp., 184 F.3d 1300, 1306 (11th Cir. 1999). However, “it
is not the role of the district court to make ultimate conclusions as to the persuasiveness of
proffered evidence.” Quiet Tech., 326 F.3d at 1341. Instead, “[v]igorous cross-examination,
presentation of contrary evidence, and careful instruction on the burden of proof are the
traditional and appropriate means of attacking shaky but admissible evidence.” Daubert, 509
U.S. at 596.
II.
Federal Fails to Establish Harris’ Opinion on Delay Apportionment Using the 75/25
Figure Is Based on Reliable Methodology
Plaintiff argues Harris’ opinions assuming an allocation figure of 75/25 responsibility for
containment-related delays should be excluded because it relies on information unknown to
Harris and is nothing more than a “plug number” provided by counsel. Doc. 129-1 at 5. Plaintiff
contends Harris’ opinions, using this plug number, are not based on a reliable methodology. Id.
at 6–7; Doc. 147 at 3–6.
7
Federal opposes Plaintiff’s Motion. Doc. 138. Federal contends Harris’ reliance on the
figure is permissible because Federal will prove at trial a 75/25 allocation of responsibility is
correct. Federal also argues experts are permitted to offer opinions based on assumptions and
testify to hypotheticals, and Harris’ opinions are just that. Instead of exclusion, Federal argues
the proper way to attack Harris’ testimony and the figure he relies on is through crossexamination at trial. Id. at 2, 5–7.
While Federal is correct experts are permitted to offer opinions that rely on assumptions,
those assumptions must have some basis in the record. See Tillman v. C.R. Bard, Inc., 96 F.
Supp. 3d 1307, 1320 n.14 (M.D. Fla. 2015) (declining to exclude expert opinion based on
assumption for which expert offered some support but noting “[a]n expert’s opinion, where
based on assumed facts, must find some support for those assumptions in the record) (quoting
McLean v. 988011 Ontario, Ltd., 224 F.3d 797, 800 (6th Cir. 2000)). But, “the facts relied upon
by an expert ‘must find some support . . . in the record’ and ‘must be supported by more than
subjective belief and unsupported speculation.’” In re Delta/Airtran Baggage Fee Antitrust
Litig., 245 F. Supp. 3d 1343, 1361 (N.D. Ga. 2017) (quoting McLean, 224 F.3d at 800–01);
see also Vincent v. Am. Honda Motor Co., No. CV 108-067, 2010 WL 11537726, at *5 (S.D.
Ga. July 1, 2010) (“There must ‘be sufficient facts already in evidence or disclosed by the
witness as a result of his investigation to take the testimony out of the realm of guesswork and
speculation.’”) (quoting Polk v. Ford Motor Co., 529 F.2d 259, 271 (8th Cir. 1976)); Grand Slam
Club/Ovis v. Int’l Sheep Hunters Ass’n Found., Inc., No. 2:06-CV-4643, 2008 WL 11375373, at
*4 (N.D. Ala. Jan. 15, 2008) (explaining expert testimony should be excluded when it relies on
assumptions without support in the record).
8
Here, Federal has not shown the 75/25 containment-related delay figure has any support
in the record. Instead, Federal offers nothing but conclusory statements there is “ample support”
for the apportionment of delay figure. Doc. 138 at 5. In Harris’ deposition and Reports, he
admits the 75/25 allocation of responsibility for containment-related delays is merely an
unverified plug number provided to him by Federal’s counsel. Doc. 129-2 at 18; Doc. 129-3 at
4–5. Federal did not ask Harris to validate the 75/25 figure, and there is no indication Harris
attempted to do so. Doc. 129-2 at 18. Notably, Harris did not perform an analysis of Federal’s
allocation, as he did with JS Held’s expert report. Instead, Harris made arbitrary adjustments to
his own expert opinions based on Federal’s counsel’s representations, and he relies on Federal’s
assurance it will prove the figure at trial. But, Federal, as the proponent of Harris, is required to
provide support for the figure at this juncture—which it has failed to do. Allison, 184 F.3d at
1306 ; Rink v. Cheminova, Inc., 400 F.3d 1286, 1292 (11th Cir. 2005) (explaining it is the
proponent of the expert’s burden to prove reliability by a preponderance of the evidence). 5
Federal’s failure to show the 75/25 containment-related delay figure has support in the
record is what distinguishes the instant case from the cases on which Federal relies. For
example, in Vincent, 2010 WL 11537726, on which Federal relies, doc. 138 at 6, the Court found
the expert’s “assumptions are founded upon sufficient facts in the record.” This finding was
central to the Court determining the expert’s testimony was sufficiently reliable. Id. at *5–6;
see also Mcgarity v. FM Carriers, Inc., No. CV410-130, 2012 WL 1028593 (S.D. Ga. Mar. 26,
2012) (finding the expert relied on evidence when forming his opinion); White v. Hall, No. 5:18cv-72, 2020 WL 653833 (M.D. Ga. Nov. 6, 2020) (finding an expert opinion reliable because the
Federal refers to Plaintiff TSI as having the burden. Doc. 138 at 5. This is incorrect. Federal, as
the proponent of Harris, has the burden of showing his testimony is admissible. Allison, 184 F.3d at 1306
(11th Cir. 1999); Rink, 400 F.3d at 1292.
5
9
opinion had factual support). In contrast, Harris’ opinions based on the 75/25 containmentrelated delay figure—a figure that plainly has no support in the record—should be excluded.
Buland v. NCL (Bahamas) Ltd, 992 F.3d 1143, 1151 (11th Cir. 2021) (“The unsupported
assumption made [the expert’s] testimony unreliable.”); Reed v. Royal Caribbean Cruises Ltd.,
No. 19-24668-CIV, 2021 WL 2592888, at *3–5 (S.D. Fla. May 3, 2021) (excluding plaintiff’s
expert’s testimony where plaintiff failed to identify any portion of the record supporting the
expert’s assumptions); Go Med. Indus. Pty, Ltd. v. Inmed Corp., 300 F. Supp. 2d 1297, 1317
(N.D. Ga. 2003) (excluding expert testimony where the opinion “speculate[s] and assume[s]
premises without any indication of support”).
It is important to note Harris provided his own, independent analysis of containmentrelated delay responsibility, where he assigned delay responsibility among the parties, based on
his experience and expertise and review of relevant aspects of the project. Doc. 129-2 at 127–52,
155. When performing his analysis, Harris did not reach the 75/25 allocation for containmentrelated delays—he came up with his own expert opinion on responsibility for these delays. Id. at
76, 148. Federal, however, directed Harris to replace that portion of his expert opinion with its
own conclusions, the 75/25 figure. Federal essentially asked Harris to assume his own expert
opinion about containment-delay responsibility was incorrect, and to, instead, accept Federal’s
own conclusion. This approach is impermissible because Federal’s conclusion—the 75/25
figure—is not based on any discernible methodology or anything in the record. Federal simply
told Harris 75/25 is the correct allocation and assured him it would be proven at trial. Federal
could have offered some support for 75/25 figure in its Response to Plaintiff’s Motion, but it
failed to do so. Instead, Federal still maintains its “wait and see” approach attempting to assure
10
all that the figure will be eventually proven at trial. To be clear, Federal has had ample
opportunity to provide some explanation for the 75/25 figure but has failed to do so.
It is also noteworthy that containment-related delay responsibility is not a trivial matter in
this litigation. Containment-related delays represent a significant component of overall delays,
and allocation of those delays will likely have a material impact on responsibility for delays
generally. Federal’s position would effectively excise a major component of Harris’ opinion
(which was the result of detailed expert analysis) and replace it with an unfounded assumption.
Any opinion Harris intends to offer based on that unfounded assumption would undoubtedly be
material to the case, but also inherently unreliable.
Federal attempts to salvage this portion of Harris’ opinions by arguing Harris’ use of the
75/25 allocation figure is akin to removing one figure in a formula and replacing it with another.
Doc. 138 at 9; Doc. 158 at 6–7, 9. The problem is Harris did not use a formula in forming his
opinion. He engaged in a comprehensive analysis of various containment-related delays and
offered individualized opinions on those delays. Indeed, Federal’s counsel had to create a
fictitious formula for the purposes of even making this argument. Doc. 138 at 8; Doc. 158 at 8–
10 (during argument Federal’s counsel was unable to articulate any particular formula used by
Harris). Contrary to Federal’s counsel’s assertions, there is no discernible formula utilized by
Harris, and using the 75/25 allocation figure is not akin to merely swapping out variables.
In sum, Harris developed expert opinions about responsibility for containment-related
delays based on his specialized knowledge and facts he identified during his investigations.
Federal wants Harris to replace his own independent expert opinion on containment-related delay
responsibility with a figure provided by Federal’s counsel—where that figure has no basis in the
record—and then offer different expert opinions based on that unsupported assumption.
11
Opinions from Harris based on this unsupported assumption would not be reliable and, therefore,
must be excluded.
CONCLUSION
For the foregoing reasons, the Court, the Court GRANTS Plaintiff’s Motion to Exclude.
Federal has not met its burden in showing Harris should be permitted to offer opinions on
responsibility for delays, where those opinions are based on Federal’s counsel’s unsupported
75/25 containment-related delay figure. Harris is not permitted to offer expert opinion testimony
based on this allocation. Harris is otherwise permitted to testify, including on his independent
conclusions regarding containment delay. Because the Court finds the opinion is not reliable, the
Court declines to address whether Harris’ opinion is helpful.
SO ORDERED, this 13th day of January, 2022.
____________________________________
BENJAMIN W. CHEESBRO
UNITED STATES MAGISTRATE JUDGE
SOUTHERN DISTRICT OF GEORGIA
12
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?