Anderson Burton Construction, Inc. v. Environmental Control Specialists, Inc.
Filing
180
ORDER (1) DENYING MOTION FOR SUMMARY JUDGMENT NO. 2 RE: CAUSATION, ECF NO. 100 ; AND (2) DENYING MOTION FOR SUMMARY JUDGMENT NO. 3 RE: BREACH OF CONTRACT, ECF NO. 102 . Signed by CHIEF JUDGE J. MICHAEL SEABRIGHT on 8/22/2018. (afc) ORDER furthermore GRANTS Plaintiff's Request for Judicial Notice (ECF 92 ), and DENIES the Motions to Strike, ECF nos. 147 and 163 . ORDER follows hearing held 6/21/2018. Minutes: ECF 170 .
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF HAWAII
ANDERSON BURTON
CONSTRUCTION, INC., a California
corporation,
Civ. No. 17-00063 JMS-KSC
ORDER (1) DENYING MOTION
FOR SUMMARY JUDGMENT NO.
2 RE: CAUSATION, ECF NO. 100;
AND (2) DENYING MOTION FOR
SUMMARY JUDGMENT NO. 3 RE:
BREACH OF CONTRACT, ECF NO.
102
Plaintiff,
vs.
ENVIRONMENTAL CONTROL
SPECIALISTS, INC., a Hawaii
corporation; IN & OUT BUILDERS,
INC., a Hawaii corporation; and DOES
1-10,
Defendants.
ORDER (1) DENYING MOTION FOR SUMMARY JUDGMENT NO. 2
RE: CAUSATION, ECF NO. 100; AND (2) DENYING MOTION FOR
SUMMARY JUDGMENT NO. 3 RE: BREACH OF CONTRACT,
ECF NO. 102
Anderson Burton Construction, Inc. (“Plaintiff”) filed its First
Amended Complaint (the “FAC”), ECF No. 38, bringing several claims against
Environmental Control Specialists, Inc. (“ECS”) and In & Out Builders, Inc.
(“IOB”) (collectively, “Defendants”). IOB then brought several motions for
summary judgment.
1
In a separate order, the court granted in part and denied in part IOB’s
Motion for Summary Judgment No. 1 Re: Waiver of Subrogation, ECF No. 98.
ECF No. 179. Now before the court are IOB’s two remaining motions for
summary judgment: Motion for Summary Judgment No. 2 Re: Causation, ECF
No. 100; and Motion for Summary Judgment No. 3 Re: Breach of Contract, ECF
No. 102. Because there are genuine issues of material fact concerning causation
and breach of contract, the Motions are DENIED. 1
IOB moves for summary judgment based on lack of causation,
arguing that IOB’s work did not cause the property damage. ECF No. 100-1 at 11.
Drawing all reasonable inferences on behalf of the nonmoving party, the court
easily determines that the February 19, 2018 Widing Deposition (the “2/19/18
Widing Deposition”), ECF No. 101-5, and the September 24, 2017 Ballesteros
Deposition (the “9/24/17 Ballesteros Deposition”),2 ECF No. 134-7, create genuine
1
The parties are familiar with the facts, and the court will not repeat them here.
2
IOB argues that, under Federal Rule of Civil Procedure 32(a), the 9/24/17 Ballesteros
Deposition is not admissible because IOB was neither present nor represented at the taking of the
deposition. ECF No. 147-1 at 11. Depositions may be considered as Rule 56 affidavits for
purposes of a motion for summary judgment, and thus need not comply with Rule 32(a). Hoover
v. Switlik Parachute Co., 663 F.2d 964, 967 (9th Cir. 1981). “Thus, the relevant inquiry is
whether the documents . . . otherwise qualify as affidavits.” Id. at 966. Here, the 9/24/17
Ballesteros Deposition qualified as an affidavit under Rule 56 because the deposition was made
based on Ballesteros’ personal knowledge, set out facts that would be admissible in evidence,
and showed that Ballesteros was competent to testify on the matters stated. See Fed. R. Civ. P.
56(c)(4). Thus, the 9/24/17 Ballesteros Deposition may be considered for purposes of summary
(continued . . .)
2
issues of material fact concerning whether IOB caused property damage to the
Visitor’s Center. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S.
574, 587 (1986) (recognizing that inferences drawn from underlying facts must be
viewed in the light most favorable to the party opposing summary judgment).
Thus, the court DENIES the Motion for Summary Judgment No. 2 Re: Causation.
IOB separately moves for summary judgment based on breach of
contract. ECF No. 102. IOB argues that the IOB Subcontract only required
indemnification for damages caused by IOB, and IOB did not cause the damage to
the Visitor’s Center. ECF No. 102-1 at 1. As discussed above, there is a genuine
issue of material fact concerning whether IOB caused the damage to the Visitor’s
Center. IOB also argues that there is no breach of contract because the IOB
Subcontract did not require IOB to protect the interior of the Visitor’s Center from
weather-related damage. Id. But the contract between the National Park Service
and Plaintiff (the “Prime Contract”) is incorporated into the IOB Subcontract, 3
(. . . continued)
judgment as a Rule 56 affidavit. Further, IOB is not prejudiced by the court’s holding because
IOB was given the opportunity to cross-examine Ballesteros in a later deposition.
3
The IOB Subcontract at ¶ 1.B. provides, in relevant part:
SUBCONTRACTOR agrees to be bound to PRIME
CONTRACTOR in the same manner and to the same extent as
PRIME CONTRACTOR is bound to OWNER under the Contract
(continued . . .)
3
ECF No. 38-3 at 2, and IOB’s roofing work pertains to the Prime Contract’s
provision requiring Plaintiff to “[m]aintain[] the building in a weather tight
condition throughout the construction period.” ECF No. 133-5 at 17. IOB is thus
also required to maintain the Visitor’s Center so that it is weather tight. Id.; see
also ECF No. 38-2 at 2. Accordingly, the Motion for Summary Judgment No. 3
Re: Breach of Contract is DENIED. 4
///
///
///
///
(. . . continued)
Documents, to the extent of the work provided for in this
Subcontract, and that where, in the Contract Documents, reference
is made to PRIME CONTRACTOR, and the work or specifications
therein pertains to SUBCONTRACTOR’s trade, craft, or type of
work, then such work or specification shall be interpreted to apply
to SUBCONTRACTOR instead of PRIME CONTRACTOR.
ECF No. 38-3 at 2. The contract between the National Park Service and Plaintiff is listed in the
IOB Subcontract as one of the “Contract Documents.” ECF No. 38-3 at 2.
4
In addition to the two Motions, Plaintiff filed a Request for Judicial Notice, ECF No.
92, and Plaintiff and IOB each filed motions to strike, ECF Nos. 147 and 163. Pursuant to
Federal Rule of Evidence 201(b)(2), the court GRANTS the Request for Judicial Notice, taking
judicial notice of the weather information in ECF No. 92-4, while acknowledging that the hourly
data is recorded at “PHOG located miles away from Haleakala National Park, Hawaii,” ECF No.
92-4. In its discretion, the court DENIES the motions to strike. In denying these motions, the
court finds no prejudice to either Plaintiff or Defendants.
4
For the foregoing reasons, the Motion for Summary Judgment No. 2
Re: Causation is DENIED; and the Motion for Summary Judgment No. 3 Re:
Breach of Contract is DENIED. Further, the Request for Judicial Notice is
GRANTED; IOB’s Motion to Strike is DENIED; and Plaintiff’s Motion to Strike
is DENIED.
IT IS SO ORDERED.
DATED: Honolulu, Hawaii, August 22, 2018.
/s/ J. Michael Seabright
J. Michael Seabright
Chief United States District Judge
Anderson Burton Constr., Inc. v. Envt’l Control Specialists, Inc., et al., Civ No. 17-00063 JMSKSC, Order (1) Denying Motion for Summary Judgment No. 2 Re: Causation, ECF No. 100; and
(2) Denying Motion for Summary Judgment No. 3 Re: Breach of Contract, ECF No. 102
5