PECK ORMSBY CONSTRUCTION COMPANY v. City of Rigby et al
Filing
96
AMENDED MEMORANDUM ORDER Re: Motions to Dismiss and to Compel Arbitration. Western's motion to dismiss Peck Ormsby's bond claim is GRANTED; Western's motion to dismiss Rigby's maintenance bond claim is GRANTED; Parkson's moti on to dismiss Rigby's indemnification claim is GRANTED; Parkson's motion to compel arbitration of Rigby's breach of contract claim is DENIED; and the stay of discovery entered by the court on 8/22/11 is LIFTED. Signed by Judge William B. Shubb. (caused to be mailed to non Registered Participants at the addresses listed on the Notice of Electronic Filing (NEF) by jm)
1
2
3
4
5
6
7
8
UNITED STATES DISTRICT COURT
9
FOR THE DISTRICT OF IDAHO
10
----oo0oo----
11
12
PECK ORMSBY CONSTRUCTION
COMPANY, a Utah corporation,
NO. CIV. 1:10-545 WBS
13
Plaintiff,
AMENDED MEMORANDUM AND ORDER
RE: MOTIONS TO DISMISS AND TO
COMPEL ARBITRATION
14
v.
15
18
CITY OF RIGBY, an Idaho
municipal corporation; PARKSON
CORPORATION, a Delaware
corporation; and WESTERN
SURETY COMPANY, a South Dakota
corporation,
19
Defendants.
16
17
/
20
21
AND RELATED COUNTERCLAIMS AND
CROSS-CLAIMS.
/
22
23
24
----oo0oo---Plaintiff Peck Ormsby Construction Company (“Peck
25
Ormsby”) brought this action against defendants City of Rigby
26
(“Rigby”), Parkson Corporation (“Parkson”), and Western Surety
27
Company (“Western”) arising from a construction project in Rigby
28
for which Peck Ormsby is the general contractor and Parkson is a
1
1
subcontractor.
After the court granted Parkson’s and Western’s
2
motions to dismiss with leave to amend, Peck Ormsby filed an
3
amended complaint and then a Second Amended Complaint (“SAC”),
4
alleging a claim for breach of contract against Rigby and a bond
5
claim against Western.
6
a counterclaim for breach of contract against Peck Ormsby and
7
cross-claims against Parkson for breach of contract and
8
indemnification and a bond claim against Western.
9
55.)
(Docket Nos. 44, 54, 64.)
Rigby brought
(Docket No.
Currently before the court are Parkson’s and Western’s
10
motions to dismiss the claims against them and Parkson’s motion
11
to compel arbitration of Rigby’s breach of contract claim.
12
I.
13
Factual and Procedural Background
In January of 2008, Rigby and Peck Ormsby entered into
14
an agreement (the “Prime Contract”) whereby Peck Ormsby agreed to
15
construct a wastewater treatment plant in Rigby.
16
One of the components of the plant, a cloth filtration system,
17
would be made by a subcontractor, who was required under the
18
Prime Contract to provide a written guarantee to Rigby that the
19
filtration system would meet particular specifications.
20
Am. Answer, Crosscl. & Countercl. ¶ 15 (Docket No. 55).)
21
(SAC ¶¶ 7, 11.)
(Rigby’s
On April 29, 2008, Peck Ormsby and Parkson entered into
22
an agreement (the “Purchase Order”) whereby Parkson would supply
23
the filtration system.
24
language in the Purchase Order was modified by an agreement (the
25
“Letter Agreement”) signed by Parkson and Peck Ormsby earlier on
26
April 29, 2008, declaring that “Parkson is not in privity of
27
contract with the Owner [Rigby].”
28
Parkson provided Rigby a “Performance Guarantee” for its
(SAC ¶ 9, 13.)
2
Parkson alleges that the
(Rothenberg Decl. Ex. A at 2.)
1
equipment “as required by the technical specifications [of the
2
Prime Contract’s technical specifications]” in July of 2008.
3
(Mot. for Recons. at 7.)
4
On August 15, 2008, Keller Associates (“Keller”), the
5
engineer for the project, reviewed and approved Parkson’s
6
submittals for the filtration system.
7
filtration system was installed and operational by August 18,
8
2009.
(SAC ¶ 14.)
The
(Id. ¶ 15.)
On September 9, 2009, Peck Ormsby received a letter
9
10
from Keller stating that the filtration system did not meet the
11
specified performance criteria.
12
the letter to Parkson.
13
(Id. ¶ 16.)
Peck Ormsby sent
(Id. ¶ 17.)
On April 16, 2010, pursuant to a Change Order to the
14
Prime Contract extending the time of final completion for the
15
project, Parkson as principal and Western as surety executed a
16
Maintenance Bond to guarantee the filtration system against
17
defects in material or workmanship, naming Peck Ormsby and Rigby
18
as dual obligees.
19
(Id. ¶¶ 19-20.)
On July 20, 2010, Peck Ormsby received a “rejection
20
letter” from Rigby and Keller formally rejecting the filtration
21
system “based on five (5) reasons indicating that the Equipment
22
is defective.”
23
letter, but has not repaired the alleged defects.
24
23.)1
(Id. ¶ 21.)
Parkson acknowledged receipt of the
(Id. ¶¶ 22-
25
26
27
28
1
The parties have requested that the court consider
certain documents in deciding the motions to dismiss. As a
general rule, “a district court may not consider any material
beyond the pleadings in ruling on a Rule 12(b)(6) motion.” Hal
Roach Studios, Inc. v. Richard Feiner & Co., 896 F.2d 1542, 1555
3
1
2
II.
Discussion
A.
3
Motions to Dismiss
On a motion to dismiss, the court must accept the
4
allegations in the complaint as true and draw all reasonable
5
inferences in favor of the plaintiff.
6
U.S. 232, 236 (1974), overruled on other grounds by Davis v.
7
Scherer, 468 U.S. 183 (1984); Cruz v. Beto, 405 U.S. 319, 322
8
(1972).
9
contain sufficient factual matter, accepted as true, to ‘state a
Scheuer v. Rhodes, 416
“To survive a motion to dismiss, a complaint must
10
claim to relief that is plausible on its face.’”
Ashcroft v.
11
Iqbal, 556 U.S. 662, ---, 129 S. Ct. 1937, 1949 (2009) (quoting
12
Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)).
13
“plausibility standard,” however, “asks for more than a sheer
14
possibility that a defendant has acted unlawfully,” and “[w]here
15
a complaint pleads facts that are ‘merely consistent with’ a
This
16
17
18
19
20
21
22
23
24
25
26
27
28
n.19 (9th Cir. 1989). However, the court may consider documents
on which the complaint necessarily relies if their authenticity
is not disputed. See Lee v. City of Los Angeles, 250 F.3d 668,
688 (9th Cir. 2001). On that ground and because the parties have
so agreed, the court will consider documents related to the Peck
Ormsby-Parkson agreement (Purchase Order Acknowledgment;
Parkson’s Quotation, including Standard Conditions of Sale,
Quotation Addendum, and General Arrangement Drawing; and Addenda
to Purchase Order cover letter and Supplier Purchase Order), and
Western’s Maintenance Bond. (Rothenberg Decl. Exs. A-C (Docket
No. 13); Micheli Decl. Ex. A (Docket No. 16).)
In deciding the motion to compel arbitration, the court
“may consider the pleadings, documents of uncontested validity,
and affidavits submitted by either party.” Macias v. Excel Bldg.
Servs. LLC, 767 F. Supp. 2d 1002, 1007 (N.D. Cal. 2011) (quoting
Ostroff v. Alterra Healthcare Corp., 433 F. Supp. 2d 538, 540
(E.D. Pa. 2006)). The parties request that the court consider
the documents comprising the Prime Contract between Rigby and
Peck Ormsby, the Purchase Order between Peck Ormsby and Parkson,
and the Performance Guarantee. (Mastin Decl. Ex. A (Docket No.
60); Ritchie Aff. Exs. A-F (Docket No. 72).) Accordingly, the
court will consider these documents in deciding the motion to
compel arbitration.
4
1
defendant’s liability, it ‘stops short of the line between
2
possibility and plausibility of entitlement to relief.’”
3
(quoting Twombly, 550 U.S. at 556-57).
4
1.
Id.
Western’s Motions to Dismiss Rigby’s Maintenance
5
Bond Cross-Claim and Peck Ormsby’s Bond Claim
6
The bond pursuant to which Peck Ormsby and Rigby bring
7
their claims against Western states that Parkson “is required to
8
guarantee the work installed under [the Purchase Order] against
9
defects in materials or workmanship, which may develop during the
10
period of one year ending April 20, 2010.”
11
(Docket No. 16-3).)
12
recovery pursuant to the bond on the ground that Parkson failed
13
to repair the filtration system after being informed in the
14
September 9, 2009, letter and the July 20, 2010, rejection letter
15
that the filtration system did not meet the performance
16
standards.
17
(Mitcheli Decl. Ex. A
Peck Ormsby and Rigby sue Western for
Both Peck Ormsby and Rigby fail to plead liability with
18
the requisite specificity.
19
the letters sent to Parkson informed it of “defects in materials
20
or workmanship”; indeed, it appears from the allegations that the
21
filtration system had no actual defects but simply failed to meet
22
the performance standards set out in the Purchase Order and Prime
23
Contract.2
24
performance standards.
25
construed to apply to performance issues, the parties have not
There is no indication that either of
Western’s maintenance bond does not incorporate those
Even if the term “defect” could be
26
27
28
2
The court notes that it is unlikely Western would have
acted as surety to a bond in April of 2010 if Parkson had already
been informed of a defect in September of 2009.
5
1
provided any allegations regarding the type of defect that
2
occurred.
3
possibility to plausibility of entitlement to relief.
4
The bond claims simply do not cross the line from
Because Western cannot be held liable unless Parkson
5
failed to meet its obligations under the bond, see Asociacion de
6
Azucareros de Guatemala v. U.S. Nat’l Bank of Or., 423 F.2d 638,
7
641 (9th Cir. 1970), the court will dismiss Peck Ormsby’s and
8
Rigby’s bond claims against Western.
9
previously been given leave to amend in order to plead these
Peck Ormsby and Rigby have
10
claims with the requisite specificity, but have failed to do so;
11
accordingly, the court will not give leave to amend a second
12
time.
13
2.
Parkson’s Motion to Dismiss Rigby’s
14
Indemnification Claim
15
Rigby seeks indemnification from Parkson for any
16
damages Peck Orsmby recovers on its breach of contract claim
17
against Rigby.
18
must allege (1) an indemnity relationship, (2) actual liability
19
of the indemnitee to a third party, and (3) a reasonable
20
settlement amount.
21
284 (1988).
22
relationship, it has not alleged that it has been found liable to
23
Peck Ormsby or that a settlement has been reached.
24
time, Rigby cannot bring a claim for indemnification against
25
Parkson.
26
To state a claim for indemnification, a plaintiff
Chenery v. Agri-Lines Corp., 115 Idaho 281,
Even if Rigby has properly alleged an indemnity
Until that
Rigby argues that it is required to assert the claim
27
now, even though it admits no settlement has taken place.
28
However, Rigby’s claim against Parkson is permissive, not
6
1
compulsory.
2
666 F.2d 361, 363 (9th Cir. 1982).
3
claim for indemnity against Parkson if and when judgment is
4
entered against Rigby, the court will dismiss this claim.
5
B.
See Fed. R. Civ. P. 13(a), (g); Peterson v. Watt,
Because Rigby may bring a
Parkson’s Motion to Compel Arbitration of Rigby’s
6
Breach of Contract Claim
7
The Prime Contract between Rigby and Peck Ormsby
8
provides that the subcontractor installing the filtration system
9
would be required to “provide a written guarantee that the
10
installed filter system will produce an effluent that meets the
11
suspended solids requirements of this specification, based on the
12
specified wastewater quality entering the filtration process.”
13
(Ritchie Aff. ¶ 5, Ex. D (Docket No. 70-5).)
14
between Peck Ormsby and Parkson states that Parkson agrees “to
15
execute to [Peck Ormsby] and/or [Rigby], a guarantee in writing
16
for [Parkson’s] work.”
17
Agreement executed prior to the Purchase Order states that:
18
19
20
21
22
(Id. Ex. E.)
The Purchase Order
However, the Letter
Parkson agrees to be bound to the Contract in accordance
with the technical and general portions of the documents
that form a part of the Prime Contract only to the extent
they are applicable to the supply and delivery of the
material, equipment and workmanship under the Contract
and in accordance with the terms and conditions of the
Seller’s Quotation and the Drawings and Specifications as
amended during the Submittal process. Parkson is not in
privity of contact with the Owner. Therefore, no terms
and conditions between you and the Owner govern Parkson.
23
24
(Rothenberg Decl. Ex. A at 2.)
25
Parkson provided the Performance Guarantee to Rigby “as
26
required by the technical specifications [of the Prime Contract’s
27
technical specifications],” (Mot. for Recons. at 7), in July of
28
2008, stating that Parkson would provide a filtration system that
7
1
would meet express performance and design specification standards
2
for effluent.
3
Guarantee also contains an arbitration clause and Florida choice
4
of law provision.
5
Performance Guarantee provided by Parkson for breach of contract,
6
and Parkson moves to compel arbitration of the claim.
(Ritchie Aff. ¶ 7, Ex. F.)
(Id.)
The Performance
Rigby now sues Parkson under the
7
The Federal Arbitration Act (“FAA”) provides that a
8
party may seek an order to compel arbitration from a district
9
court where another party fails, neglects, or refuses to
10
arbitrate.
9 U.S.C. § 4.
The Act “leaves no place for the
11
exercise of discretion by a district court, but instead mandates
12
that district courts shall direct the parties to proceed to
13
arbitration on issues as to which an arbitration agreement has
14
been signed.”
15
218 (1985).
16
to determining (1) whether a valid agreement to arbitrate exists
17
and, if it does, (2) whether the agreement encompasses the
18
dispute at issue.”
19
207 F.3d 1126, 1130 (9th Cir. 2000).
20
has failed to comply with a valid arbitration agreement, the
21
district court must issue an order compelling arbitration.
22
v. Wedbush, Noble, Cooke, Inc., 841 F.2d 282, 285 (9th Cir.
23
1988), overruled on other grounds by Ticknor v. Choice Hotels
24
Int’l, Inc., 265 F.3d 931 (9th Cir. 2001).
Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213,
“The court’s role under the Act is therefore limited
Chiron Corp. v. Ortho Diagnostic Sys., Inc.,
Upon a showing that a party
Cohen
25
Although the FAA sets forth a policy favoring
26
arbitration, “a party cannot be required to submit to arbitration
27
in any dispute which he has not agreed so to submit.”
28
Steelworkers of Am. v. Warrior & Gulf Navigation Co., 363 U.S.
8
United
1
574, 582 (1960); see also Three Valleys Mun. Water Dist. v. E.F.
2
Hutton & Co., 925 F.2d 1136, 1139 (9th Cir. 1991).
3
a party has submitted to arbitration is first and foremost a
4
matter of contractual interpretation that must hinge on the
5
intent of the parties.
6
Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473
7
U.S. 614, 626 (1985).
8
9
Thus, whether
United Steelworkers, 363 U.S. at 582;
Rigby does not dispute Peck Ormsby’s contention that
the arbitration clause, if valid, encompasses the breach of
10
contract claim; Rigby only argues that the arbitration clause in
11
the Performance Guarantee did not constitute a valid agreement
12
because Rigby never signed the Performance Guarantee or consented
13
to arbitrate future disputes with Parkson.
14
The commonly accepted meaning of “guarantee” is “[t]he
15
assurance that a contract or legal act will be duly carried out.”
16
Black’s Law Dictionary 772 (9th ed. 2009).
17
“performance” is defined to mean “[t]he successful completion of
18
a contractual duty.”
19
the term ‘performance guarantee’ is an assurance or promise that
20
a contractual obligation will be fulfilled.”
21
Props, LLC, Civil Nos. 1:10cv98, 1:10cv198, 2011 WL 1131057, at
22
*7 (W.D.N.C. Mar. 25, 2011).
23
Id. at 1252.
The term
Thus, “the plain meaning of
In re Versant
Parkson was allegedly required by the Purchase Order to
24
give Rigby a Performance Guarantee.
Parkson argues that it was
25
not bound by the terms of the Purchase Order incorporating the
26
Prime Contract because the Letter Agreement expressly states that
27
“no terms and conditions between you [Peck Ormsby] and the Owner
28
[Rigby] govern Parkson.”
(Rothenberg Decl. Ex. A at 2.)
9
1
However, the Letter Agreement also states that “Parkson
2
agrees to be bound to the [Purchase Order] in accordance with the
3
technical and general portions of the documents that form a part
4
of the Prime Contract only to the extent that they are applicable
5
to the supply and delivery of the material, equipment and
6
workmanship under the [Purchase Order] . . . .”
7
Contract’s technical specifications on the provision of cloth
8
filter equipment requires the subcontractor to provide Rigby with
9
a Performance Guarantee.
(Id.)
(Ritchie Aff. Ex. D ¶ 1.04.)
The Prime
This
10
contractual language, combined with Parkson’s statement that it
11
provided the Performance Guarantee to Riby “as required by the
12
technical specifications of [the Prime Contract],” (Mot. for
13
Recons. at 7), suggests that the portion of the Prime Contract
14
requiring a Performance Guarantee has been incorporated under the
15
terms of the Letter Agreement.
16
privity of contract between Parkson and Rigby, Parkson was
17
obligated to Peck Ormsby to provide Rigby with a Performance
18
Guarantee.
19
was fulfilling a preexisting obligation.3
Regardless of whether there was
By giving Rigby the Performance Guarantee, Parkson
Under Idaho contract law, a party cannot unilaterally
20
21
amend an agreement by adding an arbitration clause unless the
22
original contract expressly provided that party with the right to
23
make such a modification.
24
Idaho 1, 3 (2008).
25
clause in the Performance Guarantee it was contractually
MBNA Am. Bank, N.A. v. Fouche, 146
Parkson unilaterally placed an arbitration
26
3
27
28
In deciding this motion, the court makes no judgment
regarding the merits of the underlying breach of contract claim.
See United Computer Sys., Inc. v. AT & T Corp., 298 F.3d 756, 766
(9th Cir. 2002).
10
1
obligated to give to Rigby without the right to do so.
2
At oral arguments on the Motion for Reconsideration,
3
Parkson argued for the first time that there are three exceptions
4
to the pre-existing duty rule.4
5
-- that Parkson had no pre-existing duty to Rigby -- has already
6
been addressed by this court.
7
presents is that the Uniform Commercial Code (“UCC”) has
8
abolished the pre-existing duty rule for the sale of goods.
9
U.C.C. § 2-209; Idaho Code Ann. § 28-2-209(1).
The first articulated exception
The second exception that Parkson
See
It is not clear
10
that UCC § 2-209 applies in this case because it covers
11
“agreement[s] modifying a contract,” U.C.C. § 2-209(1), not the
12
unilateral inclusion of a contract provision.
13
there was neither an agreement nor a pre-existing contract to
14
modify.
15
suggests that the Performance Guarantee should not be considered
16
an “agreement” under UCC § 2-209.
17
denies that it was in privity of contract with Rigby prior to the
18
Performance Guarantee, the Performance Guarantee did not modify a
19
pre-existing contract.
20
existing duty rule does not govern this case.
In this case,
Rigby never signed the Performance Guarantee, which
Further, as Parkson also
Thus, UCC § 2-209's abolition of the pre-
21
Even if UCC § 2-209 applied in this case, its
22
application here would be contrary to the FAA’s requirement that
23
parties expressly agree to submit to arbitration.
See United
24
25
26
27
28
4
The court was led to believe that support for these
three exceptions was provided in a letter brief presented by
Parkson at oral arguments. Based upon this representation, the
court granted Rigby permission to file a letter brief in response
to Parkson’s submission. Upon later review of Parkson’s letter
brief, the court discovered that it did not in fact present
support for the three exceptions.
11
1
Steelworkers of Am., 363 U.S. at 582.
2
authority, nor has Parkson cited cases, supporting the
3
application of UCC § 2-209 to unilaterally imposed arbitration
4
provisions.
5
The court is aware of no
Courts have occasionally upheld the unilateral
6
inclusion of arbitration provisions under UCC § 2-207.
See,
7
e.g., Dixie Aluminum Prods. Co. v. Mitsubishi Int’l Corp., 785 F.
8
Supp. 157, 160-61 (N.D. Ga. 1992) (finding inclusion of
9
arbitration clause in confirming document did not materially
10
alter agreement where there was no unfair surprise because the
11
document had been used in prior dealings between the parties).
12
Unlike UCC § 2-209, which applies to the modification of pre-
13
existing contracts, UCC § 2-207 allows for the possibility that
14
additional terms added to a written confirmation between
15
merchants may form part of the original contract.
16
arbitration provisions included in written confirmations are not
17
automatically binding under UCC § 2-207.
18
Aikman Corp., 453 F.2d 1161, 1169 n.8 (6th Cir. 1972) (finding
19
the validity of an arbitration provision in a written
20
confirmation rests upon the particular facts of the case).
21
However,
See Dorton v. Collins &
Courts interpreting whether UCC § 2-207 permits a
22
unilaterally imposed arbitration provision must first determine
23
whether the arbitration provision materially alters the
24
underlying contract.
25
is influenced by whether the inclusion of the arbitration term
26
presents an unfair surprise based on the parties’ prior dealings
27
or industry standards.
28
Elecs., 828 F. Supp. 178, 183-84 (S.D.N.Y. 1993) (holding that
U.C.C. § 2-207(2)(b).
Such a determination
See, e.g., Hatzlachh Supply v. Moishe’s
12
1
arbitration provision was not a material alteration where the
2
buyer had previously received 42 invoices that all included the
3
arbitration provision); Dixie Aluminum Prods., 785 F. Supp. at
4
160-61 (finding arbitration provision had been used in prior
5
dealings between the parties).
6
The occasional allowance of unilaterally imposed
7
arbitration provisions under UCC § 2-207 does not suggest that
8
such provisions should be upheld under UCC § 2-209's pre-existing
9
duty rule.
Under UCC § 2-207, the court asks whether the
10
arbitration provision unilaterally included in a written
11
confirmation should be considered part of the underlying
12
contract.
13
duty rule covers agreements modifying existing, finalized
14
contracts.
15
for mutual agreements under UCC § 2-209, has no place in the
16
application of UCC § 2-207 to unilaterally included provisions
17
because the contract finalized by the written confirmation
18
constitutes the consideration.
19
test under UCC § 2-209 as there is under UCC § 2-207 because,
20
presumably, the mutual intention of the parties under UCC § 2-209
21
is to alter the existing contract.
22
Under UCC § 2-209, the elimination of the pre-existing
A discussion of consideration, which is not necessary
There is no “materially alter”
UCC § 2-207 governs contract provisions added by a
23
party unilaterally, whereas UCC § 2-209 governs provisions that
24
alter a pre-existing contract based on mutual agreement.
25
Parkson claims that the Performance Guarantee created a mutual,
26
binding agreement between itself and Rigby.
27
mutual intention to arbitrate disputes in this case because Rigby
28
never signed the Performance Guarantee or in any way agreed to
13
Here,
However, there is no
1
arbitrate disputes with Parkson.
2
The final exception proposed by Parkson to the pre-
3
existing duty rule is triggered when the promisee undertakes to
4
do something in addition to what he already is obligated to do
5
under his pre-existing duty.
6
undertake testing and recommend solutions if the equipment it
7
provided were to fail, it made additional promises to Rigby that
8
were not found in the technical specifications of the Prime
9
Contract.
Parkson claims that by agreeing to
This exception does not apply in this case as it
10
governs contract modifications mutually agreed upon by the
11
parties.
12
Airways, 944 F.2d 983, 991 (applying the exception “if the
13
bargained-for performance rendered by the promisee includes
14
something that is not within the requirements of the pre-existing
15
duty”); Great Plains Equip, Inc. v. Nw. Pipeline Corp., 132 Idaho
16
754, 769-70 (1999) (applying the exception after finding that the
17
parties implicitly agreed to the contract modification).
18
Allowing such a unilateral contract modification to impose
19
arbitration would permit Parkson to circumvent the FAA
20
requirement that the parties expressly agree to arbitrate their
21
claims.
22
See, e.g., Care Travel Co., Ltd. v. Pan Am. World
Parkson provided the Performance Guarantee to Rigby
23
under its pre-existing duty to Peck Ormsby.
24
the Performance Guarantee nor affirmatively agreed to the
25
arbitration provision contained within it.
26
agreed to arbitrate disputes with Parkson, the court will deny
27
28
14
Rigby never signed
Because Rigby never
1
Parkson’s motion to compel arbitration.5
2
IT IS THEREFORE ORDERED that:
3
(1) Western’s motion to dismiss Peck Ormsby’s bond
4
claim be, and the same hereby is, GRANTED;
5
6
(2) Western’s motion to dismiss Rigby’s maintenance
bond claim be, and the same hereby is, GRANTED;
(3) Parkson’s motion to dismiss Rigby’s indemnification
7
8
claim be, and the same hereby is, GRANTED;
(4) Parkson’s motion to compel arbitration of Rigby’s
9
10
breach of contract claim be, and the same hereby is, DENIED; and
(5) The stay of discovery entered by the court on
11
12
August 22, 2011, is hereby LIFTED.
13
DATED:
November 7, 2011
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
5
In the event that the court is not persuaded to change
its mind, Parkson requests further clarification of the effect of
the court’s ruling on Parkson and Rigby’s contractual
relationship. This determination is outside the scope of the
original order. This Amended Order only addresses the
invalidation of the arbitration provision of the Performance
Agreement and does not address the validity of any other
provision.
15
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?