Strickland v. Arch Insurance Company
Filing
48
ORDER granting Arch's 24 Motion for Summary Judgment; denying Strickland's 26 Motion for Summary Judgment. The Clerk is DIRECTED to enter the appropriate judgment and close this case. Signed by Chief Judge Lisa G. Wood on 1/10/2017. (ca)
In tl^e
States! Biiectrtct Conrt
for tl^e ^ontfiem Bi£(trtct of(ieorstn
Wujfttstii 29ttits[ton
DEVIN B. STRICKLAND,
Plaintiff,
No, 5:14-CV-70
V.
ARCH INSURANCE COMPANY,
Defendant.
ORDER
Before
Defendant
the
Arch
Court are Plaintiff Devin B. Strickland and
Insurance
judgment motions.
Co.'s
{''Arch")
Dkt. Nos. 24, 26.
competing
summairy
The motions have been
fully briefed and the Court heard oral arguments on both
motions.
The
Dkt. Nos. 28, 31-32, 35-36, 38.
motions
present
construction
finished,
limitations,
when
the
a
so
simple
as
public
to
question:
trigger
authority
a
finds
satisfactory and takes responsibility for it?
Is
public
statute
the
of
project
Or does the
authority also need to issue formal "final acceptance"?
No
final acceptance is needed, because O.C.G.A. § 13-10-65 is
concerned
policy and
A0 72A
(Rev. 8/82)
with
actual
procedure."
work,
not
the
authority's
"internal
U.S. Fidelity & Guar. Co. v. Rome
Concrete Pipe Co., 353 S.E.2d 15, 16-17 (Ga. 1987).
For this
reason, as discussed below, the Court GRANTS Arch's motion,
dkt. no. 24, and DENIES Strickland's motion, dkt. no. 26.
FACTUAL BACKGROUND
Strickland supplied sand to Douglas Asphalt for use on a
Georgia Department of Transportation
Dkt. No. 24-1 nil 1-2.
n 4.
C'GDOT") road project.
Douglas Asphalt went into default.
Id.
Arch took over Douglas Asphalt's duty, pursuant to an
agreement, then arranged for the work's completion by a third
party.
Id. K 5; Dkt. No. 24-3 at 6-9, 16-17.
never paid.
Dkt. No. 31-3 1| 7.
on August 22, 2014.
He sued Arch seeking recovery
Dkt. No. 1-1 at 4.
to this Court on September 19, 2014.
According
to
GDOT,
Strickland was
the
The suit was removed
Dkt. No. 1.
underlying
road
work
was
''substantially complete," "ready for final inspection," and
"complete and satisfactory" on August 25, 2010.
at
12:2-10.
The
September 1, 2010.
builder
requested
final
Dkt. No. 22-3 at 1.
Dkt. No. 22
inspection
on
It requested that
GDOT take over project maintenance on January 25, 2012, "since
all the [work] [had] been completed."
Dkt. No. 22-4 at 1.
On
February 1, 2012, GDOT's area engineer informed his district
engineer
that
completed."
the
"project
Dkt. No. 22-5 at 1.
ha[d]
been
satisfactorily
Arch chimed in on February
8, 2012, informing GDOT that "[t]he project ha[d] been open to
unrestricted
completed.
On
traffic"
and
all
work
was
satisfactorily
Dkt. No. 22-7 at 1.
March
12,
2012,
GDOT
accepted
project
maintenance
responsibility retroactive to September 14, 2011.
22-8.
Dkt. No.
It considered all construction work complete, and all
that remained to be done was ''the final close out" paperwork.
Id. at 16:22-17:7.
Therefore, in summer 2012,
"semifinal" payment.
Id. at 15:8-16.
semifinal
auditor
in
that
Id. at 15:18-24.
money.
an
would
GDOT issued
The payment was only
later
check
for
errors.
GDOT did not end up paying any additional
Id. at 15:25-16:1.
Up until GDOT's "final written acceptance," the builder
had the duty to protect the project and repair any damage to
it.
Dkt. No. 22 at 22:10-18.
on September 22, 2014.
Final written acceptance issued
Dkt. No. 22-10 at 1.
Strickland found out shortly before this that GDOT was
"prepar[ing] to close out the job."
53:3.
Dkt. No. 23 at 52:25-
He was told by a GDOT employee that the project had not
yet been closed, but he needed to file any claims he had
immediately.
Id. at 54:3-10.
He was assured that GDOT would
not close out the project if there were any pending lawsuits,
so he responded by filing the instant suit.
Id. at 54:13-15.
In part, he had not taken earlier action because of a
GDOT
employee's
assurances
that
he
would
be
paid
and
indications that the project might need additional sand.
Id.
at 41:20-43:16; see also id. at 44:10-11
really tried to
demonstrate I was a team player . . . .").
However, he had
demanded payment in a September 7, 2012 letter to Arch, with
ten pages of records attached.
Dkt. No. 24-3 at 22-33.
Arch sought more documents, he did not respond.
When
Id. at 3.
LEGAL STANDARD
Summary judgment is required where ''the movant shows that
there is no genuine dispute as to any material fact and the
movant is entitled to judgment as a matter of law."
Civ. P. 56(a).
A fact is "material" if it "might affect the
outcome of the suit under the governing law."
Grp.
V.
Fed. R.
FindWhat.com, 658
FindWhat Inv^ r
F.3d 1282, 1307 (11th Cir. 2011)
(quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248
(1986)).
A dispute is "genuine" if the "evidence is such that
a reasonable jury could return a verdict for the nonmoving
party."
to
the
Id.
The court must view the evidence most favorably
nonmovant
party's favor.
and
draw
all reasonable
inferences
in
that
Johnson v. Booker T. Washington Broad. Serv.,
Inc., 234 F.3d 501, 507 (11th Cir. 2000).
DISCUSSION
The
statute
of
limitations
bars
Strickland's
suit.
O.C.G.A. § 13-10-65 bars suits for recovery on public works
payment bonds "[brought after] one year from the completion of
the contract and the acceptance of the . . . construction by
the proper public authorities."
both
required.
performance,
authority."
and
Completion
acceptance
Completion and acceptance are
refers
^^to
to
action
the
by
builder's
the
public
U.S. Fidelity & Guar. Co. v. Rome Concrete Pipe
Co., 353 S.E.2d 15, 16 (Ga. 1987).
Both were finished here as
of September 14, 2011, and Strickland did not file this suit
until August 22, 2014.
16:22-17:7,
23:14-18;
See Dkt. No. 1-1; Dkt. No. 22 at
Dkt.
No.
22-8.
Thus,
his
claim
is
barred.
I. WORK WAS COMPLETED BY SEPTEMBER 14, 2011.
Work on the road project here was completed by September
14, 2011.
Georgia's statute of limitations begins to run as
of ^^completion of the actual construction work"—not the public
authority's "'complet[ion] [of the project] under its policy
and procedures."
Rome Concrete Pipe Co., 353 S.E.2d at 17.
This gives the builder clear notice as to when to expect a
lawsuit, whereas interpreting the statute otherwise would keep
the window open until a year after some bureaucratic basilica
unpredictably sends up white smoke.
Id. at 16-17.
Thus,
Georgia's rule, like other statutes of limitation, ^^prevent[s]
surprises."
Order of R.R. Telegraphers v. Ry. Express Agency,
321 U.S. 342, 348-49 (1944).
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?