Kingston Environmental Services, Inc., United States for the use and benefit of v. David Boland, Inc.
Filing
178
ORDER GRANTING PLAINTIFF'S MOTION TO LIFT STAY re #169 - Signed by JUDGE DERRICK K. WATSON on 6/28/2019. For the foregoing reasons, Plaintiff's Amended Motion to Lift Stay (Dkt. No. 169) is GRANTED. Plaintiff's previously filed Motion to Lift Stay (Dkt. No. 168) is DENIED as moot. (emt, )
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF HAWAI‘I
UNITED STATES for the use and
benefit of KINGSTON
ENVIRONMENTAL SERVICES,
INC., a Missouri corporation,
Plaintiff,
vs.
DAVID BOLAND, INC., WESTERN
SURETY COMPANY, GRANITE
PRECASTING & CONCRETE, INC.,
and HAWAII GEOPHYSICAL
SERVICES, LLC,
Defendants,
and
UNITED STATES for the use and
Benefit of DAVID BOLAND, INC.
Counterclaim Plaintiff,
vs.
KINGSTON ENVIRONMENTAL
SERVICES, INC. and BERKELY
REGIONAL INSURANCE
COMPANY,
Counterclaim Defendants.
CIVIL NO. 16-00205 DKW-WRP
ORDER GRANTING PLAINTIFF’S
MOTION TO LIFT STAY
INTRODUCTION
Plaintiff Kingston Environmental Services, Inc. (“Kingston”) moves to lift
the stay of its action against Defendants Western Surety Company and David
Boland, Inc. (“Boland” and together with Western Surety, the “Defendants”).
Kingston is Boland's subcontractor on a military construction project on Oahu.
Pursuant to this Court’s August 2017 Order granting Defendants’ Motion to Stay,
over the course of the past two years, Kingston has pursued contractuallymandated administrative remedies for its breach of contract claims, obtaining
contracting officer final decisions (COFDs) regarding the extent of the
government’s liability for those claims. Finding that Kingston has satisfied its
contractual obligation to exhaust administrative remedies prior to proceeding with
its civil action against Boland, the Court GRANTS Plaintiff’s Amended Motion to
Lift Stay (Dkt. No. 169).
BACKGROUND
I.
The Project and Subcontract
Boland is the prime contractor (Contract No. W9128A-12-C-0009 or “Prime
Contract”) on an infrastructure construction project for the United States Army
Corps of Engineers (“USACE”) at Wheeler Army Airfield, Oahu, Hawaii (the
“Project”). Defendant Western Surety issued performance and payment bonds on
2
behalf of Boland for the Project. Complaint, Dkt. No. 1, ¶¶ 10–11. Boland
subcontracted with Kingston to provide labor, materials, equipment, and services
(“Subcontract”).1
Kingston contends that Boland mismanaged the Project, which had an
original completion date of approximately May 2015. Boland acknowledges that
the Project was behind schedule, and that its management of the Project may have
been “below average” due to its “strained relationship” with the government but
asserts that the majority of the issues forming the basis for Kingston’s claims
against Boland are issues for which the USACE is or may be responsible.
Kingston Ex. A, 7/19/17 Hildebrandt Dep. at 83–85; Dkt. No. 134-1.
Kingston filed this action on April 29, 2016 seeking payment from Western
Surety of its bonds under the Miller Act, 40 U.S.C. § 3133 et seq., (Count I) and
alleging that Boland breached the Subcontract (Count II). Complaint ¶¶ 38–50.
II.
The Stay
At the time it initiated this action, Kingston had not submitted requests to
Boland to sponsor or submit to the government all claims for which the USACE
might be responsible for Kingston’s losses. See Order Granting in Part
1
Kingston’s 2012 Subcontract is attached as Exhibit A to the Declaration of Craig Hildebrandt,
Dkt. No. 116-1, and as Exhibit B to Boland’s Concise Statement of Facts, Dkt. No. 116-2.
3
Defendants’ Motion for Partial Summary Judgment and Staying Case (2017
Order), Dkt. No. 145, August 30, 2017. The parties disputed whether Kingston
could pursue the claims asserted here prior to exhausting the remedial procedure
specified in the Subcontract, as Kingston had done previously with other claims.
Id.
On June 16, 2017, Defendants filed a Motion for Summary Judgment, which
argued that Kingston failed to comply with the contractually-mandated remedial
procedure in Subcontract Paragraph 13A, which is a condition precedent to the
present civil action. See Dkt. No. 115. Defendants moved to stay this action and
enforce the administrative remedies outlined in Subcontract Paragraph 13A, which
provides that any claims by Kingston against Boland for which the USACE “may
be responsible” must be pursued first by Boland on behalf of Kingston through the
remedial procedures set forth in the Prime Contract between Boland and the
USACE. Paragraph 23 of the Subcontract, entitled “Waivers and Stays,” provides
that Kingston agrees to stay any action pending the completion of the Prime
Contract’s remedial procedure as required by Paragraph 13. Finding that
Kingston was contractually obligated to exhaust claims for which the USACE
might bear responsibility, this Court stayed proceedings.
4
Since August 2017, Kingston has pursued its claims administratively,
submitting the following seven claims to the contracting officer:
1.
2.
3.
4.
5.
6.
7.
CP-141.7 Cost Overrun Claim
CP-141.1 UXO Claim
CP-141.2 FPVC Claim
CP-141.3 Box Culvert Utility Relocation Claim
CP-141.4 Utility Pole Pads Claim
CP-141.5 Box Culvert Select Backfill Claim
CP-141.6 Airdrome Construction Entrance Claim
Amended Motion to Lift Stay (Motion), Dkt. No. 169, at 3. In February 2019, the
contracting officer found that the USACE was responsible for Claim #2, the
“UXO” claim (CP141.1), in the amount of $1,900.2 Id., 4. The six remaining
claims were rejected, including Claim #1, the $6,882,738 “Cost Overrun” claim
that makes up the bulk of Kingston’s claims against Boland. Id. Kingston agreed
with three of the COFDs rejecting USACE liability, Claim #1, Claim #3, and
Claim #7, and elected to only appeal the other three COFDs, Claim #4, Claim #5,
and Claim #6, to the Armed Services Board of Contract Appeals (ASBCA). Id.
The ASBCA has not yet reached a decision on the three appealed COFDs. See
2
Plaintiffs state that the COFDs are attached as Exhibit A (Motion at 4) but no such attachment
was filed. As a result, the Court is unable to determine on what day the COFDs were issued or
the precise content of the COFDs.
5
Defendants’ Opposition to Plaintiff’s Amended Motion to Stay (Opp.), Dkt. No.
176.
On April 24, 2019, Plaintiff filed an Amended Motion to Lift Stay
(Motion). 3 Dkt. No. 169. On May 16, 2019, Defendants filed an Opposition
(Dkt. No. 176), and Plaintiff timely replied (Dkt. No. 177). Pursuant to Local
Rule 7.2(d), the Court finds this matter suitable for disposition without a hearing.
LEGAL FRAMEWORK
“[T]he power to stay proceedings is incidental to the power inherent in every
court to control disposition of the cases on its docket with economy of time and
effort for itself, for counsel, and for litigants.” Landis v. N. Am. Co., 299 U.S.
248, 254 (1936). “The exertion of this power calls for the exercise of sound
discretion.” CMAX, Inc. v. Hall, 300 F.2d 265, 268 (9th Cir. 1962); see Clinton v.
Jones, 520 U.S. 681, 706 (1997) (“The District Court has broad discretion to stay
proceedings as an incident to its power to control its own docket.”); Lockyer v.
Mirant Corp., 398 F.3d 1098, 1109 (9th Cir. 2005) (“A district court has
discretionary power to stay proceedings in its own court[.]”). When a stay is
requested because of pending proceedings that bear on the case, the court may
3
Kingston erroneously filed an unsigned version of this Motion on April 24, 2019. (Dkt. No.
168). That motion is superseded by this one and the previous motion is DENIED as moot.
6
grant a stay in the interests of the efficiency of its own docket and fairness to the
parties. See Leyva v. Certified Grocers of Cal. Ltd., 593 F.2d 857, 863 (9th Cir.
1979); see also Mediterranean Enters., Inc. v. Ssangyong Corp., 708 F.2d 1458,
1465 (9th Cir. 1983) (“A trial court may, with propriety, find it is efficient for its
own docket and the fairest course for the parties to enter a stay of an action before
it, pending resolution of independent proceedings which bear upon the case.”).
The Ninth Circuit set out the following framework for analyzing motions to
stay pending resolution of related matters:
Where it is proposed that a pending proceeding be stayed, the
competing interests which will be affected by the granting or
refusal to grant a stay must be weighed. Among those
competing interests are the possible damage which may result
from the granting of a stay, the hardship or inequity which a party
may suffer in being required to go forward, and the orderly
course of justice measured in terms of the simplifying or
complicating of issues, proof, and questions of law which could
be expected to result from a stay.
Lockyer, 398 F.3d at 1110 (9th Cir. 2005) (quoting CMAX, 300 F.2d at 268).
DISCUSSION
Kingston moves to lift the August 2017 stay imposed by this Court and to
allow it to pursue its claims against Boland. Kingston argues that, by obtaining
COFDs, it has satisfied its contractual obligation to pursue administrative remedies
determining the extent of the government’s liability, if any, for the claims Kingston
7
seeks to assert against Boland. Defendants argue that (1) Kingston must appeal all
COFDs to the ASBCA to fully exhaust administrative remedies under the contract
before it can pursue claims against Boland in this Court, and (2) that the Court
should decline to lift the stay until all of the appeals to the ASBCA have been
resolved. For the reasons set forth below, the Court concludes that litigation of
Kingston’s claims in this Court should resume because Kingston has exhausted the
contractual remedial procedure required under the Subcontract and further delay is
unwarranted. Kingston’s Motion is therefore GRANTED.
In granting Defendants’ 2017 Motion to Stay, the Court ruled that
Subcontract paragraphs 13A and 23 applied to Kingston’s action in this Court, and
that Kingston was therefore required to pursue administrative remedies and stay
the instant action pending exhaustion of those remedies. See August 2017 Order.
The question now before the Court is whether the COFDs Kingston obtained
pursuant to the Court’s order satisfy Kingston's exhaustion obligation. In other
words, the parties dispute the meaning of paragraph 13A’s administrative remedies
requirement.
Paragraph 13A, in relevant part, provides:
The contractual remedial procedure described in section 0700Contract Clauses, 52.233-1 Disputes, (JUL2002) of the Prime
Contract [between Boland and USACE] relating to claims for
which the Owner may be responsible is specifically incorporated
8
herein by reference and made a part of this Subcontract
Agreement. The Subcontractor shall first pursue and fully
exhaust said procedure before commencing any other action
against the Contractor or its surety for any claims it may have
arising out of its performance of the Work herein[…]. Final
determination of the Subcontractor’s claim(s) by the appropriate
board or court shall be final and binding on the Subcontractor
and the Contractor shall have no further liability, responsibility,
or obligation to the Subcontractor except as may be otherwise
provided in this Subcontract Agreement.
The operative clause, identified by both parties, is the reference to the Prime
Contract’s remedial mechanism: “The contractual remedial procedure described in
section 0700-Contract Clauses, 52.233-1 Disputes, (JUL2002) of the Prime
Contract.” Although neither party provided the Court with the Prime Contract
itself, both agree that the remedial provision of the Prime Contract incorporates by
reference Federal Acquisition Regulation (FAR) §52-233-1, entitled “Disputes.”
Motion at 5; Opposition at 4 (cited as 48 C.F.R §52.233-1). FAR §52-233-1 does
not use the word “exhaust” or otherwise describe when a claim is exhausted.
Kingston argues that the FAR provision clearly states that a COFD is final in
the absence of an appeal and that the decision to appeal a COFD is at the discretion
of the contractor. See Motion at 5. Defendants respond, without citation to any
authority, that “[t]he issuance of a [COFD] is merely the first step in the
administrative contractual remedial procedure…under the terms of paragraph
13A….” Opp. at 5. Specifically, Defendants argue that Kingston has
9
“summarily ignored the clear language and mandate of the Subcontract Agreement
and the Court’s holding regarding what must be exhausted contained in the Stay
Order” by “abandoning certain claims after having obtained a COFD.” Motion at
7-8. In short, Defendants argue that Kingston is required to appeal all COFDs that
rejected government liability before it can claim to have exhausted administrative
remedies and before it may pursue those claims against Boland here.
Defendants’ argument fails for several reasons. The relevant section of
FAR §52-233-1, subparagraph f, states that “[t]he Contracting Officer’s decision
shall be final unless the Contractor appeals or files a suit as provided in the Act.”
Motion at 5. The provision is unambiguous that a COFD is final without an
appeal. Moreover, nowhere in the cited FAR section or in the cited language from
the Prime and Subcontract does it state that COFDs must be appealed. 4
In ordering Kingston to pursue administrative remedies that would
determine the government’s liability, the Court agreed with Defendants, over
Kingston’s objections, that the extent of the government’s liability should not be
4
Both parties reference and make much of the language of 41 U.S.C. §7104(a), which states “A
contractor, within 90 days from the date of receipt of a contracting officer’s decision under
section 7103 of this title, may appeal the decision to an agency board as provided in section 7105
of this title.” Motion at 5; Opp at 8. Although this statutory provision addresses the avenues of
appeal of COFDs, it does little to answer the question of when administrative remedies have
been exhausted.
10
decided by this Court. Indeed, the Court made no findings as to whether or not
the government was liable, even in part, for any of the claims Kingston sought to
pursue against Boland. The Court, in fact, recognized that Kingston’s theory of
liability asserted the contrary:
"Kingston argues that it seeks compensation for delays and
cost-overruns based exclusively on Boland’s poor Project
management…The Court expresses no opinion as to who is
ultimately at fault for the delays and cost-overruns
experienced on the Project—that is a question that is not
properly before this Court in the first instance.”
Order at 15. Pursuant to the Court’s Order, Kingston obtained COFDs, which
found the government not liable for six of the seven claims Kingston presented.
Thus, the COFDs have now provided an answer to the question of government
liability in the first instance such that this Court can proceed with the question
properly before it: the extent of Boland’s liability for Kingston’s claims.
The scant case law cited by either party does nothing to disturb this
conclusion. Rather, the three cases cited by both parties show only that the Court
of Federal Claims has interpreted its own jurisdictional trigger to require
exhaustion in the form of COFDs. Olsberg Excavating Co. v. United States, 3 Cl.
Ct. 249 (1983) (finding that filing an untimely appeal of a COFD to the relevant
administrative appeals board did not preclude jurisdiction over a direct action in
the Court of Federal Claims where the appeals provision allows for an appeal of a
11
COFD in either forum); Rider v. United States, 7 Cl. Ct. 770, 776 (1985), aff'd, 790
F.2d 91 (Fed. Cir. 1986) (finding that, if the Contract Disputes Act were
applicable, the Court of Federal Claims does not have jurisdiction until a COFD
has issued.) For example, in SITCO Gen. Trading & Contracting Co. v. United
States, the court held that “a plaintiff must exhaust administrative remedies
available under the CDA [Contract Disputes Act] by submitting a claim to and
seeking a final decision from the contracting officer before filing suit.” 87 Fed.
Cl. 506, 508 (2009). The relevant provision of the CDA at issue in SITCO states,
“[a]ll claims by a contractor against the government relating to a contract shall be
in writing and shall be submitted to the contracting officer for a decision.” Id.
(citing CDA, Section 605(a)). The Court of Federal Claims in SITCO interpreted
that provision to require the plaintiff to show that the contracting officer had
rendered a final decision of its claim before invoking the court's jurisdiction. Id.
(citing Sarang Corp. v. United States, 76 Fed. Cl. 560, 564 (2007) (footnotes
omitted)(emphasis added)). Although SITCO was concerned with administrative
exhaustion as a jurisdictional prerequisite for the Court of Federal Claims, the
interpretation of the meaning of administrative exhaustion is instructive. This
Court similarly concludes that the Subcontract’s administrative exhaustion
12
language only requires obtaining a COFD, not filing an appeal or obtaining an
appellate ruling on the COFD.
Defendants additionally argue that the Court should stay proceedings for
discretionary reasons, asserting that allowing Kingston to pursue claims in this
Court while its appeals are pending before the ASBCA will result in “piecemeal”
outcomes. That is because, at least in part, Defendants perceive an overlap
between those claims on appeal to the ASBCA and those claims which Kingston
wishes to pursue here. Opp. at 10; Attachment A, Hildebrandt Dec. at 4.
However, Kingston has already consented to excluding the claims it has appealed
to the ASBCA from the action before this Court. Motion at 7. Even if that were
not the case, Defendants' concern is easily remedied: to the extent that favorable
resolution of the three ASBCA claims mitigates, offsets, or eliminates Boland’s
liability for the three claims pursued here, those pieces can be excised from
Kingston’s action or prayer for relief. Or, as Kingston suggests, the parsing of its
claims here can occur even without an ASBCA decision and before trial.5 Reply
at 10-11.
5
Of relevance, the total amount of the claims Kingston is appealing to the ASBCA appears to be
in the tens of thousands of dollars. When compared to the claims Kingston seeks to pursue here,
including one exceeding six million dollars, resolution of the relatively minor administrative
claims should not hold hostage pursuit of Kingston’s most substantial claim.
13
In deciding whether to grant or lift a stay, the Court must consider the
“hardship or inequity which a party may suffer” and ensure “the orderly course of
justice.” Lockyer, 398 F.3d at 1109. The Court finds that further staying
proceedings would prejudice Kingston given the time and cost it has already
incurred in pursuing administrative remedies (and given that there is no contractual
reason to further delay). Just as importantly, delaying the resolution of Kingston’s
largest claim against Boland, pending the appeal of some minor claims against the
government, runs counter to the fair and efficient administration of justice.
CONCLUSION
For the foregoing reasons, Plaintiff’s Amended Motion to Lift Stay (Dkt.
No. 169) is GRANTED. Plaintiff’s previously filed Motion to Lift Stay (Dkt. No.
168) is DENIED as moot. IT IS SO ORDERED.
DATED: June 28, 2019 at Honolulu, Hawai‘i.
Kingston Environmental Services, Inc., et al. v. Boland, Inc. et al., CV NO. 16-00205 DKWWRP; ORDER GRANTING PLAINTIFF’S AMENDED MOTION TO LIFT STAY
14
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?