PECK ORMSBY CONSTRUCTION COMPANY v. City of Rigby et al
Filing
84
MEMORANDUM AND ORDER re: Motions to Dismiss and to Compel Arbitration- Westerns motion to dismiss Peck Ormsby's bond claim is GRANTED; Western's motion to dismiss Rigbys maintenance bond claim is GRANTED; Parkson's motion to dismiss Ri gby's indemnification claim is GRANTED; Parkson's motion to compel arbitration of Rigbys breach of contract claim is DENIED; and the stay of discovery entered by the court on 8/2/11 is LIFTED. Signed by Judge William B. Shubb. (caused to be mailed to non Registered Participants at the addresses listed on the Notice of Electronic Filing (NEF) by jm)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
FOR THE DISTRICT OF IDAHO
10
----oo0oo----
11
12
NO. CIV. 1:10-545 WBS
PECK ORMSBY CONSTRUCTION
COMPANY, a Utah corporation,
13
MEMORANDUM AND ORDER RE:
MOTIONS TO DISMISS AND TO
COMPEL ARBITRATION
Plaintiff,
14
v.
15
18
CITY OF RIGBY, an Idaho
municipal corporation; PARKSON
CORPORATION, a Delaware
corporation; and WESTERN
SURETY COMPANY, a South Dakota
corporation,
19
Defendants.
16
17
/
20
21
AND RELATED COUNTERCLAIMS AND
CROSS-CLAIMS.
/
22
23
24
----oo0oo---Plaintiff Peck Ormsby Construction Company (“Peck
25
Ormsby”) brought this action against defendants City of Rigby
26
(“Rigby”), Parkson Corporation (“Parkson”), and Western Surety
27
Company (“Western”) arising from a construction project in Rigby
28
for which Peck Ormsby is the general contractor and Parkson is a
1
1
subcontractor.
After the court granted Parkson’s and Western’s
2
motions to dismiss with leave to amend, Peck Ormsby filed an
3
amended complaint and then a Second Amended Complaint (“SAC”),
4
alleging a claim for breach of contract against Rigby and a bond
5
claim against Western.
6
a counterclaim for breach of contract against Peck Ormsby and
7
cross-claims against Parkson for breach of contract and
8
indemnification and a bond claim against Western.
9
55.)
(Docket Nos. 44, 54, 64.)
Rigby brought
(Docket No.
Currently before the court are Parkson’s and Western’s
10
motions to dismiss the claims against them and Parkson’s motion
11
to compel arbitration of Rigby’s breach of contract claim.
12
I.
Factual and Procedural Background
13
In January of 2008, Rigby and Peck Ormsby entered into
14
an agreement (“Prime Contract”) whereby Peck Ormsby agreed to
15
construct a wastewater treatment plant in Rigby.
16
One of the components of the plant, a cloth filtration system,
17
would be made by a subcontractor, who was required under the
18
Prime Contract to provide a written guarantee to Rigby that the
19
filtration system would meet particular specifications.
20
Am. Answer, Crosscl. & Countercl. ¶ 15 (Docket No. 55).)
21
April 29, 2008, Peck Ormsby and Parkson entered into an agreement
22
(“Purchase Order”) whereby Parkson would supply the filtration
23
system.
24
Contract, Parkson provided Rigby a “Performance Guarantee” for
25
its equipment in July of 2008.
26
Countercl. ¶ 19.)
27
28
(SAC ¶ 9, 13.)
(SAC ¶¶ 7, 11.)
(Rigby’s
On
Pursuant to the requirement in the Prime
(Rigby’s Am. Answer, Crosscl. &
On August 15, 2008, Keller Associates (“Keller”), the
engineer for the project, reviewed and approved Parkson’s
2
1
submittals for the filtration system.
(SAC ¶ 14.)
The
2
filtration system was installed and operational by August 18,
3
2009.
(Id. ¶ 15.)
4
On September 9, 2009, Peck Ormsby received a letter
5
from Keller stating that the filtration system did not meet the
6
specified performance criteria.
7
the letter to Parkson.
(Id. ¶ 16.)
Peck Ormsby sent
(Id. ¶ 17.)
On April 16, 2010, pursuant to a Change Order to the
8
9
Prime Contract extending the time of final completion for the
10
project, Parkson as principal and Western as surety executed a
11
Maintenance Bond to guarantee the filtration system against
12
defects in material or workmanship, naming Peck Ormsby and Rigby
13
as dual obligees.
14
(Id. ¶¶ 19-20.)
On July 20, 2010, Peck Ormsby received a “rejection
15
letter” from Rigby and Keller formally rejecting the filtration
16
system “based on five (5) reasons indicating that the Equipment
17
is defective.”
18
letter, but has not repaired the alleged defects.
19
23.)1
(Id. ¶ 21.)
Parkson acknowledged receipt of the
(Id. ¶¶ 22-
20
21
22
23
24
25
26
27
28
1
The parties have requested that the court consider
certain documents in deciding the motions to dismiss. As a
general rule, “a district court may not consider any material
beyond the pleadings in ruling on a Rule 12(b)(6) motion.” Hal
Roach Studios, Inc. v. Richard Feiner & Co., 896 F.2d 1542, 1555
n.19 (9th Cir. 1989). However, the court may consider documents
on which the complaint necessarily relies if their authenticity
is not disputed. See Lee v. City of Los Angeles, 250 F.3d 668,
688 (9th Cir. 2001). On that ground and because the parties have
so agreed, the court will consider documents related to the Peck
Ormsby-Parkson agreement (Purchase Order Acknowledgment;
Parkson’s Quotation, including Standard Conditions of Sale,
Quotation Addendum, and General Arrangement Drawing; and Addenda
to Purchase Order cover letter and Supplier Purchase Order), and
Western’s Maintenance Bond. (Rothenberg Decl. Exs. A-C (Docket
3
1
2
II.
Discussion
A.
3
Motions to Dismiss
On a motion to dismiss, the court must accept the
4
allegations in the complaint as true and draw all reasonable
5
inferences in favor of the plaintiff.
6
U.S. 232, 236 (1974), overruled on other grounds by Davis v.
7
Scherer, 468 U.S. 183 (1984); Cruz v. Beto, 405 U.S. 319, 322
8
(1972).
9
contain sufficient factual matter, accepted as true, to ‘state a
Scheuer v. Rhodes, 416
“To survive a motion to dismiss, a complaint must
10
claim to relief that is plausible on its face.’”
11
Iqbal, --- U.S. ----, ----, 129 S. Ct. 1937, 1949 (2009) (quoting
12
Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)).
13
“plausibility standard,” however, “asks for more than a sheer
14
possibility that a defendant has acted unlawfully,” and “[w]here
15
a complaint pleads facts that are ‘merely consistent with’ a
16
defendant’s liability, it ‘stops short of the line between
17
possibility and plausibility of entitlement to relief.’”
18
129 S. Ct. at 1949 (quoting Twombly, 550 U.S. at 556-57).
19
20
1.
Ashcroft v.
This
Iqbal,
Western’s Motions to Dismiss Rigby’s Maintenance
Bond Cross-Claim and Peck Ormsby’s Bond Claim
21
22
23
24
25
26
27
28
No. 13); Micheli Decl. Ex. A (Docket No. 16).)
In deciding the motion to compel arbitration, the court
“may consider the pleadings, documents of uncontested validity,
and affidavits submitted by either party.” Macias v. Excel Bldg.
Servs. LLC, 767 F. Supp. 2d 1002, 1007 (N.D. Cal. 2011) (quoting
Ostroff v. Alterra Healthcare Corp., 433 F. Supp. 2d 538, 540
(E.D. Pa. 2006)). The parties request that the court consider
the documents comprising the Prime Contract between Rigby and
Peck Ormsby, the Purchase Order between Peck Ormsby and Parkson,
and the Performance Guarantee. (Mastin Decl. Ex. A (Docket No.
60); Ritchie Aff. Exs. A-F (Docket No. 72).) Accordingly, the
court will consider these documents in deciding the motion to
compel arbitration.
4
1
The bond pursuant to which Peck Ormsby and Rigby bring
2
their claims against Western states that Parkson “is required to
3
guarantee the work installed under [the Purchase Order] against
4
defects in materials or workmanship, which may develop during the
5
period of one year ending April 20, 2010.”
6
(Docket No. 16-3).)
7
recovery pursuant to the bond on the ground that Parkson failed
8
to repair the filtration system after being informed in the
9
September 9, 2009, letter and the July 20, 2010, rejection letter
(Mitcheli Decl. Ex. A
Peck Ormsby and Rigby sue Western for
10
that the filtration system did not meet the performance
11
standards.
Both Peck Ormsby and Rigby fail to plead liability with
12
13
the requisite specificity.
14
the letters sent to Parkson informed it of “defects in materials
15
or workmanship”; indeed, it appears from the allegations that the
16
filtration system had no actual defects but simply failed to meet
17
the performance standards set out in the Purchase Order and Prime
18
Contract.2
19
performance standards.
20
construed to apply to performance issues, the parties have not
21
provided any allegations regarding the type of defect that
22
occurred.
23
possibility to plausibility of entitlement to relief.
Western’s maintenance bond does not incorporate those
Even if the term “defect” could be
The bond claims simply do not cross the line from
Because Western cannot be held liable unless Parkson
24
25
There is no indication that either of
failed to meet its obligations under the bond, see Asociacion de
26
27
28
2
The court notes that it is unlikely Western would have
acted as surety to a bond in April of 2010 if Parkson had already
been informed of a defect in September of 2009.
5
1
Azucareros de Guatemala v. U.S. Nat’l Bank of Or., 423 F.2d 638,
2
641 (9th Cir. 1970), the court will dismiss Peck Ormsby’s and
3
Rigby’s bond claims against Western.
4
previously been given leave to amend in order to plead these
5
claims with the requisite specificity, but have failed to do so;
6
accordingly, the court will not give leave to amend a second
7
time.
8
2.
Peck Ormsby and Rigby have
Parkson’s Motion to Dismiss Rigby’s
Indemnification Claim
9
Rigby seeks indemnification from Parkson for any
10
11
damages Peck Orsmby recovers on its breach of contract claim
12
against Rigby.
13
must allege (1) an indemnity relationship, (2) actual liability
14
of the indemnitee to a third party, and (3) a reasonable
15
settlement amount.
16
284 (1988).
17
relationship, it has not alleged that it has been found liable to
18
Peck Ormsby or that a settlement has been reached.
19
time, Rigby cannot bring a claim for indemnification against
20
Parkson.
21
To state a claim for indemnification, a plaintiff
Chenery v. Agri-Lines Corp., 115 Idaho 281,
Even if Rigby has properly alleged an indemnity
Until that
Rigby argues that it is required to assert the claim
22
now, even though it admits no settlement has taken place.
23
However, Rigby’s claim against Parkson is permissive, not
24
compulsory.
25
666 F.2d 361, 363 (9th Cir. 1982).
26
claim for indemnity against Parkson if and when judgment is
27
entered against Rigby, the court will dismiss this claim.
28
B.
See Fed. R. Civ. P. 13(a), (g); Peterson v. Watt,
Because Rigby may bring a
Parkson’s Motion to Compel Arbitration of Rigby’s
6
1
Breach of Contract Claim
2
The Prime Contract between Rigby and Peck Ormsby
3
provides that the subcontractor installing the filtration system
4
would be required to “provide a written guarantee that the
5
installed filter system will produce an effluent that meets the
6
suspended solids requirements of this specification, based on the
7
specified wastewater quality entering the filtration process.”
8
(Ritchie Aff. ¶ 5, Ex. D (Docket No. 70-5).)
9
between Peck Ormsby and Parkson states that Parkson “does hereby
10
agree to be bound by the terms of the prime contract agreement,
11
construction regulations, general conditions, plans and
12
specifications, and any and all other contract documents in so
13
far as they are applicable to this purchase order.”
14
Ex. E.)
15
[Rigby], a guarantee in writing for [Parkson’s] work.”
The Purchase Order
(Id. ¶ 6,
Parkson also agreed “to execute to [Peck Ormsby] and/or
16
(Id.)
Pursuant to these obligations, Parkson provided the
17
Performance Guarantee to Rigby in July of 2008, stating that
18
Parkson would provide a filtration system that would meet
19
specific performance and design specification standards for
20
effluent.
21
contains an arbitration clause and Florida choice of law
22
provision.
23
Guarantee for breach of contract, and Parkson moves to compel
24
arbitration of the claim.
(Id. ¶ 7, Ex. F.)
(Id.)
The Performance Guarantee also
Rigby now sues Parkson under the Performance
25
The Federal Arbitration Act (“FAA”) provides that a
26
party may seek an order to compel arbitration from a district
27
court where another party fails, neglects, or refuses to
28
arbitrate.
9 U.S.C. § 4.
The Act “leaves no place for the
7
1
exercise of discretion by a district court, but instead mandates
2
that district courts shall direct the parties to proceed to
3
arbitration on issues as to which an arbitration agreement has
4
been signed.”
5
218 (1985).
6
to determining (1) whether a valid agreement to arbitrate exists
7
and, if it does, (2) whether the agreement encompasses the
8
dispute at issue.”
9
207 F.3d 1126, 1130 (9th Cir. 2000).
Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213,
“The court’s role under the Act is therefore limited
Chiron Corp. v. Ortho Diagnostic Sys., Inc.,
Upon a showing that a party
10
has failed to comply with a valid arbitration agreement, the
11
district court must issue an order compelling arbitration.
12
v. Wedbush, Noble, Cooke, Inc., 841 F.2d 282, 285 (9th Cir.
13
1988), overruled on other grounds by Ticknor v. Choice Hotels
14
Int’l, Inc., 265 F.3d 931 (9th Cir. 2001).
Cohen
15
Although the FAA sets forth a policy favoring
16
arbitration, “a party cannot be required to submit to arbitration
17
in any dispute which he has not agreed so to submit.”
18
Steelworkers of Am. v. Warrior & Gulf Navigation Co., 363 U.S.
19
574, 582 (1960); see also Three Valleys Mun. Water Dist. v. E.F.
20
Hutton & Co., 925 F.2d 1136, 1139 (9th Cir. 1991).
21
a party has submitted to arbitration is first and foremost a
22
matter of contractual interpretation that must hinge on the
23
intent of the parties.
24
Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473
25
U.S. 614, 626 (1985).
26
United
Thus, whether
United Steelworkers, 363 U.S. at 582;
Rigby does not dispute Peck Ormsby’s contention that
27
the arbitration clause, if valid, encompasses the breach of
28
contract claim; Rigby only argues that the arbitration clause in
8
1
the Performance Guarantee did not constitute a valid agreement.
The commonly accepted meaning of “guarantee” is “[t]he
2
3
assurance that a contract or legal act will be duly carried out.”
4
Black’s Law Dictionary 772 (9th ed. 2009).
5
“performance” is defined to mean “[t]he successful completion of
6
a contractual duty.”
7
the term ‘performance guarantee’ is an assurance or promise that
8
a contractual obligation will be fulfilled.”
9
Props, LLC, Civil Nos. 1:10cv98, 1:10cv198, 2011 WL 1131057, at
Id. at 1252.
The term
Thus, “the plain meaning of
In re Versant
10
*7 (W.D.N.C. Mar. 25, 2011).
11
the Purchase Order, which incorporated portions of the Prime
12
Contract, to give Rigby a Performance Guarantee.
13
the Performance Guarantee, Parkson was promising to fulfill a
14
preexisting obligation.3
15
Parkson was allegedly required by
By giving Rigby
Under Idaho contract law, a party cannot unilaterally
16
amend an agreement to add an arbitration clause unless the
17
original contract expressly provided that party with the right to
18
make such a modification.
19
Idaho 1, 3 (2008).
20
clause in the Performance Guarantee it was contractually
21
obligated to give Rigby without the right to do so.
22
Rigby never agreed to arbitrate disputes with Parkson, the court
23
will deny Parkson’s motion to compel arbitration.
24
IT IS THEREFORE ORDERED that:
25
(1) Western’s motion to dismiss Peck Ormsby’s bond
MBNA Am. Bank, N.A. v. Fouche, 146
Parkson unilaterally placed an arbitration
Because
26
3
27
28
In deciding this motion, the court makes no judgment
regarding the merits of the underlying breach of contract claim.
See United Computer Sys., Inc. v. AT & T Corp., 298 F.3d 756, 766
(9th Cir. 2002).
9
1
claim be, and the same hereby is, GRANTED;
2
3
(2) Western’s motion to dismiss Rigby’s maintenance
bond claim be, and the same hereby is, GRANTED;
4
5
(3) Parkson’s motion to dismiss Rigby’s indemnification
claim be, and the same hereby is, GRANTED;
6
7
(4) Parkson’s motion to compel arbitration of Rigby’s
breach of contract claim be, and the same hereby is, DENIED; and
(5) The stay of discovery entered by the court on
8
9
10
August 22, 2011, is hereby LIFTED.
DATED:
August 31, 2011
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
10
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?