First Insurance Company of Hawaii, Ltd. v. P and S Construction, Inc.
Filing
49
Decision and Order adopting in part 37 Report and Recommendations; denying 6 Motion to Dismiss. This court: 1. REJECTS the Report's conclusion regarding the subcontract's arbitration provision and holds that the provision is sufficien tly broad to bind FICOH; 2. ADOPTS the Report's recommendation to deny P&S's motion to dismiss but REJECTS the Report's recommendation to deny P&S's motion to stay. Therefore, IT IS HEREBY ORDERED that: 1. P&S's Motion to Di smiss is DENIED.2. P&S's Alternative Motion to Stay the proceedings pending completion of the contractually mandated provision under article 19.1 of the JWS / P&S subcontract is GRANTED. 3. The parties shall file a joint status report no later than March 19, 2019, and every quarter thereafter. In addition, the parties shall appear for a status hearing before the Magistrate Judge on March 27, 2019, at 9:00 a.m. Signed by Chief Judge Frances M. Tydingco-Gatewood on 12/19/2018. (fad, )
1
2
3
4
5
THE DISTRICT COURT OF GUAM
6
7
8
CIVIL CASE NO. 17-00091
FIRST INSURANCE COMPANY OF
HAWAII, LTD.,
9
Plaintiff,
DECISION AND ORDER
ON OBJECTIONS TO
MAGISTRATE JUDGE’S
REPORT AND RECOMMENDATION
10
vs.
11
P&S CONSTRUCTION, INC.,
12
Defendant.
13
14
Before the court is Defendant P&S Construction, Inc.’s (“P&S”) Objection to Magistrate
15
Judge Joaquin Manibusan, Jr.’s Report and Recommendation. See ECF No. 37. The Magistrate
16
Judge’s Report and Recommendation (“Report”) suggested that this court deny the Defendant’s
17
Motion to Dismiss Counts I and II of the complaint and further deny its request to stay Count II
18
pending the outcome of arbitration. See ECF No. 6. After reviewing the parties’ submissions and
19
relevant case law, the court hereby ACCEPTS in part and REJECTS in part the conclusions
20
within the Report for the reasons stated herein.
21
22
23
24
I.
BACKGROUND
A. Facts
This dispute stems from a subcontract between Defendant P&S, a Massachusetts-based
construction contractor, and JWS Refrigeration and Air Conditioning, Ltd. (“JWS”), a Guam1
1
based subcontractor. See Report at 1-2, ECF No. 37. Pursuant to the subcontract, JWS was to
2
upgrade the HVAC system in Building 18001 at Anderson Air Force Base. Id. at 1. The
3
subcontract required JWS to procure a performance bond. Subcontr. at ¶ 3.4, ECF No. 6-2.
4
Plaintiff First Insurance Company of Hawaii, Ltd. (“FICOH”) acted as surety on that
5
performance bond, which incorporates the subcontract by reference. Perf. Bond, ECF No. 7.
6
Prior to completion of the subcontract project, P&S terminated JWS and hired a replacement
7
contractor. Report at 2, ECF No. 37. P&S then initiated arbitration proceedings against JWS and
8
FICOH in Boston, Massachusetts. Id.
B. Procedural History
9
10
On April 13, 2017, JWS sued P&S in this court for breach of contract and other related
11
claims. See United States of America and JWS Refrigeration and Air Conditioning, Ltd. v. Fid.
12
and Deposit Co. of Maryland and P & S Construction, Inc., 17-CV-00043, Compl., ECF No. 1.
13
P&S moved to dismiss or, alternatively, to stay that suit pending the outcome of arbitration. See
14
id., Mot. Dismiss, ECF No. 6. The Magistrate Judge found that the parties had agreed to arbitrate
15
disputes arising from the subcontract, so the Magistrate Judge recommended staying the case
16
pending arbitration. Id., R. & R., ECF No. 60. This court adopted that recommendation on March
17
20, 2018, staying JWS’s suit. Id., Order, ECF No. 63.
18
On July 28, 2017, FICOH initiated the instant suit against P&S. 17-CV-00091, Compl.,
19
ECF No. 1. FICOH sought a declaratory judgment stating that (1) FICOH was not bound to
20
arbitrate with P&S, and (2) FICOH has no obligations under the bond it issued to P&S. Id. at 14,
21
16.
22
P&S moved to dismiss, or, alternatively, to stay FICOH’s suit pending the outcome of
23
arbitration between JWS, P&S, and FICOH. Mot. Dismiss, ECF No. 6. P&S argued that, because
24
FICOH’s performance bond incorporated the subcontract between JWS and P&S, FICOH is
2
1
bound to the subcontract’s arbitration provision covering “any and all claims or disputes arising
2
out of or relating to” the subcontract. See Subcontr. at ¶ 19.1, ECF No. 6-2. This court referred
3
P&S’s motion to the Magistrate Judge for issuance of a report and recommendation. See Order
4
(Sept. 8, 2017), ECF No. 10.
5
The Magistrate Judge heard argument on the motion and thereafter issued the Report.
6
See Transcript, ECF No. 34; see also R. &. R., ECF No. 37. The Report recommends that this
7
court deny Defendant’s motion to dismiss and further deny its request for a stay. R. & R. at 11,
8
ECF No. 37.
9
10
P&S objected to the Report and FICOH filed a Response to P&S’s objections. See Obj.
to R. & R., ECF No. 38; Response, ECF No. 43.
11
II.
LEGAL STANDARDS
12
In reviewing a magistrate judge’s report and recommendation, the district court “shall
13
make a de novo determination of those portions of the report . . . to which objection is made.” 28
14
U.S.C. § 636(b)(1). “[T]he court may accept, reject, or modify, in whole or in part, the findings
15
or recommendations made by the magistrate judge.” Id.
16
FICOH argues that this court should apply different standards of review to different
17
aspects of the Magistrate Judge’s Report. Response to Obj. at 6-7, ECF No. 43. That is, FICOH
18
submits that the Magistrate Judge’s recommendation regarding the motion to dismiss must be
19
reviewed de novo pursuant to § 28 U.S.C. § 636(b)(1)(B), because a motion to dismiss is a
20
dispositive matter. But FICOH contends that this court should review the recommendation as to
21
the motion to stay under the “clearly erroneous or contrary to law” standard, pursuant to § 28
22
U.S.C. § 636(b)(1)(A), because a motion to stay is a nondispositive pretrial matter. Neither party
23
cites to authority on this issue—that is, whether a district court should review de novo a
24
Magistrate Judge’s recommendation as to a motion to dismiss or stay, or whether a district court
3
1
should apply different standards of review, as FICOH contends.
2
This court referred Defendant’s motion in its entirety to the Magistrate Judge, pursuant to
3
28 U.S.C. § 636(b)(1)(B). See Order, ECF No. 10. This court’s order of referral did not
4
differentiate the motion to dismiss from the motion to stay. Absent that order of referral, this
5
court would have directly ruled upon Defendants’ motion. Therefore, it would be inappropriate
6
for this court to apply anything less than de novo review to the Magistrate Judge’s Report.
7
Accordingly, this court proceeds with de novo review.
8
III.
DISCUSSION
9
P&S moves to dismiss or, alternatively, to stay this case pending resolution of the
10
arbitration proceeding between &S and FICOH. Mot. Dismiss at 1, ECF No. 6. P&S argues that
11
FICOH—as surety of JWS—is subject to a binding arbitration clause in the subcontract between
12
JWS and P&S. Id. at 1-2. FICOH argues that is not bound to arbitrate because the subcontract’s
13
arbitration clause is insufficiently broad to bind a surety that did not sign the subcontract. Opp.,
14
ECF No. 18. FICOH also argues in the alternative that the arbitration provision is
15
unconscionable. Id. at 17.
16
A. The arbitration clause is sufficiently broad to bind FICOH
17
The first issue is whether FICOH is bound by the arbitration clause contained within the
18
JWS / P&S subcontract, as P&S claims, because FICOH’s performance bond incorporated the
19
terms of the JWS / P&S contract. The arbitration clause within the subcontract provides in
20
relevant part:
21
22
23
24
Subcontractor agrees that any and all claims or disputes arising out of or relating
to this Agreement or the breach thereof shall be decided, at the sole discretion of
Contractor, by submission to (1) arbitration in accordance with the Construction
Industry Arbitration Rules of the American Arbitration Association in a venue
selected solely by Contractor or (2) judicial decision by the Middlesex County
Superior Court in the Commonwealth of Massachusetts . . . .
4
1
Subcontr. at ¶ 19.1, ECF No. 6-2. The Magistrate Judge found that this language “limit[ed] the
2
scope of the arbitration provision to that between Subcontractor and Contractor.” R. & R. at 10,
3
ECF No. 37. Therefore, the Magistrate Judge concluded that the arbitration provision “is not
4
broad enough to cover the dispute between [P&S] and [FICOH].” Id. at 11.
5
In its objection, P&S cites several circuit courts which have concluded that a surety
6
becomes bound by an arbitration provision within a contract that is adopted by reference in the
7
surety’s performance bond. Obj. to R. & R. at 15-16, ECF No. 38; see, e.g., Great Am. Ins. Co. v.
8
Hinkle Contracting Corp., 497 Fed. Appx. 348, 354-55 (4th Cir. 2012); United States Fid. Guar.
9
Co. v. West Point Constr. Co., 837 F.2d 1507, 1508 (11th Cir. 1988); Exch. Mut. Ins. Co. v.
10
Haskell Co., 742 F.2d 274, 276 (6th Cir. 1984); Warren Bros. Co. v. Cardi Corp., 471 F.2d
11
1304, 1308 (1st Cir. 1973). These decisions are rooted in the federal policy favoring arbitration
12
agreements and the logic that a contractual obligation to arbitrate would “be rendered
13
meaningless by the expedient of bringing suit on a statutory payment bond.” Warren Bros. Co.,
14
471 F.2d at 1308. FICOH counters with several district court cases finding that an arbitration
15
provision was insufficiently broad to bind the surety. Response to Obj. at 16, ECF No. 43. W.
16
Sur. Co. v. U.S. Eng’g Co., 211 F. Supp. 3d 302 (D.D.C. 2016); Island Ins. Co. v. NORESCO,
17
LLC., 2012 WL 6629588 (D. Haw. 2012).
18
As noted by the Island Insurance court, the split in these decisions can be explained by
19
differing language within the underlying arbitration provisions. 2012 WL 6629588, at * 7. Courts
20
hold sureties bound when the underlying contract’s arbitration provision is broadly written to
21
cover “all disputes arising” out of the contract. Id. By contrast, sureties are not bound when the
22
arbitration provision contains language that limits the arbitration provision to the original
23
contracting parties. Id. For example, the provision at issue in Island Insurance provided that
24
“[c]laims, disputes, and matters in question arising out of or relating to this Agreement as to
5
1
matters solely between Contractor and Subcontractor . . . shall be decided by arbitration.” Id. at
2
*8. The Island Insurance court reasoned that “matters solely between Contractor and
3
Subcontractor” expressly limited the arbitration agreement to those two parties, so it did not
4
cover the surety. Id.
5
In the case before this court, the subcontract’s arbitration provision is broadly written to
6
cover “any and all claims or disputes arising out of or relating” to the subcontract. Subcontr. at ¶
7
19.1, ECF No. 6-2. The introductory phrase “Subcontractor agrees” does not limit that broad
8
language; it simply expresses that JWS was agreeing to P&S’s term. But the actual term is
9
identical to language contained within arbitration provisions that other courts have consistently
10
determined to be sufficiently broad to cover nonsignatories such as sureties. See, e.g., Exch.
11
Mut., 742 F.2d at 275 (holding that arbitration provision covering “[a]ll claims, disputes and
12
other matters in question arising out of, or relating to this contract or the breach thereof” was
13
sufficiently broad to bind a surety). Thus, this court concludes that the subcontract’s arbitration
14
provision is sufficiently broad to bind FICOH.
15
In addition to analyzing the subcontract provision, the Magistrate Judge found language
16
within the performance bond itself evinced the surety’s intent not to be bound by the
17
subcontract’s arbitration provision. R. & R. at 11, ECF No. 38. The relevant language within the
18
performance bond states: “Any suit under this bond must be instituted before the expiration of
19
two (2) years from the date on which final payment under the subcontract becomes due.” Id. at
20
10. The Magistrate Judge reasoned that “suit” refers to a proceeding “in a court of law,” as
21
opposed to an arbitration proceeding, so, by including that word, FICOH evinced an intent not to
22
arbitrate. Id. at 11.
23
It is true that the Supreme Court of Guam has defined “suit”—in a different context—to
24
mean “any proceeding by a party or parties against another in a court of law.” AG of Guam v.
6
1
Gutierrez, 2011 Guam 10 (emphasis added) (internal quotation marks omitted). However, “the
2
term ‘suit’ is ambiguous and can reasonably be interpreted to include any ‘attempt to gain an end
3
by any legal process.’” Anderson Bros., Inc. v. St. Paul Fire and Marine Ins. Co., 729 F.3d 923,
4
933 (9th Cir. 2013).
5
P&S cites to three district courts that have considered this very issue and concluded that a
6
performance bond’s reference to “suit” was “merely setting a statute of limitations in the event of
7
litigation and not evidencing an intent to preempt the arbitration clause incorporated by
8
reference.” Rashid v. United States Fid. & Guar. Co., 1992 U.S. Dist. LEXIS 22914 (S.D. W.
9
Va. Sept. 28, 1992); Transamerica Premier Insur. Co. v. Collins & Co., 735 F. Supp. 1050, 1052
10
(N.D. Ga. 1990); Cianbro Corp. v. Empresa Nacional de Ingenieria y Tecnologia, 697 F. Supp.
11
15, 19 (D. Me. 1988). This court agrees. Even assuming that the performance bond could limit
12
the subcontract’s arbitration provision—a dubious proposition, given that P&S is not a signatory
13
to the performance bond—this court concludes that the term “suit” within the performance bond
14
was not intended to have that effect. The sentence in which “suit” occurs is merely meant to
15
establish a two-year limitations period.
16
B. Whether the arbitration clause is unconscionable
17
As an alternative argument, FICOH contends that the subcontract’s arbitration clause is
18
unenforceable under Nagrampa v. Mailcoups, Inc., 469 F.3d at 1280 (9th Cir. 2006). Response
19
to Mot. Dismiss at 17, ECF No. 18. P&S counters on two grounds. Reply at 10, ECF No. 25. In
20
addition to refuting FICOH’s unconscionability arguments, P&S argues that the question of
21
unconscionability is one for the arbitrator to decide. Id.
22
Generally, a court determines whether an arbitration clause is valid. Brennan v. Opus
23
Bank, 796 F.3d 1125, 1130 (9th Cir. 2015). However, this issue “can be expressly delegated to
24
the arbitrator where the parties clearly and unmistakably provide otherwise.” Id. (internal
7
1
quotation marks omitted). The Ninth Circuit has held that incorporation of the American
2
Arbitration Association (“AAA”) rules constitutes “clear and unmistakable evidence that
3
contracting parties agreed to arbitrate arbitrability.” Id.
4
Here, the arbitration clause provided two dispute resolution mechanisms for P&S to
5
choose among: “arbitration in accordance with the Construction Industry Arbitration Rules of
6
the American Arbitration Association” or “judicial decision by the Middlesex County Superior
7
Court in the Commonwealth of Massachusetts.” Subcontr. at ¶ 19.1, ECF No. 6-2. Thus, unlike
8
the agreement in Brennan which unequivocally provided that “any controversy or claim . . . shall
9
be settled by binding arbitration in accordance with the Rules of the American Arbitration
10
Association,” 796 F.3d at 1128, the subcontract here merely indicates that P&S, “at its sole
11
discretion,” can choose to resolve this dispute under the AAA’s rules. Subcontr. at ¶ 19.1, ECF
12
No. 6-2. That P&S retained the option to invoke the AAA rules does not constitute “clear and
13
unmistakable evidence that contracting parties agreed to arbitrate arbitrability.” Brennan, 796
14
F.3d at 1130. Thus, it is for this court to decide whether the arbitration provision is
15
unconscionable.
16
Both parties cite to California law regarding the issue of unconscionability, perhaps due
17
to the lack of Guam law on this issue. See Response to Mot. Dismiss at 17, ECF No. 18; Reply at
18
10, ECF No. 25. Under California law, “[a]n agreement to arbitrate is unconscionable only if it
19
both procedurally and substantively unconscionable.” Circuit City Stores, Inc. v. Ahmed, 283
20
F.3d 1198, 1199 (9th Cir. 2002). Procedural unconscionability focuses on “‘oppression’ or
21
‘surprise’ due to unequal bargaining power.” Mohamed v. Uber Techs, Inc., 848 F.3d 1201, 1210
22
(9th Cir. 2016). Substantive unconscionability depends on whether the terms themselves are “so
23
one sided as to ‘shock the conscience.’” Baltazar v. Forever 21, Inc., 367 P.3d 6, 11 (Cal. 2016).
24
8
1
There is no evidence of procedural unconscionability in this case. All parties to this
2
dispute are sophisticated businesses, and the delegation provision is clearly labeled “Dispute
3
Resolution” within the subcontract. Subcontr. at ¶ 19.1, ECF No. 6-2. While the unilateral
4
discretion afforded to P&S is indeed one-sided, it is not so patently unjust so as to rise to
5
substantive unconscionability. See M.A. Mortenson Co. v. Saunders Concrete Co., 676 F.3d
6
1153, 1158 (8th Cir. 2012) (rejecting the argument “that an arbitration agreement is substantively
7
unconscionable because it gives one party the sole discretion to choose arbitration”). This court
8
therefore concludes that the arbitration provision is valid.
IV.
9
10
11
12
13
14
15
CONCLUSION
For the foregoing reasons, the court hereby ACCEPTS in part and REJECTS in part the
Report. Specifically, this court:
1. REJECTS the Report’s conclusion regarding the subcontract’s arbitration provision
and holds that the provision is sufficiently broad to bind FICOH;
2. ADOPTS the Report’s recommendation to deny P&S’s motion to dismiss but
REJECTS the Report’s recommendation to deny P&S’s motion to stay.
16
Therefore, IT IS HEREBY ORDERED that:
17
1. P&S’s Motion to Dismiss is DENIED.
18
2. P&S.’s Alternative Motion to Stay the proceedings pending completion of the
19
contractually mandated provision under article 19.1 of the JWS / P&S subcontract is
20
GRANTED.
21
3. The parties shall file a joint status report no later than March 19, 2019, and every
22
quarter thereafter. In addition, the parties shall appear for a status hearing before the
23
Magistrate Judge on March 27, 2019, at 9:00 a.m.
24
SO ORDERED.
/s/ Frances M. Tydingco-Gatewood
Chief Judge
9
Dated: Dec 19, 2018
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?