SMK Associates, LLC v. Sutherland Global Services, Inc
Filing
168
MEMORANDUM Opinion and Order Signed by the Honorable John Z. Lee on 7/9/18.Mailed notice(ca, )
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 1 of 14 PageID #:2235
IN THE UNITED STATES DISTRICT COURT
FOR THE NORTHERN DISTRICT OF ILLINOIS
EASTERN DIVISION
SMK ASSOCIATES, LLC,
Plaintiff,
v.
SUTHERLAND GLOBAL SERVICES,
INC., and MICHAEL BARTUSEK,
Defendants.
)
)
)
)
)
)
)
)
)
)
14 C 0284
Judge John Z. Lee
MEMORANDUM OPINION AND ORDER
Plaintiff SMK Associates, Inc. (“SMK”), brought suit against Sutherland Global Services,
Inc. (“Sutherland”) and its former Chief Financial Officer, Michael Bartusek, alleging that
Sutherland breached two contracts to sell SMK $84 million in tobacco products. Before the Court
is the question whether the liquidated damages provisions that are the basis for SMK’s damages
claim are enforceable under Illinois law, or if they constitute unenforceable penalties. For the
reasons that follow, the Court finds that the provisions at issue are unenforceable penalties.
Procedural History
SMK filed suit against Sutherland and Bartusek on January 15, 2014. See generally
Compl., ECF No. 1. In Sutherland’s July 11, 2014, answer to SMK’s second amended complaint,
Sutherland raised the affirmative defense that the “amount sought by SMK constitutes an
impermissible contractual penalty rather than liquidated damages.” Answer to 2d. Am. Compl. at
19, ECF No. 44.
Sutherland moved for summary judgment on October 29, 2015, arguing primarily that
Bartusek, who was then its Chief Financial Official (“CFO”), acted of his own accord and not on
behalf of Sutherland when he agreed to the purchase contracts with SMK. See Def.’s Mem. Supp.
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 2 of 14 PageID #:2236
Summ. J. at 8–11, ECF No. 100. In moving for summary judgment, Sutherland did not challenge
the enforceability of the contractual penalty provision. See generally id. The Court denied
Sutherland summary judgment on September 29, 2016, concluding that there was sufficient
evidence for a reasonable jury to find that Bartusek was acting on Sutherland’s behalf. SMK
Assocs., LLC v. Sutherland Glob. Servs., Inc., No. 14 C 284, 2016 WL 5476256, at *5 (N.D. Ill.
Sept. 29, 2016).
At the pretrial conference on May 24, 2017, SMK conceded that the only damages that it
sought were based on the liquidated damages clauses in the contracts. Whether a contractual
provision for damages is a valid liquidated damages provision or an unenforceable penalty clause
is a question of law. ICD Publ’ns, Inc. v. Gittlitz, 24 N.E.3d 898, 919 (Ill. App. Ct. 2014). As the
enforceability of the damages clauses at question would shape the jury trial, the parties agreed to
an evidentiary hearing on the issue. See ECF No. 154.
The Hearing
Sutherland called two witnesses at the evidentiary hearing: Michael Bartusek, who served
as Sutherland’s CFO from June 2007 to September 2014, Hearing Tr. (“Tr.”) at 7:8–12; and Martin
Borg, the sole owner, member, and employee of SMK, id. at 94:17–23.
Based upon the testimony and evidence presented at the hearing, the Court makes the
following factual findings. At the time Bartusek and Borg first communicated in February 2012,
see id. at 22:3–23:5, 106:12–21; Def.’s Hrg. Ex. 1, 2/13/2012 TradeKey Email to Bartusek; Def.’s
Hrg. Ex. 8, 2/16/2012 Email from Borg to Bartusek, 1 they were both relatively inexperienced in
cigarette sales. Borg had started SMK only a few months earlier, intending to sell branded tobacco
1
Def.’s Hrg. Exs. 1 and 8 refer to the exhibits proffered by Sutherland, and admitted by the Court,
at the hearing itself. See Tr. at 87:23–88:10. All other references to exhibits in this Memorandum Opinion
refer to the exhibits attached to the parties’ post-hearing memorandums.
2
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 3 of 14 PageID #:2237
product through duty-free distribution for export. See Tr. at 94:24–95:13. As of February 2012,
he had never completed any cigarette purchases or sales through SMK (or any other company, for
that matter), nor did he complete any similar transactions at any time relevant to this dispute. See
id. at 117:2–15. For his part, Bartusek had completed several transactions of cigarettes, but had
lost money on them. Id. at 42:4–15.
From February until August 2012, Bartusek and Borg regularly communicated about
potential cigarette sales via email, telephone, and text message. See, e.g., id. at 22:3–23:8, 121:16–
124:5, 187:17–205:14; see generally Def.’s Post-Hrg. Mem., Ex. D, ECF No. 158-1; Def.’s Hrg.
Ex. 8. During these communications, Bartusek provided price estimates for specific cigarette
brands and product sources. See, e.g., Def.’s Post-Hrg. Mem., Ex. D at SMK00014, SMK00015.
On or around June 14, 2012, Borg mailed a purchase order (“June PO”) to Bartusek at
Sutherland’s office location, see Def.’s Post-Hrg. Mem., Ex. A, 6/14/2012 PO at SMK00001, ECF
No. 158-1, although the address was slightly off. See id.; Tr. at 33:20–25. The June PO ordered
60,000 master cartons of “Marlboro Red, King Size, Flip Top Box, Swiss,” for $678 each; and
60,000 master cartons of “Marlboro Gold, Flip Top Box, Swiss,” also for $678 each. 6/14/2012
PO at SMK00001. The total purchase in the June PO came to $81,360,000. Id. According to
Bartusek, the first time he saw the June PO was in September 2012, when SMK initiated
collections proceedings against him. Tr. at 32:4–14.
On or around July 13, 2012, Borg mailed a second purchase order (“July PO”) to Bartusek
at Sutherland’s office location, see Def.’s Post-Hrg. Mem., Ex. B, 7/13/2012 PO at SMK00003,
ECF No. 158-1, again to the same slightly incorrect address. See id.; see also Tr. at 33:20–25.
The July PO ordered 1,000 master cartons of “Marlboro Red, King Size, Flip Top Box, USA,” for
$720 each; and 3,000 master cartons of “Marlboro Gold, Flip Top Box, USA,” also for $720 each.
3
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 4 of 14 PageID #:2238
7/13/2012 PO at SMK00003. The total purchase in the July PO came to $2,880,000. Id. Again,
Bartusek claims that he did not see the July PO until September 2012. Tr. at 44:18–45:1.
Both the June and July POs included a series of terms and conditions printed on the front
and back page of the purchase order (“PO Terms”), see 6/14/2012 PO at SMK00001–02;
7/13/2012 PO at SMK00003–04. These terms included product specifications for the cigarettes,
required pre-payment inspection, and specified the timeframe in which goods were to be delivered.
See id. The June PO Terms also noted that the purchase order was for a “twelve month supply to
be delivered in twelve equal monthly deliveries,” with the “initial delivery 15–25 days after date
of this PO.” 6/14/2012 PO at SMK00002. The July PO Terms, in contrast, specified that delivery
was to be “5–10 days after the date of this PO.” 7/13/2012 PO at SMK00004.
The PO Terms included a clause that the Court refers to as the “10% Damages Provision.” 2
The provision specified a “10% penalty for non performance payable to SMK Associates LLC by
vendor should goods fail to be delivered timely and/or goods are not genuine or in any other
manner different than represented by vendor to SMK Associates.”
Id.; 6/14/2012 PO at
SMK00002.
Both the June and July PO Terms “fully incorporated” an additional set of terms and
conditions contained in a separate document. See Def.’s Post-Hrg. Mem., Ex. A, SMK Associates
LLC PO Terms and Conditions (“Additional Terms”), at SMK00005–07; 6/14/2012 PO at
SMK00002 (referencing Additional Terms); 7/13/2012 PO at SMK00004 (referencing Additional
Terms). The Additional Terms specified a range of different types of damages actions available
to SMK. For example, SMK “reserve[d] the right, in addition to any and all other legal remedies
2
The relevant term in the purchase order refers to a “10% penalty,” and the parties frequently refer
to the term as a “penalty clause” and the amount of damages as a “penalty.” On this record, the Court finds
that what the parties called the clause has little bearing on whether it constitutes an unenforceable penalty
under Illinois law.
4
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 5 of 14 PageID #:2239
provided by law, to: (a) Deduct any excess transportation charges accrued . . . or (b) Cancel the
purchase order in whole or in part in case of strike, fire or other casualty which materially affects
SMK operations.” Additional Terms § 4.
The Additional Terms also provided that the “[v]endor agrees to reimburse SMK for any
costs resulting from late delivery of goods on the purchase order. In addition, SMK may, at its
sole discretion, reject or cancel any shipment of goods which will not be delivered by the agreedupon date of delivery.” Id. § 5. Furthermore, the terms required the vendor to agree to “reimburse
SMK, in full, for any other expenses that were caused by Vendor non-compliance with either the
terms herein or the terms on the purchase order, or the terms of any letter of credit regarding the
goods of the purchase order,” id. § 6, and to “reimburse SMK for any return of the goods, whether
by SMK or SMK customers, for any reason or no reason.” Id. § 7.
Borg testified that he had discussed the 10% Damages Provision with Bartusek starting in
February 2012, to determine if Bartusek was “genuine” about doing a deal or not, Tr. at 182:13–
183:1, 186:12–187:9, and that Bartusek had agreed to the clause, id. at 187:3–9. But, notably, the
numerous text messages and emails shared between Borg and Bartusek never mention the 10%
Damages Provision—or any other penalty or liquidated damages clause for that matter. See
generally Def.’s Post-Hrg. Mem., Ex. D; Def.’s Hrg. Ex. 8. According to Borg, this was because
all discussions of the clause took place over the telephone. Tr. at 109:16–110:7. In particular, he
claimed that before sending the June PO, he orally had reviewed the terms and conditions of the
purchase with Bartusek, including the 10% Damages Provision. Id. at 200:4–16.
Borg also explained his rationale for setting the amount at 10%. He chose 10%, he claims,
because it was less than the margin he expected to receive from a successful cigarette transaction,
and because he had never seen a penalty clause for less than 10%. Id. at 186:20–187:2. But Borg
5
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 6 of 14 PageID #:2240
conceded that his only exposure to penalty or liquidated damages clauses in relation to cigarette
sales was hearing about their existence from former coworkers. Id. at 182:1–8.
As Borg saw it, the 10% Damages Provision applied to any breach in the agreement,
regardless of the scale of the breach. Id. at 134:10–135: 17. That said, he admitted that SMK
could not collect both actual damages as well as damages under the 10% Damages Provision. Id.
at 138:15–139:2. Borg further clarified that he saw the June PO as a twelve-month installment
contract, where the 10% damages amount could be assessed on a month-by-month basis whenever
there was a breach. Id. at 142:1–143:24.
Not surprisingly, Bartusek categorically denied ever having discussed the 10% Damages
Provision with Borg.
Id. at 40:18–41:2.
Bartusek further testified that he never had any
conversations with Borg about what damages SMK or Borg would experience in the event of a
breach, nor about how the parties would determine those damages or how difficult it might be to
calculate them out. Tr. at 40:3–9, 88:14–89:10. For his part, Borg also conceded that he never
discussed the identity of his intended buyers with Bartusek, nor the prices that those buyers would
pay for the cigarettes. Id. at 100:10–20.
In fact, at the time that Borg sent Bartusek the June and July POs—requesting more than
$84,000,000 worth of cigarettes—Borg was not in regular communications with any potential
purchasers for those cigarettes. See id. at 148:23–171:21. Borg points to documents in an effort
to demonstrate the interest that he had received from potential buyers, but the documents are, at
best, merely introductory letters expressing initial interest, rather than a definitive discussion of
terms. See generally Def.’s Post-Hrg. Mem., Ex. E, ECF No. 158-1. Moreover, quizzically, Borg
knew almost nothing about the individuals or companies that sent the documents, or how he had
come to be in possession of them. See Tr. at 148:23–171:21.
6
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 7 of 14 PageID #:2241
Analysis
Whether a liquidated damages provision is an unenforceable penalty is a question of state
law. 3 Energy Plus Consulting, LLC v. Ill. Fuel Co., LLC, 371 F.3d 907, 909 (7th Cir. 2004). For
guidance on this question, Illinois courts look to the Restatement (2d) of Contracts, which
instructs:
Damages for breach by either party may be liquidated in the
agreement but only at an amount that is reasonable in the light of the
anticipated or actual loss caused by the breach and the difficulties of
proof of loss. A term fixing unreasonably large liquidated damages
is unenforceable on grounds of public policy as a penalty.
Grossinger Motorcorp, Inc. v. Amer. Nat’l Bank and Trust Co., 607 N.E.2d 1337, 1345 (Ill. App.
Ct. 1992) (quoting Restatement (2d) of Contracts § 356 (1979)).
Consistent with the Restatement, Illinois courts find liquidated damages clauses
enforceable when: “(1) the actual damages from a breach are difficult to measure at the time the
contract was made; and (2) the specified amount of damages is reasonable in light of the anticipated
or actual loss caused by the breach.” 4 Energy Plus, 371 F.3d at 909 (quoting Checkers Eight Ltd.
3
The Additional Terms include an Illinois choice-of-law provision. Additional Terms § 11. Of
course, the parties ultimately disagree on whether a contract was formed, which would affect the validity
of that provision. However, “[w]here the parties agree on the law that governs a dispute, and there is at
least a ‘reasonable relation’ between the dispute and the forum whose law has been selected by the parties,
[the Court] will forego an independent analysis of the choice-of-law issue and apply [the parties’ choice].”
Harter v. Iowa Grain Co., 220 F.3d 544, 560 n.3 (7th Cir. 2000) (quotation marks and citation omitted).
The parties assume in their briefs that Illinois law applies, and SMK was based in Illinois, see 2d Am.
Compl. ¶ 3, ECF No. 40, suggesting a “reasonable relation” between the state and the dispute. Accordingly,
we apply Illinois law.
4
Of note, “[s]ome Illinois courts also include a third prong: ‘[whether] the parties intended to agree
in advance to the settlement of damages that might arise from the breach.’” Energy Plus, 371 F.3d at 909
n.2 (citing Med+Plus, 726 N.E.2d at 693 and Penske Truck Leasing Co. v. Chemetco Inc., 725 N.E.2d 13,
19 (Ill. App. Ct. 2000)). The Illinois Supreme Court has never addressed whether this third prong is part
of the analysis, but has referred to the two-prong test in dicta. See People ex rel. Dep’t of Pub. Health v.
Wiley, 843 N.E.2d 259, 271 (Ill. 2006). As the third prong is not dispositive in this case, the Court does not
consider it.
7
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 8 of 14 PageID #:2242
P’ship v. Hawkins, 241 F.3d 558, 562 (7th Cir. 2001)). But if “the sole purpose of the clause is to
secure performance of the contract” or “the amount of damages is invariant to the gravity of the
breach,” the provision is likely a penalty. Checkers, 241 F.3d at 562 (citing Med+Plus Neck and
Back Pain Ctr. v. Noffsinger, 726 N.E.2d 687, 693 (Ill. App. Ct. 2000)). See also Grossinger, 607
N.E.2d at 1346 (“The damages must be a specified amount for a specific breach, not a penalty to
punish for nonperformance or as a means to secure performance.”); GK Dev., Inc. v. Iowa Malls
Fin. Corp., 3 N.E.3d 804, 817 (Ill. App. Ct. 2013) (finding that a damages provision that specified
the same amount for a total breach and a delay in securing permits was not a reasonable prediction
of damages).
“In doubtful cases, [Illinois courts] are inclined to construe the stipulated sum as a penalty,”
GK Dev., 3 N.E.3d at 816 (citing Stride v. 120 W. Madison Bldg. Corp., 477 N.E.2d 1318, 1321
(Ill. App. Ct. 1985)), “as [t]he purpose of damages is to place the nonbreaching party in a position
that he or she would have been in had the contract been performed, not to provide the nonbreaching
party with a windfall recovery,’” id. (quoting Jones v. Hryn Dev., Inc., 778 N.E.2d 245, 249 (Ill.
App. Ct. 2002)).
That being said, “[c]ourts generally give effect to [liquidated damages]
provisions ‘if the parties have expressed their agreement in clear and explicit terms and there is no
evidence of fraud or unconscionable oppression.’” Karimi v. 401 N. Wabash Venture, LLC, 952
N.E.2d 1278, 1290 (Ill. App. Ct. 2011) (quoting Hartford Fire Ins. Co. v. Architectural Mgmt.,
Inc., 550 N.E.2d 1110, 1114 (Ill. App. Ct. 1990)). Accordingly, it is the burden of the party
seeking to avoid enforcement of a liquidated damages provision to show that it is a penalty. XCO
Int’l Inc. v. Pac. Sci. Co., 369 F.3d 998, 1003 (7th Cir. 2004).
8
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 9 of 14 PageID #:2243
I.
Difficulty of Measuring Damages at the Time of Contract Formation 5
For a liquidated damages clause to be enforceable, the actual damages from a breach must
be difficult to measure at the time of contract formation. Energy Plus, 371 F.3d at 909; see also
Grossinger, 607 N.E.2d at 1345–46. In this case, the parties agree that the damages were difficult
to measure. Both SMK and Sutherland acknowledge that SMK’s lack of sales contracts with end
purchasers made estimating damages very challenging at the formation of the contract. See Pl.’s
Post-Hrg. Mem. at 14; Def.’s Post-Hrg. Mem. at 11 (citing Tr. at 149:15–171:21 and Def.’s PostHrg. Mem., Ex. E). Indeed, as Sutherland notes, SMK had “never completed the purchase or sale
of a single cigarette.” Def.’s Post-Hrg. Mem. at 11 (citing Tr. at 117:2–15). Moreover, the prices
for cigarettes were highly dynamic over the time that Borg and Bartusek were communicating.
See Tr. at 123:13–16 (Borg discussing the rapidly shifting prices Bartusek offered from February
through April 2012); id. at 206:17–23 (Borg stating that the product SMK had requested from
Bartusek had become considerably more expensive). The Court therefore finds that the damages
from the breach were difficult to measure at the time of contract formation.
5
For the purposes of this analysis, the Court assumes that SMK and Bartusek formed a contract to
sell cigarettes. That contract must have formed before SMK sent the first purchase order. The contract
thus formed at the latest on June 14, 2012.
The Court also notes that Borg and Bartusek provided sharply contradictory testimony on whether
the two ever discussed the 10% Damages Provision prior to the issuance of the purchase orders, with Borg
testifying that he had discussed the clause with Bartusek from February onward, Tr. at 182:13–183:1,
186:12–187:9, and Bartusek claiming it had never been mentioned, id. at 40:18–41:2. After considering
the demeanor of the witnesses and the record as a whole, including the fact that the damages provision was
not mentioned even once in the numerous written communications between Borg and Bartusek, the Court
finds that Bartusek’s statements are more credible and that the earliest time that the damages provision
arose between the parties was when the June and July POs were sent to Sutherland. That said, whether
Bartusek intended to agree to the clause or not does not affect the Court’s finding of whether the clause was
a penalty and thus unenforceable as a matter of law. Similarly, the Court does not address the parties’
arguments on whether the parties intended the clause to be a penalty, as it does not affect the outcome of
the case. See Energy Plus, 371 F.3d at 909 n.2.
9
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 10 of 14 PageID #:2244
II.
Reasonableness of Damages in Light of Anticipated or Actual Loss
There is a second prong to this analysis, however. For a liquidated damages clause to be
enforceable, the damages proposed in the clause must also be reasonable in light of the anticipated
or actual loss. Jameson Realty Grp. v. Kostiner, 813 N.E.2d 1124 (Ill. App. Ct. 2004) (citing
Grossinger, 607 N.E.2d at 1345–46).
Sutherland advances three arguments as to why the 10% Provision is unreasonable. First,
it argues that 10% was an unreasonable estimate of damages based upon what the parties knew (or
did not know) at the time of the contracts’ formation. Def.’s Post-Hrg. Mem. at 11–12. Next, it
contends that the figure was, in fact, unreasonable, arguing that SMK did not suffer any actual
damages as a result of the purported breaches. Id. at 11. Finally, Sutherland maintains that the
provision was unreasonable because the 10% applied to all breaches, regardless of their severity.
Id. at 10. In response, SMK asserts that Sutherland has failed to meet its burden to demonstrate
that the damages were unreasonable and offers what it calls “affirmative evidence” of the
provision’s reasonableness. Pl.’s Post-Hrg. Mem. at 13.
A.
Estimate of Anticipated and Actual Damages
Sutherland first contends that, even taking into consideration the challenge of estimating
damages at the time of contracting, SMK’s anticipated profit margins were at most about 3%,
making 10% an unreasonable estimate of anticipated damages. Def.’s Post-Hrg. Mem. at 11–12.
At the hearing, Sutherland demonstrated that when Borg sent off the June PO requesting Swiss
Marlboro Reds and Golds at $678 per master carton, he had no evidence that he could sell the
product for more than $700 per master carton. See Def.’s Post-Hrg. Mem., Ex. E; see also Tr. at
148:15–149:13 (specifying that Ex. E encompassed all the evidence that SMK had of potential
buyers); id. at 156:11–159:19 (discussing the March 29, 2012, letter of intent offering $700 per
10
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 11 of 14 PageID #:2245
master carton). Based upon this evidence, then, Borg’s anticipated profit margin at the time of
contracting was at most 3%. See Def.’s Post-Hrg. Mem. at 11–12. The only evidence indicating
a higher profit margin is from no earlier than July 3, 2012, after the contract was formed. See, e.g.,
Def.’s Post-Hrg. Mem., Ex. E at 00096 (Unibev Letter of Intent).
In response, SMK does not directly dispute Sutherland’s calculations for anticipated
damages. See Pl.’s Post-Hrg. Mem. at 13 (citing Tr. at 218:6–9). Instead, SMK argues that, given
the dynamic nature of the market for cigarettes and SMK’s lack of contracts with end-purchasers,
a straight 10% percent provision was reasonable. Id. But that argument implies that it was
reasonable for the parties to assume that, on average, SMK would make a 10% profit if Bartusek
had delivered the product. And since Borg was unable to identify any potential buyers whose
purchases would result in a profit anywhere near 10%, see Tr. at 148:23–171:21, such an
assumption is wishful thinking at best.
B.
Estimate of Actual Damages
Sutherland next argues that SMK, as a new business, suffered no actual damages under
Illinois law as a result of the alleged breach, and accordingly, 10% is an unreasonable estimate of
actual damages. Def.’s Post-Hrg. Mem. at 11. See Checkers, 241 F.3d at 562 (finding that a
liquidated damages clause that dictated damages excessive to actual damages indicated that the
clause was a penalty).
“The general rule under Illinois law is that a new business has no right to recover lost
profits.” TAS Distributing Co. v. Cummins Engine Co., 491 F.3d 625, 633 (7th Cir. 2007). “The
reasoning behind the rule is simply that a new business has not demonstrated yet what its profits
will be.” Id. at 634 (citing Milex Prods., Inc. v. Alra Lab., Inc., 603 N.E.2d 1226, 1236 (Ill. App.
Ct. 1992)).
11
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 12 of 14 PageID #:2246
There are exceptions, such as when “experts have provided convincing and non-speculative
evidence sufficient to prove lost profits.” Id. However, all of SMK’s estimates of its actual
damages rely exclusively on Borg’s speculation about his ability to re-sell cigarettes, without any
evidence of any actual anticipated sales to potential buyers. See Def.’s Post-Hrg. Mem., Ex. E;
see also Tr. at 148:15–149:13 (Borg explaining that Ex. E encompassed all the evidence that SMK
had of potential buyers); 148:23–171:21 (Borg reviewing the limited extent of his communications
with those potential buyers). Moreover, it is beyond dispute that SMK was a new business; it was
founded only a few months before Borg and Bartusek began communicating, Tr. at 94:24–95:13,
and SMK never completed any cigarette purchases or sales at any time relevant to this dispute, id.
at 117:2–15. The Court thus concludes that 10% is an unreasonable estimate of actual damages
suffered by SMK.
C.
Damages in Relation to Scope of Breach
Lastly, Sutherland argues that, because Borg admitted that the 10% applied to any and all
breaches, regardless of the severity of the breach, the 10% Damages Provision could not be a
reasonable attempt to estimate damages. Def.’s Post-Hrg. Mem. at 10–11 (citing GK Dev., 3
N.E.3d at 817); see also Tr. at 134:10–135:17. SMK counters that the provision is far less strict
than it might first appear, because the provision operated on a month-by-month basis, meaning
that the 10% damages would be imposed only for the months in which a breach occurred. Pl.’s
Post-Hrg. Mem. at 9 (citing Tr. at 142:23–143:10). SMK further contends that, even though “the
ten percent provision technically applies irrespective of whether the goods are merely delayed or
are instead not delivered at all, Borg testified that in the event of a simple delay, the parties would
work it out in the spirit of ‘an ongoing relationship.’” Id. at 9 (citing Tr. at 147:6–19).
12
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 13 of 14 PageID #:2247
SMK is right to concede that the provision “technically” applies regardless of the scale of
the breach. The provision could not be more clear—it applies “should goods fail to be delivered
timely” or if they are “in any other manner different than represented by vendor to SMK
Associates.” 6/14/2012 PO at SMK00002; 7/13/2012 PO at SMK00004. In other words, the
provision entitles SMK to 10% of the purchase price whether no cigarettes were delivered, or
whether all of the cigarettes were delivered but some did not meet the specifications in any manner.
And even if the 10% Damages Provision applies only on a month-by-month basis, as Borg
construed it, the 10% amount could be assessed whether the monthly delivery were a few days late
or not delivered at all. Accordingly, based upon the record, the Court finds that “the amount of
damages is invariant to the gravity of the breach,” Checkers, 241 F.3d at 562, indicating that the
provision was not a reasonable attempt to estimate damages.
D.
SMK’s Affirmative Evidence
In response, SMK contends that it offered affirmative evidence at the hearing
demonstrating the 10% Damages Provision’s reasonableness. Pl.’s Post-Hrg. Mem. at 13. As
examples, SMK points to Borg’s testimony that penalty clauses were standard in the industry, that
10% was the lowest percentage he had seen in a penalty clause, and that he had selected 10%
because of the margin he anticipated. Id. (citing Tr. at 186:20–187:2). But Borg’s own testimony
undercut the credibility and weight of these explanations. First, Borg admitted that his only
personal experience with penalty clauses in relation to cigarette sales was having heard about their
existence from former coworkers. Tr. at 182:1–8.
Moreover, as discussed above, the record
considered in its entirety, including the paucity and generality of Borg’s own sales research and
communications with buyers, demonstrate that an anticipated return of 10% was unreasonable.
13
Case: 1:14-cv-00284 Document #: 168 Filed: 07/09/18 Page 14 of 14 PageID #:2248
Accordingly, having considered the record as a whole, the Court finds that, while actual
damages from a breach were difficult to measure at the time of the alleged contract formation, the
10% Damages Provision is unreasonable in light of the anticipated and actual loss caused by the
purported breaches, because the 10% amount was invariant to the scale of any breach, the
anticipated loss was far lower than 10%, and there were no actual damages suffered as a result of
the alleged breaches. The Court thus concludes that Sutherland has sustained its burden of
demonstrating that the liquidated damages provisions contained in the June and July POs are an
unenforceable penalty clause under Illinois law.
Conclusion
For the reasons stated herein, the liquidated damages provisions that form the basis for
SMK’s damages claim are unenforceable penalties under Illinois law. The Court sets a status
hearing for 7/16/18 at 9:30 a.m.
IT IS SO ORDERED.
ENTERED
7/9/18
__________________________________
John Z. Lee
United States District Judge
14
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?