U.S. Composite Pipe South, LLC v. Frank Coluccio Construction Company, Inc. et al
Filing
163
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR SUMMARY JUDGMENT, OR FOR PARTIAL SUMMARY JUDGMENT re: 87 , 94 , 106 , 114 , 121 . Signed by JUDGE J. MICHAEL SEABRIGHT on 10/7/2014. Excerpt of Conclusion: "[T]he Motions and Substantive Joinder (Doc. Nos. 87 , 94 , 106 , 114 , and 121 ) are DENIED, except for Composite Pipe's claim that it is entitled to the second installment payment...." "To that extent only, the court GRANTS Composite Pipe's Motion for Summary Judgment in part. Doc No. 106 . All other issues remain for trial." Written Order follows hearing on SJ motions held 9/29/2014. Minutes of hearing: doc no . 162 ]. (afc)CERTIFICATE OF SERVICEParticipants registered to receive electronic notifications received this document electronically at the e-mail address listed on the Notice of Electronic Filing (NEF).
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF HAWAII
U.S. COMPOSITE PIPE SOUTH,
LLC,
)
)
)
Plaintiff,
)
)
vs.
)
)
FRANK COLUCCIO
)
CONSTRUCTION COMPANY, and )
SAFECO INSURANCE COMPANY )
OF AMERICA,
)
)
Defendants.
)
_______________________________ )
FRANK COLUCCIO
)
CONSTRUCTION COMPANY,
)
)
Counterclaimant,
)
)
vs.
)
)
U.S. COMPOSITE PIPE SOUTH,
)
LLC,
)
)
Counterclaim Defendant,
)
)
and
)
)
WESTCHESTER FIRE INSURANCE )
COMPANY, and CITY AND
)
COUNTY OF HONOLULU,
)
)
Additional Counterclaim
)
Defendants.
)
_______________________________ )
CIVIL NO. 12-00538 JMS-KSC
ORDER GRANTING IN PART AND
DENYING IN PART MOTIONS FOR
SUMMARY JUDGMENT, OR FOR
PARTIAL SUMMARY JUDGMENT
ORDER GRANTING IN PART AND DENYING IN PART MOTIONS FOR
SUMMARY JUDGMENT, OR FOR PARTIAL SUMMARY JUDGMENT
I. INTRODUCTION
Currently before the court are several Motions for Summary
Judgment, or for Partial Summary Judgment, in this diversity action stemming
from a $37 million sewer construction contract (the “Beachwalk Contract”)
between Counterclaim Defendant City and County of Honolulu (the “City”) and
Defendant/Counterclaimant Frank Coluccio Construction Company (“FCCC”).
At one level, the dispute is relatively simple -- is Plaintiff U.S.
Composite Pipe South, LLC (“Composite Pipe”) entitled to full payment from
FCCC for specialized sewage pipe that Composite Pipe supplied for the
Beachwalk Contract, or, on the other hand, is FCCC entitled to damages and to
withhold payment because of problems with the pipe? But in addressing those
questions, the case becomes highly complex, both procedurally and factually. The
Motions from all sides raise a variety of issues ranging from contractual
interpretation and civil engineering to possible applications of provisions of
Hawaii’s Uniform Commercial Code (“UCC”).
After considerable effort reviewing the lengthy evidentiary record,
the court readily concludes that a myriad of genuine issues of material fact exist.
2
Accordingly, except as to one issue, the Motions are DENIED. The evidence is
undisputed, however, that Composite Pipe is entitled at this stage to the second (of
three) installment payments for the pipe at issue, and Composite Pipe’s Motion is
GRANTED to that extent.
II. BACKGROUND
Before setting forth the basic background, it bears emphasizing that
the record contains obvious disputes of fact as to many salient points -- for
example, the precise contractual obligations of the parties; the circumstances
leading to the change in pipe at issue; whether the pipe met proper standards;
whether the pipe was delivered late; responsibility for the July 2012 flooding of
the sewage shaft; and whether that inundation caused damage to FCCC’s
equipment that, in turn, caused foreseeable consequential damages regarding a
different sewage construction contract at Ala Moana Beach Park between FCCC
and the City.
The parties -- with counsel experienced in commercial and
construction litigation -- know that the court cannot resolve disputes of material
fact at the summary judgment stage. See, e.g., McGinest v. GTE Serv. Corp., 360
F.3d 1103, 1113 n.5 (9th Cir. 2004) (“[I]t is axiomatic that disputes about material
facts and credibility determinations must be resolved at trial, not on summary
3
judgment.”). In that sense, it is not helpful for the parties to argue, as they
sometimes do here, that opposing testimony is false or not credible. See, e.g.,
Dominguez-Curry v. Nev. Transp. Dep’t, 424 F.3d 1027, 1036 (9th Cir. 2005)
(“[T]he judge does not weigh disputed evidence with respect to a disputed material
fact. Nor does the judge make credibility determinations with respect to
statements made in affidavits, answers to interrogatories, admissions, or
depositions.”) (quoting T.W. Elec. Serv., Inc. v. Pac. Elec. Contractors Ass’n, 809
F.2d 626, 630 (9th Cir. 1987)).
With this background, the court sets forth the details of the action
only as necessary to establish the key disputes of fact, and to make certain rulings
of law that might focus further proceedings in this matter (including the non-jury
trial currently set to begin on December 9, 2014).
A.
The Beachwalk Contract and Composite Pipe’s Complaint
The June 23, 2009 Beachwalk Contract between the City and FCCC
was for construction of a “Beachwalk [Wastewater Pump Station] to Ala Moana
Park Sewer: Phase 1 -- Force Main System[.]” Doc. No. 1, Compl. ¶ 7. Among
other things, the Beachwalk Contract involved the placement of sewage piping
from Waikiki to a station near Ala Moana Park, and required installation of a
specialized double-curved section of pipe to be placed under the Ala Wai Canal.
4
The project was necessitated by a consent decree between the City and the
Environmental Protection Agency resulting, at least in part, from a well-publicized
sewage failure in 2006.
For this purpose, Composite Pipe provided $3.5 million worth of
“Meyer Pipe” (manufactured by a German company, Meyer Rohr + Schacht,
which is now insolvent) to FCCC pursuant to a November 13, 2011 Purchase
Order (the “Purchase Order”) between Composite Pipe and FCCC.1 (That
Purchase Order led to “Change Order No. 4” of the Beachwalk Contract.)
Composite Pipe was to be paid in installments by FCCC: fifty percent upon
signing of the Purchase Order, twenty five percent upon delivery to the job site,
and twenty five percent after installation and pressure testing. Id. ¶ 12. Allegedly,
Composite Pipe delivered the pipe to FCCC, FCCC installed it, and the City
eventually accepted the Beachwalk Contract project after pressure testing. FCCC
paid the first installment to Composite Pipe, but has allegedly refused or
wrongfully delayed payment of the second and third installments. Id. ¶¶ 28, 30.2
1
Composite Pipe’s surety is Additional Counterclaim Defendant Westchester Fire
Insurance Company (“Westchester”). Doc. No. 42, Am. Counterclaim ¶¶ 3, 77. Similarly,
FCCC’s surety for payment under the Purchase Order is Defendant Safeco Insurance Company of
America (“Safeco”). Doc. No. 1, Compl. ¶¶ 18, 19.
2
The City paid FCCC for the second increment (which has not, in turn, been paid to
Composite Pipe), but the City has not paid FCCC (pending this litigation, apparently at the
(continued...)
5
Composite Pipe filed this action to recover over $1.8 million as payment for those
installments with interest, as well as attorneys’ fees and costs. Id. ¶ 34.
B.
FCCC’s Amended Counterclaim
As part of its defense, FCCC filed an Amended Counterclaim against
Composite Pipe, joining the City as an “Additional Counterclaim Defendant”
under Federal Rules of Civil Procedure 13(a) and (h). FCCC contends it need not
make the final payments because (1) the pipe did not meet certain specifications
and/or was defective; (2) FCCC is entitled to liquidated damages because the pipe
was delivered late; and (3) FCCC is entitled to a large offset (or related damages
from the City) because of a breach of contract and negligence by Composite Pipe
and/or the City. See generally Doc. No. 42, Am. Counterclaim.
The Amended Counterclaim makes detailed allegations about how
and why the Meyer Pipe was chosen -- it was selected by the City as a replacement
for “Al Watari Pipe” from a Kuwaiti firm that was described, and relied upon, in
City bidding documents when FCCC originally bid on the Beachwalk Contract.
The Amended Counterclaim alleges some of the specific circumstances (e.g.,
change orders, negotiations, and communications with the City and its retained
2
(...continued)
request of Composite Pipe) for the third increment. See Doc. No. 142-20, FCCC Ex. 15,
Franklin Dep. at 116.
6
managing agent, AECOM Technology Corporation) which FCCC believes
establish that the City is responsible for negotiating the November 2011 Purchase
Order, and choosing, approving, and/or later accepting the Meyer Pipe.3
FCCC alleges that the Meyer Pipe was defective and did not meet
engineering specifications set forth in the Purchase Order and/or Beachwalk
Contract (including Change Order No. 4). And it describes further problems that
arose during and after installation, leading to questions as to who was responsible
for those problems and whether FCCC is entitled to consequential or other
damages as a result. See generally id. at pp. 7-21.
In particular, FCCC alleges that during installation of the pipe, a
“catastrophic” failure occurred on or about July 7, 2012, resulting in an inundation
and flooding of “the shaft and pipe train.” Id. ¶ 62. This failure “caused property
damage to FCCC’s microtunneling boring machine and other equipment, and over
3
For example, FCCC alleges:
The City unilaterally chose the Meyer Pipe, and then unilaterally
chose to be the sole negotiator of the Purchase Order, over the
objections of FCCC, and then ordered FCCC to sign the purchase
order which the City had negotiated with [Composite Pipe]. The
correspondence, change order, and other documentation regarding
this City-mandated transaction (including the City’s “informal”
ordering of the replacement gaskets), all show that the Meyer Pipe
was the choice of and is the responsibility of the City.
Doc. No. 42, Am. Counterclaim ¶ 34.
7
two months of delay for dewatering and repair operations.” Id. Composite Pipe
and the City dispute that there was anything wrong with the Meyer Pipe, and
proffer evidence (in turn, disputed by FCCC) that the July 7, 2012 inundation was
not caused by any problem with the pipe, but rather was caused by FCCC’s own
installation errors.
Separately, FCCC alleges that “Meyer Pipe No. 19 . . . was used with
an Intermediate Jacking Station and broke during initial coupling on Saturday,
September 15, 2012.” Id. ¶ 68. “The broken pipes caused delays as the broken
pipe was removed and the situation analyzed to determine the cause.” Id. “The
damages caused by the delays [to FCCC] were in an amount not less than
$119,609.84.” Id. ¶ 73. The parties dispute whether the cause of this September
15, 2012 breakage was FCCC’s installation error (as Composite Pipe and the City
contend), or the result of Composite Pipe’s inadequate or improper notification or
labeling as to the characteristics of different pieces of pipe. Id. ¶¶ 70-72.
And FCCC seeks consequential damages resulting from the loss of
use of its specialized microtunneling boring machine (or related delay), and in
particular, costs related to a separate October 2011 sewage construction contract
between FCCC and the City (the “Ala Moana Contract”). Id. ¶¶ 78, 116. The
theory is that damage to the machine, or delay resulting from the inundation, in
8
turn affected FCCC in its implementation of the Ala Moana Contract. The City
“through oral discussions was aware that FCCC was planning on using the same
[microtunneling boring] machine on both [the Beachwalk and Ala Moana]
projects, which was why the Ala Moana Bid [by FCCC] was over 25 million
dollars below the next lowest bid.” Doc. No. 145-1, Don Bergman Decl. ¶ 3.
The Amended Counterclaim consists of five causes of action against
Composite Pipe, Westchester, or the City. Count One alleges “breach of contract
and breach of warranty” against Composite Pipe as follows:
83. FCCC has performed all of its obligations under the
Purchase Order.
84. [Composite Pipe] has breached the Purchase Order
by reason of its (a) failure to timely deliver the
[Composite Pipe] Meyer Pipe; (b) delivery of pipe that
did not conform to the requirements of the Purchase
Order; (c) breach of express and implied warranties; and
(d) delivery of pipes with defects in material and/or
which did not comport with standards of proper
workmanship.
85. FCCC has suffered damages as a direct and
proximate cause of [Composite Pipe’s] breaches of
contract, including but not limited to direct damages and
consequential damages from the effect of lost time on the
Ala Moana Contract with the City, in an amount to be
proved at trial.[4]
4
At the September 29, 2014 hearing, FCCC represented to the court and the other parties
(continued...)
9
86. FCCC is also entitled to $78,000 in liquidated
damages.
Doc. No. 42, Am. Counterclaim at 22.
Count Two asserts a claim against Westchester based on its
performance bond to satisfy Composite Pipe’s obligations. Id. at 23.
Count Three asserts negligence against Composite Pipe and the City
as follows:
92. [Composite Pipe] had a duty to provide pipe which
met certain standards of care in it manufacture.
93. The City, by warranting the adequacy of the
[Composite Pipe] Meyer Pipe, and by inspecting and
accepting it, also had a duty of due care.
94. [Composite Pipe] breached its duty by supplying
defective pipe.
95. The City breached its duty by accepting and
warranting the use of defective pipe.
4
(...continued)
that it was not pursuing this allegation as to Composite Pipe, i.e., that it was not seeking
“consequential damages from the effect of lost time on the Ala Moana Contract with the City”
from Composite Pipe (only from the City). Accordingly, in reliance on that representation, the
court considers consequential damages related to the Ala Moana Contract to be sought only as to
the City. In any event, in contrast to the City as discussed below, FCCC has pointed to no
evidence that could indicate that any such consequential damages regarding the Ala Moana
Contract -- which did not involve Composite Pipe -- were reasonably foreseeable to Composite
Pipe. See, e.g., Amfac, Inc. v. Waikiki Beachcomber Inv. Co., 74 Haw. 85, 128, 839 P.2d 10, 33
(1992) (holding that consequential damages for breach of contract are recoverable only “as may
reasonably be supposed to have been in the contemplation of the parties at the time the contract
was entered into.”) (quoting Jones v. Johnson, 41 Haw. 389, 393 (1956)).
10
96. As a result of that breach, FCCC suffered property
damage to its micro-tunneling boring machine, and other
equipment, and other damages, in an amount to be
determined at trial, for which [Composite Pipe] and the
City are jointly and severally liable.
Id. at 24.
Count Four alleges misrepresentation against Composite Pipe as
follows:
98. [Composite Pipe] represented that all of the pipes
without a steel coupling bell were of the same
dimensions, and could be used as a lead pipe for an
[intermediate jacking station].
99. This representation was made by or on behalf of
persons who either had a financial interest in the
transaction or a duty to provide accurate information.
100. FCCC reasonably relied on this representation.
101. This representation was false.
102. As a result of this representation, FCCC has been
damaged in an amount to be proved at trial.
Id. at 24-25.
Finally, Count Five alleges “breach of contract and implied
warranties” against the City. In particular, FCCC lists several implied and express
warranties that City allegedly made to FCCC regarding the Meyer Pipe’s
specifications and performance. Id. ¶¶ 104-110. FCCC concludes:
11
As a result of the breaches by the City of its contractual
obligations and its express and implied warranties, the
City is liable to FCCC and FCCC has been damaged in
an amount to be proved at trial, including but not limited
to the following damages:
•
•
•
•
•
•
Standby Delay from November 11/1/2012 to
6/15/2012: $3,435,290.72
Consequential Acceleration Costs for Ala Moana
Project: $4,979,654.01
Assembly and Installation of Additional IJS:
$71,548.64
Purchase of Tunnel Repair Bands: $84,591.90
Shaft Inundation (Recovery/Standby) 7/7/2012 to
9/6/2012: $2,198,955.34
Loss Due to Meyer Pipe #19 Broken + Replaced =
$119,609.84.
Id. ¶ 116.
C.
Procedural Background
Four Motions are pending: (1) FCCC’s Motion for Partial Summary
Judgment (regarding breach of contract and payment), Doc. No. 87; (2) Composite
Pipe’s Motion for Summary Judgment, Doc. No. 106; (3) FCCC’s Motion for
Partial Summary Judgment on the Issue of Plaintiff’s Defense to Liquidated
Damages, Doc. No. 94; and (4) the City’s Motion for Partial Summary Judgment
on the Issue of Consequential Damages, Doc. No.114. Additionally, the City filed
a Substantive Joinder to Composite Pipe’s Motion, seeking similar relief on behalf
12
of the City. Doc. No. 121.5
Several of the Motions were originally set for hearing on July 28,
2014, but that hearing was continued at the request of counsel and after initial
limited review of the Motions by the court. See Doc. Nos. 117, 119. (Meanwhile,
on July 30, 2014, the court granted FCCC’s Motion to Strike the City’s affirmative
defense of lack of subject matter jurisdiction. See Doc. No. 130.) The court
deemed the pending Motions to be “related motions” under Local Rule 7.9, and
Oppositions and Replies were filed on September 8, 2014, and September 15,
2014. See Doc. Nos. 141, 144, 148, 151, 154, 155. The court held a hearing on
September 29, 2014.
///
///
///
5
The court DENIES FCCC’s request to strike the City’s Substantive Joinder as being
filed late, or in contravention of a court order. See Doc. No. 141, FCCC’s Opp’n at 2. Under
Local Rule 7.9, the Substantive Joinder was due “within seven (7) days of the filing of the
motion . . . joined in.” Composite Pipe’s Motion was filed on July 7, 2014, and the City’s
Substantive Joinder was thus timely filed on July 14, 2014. (The City had previously sought to
extend the July 14, 2014 deadline, but the court denied that request, see Doc. No. 120, and FCCC
apparently misinterpreted that denial as precluding any substantive joinder at all.)
Under Local Rule 7.9, a substantive joinder “means a joinder based on a memorandum
supplementing the motion . . . joined in.” The City’s Substantive Joinder “supplement[s] the
motion joined in” by raising additional arguments for why the court should grant the City similar
relief to what Composite Pipe is seeking. Because the court otherwise denies the Substantive
Joinder, it need not address whether the Substantive Joinder raises issues beyond merely
“supplementing” Composite Pipe’s Motion.
13
III. STANDARD OF REVIEW
Summary judgment is proper where there is no genuine issue of
material fact and the moving party is entitled to judgment as a matter of law. Fed.
R. Civ. P. 56(a). Rule 56(a) mandates summary judgment “against a party who
fails to make a showing sufficient to establish the existence of an element essential
to the party’s case, and on which that party will bear the burden of proof at trial.”
Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986); see also Broussard v. Univ. of
Cal. at Berkeley, 192 F.3d 1252, 1258 (9th Cir. 1999).
“A party seeking summary judgment bears the initial burden of
informing the court of the basis for its motion and of identifying those portions of
the pleadings and discovery responses that demonstrate the absence of a genuine
issue of material fact.” Soremekun v. Thrifty Payless, Inc., 509 F.3d 978, 984 (9th
Cir. 2007) (citing Celotex, 477 U.S. at 323); see also Jespersen v. Harrah’s
Operating Co., 392 F.3d 1076, 1079 (9th Cir. 2004). “When the moving party has
carried its burden under Rule 56[(a)], its opponent must do more than simply show
that there is some metaphysical doubt as to the material facts [and] come forward
with specific facts showing that there is a genuine issue for trial.” Matsushita
Elec. Indus. Co. v. Zenith Radio, 475 U.S. 574, 586-87 (1986) (citation and
internal quotation signals omitted); see also Anderson v. Liberty Lobby, Inc., 477
14
U.S. 242, 247-48 (1986) (stating that a party cannot “rest upon the mere
allegations or denials of his pleading” in opposing summary judgment).
“An issue is ‘genuine’ only if there is a sufficient evidentiary basis on
which a reasonable fact finder could find for the nonmoving party, and a dispute is
‘material’ only if it could affect the outcome of the suit under the governing law.”
In re Barboza, 545 F.3d 702, 707 (9th Cir. 2008) (citing Anderson, 477 U.S. at
248). When considering the evidence on a motion for summary judgment, the
court must draw all reasonable inferences on behalf of the nonmoving party.
Matsushita Elec. Indus. Co., 475 U.S. at 587; see also Posey v. Lake Pend Oreille
Sch. Dist. No. 84, 546 F.3d 1121, 1126 (9th Cir. 2008) (stating that “the evidence
of [the nonmovant] is to be believed, and all justifiable inferences are to be drawn
in his favor.” (citations omitted)).
IV. DISCUSSION
The Motions and Substantive Joinder raise two general categories of
issues: (1) those addressing the Complaint (e.g., whether Composite Pipe is
entitled to the remaining payments for the Meyer Pipe), and (2) those addressing
the Amended Counterclaim (e.g., whether FCCC is entitled to direct, liquidated, or
consequential damages -- either by way of set-off or separately -- because of the
condition of the pipe). The court addresses the Motions as they relate to those two
15
general categories.
A.
Whether Composite Pipe Is Entitled to Remaining Payments from
FCCC
Paragraph 10.1 of the Purchase Order provides that FCCC is to pay
Composite Pipe, “[u]nless otherwise specified,” as follows:
Down payment of 50% of the total value of the order to
be paid upon receiving the signed purchase order, 25%
of the total value of the order to be paid upon delivery of
the pipe on the jobsite (based on signed delivery
documents), and the remaining 25% to be paid
immediately after pipe is installed and satisfactorily
pressure tested (50 psi for one hour).
Doc. No. 103-5, Pl.’s Ex. 1 at 5-6. FCCC made the first payment of fifty percent;
this action revolves around the second and third payments, which the court
addresses separately (beginning with the third).
1.
Questions of Fact Preclude Summary Judgment in Favor of Either
Party as to the Third (Or Final) Payment
FCCC moves for partial summary judgment, Doc. No. 87, asserting
that, as a matter of law, it need not make final payment because the pipe was
defective and did not satisfy the specifications of the Purchase Order, i.e., the pipe
was not “satisfactorily pressure tested (50 psi for one hour).” Doc. No. 103-5,
Pl.’s Ex. 1 at 6. On the other hand, Composite Pipe not only disputes that
assertion, but moves for summary judgment on its own behalf, contending that it is
16
undisputed that it is entitled to full payment. Doc. No. 106.
FCCC claims that the specifications call for passing a hydrotest “at 50
psi with no pressure drop for one hour” (i.e., no leaks for one hour). According to
post-installation testing, the system did not meet that standard. See, e.g., Doc. No.
88-1, Tim Pearia Decl. ¶ 8 (“The Meyer Pipe was hydrotested twice on November
10, 2012, and failed to hold pressure of 50 psi.”); id. ¶ 9 (“The Meyer Pipe was
hydrotested again on November 13, 2012, and failed to hold pressure of 50 psi.”);
id. ¶¶ 10, 11 (similar); Doc. No. 88-9, FCCC Ex. 7 (similar); Doc. No. 88-11,
FCCC Ex. 9 (“The pipe did not hold the pressure.”). FCCC cites to evidence
indicating that the parties intended such a standard when the Meyer Pipe was
selected. See, e.g., Doc. No. 88-5, FCCC Ex. 3 (“25% [a]fter successful in situ
hydrostatis pressure test (50 psi w/ zero drip for 1 Hr.)”); Doc. No. 88-6, FCCC
Ex. 4 (“Payment Terms are acceptable per K.T.I & TRI. . . . 25% FOB Hawaii;
25% after successful in situ hydrostatic pressure test (50 psi w/zero drop for 1
hour)”); Doc. No. 88-8, FCCC Ex. 6 (“Contractor shall hydrotest the pipe at 50 psi
for 1 hour with no allowable pressure drop.”). Accordingly, FCCC seeks partial
summary judgment as to Composite Pipe’s claim for payment against FCCC.
But there is a dispute of material fact as to whether the pipe was
actually required to “hold pressure” with “zero drop for one hour.” Composite
17
Pipe argues that nothing in the Purchase Order says “zero drop” -- it simply says
“50 psi for one hour.” Composite Pipe also argues that paragraph 10.1 of the
Purchase Order concerns only the timing of payment, and the actual pipe
specifications are covered in the Beachwalk Contract, sections of which are
incorporated into the Purchase Order. In any event, Composite Pipe points out
that the City ultimately changed the specifications in the Beachwalk Contract
(after the November 2012 hydrostatic testing) to allow for loss of pressure “up to a
rate of 0.5 psi every 10 minutes.” Doc. No. 103-1, Bezhad Basiri Decl. ¶ 4; Doc.
No. 103-18, Pl.’s Ex. 14. Thus, Composite Pipe argues that, even if the pipe did
not meet requirements in the Purchase Order, FCCC has not been damaged
because the City accepted the final project.
The intent of the parties is disputed, and the language of the Purchase
Order is ambiguous. Some evidence indicates that the parties to the Purchase
Order (Composite Pipe and FCCC) may indeed have intended the pipe to have no
pressure drop for one hour of testing. See, e.g., Doc. No. 88-6, FCCC Ex. 4; Doc.
No. 88-8, FCCC Ex. 6. But there is evidence to the contrary. See, e.g., Doc. No.
103-1, Basiri Decl. ¶ 4. And even if the City ultimately changed certain
specifications in the Beachwalk Contract, the City is not a party to the Purchase
Order -- those specifications may not necessarily control the requirements of the
18
Purchase Order. Further, there is evidence that all parties (including the City)
were involved in setting the terms of the Purchase Order. See, e.g., Doc. No. 1032, Kenneth Thompson Decl. ¶ 7.
Moreover, even if the Beachwalk Contract’s original standards
control, there is ample evidence that the Meyer Pipe differed in many respects
from the Al-Watari Pipe that was originally contemplated by all sides when the
Beachwalk Contract was signed in 2009. See, e.g., Doc. No. 142-3, Don Bergman
Decl. ¶¶ 6-11. Evidence indicates that FCCC was therefore concerned about the
quality of the Meyer Pipe, and documents indicates that FCCC insisted on express
warranties from Composite Pipe, and that all parties were involved with
discussions about “zero” leakage for one hour. See, e.g., id. ¶¶ 15, 16; Doc. No.
142-12, FCCC Ex. 7; Doc. No. 142-13, FCCC Ex. 8.
It is premature to address how FCCC might have been damaged if the
pipe did not meet specifications. FCCC claims that “leakage would subject FCCC
to potential [future] claims” and thus it “was well within its right to insist that final
payment would be contingent on a pipe that did not leak.” Doc. No. 141, FCCC’s
Opp’n at 7.
There is another obvious material question of fact -- why did the
system leak? Composite Pipe asserts that any leakage was not due to any defects
19
in the Meyer Pipe, but the result of FCCC’s installation errors. FCCC asserts the
opposite. And there is other evidence that the pipe did not leak at all, at least at
the factory. See, e.g., Doc. No. 103-2, Thompson Decl. ¶ 11 (“[T]he [Meyer Pipe]
and its joints were successfully tested in the factory to hold 50 psi of pressure with
no pressure loss, verifying the integrity and quality of the pipe and joints.”). A
November 23, 2011 letter from the City to FCCC sums up the issue -- the City
states to FCCC that “[a]ny leaks or failures resulting from pipe performance and
not from the installation of the curved piping will be the responsibility of the pipe
manufacturer[.]” Doc. No. 88-7, FCCC’s Ex. 5. And given the record before the
court (as discussed further below), the cause of the leaks is not a question that can
be resolved at summary judgment.6
2.
It Is Undisputed That Composite Pipe Is Entitled to the Second
Installment Payment
Although there are questions of fact regarding whether the pipe met
specifications, such disputes only justify FCCC withholding the third payment
under the terms of the Purchase Order. Contractually, it is undisputed that the
6
Composite Pipe further argues that, even if the pipe was somehow defective, the
Purchase Order contains limitation of liability provisions that restrict FCCC’s remedies to
demanding replacement, and do not allow FCCC to withhold payment. As discussed further
below when the court addresses issues regarding the Amended Counterclaim, it is unclear
whether the Purchase Order’s general limitation provisions apply, where (1) there is substantial
evidence indicating that Composite Pipe made more specific express warranties, and (2) certain
provisions of Hawaii’s UCC may apply.
20
conditions for the second payment have been satisfied. The City has paid FCCC
for that installment, and the pipe was delivered and incorporated into the project.
The Purchase Order clearly provides “25% of the total value of the order to be
paid upon delivery of the pipe on the jobsite (based on signed delivery
documents).” Doc. No. 103-5, Pl.’s Ex. 1 at 6. Indeed, FCCC’s own Motion
arguing that it need not pay Composite Pipe is directed only at the third payment -FCCC asks the court to “determin[e] that the final 25% payment on the material
supplied by [Composite Pipe] is not due because Meyer Pipe failed to pass the
hydrostatic test requirement of holding 50 pounds per square inch of pressure,
without a drop, for one hour.” Doc. No. 87, FCCC’s Mot. at 2 (emphasis added).
FCCC argues that it might still be entitled to damages from
Composite Pipe. But even assuming FCCC eventually prevails on its Amended
Counterclaim as to Composite Pipe, or assuming that Composite Pipe must pay
some liquidated damages for late delivery, this does not mean FCCC is necessarily
entitled to withhold payment to Composite Pipe -- especially where it is now
undisputed that such a payment was due. It only means Composite Pipe might be
separately liable for damages later.7
7
FCCC cites to Hawaii Revised Statutes (“HRS”) § 490:2-717, a provision of Hawaii’s
UCC, which provides:
(continued...)
21
Accordingly, the court GRANTS in part Composite Pipe’s Motion for
Summary Judgment. Pursuant to ¶ 10.1 of the Purchase Order’s General Terms
and Conditions, the second payment of $899,159 is due to Composite Pipe from
FCCC. See Doc. No. 103-5, Pl.’s Ex. 1 at 6; Doc. No. 103-2, Thompson Decl.
¶ 13 (indicating the amount of the second payment is $899,159).
The Purchase Order also calls for interest if amounts are not timely
paid. In particular, paragraph 10.4 of its General Terms and Conditions provides:
Failure to pay Full Price when due. If the Full Invoice
Price is not paid within the agreed period from due date,
a Late Payment Finance Charge equal to one percent %
per month (equivalent to an annual percentage rate of
12% per annum) on entire past due balance will be paid
by Buyer. Interest shall begin to accrue sixty (60) days
7
(...continued)
The buyer on notifying the seller of his intention to do so may
deduct all or any part of the damages resulting from any breach of
the contract from any part of the price still due under the same
contract.
FCCC, however, has not proffered evidence (much less argued the point) that meets its
initial burden to demonstrate that it fulfilled the notification requirement, nor has it established
that this section otherwise applies to the second payment. Cf. Quaker Alloy Casting Co. v.
Gulfco Indus., Inc., 686 F. Supp. 1319, 1344 (N.D. Ill. 1988) (addressing whether an unpaid
amount was “still due” under UCC § 2-717, and suggesting that “a reactive counterclaim after
suit was filed” is insufficient “notice” of a buyer’s “intention to . . . deduct all or any part of the
damages resulting from any breach of the contract”). Although there might be some basis for
§ 490:2-717’s application as to the final payment, FCCC has not pointed to any evidence
indicating that it would have had a basis to invoke that section at the time the pipe was delivered
(when the second payment became due). “Section 2-717 is not a general set-off provision
permitting a buyer of goods to adjust its continuing contract obligations according to the equities
perceived by the buyer.” ITV Direct, Inc. v. Healthy Solutions, LLC, 379 F. Supp. 2d 130, 133
(D. Mass. 2005) (internal quotation omitted).
22
from date of delivery.
Doc. No. 103-5, Pl.’s Ex. 1 at 6. Applying this provision, Composite Pipe submits
an unopposed declaration indicating that interest began accruing on September 1,
2012, which is “[sixty] days after delivery of all parts of the order.” Doc. No. 1032, Thompson Decl. ¶ 13. It computes the total principle and interest owed for the
second installment payment as of July 31, 2014 as $1,105,793. Id.8 These figures
are undisputed, and are consistent with the court’s calculations using the same
figures (principle of $899,159 at an interest rate of twelve percent per year).
Accordingly, the court awards interest at a corresponding per diem interest rate
($899,159 x 0.12/365, or approximately $295.61 per day).
B.
Questions of Fact Prevent Summary Judgment as to the Amended
Counterclaim
FCCC’s Amended Counterclaim seeks damages from Composite Pipe
and the City based on the condition of (and selection or approval of) the Meyer
Pipe. Composite Pipe moves for summary judgment as to those claims,
contending that it is undisputed that FCCC’s damages (e.g., damages to FCCC’s
microtunneling machine incurred in the July 2012 inundation, and related
8
This figure of $1,105,793 corresponds to a per diem rate of slightly over $295.61
($899,159 x 0.12/365) for 699 days from September 1, 2012 until July 31, 2014. Given that rate,
it consists of principle of $899,159 and interest of $206,634. The court will proceed with that
per diem interest rate ($899,159 x 0.12/365, or approximately $295.61 per day).
23
consequential damages) were caused by FCCC’s installation errors, and were not
the result of any defects in the pipe. Composite Pipe also asserts that relief is
barred by contractual limitation of liability provisions in the Purchase Order. The
City’s Substantive Joinder seeks the same relief as to the City, contending that it is
undisputed that it has no responsibility, either factually or based on limitation
provisions in the Beachwalk Contract.9
1.
The Cause of the July 2012 Inundation Is Disputed
Without detailing all the evidence, there are obvious disputes of fact
as to the cause of the inundation and resulting damage to FCCC’s equipment. For
example, Composite Pipe proffers evidence that FCCC failed to properly install
the shaft seal, contending it failed to follow “shop drawings” and “reversed the
1/2" and 3/4" seals so that the thinner and longer seal was directly exposed to the
[microtunneling machine] when it was launched rather than being protected by the
thicker 3/4" seal.” Doc. No. 107-3, William Harrel Decl. ¶¶ 2, 3. It also asserts
that FCCC “failed to launch its [microtunneling machine] in the center of the seal
opening,” id. ¶ 3, and “did not properly adjust the slide plates to reinforce the ring
seal at [the] first IJS installation[.]” Id. ¶ 12. Likewise, the City’s Substantive
9
In a similar Motion discussed below, the City also asserts it cannot be liable for
consequential damages based on contractual and statutory provisions limiting remedies.
24
Joinder argues that -- even if it had some duty of inspection, or was responsible
initially for choosing the Meyer Pipe -- FCCC had ultimate responsibility for
installation, and it did so incorrectly. See, e.g., Doc. No. 122-1, William Wanner
Decl. ¶¶ 11, 13, 16 (“[T]he two seal gaskets were installed reversed from the
approved shop drawing and . . . this was a significant contributing factor to the
failure of the seal[.]”).10
10
The City also argues that FCCC was not relieved of its ultimate obligations in the
Beachwalk Contract. See Doc. No. 122-7, City’s Ex. 6 at 22 (General Conditions § 4.6(c),
providing: “The presence or absence of an inspector shall not result in the waiver of any
requirements of the contract[.]”); Doc. No. 122-3, City’s Ex. 2 at 5 (General Condition § 107(L),
providing: “The action of implementing or not implementing a specific recommendation does not
relieve the Contractor of the sole liability and/or responsibility of the construction and operation
of the project.”); Doc. No. 122-6, City’s Ex. 5 at 2 (requiring FCCC “to collaborate with the pipe
manufacturer to make sure the jacking pipe and intermediate jacking stations are compatible with
[FCCC’s] microtunneling machine and system operation”).
FCCC responds, however, by claiming that specifications referred to in the Purchase
Order make the City responsible for inspection and acceptance of the pipe. See Doc. No. 122-6,
City’s Ex. 5 at 11 (Revised Specification 406 providing “Pipe Acceptance and Rejection. . . .
[O]nly pipe marked by the Officer-in-Charge [i.e., the City] after delivery to the job site shall be
used in the work. The quality of materials, the manufacturing process, and the finished pipe shall
be subject to inspection and approval by the Officer-in-Charge.”). FCCC also points to a specific
clause in a revised Meyer Pipe specification that it claims excuses it from full performance if
there is “a problem with the pipe.” In particular, the revised specification states:
The requirement of this specification section is that [FCCC] is
responsible to not exceed 650 tons of jacking force on the pipe and
to install on line and grade unless unable to do so due to differing
site conditions or a problem with the pipe. [FCCC] is expected to
collaborate with the pipe manufacturer to make sure the jacking
pipe and intermediate jacking stations are compatible with
[FCCC’s] microtunneling machine and system operation.
Doc. No. 145-3, FCCC’s Ex. 2 at 2 (emphasis added); see also Doc. No. 142-11, FCCC’s Ex. 6
at 2. The parties dispute the meaning of this provision -- it could concern only the amount of
(continued...)
25
But FCCC disputes all of these assertions. See, e.g., Doc. No. 142-1,
Timothy Coss Decl. ¶ 7 (“Exhibit 8 is not a shop drawing . . . [i]t is simply an
illustration, designed to provide some assistance to the contractor.”); id. ¶ 8 (“The
assertion that FCCC ‘reversed’ the seal, and thereby improperly installed it, is
false”); id. ¶ 10 (“It is my opinion, which I have shared with FCCC, that placing
the 1/2 inch seal in front of the 3/4 inch seal is most often the better
arrangement.”); id. ¶ 12 (“[I]t is common to launch the machine ‘high.’ . . . . [I]t
is well within industry standards and the discretion to be exercised by an
experienced micro-tunneling contractor.”); id. ¶ 14 (“[T]he slide plates should not
be adjusted to a tight tolerance, particularly when the machine is launched.”).
Instead, FCCC asserts that the Meyer Pipe did not meet specifications, was
defective, and caused or contributed to the July 12, 2012 inundation. See, e.g., id.
¶ 17 (“I viewed the Meyer Pipe. I saw sharp protrusions and rough edges . . . . the
Meyer Pipe was not of good quality, and the sharp protrusions and rough edges in
particular were well below the standard of care that would be expected in
producing a quality jacking pipe.”). See also Doc. No. 142-3, Don Bergman Decl.
10
(...continued)
jacking force required (not to exceed 650 tons) or it could also relieve FCCC of “installing on
line and grade” due to “a problem with the pipe.” These are all questions of fact not susceptible
of resolution at this summary judgment stage.
26
¶¶ 7-12 (detailing alleged failures of the pipe); id. ¶ 13 (“[T]he inundation
occurred when the compromised seal could not hold pressure when the smaller
diameter of the Meyer [Pipe] passed through the seal. The Meyer Pipe was out of
tolerances by over one inch in both the case of the pipe and the IJS stations.”);
Doc. No. 107-20, Pl.’s Ex. 16 at 6 (Wanner dep. at 50) (“The Meyer pipe does not
meet that ASTM [Specification 406] to the letter.”). Doc. No. 122-1, Wanner
Decl. ¶¶ 11, 13, 14, 15.
Although both sides challenge the credentials or credibility of
witnesses, the court cannot resolve such disputes at summary judgment. See, e.g.,
McGinest, 360 F.3d at 1113 n.5. In short, genuine disputes of material fact
prevent summary judgment on this question.
2.
Limitation Provisions in the Purchase Order Are Ambiguous
Composite Pipe further argues that, even if the pipe was somehow
defective, the Purchase Order limits liability, disclaims consequential damages,
and restricts FCCC to demanding the pipe’s replacement. Specifically, Composite
Pipe points to ¶¶ 8.1 and 8.5 of the Purchase Order, which provide:
8.1 Seller assumes no responsibility for work done or
expense incurred by the Buyer or others in connection
with defective pipe or goods sold under this Agreement
and repairs or replacement due to defective pipe.
....
27
8.5 If the product is found to be defective, the product
would be replaced under the manufacturer’s warranty.
. . . The manufacturer insists on the ability to replace the
pipe to provide a continued warranty. The manufacturer
will already have all the tooling and necessary means to
rapidly create the pipe and ship it to the site more
quickly than any other manufacturer of the same pipe.
Doc. No. 103-5, Pl.’s Ex. 1 at 5.
FCCC responds by pointing to substantial evidence that Composite
Pipe made explicit (and implied) warranties, citing to provisions of Hawaii’s UCC
that allow it to seek damages.11 See, e.g., Doc. Nos. 142-12 & 142-13, FCCC’s
Exs. 7, 8 (letters from Composite Pipe regarding express warranties); Doc. No. 884, FCCC Ex. 2 (August 4, 2011 email from FCCC stating “the owner is adamant
about the inclusion of the entirety of their requirements regarding
warranty/liability”); Doc. No. 88-5, FCCC’s Ex. 3 (August 11, 2011 email setting
forth meeting agenda item “Limitation of Warranty - Remove exclusion of
Consequential Damages and Labor Incidental to Repair Defective Material or
Workmanship”); Doc. No. 88-6, FCCC’s Ex. 4 (summary of discussion items
including “Limitation of Warranty”). See also Doc. No. 103-5, Pl.’s Ex. 1,
11
FCCC contends that the UCC applies because the Purchase Order “reserved its rights
to all damages allowed by law, equity and contract.” Doc. No. 141, FCCC’s Opp’n at 10 (citing
to ¶ 6 of the Purchase Order’s General Terms and Conditions, proving “Compliance with Law.
Seller represents that the goods covered by this order were and/or are not produced, sold or
priced in violation of any federal, state or local law”); Doc. No. 103-5, FCCC’s Ex. 1 at 2; Doc.
No. 95-3, FCCC’s Ex. 3 at 2.
28
Purchase Order ¶¶ 7.1, 7.2, 7.4 (express warranties to comply with specifications
402 and 406).
At minimum, these specific warranties create a question of fact as to
whether they could override the more general terms (¶¶ 8.1 and 8.5) of the
Purchase Order. See, e.g., Kaiser Hawaii Kai Dev. Co. v. Murray, 49 Haw. 214,
227-28, 412 P.2d 925, 932 (1966) (“[I]n case of inconsistency between general
and specific provisions, the specific controls the general[.]”); Restatement
(Second) of Contracts § 203 (1981) (“In the interpretation of a promise or
agreement or a term thereof, . . . specific terms and exact terms are given greater
weight than general language.”); Israel v. Chabra, 906 N.E.2d 374, 380 n.3 (N.Y.
App. 2009) (“The better and apparent majority rule for resolving irreconcilable
differences between contract clauses is to enforce the clause relatively more
important or principal to the contract. This rule is tempered by the corollary that
the more specific clause controls the more general.”) (quoting 11 Samuel Williston
& Richard A. Lord, A Treatise on the Law of Contracts § 32:15 at 507-10 (4th ed.
1999 & Supp. 2010)).
In this regard, FCCC relies on ¶ 8.2 of the Purchase Order, which -perhaps inconsistently with ¶¶ 8.1 and 8.5 -- provides that “Seller assumes no
liability for any special or consequential damages, other than what is expressly
29
stated in the manufacturer’s warranty.” Doc. No. 103-5, Pl.’s Ex. 1 at 5
(emphasis added). This paragraph was specifically negotiated. According to
FCCC, this language differs from industry standard, and from Composite Pipe’s
initially-proposed contractual language. See Doc. No. 142-3, Don Bergman Decl.
¶ 20; Doc. No. 142-15, FCCC’s Ex. 10 at 3 ¶ 8.2. And this negotiated language
suggests that “special and consequential damages” have been preserved to the
extent “expressly stated in the manufacturer’s warranty.”
3.
Questions of Fact Remain as to “Meyer Pipe No. 19”
Both Composite Pipe and the City move for summary judgment as to
FCCC’s claim for damages in its Amended Counterclaim regarding “Meyer Pipe
No. 19.” FCCC’s claim arises from a September 15, 2012 incident in which pipe
“broke during initial coupling” with an intermediate jacking station (“IJS”), and
“caused delays as the broken pipe was removed and the situation analyzed to
determine the cause.” Doc. No. 42, Am. Counterclaim ¶ 68. FCCC claims at least
$119,609.84 in damages for “Loss Due to Meyer Pipe #19 Broken + Replaced.”
Id. ¶ 116.
Again, disputes of fact preclude entry of summary judgment.
Composite Pipe and the City contend that any damages resulting from the
September 15, 2012 incident are solely FCCC’s responsibility -- FCCC simply
30
attempted to install the wrong piece of pipe (which had the wrong dimensions to
fit properly onto the IJS), and an experienced sewage construction contractor like
FCCC should have known which piece of pipe to install. Ultimately, however,
even if these arguments make complete sense and may well carry the day at trial,
FCCC has proffered enough evidence to demonstrate a triable issue at this
summary judgment stage.
In particular, Tim Pearia, FCCC’s project manager for the Beachwalk
Contract, testifies that Composite Pipe advised and confirmed to FCCC in an
email that “any of the pipes without a steel coupling bell could be used as a lead
pipe.” Doc. No. 142-4, Pearia Decl. ¶ 8. Under the contract’s specifications “the
Meyer supplied Intermediate Jacking Stations were supposed to be the same
outside dimension as the jacking pipe,” id. ¶ 7, but in actuality, the IJS did not
have exact same dimensions as at least some of the pipe. FCCC’s theory is that
Composite Pipe did not properly indicate that some pipe “was not suitable for
installation as the lead IJS pipe.” Id. ¶ 11. That is, Composite Pipe failed to
inform FCCC that “Pipe 19 was too large to be used as a lead pipe to the IJS[.]”
Id. ¶ 12. Only after an after-the-fact investigation did FCCC discover that “there
were four special pipe numbers that were to be used for the lead IJS pipes.” Id.
¶ 14. (In contrast, Composite Pipe points out that the proper pipes were shipped
31
and stored separately, and were marked in some manner with green paint. See
Doc. No. 107-3, Harrel Decl. ¶ 15).
Composite Pipe argues that a multimillion dollar company
specializing in large sewage construction projects could not be misled by an email
from a marketing representative, and thus would not continue to apply higher and
higher jacking force when installing a lead pipe when the pipe did not fit. Maybe
so. But drawing such a conclusion at the summary judgment stage would involve
an inappropriate credibility determination. Construing FCCC’s evidence in its
favor, the court concludes that a material dispute of fact exists. See, e.g., Posey,
546 F.3d at 1126 (“[T]he evidence of [the nonmovant] is to be believed, and all
justifiable inferences are to be drawn in his favor.”) (citations omitted).
4.
Questions of Fact Remain as to Liquidated Damages
Section 1.1 of the Purchase Order’s General Terms and Conditions,
regarding “delivery,” provides in part: “Shipment to be based upon the attached
schedule. . . . Seller shall be liable to the Buyer for liquidated damages of $1,000
per calendar day for late delivery[.]” Doc. No. 95-3, FCCC’s Ex. 1 at 3.
FCCC seeks $78,000 in liquidated damages from FCCC, asserting
that all sections of the pipe were to be delivered by April 24, 2012, but delivery
was not complete until July 11, 2012 (or 78 days late). Doc. No. 95-1, Pearia
32
Decl. ¶¶ 5-6. Composite Pipe has asserted to FCCC as a defense that the delivery
date was modified by a change order involving the City regarding additional pipe.
In response, FCCC denies that there was such an extension, and it moves for
partial summary judgment as to this limited issue. Doc. No. 94. That is, it seeks a
determination that Composite Pipe “has no basis for defending against FCCC’s
claim for liquidated damages based on the assertion that the delivery date for the
Purchase Order at issue was modified by a Change Order.” Id. at 2.12 To this end,
FCCC submits evidence that the Purchase Order was never officially amended by
a Change Order, that FCCC was never asked by the City to change the delivery
schedule, and that FCCC never agreed to change the delivery schedule. See Doc.
No. 95-1, Pearia Decl. ¶¶ 7-13, 16-17.
Composite Pipe, however, disputes FCCC’s assertions by offering
conflicting evidence. In particular, Composite Pipe’s representative, Bezhad
Basiri, declares that a change order regarding additional pipe “was negotiated in a
telephone conference between myself, representatives of [the City], and FCCC.”
Doc. No. 105-1, Basiri Decl. ¶ 7. He contends that this “would delay completion
12
The Motion does not seek at this stage to adjudicate the entitlement to, or the amount
of, any liquidated damages -- it only seeks to narrow issues for trial. FCCC reasons that “[b]y
conclusively adjudicating at this time [Composite Pipe’s] claim that there was a Change Order
which altered the terms of the Purchase Order, the Court can simplify the issues for trial, and
assist the parties in resolving this dispute.” Doc. No. 94-1, FCCC’s Mem. in Supp. at 7.
33
and shipping of the entire order from Germany. . . . We accordingly negotiated
and agreed to an extension of time of the Purchase Order delivery requirements[.]”
Id. He states that he “was advised by email from [the City] that the Change Order
was agreed and that the City would take care of getting FCCC’s signature on it, so
we proceeded in reliance on it.” Id. ¶ 8. (He also attests to other reasons that
delivery may have been excused, such as labor strikes at the Panama Canal, that
Composite Pipe claims can extend the delivery date under a force majeure clause
in the Purchase Order. Id. ¶ 9.).
FCCC conceded at the September 29, 2014 hearing that a genuine
issue of material fact exists as to liquidated damages, given the Basiri Declaration
(which FCCC claims is false). Accordingly, FCCC’s Motion is DENIED as to
liquidated damages.
5.
Questions of Fact Remain as to Claims Against the City for
Consequential Damages
Last, the City moves for summary judgment on FCCC’s claims for
consequential damages against the City. Doc. No. 114. The Motion is directed
only at Count Five of the Amended Counterclaim, which asserts a breach of the
Beachwalk Contract and/or breach of implied warranties. That is, the City does
not move as to Count Three -- which alleges negligence against the City and
34
Composite Pipe -- and the Motion only asserts that FCCC is not entitled to seek
consequential damages (it does not otherwise seek judgment as to Count Five).13
Specifically, the City’s Motion contends that:
The undisputed facts show that as a matter of law, FCCC
is not entitled to recovery of any consequential damages
relating to the increased costs on the Ala Moana Project
because (1) the Hawaii Public Procurement Code, which
provides the exclusive remedies available to a Contractor
in a breach of Contract action against the City, does not
allow the recovery of consequential damages, (2) the
express terms of the Beachwalk Contract do not allow
for the recovery of consequential damages, and (3) the
alleged consequential damages were not in the
contemplation of the parties at the time the Beachwalk
Contract was executed.
Doc. No. 114-1, City’s Mot. at 3.
13
In its Opposition, FCCC argues, among other grounds, that its Amended Counterclaim
sounds in negligence (to which any restrictions in the Procurement Code, or in the Beachwalk
Contract do not apply). To this, the City’s Reply argues that Hawaii does not recognize a
“negligent breach of contract” (see Francis v. Lee Enters., Inc., 89 Haw. 234, 239, 971 P.2d 707,
712 (1999)), and attempts to raise the “economic loss doctrine.” See, e.g., Leis Family Ltd.
P’ship v. Silversword Eng’g, 126 Haw. 532, 538, 273 P.3d 1218, 1224 (Haw. App. 2012)
(“Newtown Meadows, although a construction case not involving design professionals, clearly
stands for the proposition that the economic loss doctrine bars the recovery of purely economic
losses, even in the absence of privity of contract, so long as ‘allowing such recovery would blur
the distinction between contract and tort law.’”) (quoting Ass’n of Apartment Owners of
Newtown Meadows v. Venture 15, 115 Haw. 232, 292, 167 P.3d 225, 285 (2007)). The City has
not, however, moved for summary judgment as to Count Three (negligence), and it is
inappropriate for the court to address its validity based on a Reply memorandum. Although the
doctrine can bar consequential damages, Burlington Ins. Co. v. United Coatings Mfg. Co., 518 F.
Supp. 2d 1241, 1254 (D. Haw. 2007), “[a]n exception to the rule exists when the finished
product causes damage to ‘other property.’” Keahole Point Fish LLC v. Skretting Canada Inc.,
971 F. Supp. 2d 1017, 1030 (D. Haw. 2013) (citing Kawamata Farms, Inc. v. United Agric.
Prods., 86 Haw. 214, 254, 948 P.2d 1055, 1095 (1997)). Accordingly, the court will not address
Count Three further, and leaves such issues for trial.
35
a.
Foreseeability of consequential damages
The City argues that consequential damages related to the Ala Moana
Contract were not foreseeable -- and it relies wholly on a statement of law that
consequential damages for breach of contract are recoverable only “as may
reasonably be supposed to have been in the contemplation of the parties at the
time the contract was entered into.” Amfac, Inc. v. Waikiki Beachcomber Inv. Co.,
74 Haw. 85, 128, 839 P.2d 10, 33 (1992) (quoting Jones v. Johnson, 41 Haw. 389,
393 (1956)) (emphasis added). Because the Ala Moana Contract was -- at best -still out for bid when the Beachwalk Contract was signed in 2009, the City
contends that any consequential damage related to the Ala Moana Contract that
results from any breach by the City of the Beachwalk Contract (e.g., from loss of
used of the microtunneling machine) could not have been contemplated. Such
damages were not foreseeable.
But this entire action arises out of the selection and condition of the
Meyer Pipe, which also was not contemplated in 2009 when the Beachwalk
Contract was signed. Likewise, the Amended Counterclaim concerns the Meyer
Pipe and events that occurred upon installation and after. The eventual “Change
Order No. 4” regarding the Meyer Pipe (or the Purchase Order) are the agreements
at issue for purposes of whether selection of, or defects with, the Meyer Pipe could
36
have caused foreseeable consequential damages. And the evidence indicates that
the Ala Moana Contract was executed on October 25, 2011, while the Purchase
Order was signed on November 13, 2011 (and the corresponding “Change Order
No. 4” for the Beachwalk Contract was fully executed on January 30, 2012) -both operative dates being after the Ala Moana Contract. See Doc. No. 145-1,
Bergman Decl. ¶ 3; Doc. No. 145-2, FCCC’s Ex. 1 at 4 (“[Beachwalk] Contract
Change Order No. 4,” last executed on January 30, 2012).
Given these dates, questions of fact remain as to whether
consequential damages were reasonably foreseeable. FCCC proffers evidence of a
plausible -- if not weak -- theory that the City could have foreseen that problems
with the Meyer Pipe could result in larger problems with the Beachwalk Contract
and affect FCCC’s implementation of the Ala Moana Contract. See Doc. No. 1451, Bergman Decl. ¶ 2 (“FCCC has a long history of performing work for the City,
and of moving equipment from one completed job to the next. The City is well
aware of this history.”); id. ¶ 3 (“The Ala Moana Contract was executed on
October 25, 2011. At that time, the City through oral discussions was aware that
FCCC was planning on using the same machine on both projects, which was why
the Ala Moana Bid was over 25 million dollars below the next lowest bid.”).
37
b.
Procurement code and contractual provisions are ambiguous
The City argues that the state procurement code provides the
exclusive remedy for “contract controversies,” and that it (and similar provisions
of the Beachwalk Contract) do not allow for consequential damages.
HRS § 103D-704 provides, in pertinent part, that “[t]he procedures
and remedies provided for in this part, and the rules adopted by the policy board,
shall be the exclusive means available for persons aggrieved in connection with
. . . a contract controversy[.]” In turn, Hawaii Administrative Rule (“HAR”) § 3125-7 provides:
(4) Cost adjustment. If the performance of all or part of
the work is suspended for reasons beyond the control of
the Contractor [FCCC], an adjustment shall be made for
any increase in the cost of performance of this contract
(excluding profit) necessarily caused by such suspension,
and the contract modified in writing accordingly.
However, no adjustment under this section shall be made
for any suspension:
(A) To the extent that performance would
have been so suspended, delayed, or interrupted by
any other cause, including the fault or negligence
of the Contractor; or
(B) For which an adjustment is provided for
or excluded under any other provision of this
contract.
Id. (emphasis added). Similarly, Section 8.1(d) of the “General Conditions”
38
incorporated into the Beachwalk Contract,14 provides:
8.1 Suspension of work . . . .
....
(d) Cost adjustment. If the performance of all or part of
the work is suspended for reasons beyond the control of
the Contractor, an adjustment shall be made for any
increase cost of performance of the contract (excluding
profit) necessarily caused by such suspension, and the
contract modified in writing accordingly.
However, no adjustment under this section shall be made
for any suspension:
(1) To the extent that performance would
have been so suspended, delayed, or interrupted by
any other cause, including the fault or negligence
of the Contractor; or
(2) For which an adjustment is provided for
or excluded under any other provision of the
contract.
Doc. No. 115-7, City’s Ex. F at 47 (emphasis added).
FCCC argues, however, that its alleged consequential damages do not
involve whether “the performance of all or part of the work is suspended for
reasons beyond the control of the Contractor” and do not involve a “suspension of
work.” Instead, it argues that it seeks consequential damages that arise from
“physical damages” to its microtunneling machine, which are not suspension or
“delay” damages. And it contends that the statutory and contractual language does
14
See Doc. No. 115-2, City’s Ex. A at 2; Doc. No. 115-5, City’s Ex. D, Frank Coluccio
Dep. at 97.
39
not actually bar consequential damages -- there is no unambiguous exclusion of
such damages.
Material disputes of fact remain as to the applicability of HAR § 3125-7 and § 8.1 of the Beachwalk Contract. Although the sections no doubt apply
to this dispute, the actual application of the language (which is ambiguous) is
unclear. The parties (the City in particular) have not explained how the language
applies to the dispute at hand. It is thus inappropriate to grant judgment in favor
of the City at this stage of the proceedings, and on the current evidentiary record.
V. CONCLUSION
For the foregoing reasons, the Motions and Substantive Joinder (Doc.
Nos. 87, 94, 106, 114, and 121) are DENIED, except for Composite Pipe’s claim
that it is entitled to the second installment payment (25 percent of the purchase
price, or $899,159.00), plus interest at a rate of twelve percent per annum. To that
///
///
///
///
///
///
40
extent only, the court GRANTS Composite Pipe’s Motion for Summary Judgment
in part. Doc. No. 106. All other issues remain for trial.
IT IS SO ORDERED.
DATED, Honolulu, Hawaii: October 7, 2014.
/s/ J. Michael Seabright
J. Michael Seabright
United States District Judge
U.S. Composite Pipe S., LLC v. Frank Coluccio Constr. Co., et al., Civ. No. 12-00538 JMSKSC, Order Granting in Part and Denying in Part Motions for Summary Judgment, or for Partial
Summary Judgment
41
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?