The United States of America for the Use and Benefit of TSI Tri-State Painting, LLC v. Federal Insurance Company

Filing 26

ORDER denying Defendant Federal Insurance Company's 8 Motion to Dismiss, or in the Alternative, to Stay this Action. Signed by Chief Judge Lisa G. Wood on 12/20/2016. (ca)

Download PDF
Kn t|ie tUntteb States! SBisitritt Court tor ttie ^onttiem IBtsitrtct ot <fleorsta pmnotoick Biliiotott THE UNITED FOR THE STATES USE AND OF AMERICA BENEFIT OF TSI TRI-STATE PAINTING, LLC, Plaintiff, CV 216-113 V. FEDERAL INSURANCE COMPANY, Defendant. ORDER Before the Court is Defendant Federal Insurance Company's (^'Federal") Motion to Dismiss or, in the Alternative, to Stay this Action (Dkt. No. 8). For the reasons stated below. Federal's motion is DENIED. BACKGROUND The facts stated herein are taken solely from Plaintiff Tri-State Painting, LLC's (^^TSI") Complaint and are assumed to be true, pursuant to Rule 12(b)(6). limited liability corporation Georgia. provides A0 72A (Rev. 8/82) Dkt. No. 1 % 1. surety bonds TSI is a New Hampshire licensed to do business in Federal is an insurance company which to companies entering construction contracts with the federal government. % 2. not a party to the contract at issue here. Federal was Instead, Federal acted as a surety to the primary contractor, Sauer Incorporated C'Sauer"). Sauer, in turn, entered into a primary contract with Naval Facilities Engineering Command SE {the ^^Government"). TSI was a subcontractor to this primary contract. On or about June 24, 2011, the Naval Facilities Engineering Command SE issued a Request for Proposal. M. H 6. On September 23, 2011, the Government and Sauer entered into a contract for the rehabilitation of Wharf 2 at the Naval Submarine base in Kings Bay, Georgia (the '"Project") at a price of $28,126,400.00. M. f 7. One element of the Project was paint removal and refinishing within Wharf 2. H 8. The Project represented that only a limited area contained leadbased paint. In spring 2012, Sauer executed a subcontract Coatings for paint removal and replacement. with CL TSI alleges that CL Coatings refused to execute the subcontract because lead paint existed in more areas than stated in the contract. Id. H 13. Subsequently, Sauer entered into a subcontract with TSI (the "Contract") to replace CL Coatings. TSI alleges, however, that it was never informed that lead-based paint existed in areas beyond those stated in the original contract. f 15. Sauer and TSI executed the Contract on June 15, 2012. H 18. Id. During the start of work, TSI discovered lead paint in the air in worksites beyond those stated in TSI's contract with Sauer. HH 19-22. Sauer then directed TSI to stop work and informed the Government of the problem. accept the result. However, additional testing revealed high lead levels in the air. results and work The Government did not Ultimately, the Government accepted the stopped. renegotiate the Contract. Sauer and TSI Dkt. No. 1 p. 11. then began to Changes to the re negotiated contract included the purchasing of new equipment and containment systems necessary associated with the lead paint. to mitigate the problems lA. at pp. 11-12. Work on the Project re-commenced with the new systems in place on July 12, 2013. Id. H 43. On or about August 15, 2013, the containment systems failed due to high winds, and TSI was forced to stop work. H 46. Work restarted, but further delays occurred because containment systems were not ready for additional equipment. H 50. On September 20, 2013, the Government modified the contract to include an additional $6,843,906.88, with $4,586,874.70 designated for subcontractor lead-paint work, and an additional 384 days beyond the original contract date. H 51. Sauer reserved its rights against the Government because it claimed that this amount was insufficient to cover the additional cost. Id. H 53. to TSI. equipment, Sauer, however, did not pass this time extension on Nor did Sauer provide any additional funds for new which Additional was required due to the lead contamination. problems with the containment systems occurred. Eventually, TSI notified Sauer that it could not effectively work under such conditions. H 53. On December 31, 2013, TSI requested an additional 141 days to complete the Project, but Sauer did not respond. H 64. Additional delays and mismanagement occurred in 2014-15. ultimately stopped work. TSI refused. TSI Sauer ordered TSI to restart work and TSI alleges that Sauer's series of missteps added additional costs to its work. delays and ]^. at pp. 17-24. On or about March 23, 2016, TSI submitted a certified claim to Sauer in the amount of $14,254,752. Federal acts as Sauer's certified claim to Federal. any sum to TSI. H 85. surety. TSI also submitted a Neither Sauer nor Federal has paid TSI now brings a claim against Federal for a Breach of Payment under the Miller Act. Id. DISCUSSION The Miller Act provides that all persons contracting ''for the construction, alteration, or repair of any public building or public work of the United States" at a cost exceeding $100,000 shall provide a payment bond "for the protection of all persons supplying labor and material." 40 U.S.C. §§ 3131(b), 3131(b)(2). The Miller Act allows any person who has furnished labor or material for the construction of a ^'public building or public work" and who has not been paid in full to bring a civil action on the payment bond in federal district court. §§ 3133(b)(1), 3133(b)(3). Federal does not dispute that the Miller Act applies to this case. Instead, Federal argues that TSI's claims must be dismissed because the Contract bars recovery on TSI's claims for delay, disruption, or interference under the Miller Act. No. 14 p. 2-4. Dkt. Alternatively, Federal argues that this action should be stayed pending renegotiation of the agreement between Sauer and the Government. Dkt. No. 8-1 p. 11. The Court addresses each argument in turn. I. Federal's Motion to Dismiss The Court first addresses Federal's Motion to Dismiss. When ruling on a Rule 12(b)(6) motion to dismiss, a district court must accept as true the facts set forth in the complaint and draw all reasonable inferences in the plaintiff's Randall v. Scott, 610 F.3d 701, 705 (11th Cir. 2010). favor. Although a complaint need not contain detailed factual allegations, it must contain relief above sufficient factual material the speculative level." Twombly, 550 U.S. 544, 555 (2007). should ''contain either direct ^'to raise Bell a Atl. right to Corp. v. At a minimum, a complaint or inferential allegations respecting all the material elements necessary to recovery under some viable legal theory." sustain a Fin. Sec. Assurance, Inc. V. Stephens, Inc., 500 F.3d 1276, 1282-83 (11th Cir. 2007) (per curiam) (quoting Roe v. Aware Woman Ctr. for Choice, Inc., 253 F.3d 678, 683 (11th Cir. 2001)). Federal argues that Paragraph 3 of the Contract provides it an affirmative defense against TSI's claims. Dkt. No. 14 p. 2. Paragraph 3 waives all damages for delays under the condition that no extension was requested. Dkt. No. 1-3. Federal argues that Paragraph 3 warrants dismissal of any action based upon delay because 1) Paragraph 3 applies regardless of whether a time extension was actually granted by Sauer and 2) delays in the Project were within the parties' contemplation. Dkt. No. 14 p. 4-6. Although this action was brought under the Miller Act, this is effectively a contract case, and the law of the state in which the governs. agreement was executed and was to be performed U.S. f/u/b/o Seminole Sheet Metal v. SCI, Inc., 828 F.2d 671, 675 (11th Cir. 1987). Therefore, Georgia contract law governs this case, despite the federal cause of action. Under Georgia law, ^'no-damages-for-delays" provisions like Paragraph 3 are enforceable. L & B Enters., 482 S.E.2d 279, 280 (Ga. 1997). Constr. Co. v. Ragan No-damages-for-delay clauses may be unenforceable, however, if subject to a condition precedent which does not occur. United States f/u/b/o Pertun Constr. Co. v. Haarvesters Grp., Inc., 918 F.2d 915, 919 (11th Cir. 1990). Part one of Paragraph 3 plainly prevents TSI from obtaining damages for delay: Sauer shall not be liable to Subcontractor for any delay, disruption or interference to Subcontractor's Work caused by . . . (10) unexpected soil or other physical conditions . . . (13) any other cause direct control; provided, however, Sauer with Subcontractor in submitting against beyond Sauer's will cooperate the Owner any just claim arising from any such delay that is permitted by the General Contract. Dkt. No. 1-3 1 3. However, part two subjects this clause to a condition precedent: Should the Subcontractor's Work be delayed, disrupted or interfered with solely as a result of the acts or omissions of Sauer or anyone employed by Sauer on the Project, then Subcontractor shall receive an extension of time equal to the actual delay to critical path activities caused by these delays, as determined by Sauer. . . . An extension of time, as determined extension of time Subcontractor's sole by Sauer, shall be remedy or the decision allowed, for that shall delay. In be no the exchange. Subcontractor expressly waives the right to bring against Sauer any claim for damage for delay, inefficiency, disruption, acceleration, interference, extra work resulting from such delay, extended overhead, wage escalation, overtime wage provisions, lost opportunity or lost profit or financial impact on Subcontractor's other projects. Id. Federal condition argues precedent, that subpart rather than (13) part of part two. one is the Specifically, Federal reads part one to mean that Sauer need only '''cooperate" with TSI in a claim against the Government in order for the nodamage-for-delay clause However, interpretation this paragraph, to take effect. ignores Dkt. the No. 14 entire p. 5. second which creates a condition precedent to the first. Furthermore, it is plausible subpart (13) is one of thirteen scenarios in which Sauer is not liable for delay—not a condition precedent to the other twelve. Regarding the second part. Federal concedes that it creates a condition precedent to the no-damages-for-delay clause. No. 14 p. 6. Dkt. Federal asserts, however, that "an extension of time or the decision that no extension of time" was TSI's only remedy under the Contract. However, TSI alleges decision regarding an extension of time was ever made. 54, 64. that no Dkt. 1 Therefore, even if an extension of time or a decision regarding one was TSI's only remedy, TSI alleges that neither occurred. Federal also alleges that the "delays in question" were within the contemplation of the parties and that the parties agreed that "Sauer omissions." the parties' would not Dkt. No. 14 p. 6. contemplation could delay the Project. be liable for its own acts or Paragraph 3 does indeed indicate that some "unexpected" Dkt. No. 1-3 f 3. condition However, in order to be free from delay-damage liability, Sauer needed to either provide an extension or make a decision regarding whether one would be given. Again, TSI alleges that Sauer gave no such extension and made no such decision. whether a delay was contemplated, Therefore, regardless of Paragraph 3's effectiveness relies on the factual question of whether Sauer gave notice of an extension or not—which cannot be decided on a motion to dismiss. Finally, the Court notes that while Federal relies heavily on subsection assumption: (13), that its the reliance delays is due to ''beyond Sauer's direct control." that Sauer in fact knew about based excess on a key lead factual levels were TSI's complaint alleges the excess lead levels from its previous contract with CL Coatings and, therefore, may have been able to prevent TSI's delays. Dkt. No. 1 HH 13, 15. It is certainly plausible that Sauer knew about the excess lead paint issue and failed allegations as to true, notify the TSI. Court Therefore, denies taking Federal's all Motion to Dismiss. Federal repeatedly points to a "TSI Claims" document from TSI which appears to indicate the extent of TSI's damages for various claims in this case. TSI argues that the Court should disregard it Complaint. documents this document as The Court agrees. attached to a is not "central" to TSI's At the motion-to-dismiss stage, motion to dismiss are not properly considered by the court unless (1) they are plaintiff's claim, such as a contract in a central to the breach-of-contract action, and (2) their authenticity is not challenged. Horsley V. Feldt, 304 F.3d 1125, 1134 (11th Cir. 2002). Essentially, the Plaintiff's Complaint must be ^^based on" the TSI Claims document in order for the Court to consider it at this stage. Carter v. HSBC Mortg. Servs., Inc., 622 F. App'x. 783, 787 (11th Cir. 2015). This is plainly not the case here. TSI's Complaint is based on the Contract and its provisions, not the TSI Claims document. Dkt. No. 1. Regardless, the Court finds that the TSI Claims document is non-dispositive at this stage. The TSI Claims document does nothing to establish that Sauer is not liable for breach of believe that the those damages. Government could contract—only that TSI may be responsible for some of This is an insufficient basis for the Court to grant a motion to dismiss. II. Motion to Stay Federal stayed alternatively pending argues negotiation between regarding additional compensation. that this Sauer and case should the be Government Dkt. No. 8-1 p. 10. The Court should not exercise its power to stay proceedings lightly. ^^When confronted with a motion to stay, the district court must consider caseload, its and own interests the parties' in an orderly competing 10 disposition interests in of its the two actions." Markel Int^l Ins. Co. 1374, 1376 {S.D. Ga. 2008) v. O^Quinn, 566 F. Supp. 2d (citation omitted). The power to stay a proceeding is ''incidental to the power inherent in every court to control the disposition of the causes on its docket with economy of time and effort for itself, for counsel, and for litigants." Landis v. N. Am. Co., 299 U.S. 248, 254 (1936). district court therefore determining whether a has broad stay is A discretionary authority in appropriate. CTI-Container Leasing Corp. v. Uiterwyk Corp., 685 F.2d 1284, 1288 (11th Cir. 1982); see also Chudasama v. Mazda Motor Corp., 123 F.3d 1353, 1366 (11th Cir. 1997) ("[D]istrict courts enjoy broad discretion in deciding making its how best to manage the case determination, a court "must before them."). In . . . examine the relative prejudice and hardship worked on each party if a stay is or is not granted." Pise v. Express Marine, Inc., 2008 WL 2163920, at *3 (S.D. Ala. May 19, 2008). The stayed. Miller Act controls whether this action should be The Miller Act provides a federal cause of action for subcontractors involving the completing seeking payment government. its judgment on the work, a If in not construction paid subcontractor surety bond. within may sue 90 and contracts days of collect 40 U.S.C. § 3133(b)(1). The Miller Act is "highly remedial in nature" and "entitled to a liberal construction and application 11 in order to properly effectuate the Congressional intent to protect those whose labor and material go into public projects." Sherman v. Carter, 353 U.S. 210, 216 United States ex rel. (1957) (references and citations omitted). However, waived where the the subcontractors' Miller Act rights subcontract contains a provision may making be the disputes clause of the primary contract expressly applicable to the subcontract, and where the subcontract contains an express waiver of the subcontractor's Miller Act remedy. United States V. David Boland, Inc., 922 F.Supp. 597 (S.D. Fla. 1996). Thus, the Court looks to the four corners of the contract to determine if both conditions have been met. Federal argues that the Contract binds TSI to any dispute resolution Sauer engages in with the Government. 12. TSI argues that the Contract does Dkt. No. 22 p. not require dispute resolution between TSI and the Government, but only between TSI and Sauer. Id. at p. 13. It is undisputed that Sauer has not requested that TSI engage in arbitration with it. Therefore, the only question before the Court is whether it should stay this case while Sauer negotiates its contract with the Government. Federal points to Paragraphs 3, 9, and 14. three provisions in the Contract: However, the Court finds that only Paragraph 14, '^Claims; Dispute Resolution" is relevant: 12 If Sauer and [TSI] have a dispute arising under or relating to the Agreement or its breach, which involves the correlative rights or duties of Owner, such dispute shall be decided in accordance with the General Contract. . . . [TSI] and its surety, if any, shall be bound to Sauer to the same extent that Sauer is bound to Owner by the terms of the General determinations Contract, made under and the by any General decisions Contract by or any authorized person, board, court, or other tribunal. Federal urges the Court to compare Paragraph 14 to the contract provision in a similar case. United States v. David Boland, Inc., 922 F. Supp. 597 (S.D. Fla. 1996). As is the case here, Boland involved a subcontractor's claim against a general contractor under the Miller Act. presented before the Boland Id. at 598. court, like the The question one here, was whether the subcontractor's claims should be stayed pending the resolution of the prime contract between the government and the primary contractor. finding that the The Court found in the affirmative, contract contained '"clear and unambiguous" language indicating that the subcontractor's action was to be stayed. language at 599. here. However, the Court finds no such clear Where the provision in Boland expressly indicated that the subcontractor agreed to a stay in the event of mediation between the prime contractor and the government, no such language is present in this case. In fact, the word "stay" is plainly absent from the above provision. Furthermore, would effectively the be Court is wary indefinite. 13 of granting The Eleventh a stay Circuit that has previously indicated disfavor regarding indefinite stays. Ortega Trujillo v. Conover & Co. Commc^nS/ 221 F.3d 1262 (11th Cir. 2000); King v. Cessna Aircraft Co., 505 F.3d 1160 (11th Cir. 2007). Federal has provided no compelling reasons why this case be should stayed indefinitely, nor does the contractual language indicate mandatory waiver of TSI's Miller Act rights. Thus, the Court denies Federal's request to stay these proceedings. CONCLUSION For the reasons set forth above, it is hereby ordered that Defendant Federal Insurance Company's Motion to Dismiss or, in the Alternative, to Stay this Action (Dkt. No. 8) is DENIED. SO ORDERED, this 20th day of December, 2016. LISA GODBEY WOOD, CHIEF JUDGE UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF GEORGIA 14

Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.


Why Is My Information Online?