Premcor Refining Group, Inc v. Apex Oil Company, Inc. et al
Filing
228
ORDER denying 219 Motion for Reconsideration. Signed by Chief Judge Nancy J. Rosenstengel on 3/13/2020. (dhg)
IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF ILLINOIS
THE PREMCOR REFINING GROUP
INC.,
Plaintiff,
v.
Case No. 3:17-CV-738-NJR
APEX OIL COMPANY, INC., et al.,
Defendants.
MEMORANDUM AND ORDER
ROSENSTENGEL, Chief Judge:
Pending before the Court is a Motion for Reconsideration filed by Defendant Apex
Oil Company, Inc. (“Apex”) (Doc. 219). For the reasons set forth below, the Court denies
the motion.
This action arises out of claims under the Comprehensive Environmental
Response, Compensation, and Liability Act, 42 U.S.C. § 9601 et seq. (“CERCLA”), brought
by Premcor against Apex Oil Company, Inc. (“Apex”) and seven other defendants.
Premcor seeks recovery of costs incurred in remediation activities ordered by the Illinois
Environmental Protection Agency (“IEPA”) to clean up environmental contamination at
a refinery in Hartford, Illinois (Doc. 130, p. 1-2). The plume of environmental
contamination arising from the refinery in Hartford and extending under the Village of
Hartford has been the subject of a number of federal and state proceedings extending
over the past two decades, and Apex has sought to be dismissed from this lawsuit based
on a 2016 consent order with the IEPA (“Apex Consent Order”)(Doc. 143-1). This Court
Page 1 of 19
initially ruled that Premcor’s contribution claim against Apex under Section 113(f) of
CERCLA was estopped by the settlement bar in Section 113(f)(2) of CERCLA (“CERCLA
Settlement Bar”) due to the Apex Consent Order (Doc. 189). Premcor filed a Motion for
Reconsideration of that dismissal, and based on its further review of the factual record,
this Court concluded in its order of January 15, 2020 (“Reconsideration Order”) that
because the Apex Consent Order explicitly carved out liability allocated to Apex under
earlier federal judicial and administrative orders, the “matters addressed” in the Apex
Consent Order were too circumscribed for it to effectively prevent suit under the
CERCLA Settlement Bar (Doc. 213). Apex has now filed its own Motion for
Reconsideration, arguing that this Court misapprehended the scope of the territories to
which the Apex Consent Order and earlier federal orders were to be applied, claiming
that the federal orders did not apply to pollution under the refinery itself and that the
Apex Consent Order thus should prevent suit under the CERCLA Settlement Bar
(Doc. 219).
Having reviewed its Reconsideration Order, the Court is unpersuaded by Apex’s
arguments. The Court, however, notes that its usage of the term “Hartford Site” in its
earlier order may have led to confusion, and it will restate briefly the complex factual and
procedural background of this action and revisit the reasoning behind its Reconsideration
Order.
FACTUAL & PROCEDURAL BACKGROUND
As Apex’s confusion regarding the Court’s Reconsideration Order stems from
the usage of the term “Hartford Site,” before discussing chronologically the facts and
Page 2 of 19
procedure of this action the Court will first discuss two demarcated territories that are
relevant to the action.
Figure 1: Hartford Village Site (Doc. 219 at 3)
The territory surrounded by the checked “site boundary” line in Figure 1 will
hereafter be referred to by the Court as the “Hartford Village Site.” This is the territory
that is referred to as the “Hartford Site” in federal administrative orders and in the earlier
federal proceeding in this Court before Judge David Herndon.
Page 3 of 19
Figure 2: Hartford Refinery (Doc. 132 at 132)
The territory surrounded by red highlighted lines in Figure 2 indicates portions of
the land beneath the Hartford Refinery that are addressed in Premcor’s current action.
The Apex Consent Order as well as Premcor’s separate consent order both deal with
refinery territory and do not directly deal with abatement efforts within the Hartford
Village Site. This territory beneath Premcor’s refinery will hereafter be referred to by this
Court as the “Hartford Refinery.”
Page 4 of 19
Figure 3: Hydrocarbon Plume (Doc. 219-1 at 91)
Figure 3 serves to illustrate the extent of some of the hydrocarbon-based
contamination in the Hartford area, which arose under the territory of Hartford Refinery
and has spread in a plume that has extended beneath the Hartford Site.
History of Hartford Refinery Contamination and Enforcement Proceedings
The Hartford Refinery was first constructed in 1940 and has subsequently been
expanded and modified extensively and passed between various corporate owners. See
Order Following Bench Trial, United States v. Apex Oil Company, Inc., No. 05-cv-242-DRH
(S.D. Ill. July 28, 2008), ECF No. 199 [hereinafter Herndon Findings]. While not all of these
changes and transitions in ownership are relevant to consideration of this motion, the
Court notes that a corporate predecessor to Apex owned the Hartford Refinery during
Page 5 of 19
the 1980s, while the Hartford Refinery was acquired in 1988 by the company now known
as Premcor. Herndon Findings at 2–3.
In the late 1970s, reports of gas odors and fires in the Village of Hartford led to an
investigation into the causes of these phenomena. Id. at 15. Investigations revealed a pool
of hydrocarbons beneath the Village of Hartford, and further investigations indicated
extensive contamination extending beneath the refinery as well. Id. at 19, 30. This
hydrocarbon contamination was caused by numerous spills and leaks of petroleum
products, as well as subterranean disposal of hydrocarbon wastes, at the Hartford
Refinery. Id. at 30–32. Once hydrocarbons and associated wastes were spilled on the
territory of the Hartford Refinery, they spread beneath the Village of Hartford through
groundwater, forming an irregular plume of hazardous substances. Id. at 36–37, 40–44.
This plume of contamination is important to keep in mind—the pollution at issue
in this action is not solid waste which remains neatly confined in one place. Rather, it is
an irregular mix of hydrocarbons and byproducts in liquid and vapor forms, in different
densities and viscosities, moving slowly through a variety of geological substrata that
extend beneath the area without regard for neat property boundaries. See id. at 13 (noting
that a hydrocarbon release “will continue its movement in the subsurface), at 29–30
(describing pools of heavier and lighter hydrocarbons within plume), at 37–38
(discussing how changing groundwater patterns affect movement of plume), at 55–58
(discussing findings of hydrocarbon vapors in soil underlying Hartford Refinery and
Village of Hartford).
Page 6 of 19
In 2002, a series of severe hydrocarbon vapor intrusion events in the Hartford
Village Site attracted the attention of the Illinois Department of Public Health (“IDPH”)
and the IEPA. Id. at 73–78. IEPA and IDPH discovered elevated levels of hexane and
benzene in the air, as well as light-range hydrocarbons in the soil. IDPH concluded that
hydrocarbon vapor intrusions constituted a public health hazard in the Hartford Village
Site and that such intrusions could occur again and create an urgent public health hazard.
Because of this perceived health emergency, IEPA asked the United States Environmental
Protection Agency (“U.S. EPA”) to get involved. Id. at 81. U.S. EPA assessed the
contamination at the Hartford Village Site and met with five oil companies that U.S. EPA
believed to be responsible. Id. at 82. That meeting included both Apex and Premcor. Id.
After lengthy negotiations, U.S. EPA entered an Administrative Order on Consent with
Premcor and two other companies on March 17, 2004 (“2004 AOC”). Id. at 84. Apex chose
not to participate in that agreement. Id.
The 2004 AOC was specifically designed to immediately address the public health
hazard within the Hartford Village Site, but that document also observed that
contamination began with leaks that occurred on the land beneath the refinery and then
migrated into a subsurface pool extending beneath the Hartford Village Site. In the Matter
of the Hartford Area Hydrocarbon Plume Site, Docket R7003-5-05-001, CWA1321-5-04-001
(U.S. EPA) (Doc. 219-1 at 48). The U.S. EPA ordered the parties to the 2004 AOC to take
certain measures to monitor and remediate the contamination at the Hartford Village Site,
while reserving the right to take further action to “prevent, abate or minimize an actual
or threatened release…on, at, or from the Site.” Id. at 63.
Page 7 of 19
As Apex was not among the parties that voluntarily entered the 2004 AOC, in 2005
the United States commenced a lawsuit in this court against Apex under the Resource
Conservation and Recovery Act (“RCRA”). United States v. Apex Oil Company, Inc., No.
05-cv-242-DRH (S.D. Ill.). After discovery and a bench trial, Judge Herndon of this Court
issued extensive findings of fact. Herndon noted that immediate measures contemplated
for remedying contamination within the Hartford Village Site were initial steps, which
would take 15-25 years. Id. at 159–61. These initial steps would not remediate
contaminated groundwater beneath the Hartford Village Site or Hartford Refinery, but
would lay a framework “so that large scale groundwater remediation can begin[.]” Id.
Herndon again noted that contaminated groundwater would continue to flow from the
Hartford Refinery to the Hartford Village Site without steps taken to control migration
from the Hartford Refinery Site. Id.
Based on his review of the history of hydrocarbon contamination around the
Village of Hartford and the Hartford Refinery, Judge Herndon found that Apex had
spilled hydrocarbons at the Hartford Refinery and that some of this waste had migrated
beneath the Village of Hartford. Herndon Findings at 173 ¶ 467. Judge Herndon further
noted that some hydrocarbons spilled by Apex remained beneath Hartford Refinery but
could in the future migrate beneath the Hartford Village Site. Id. at ¶ 468. Judge Herndon
found that both the waste currently beneath the Hartford Village Site and the waste
remaining beneath the Hartford Refinery could present an imminent and substantial
endangerment to the Hartford Village Site. Id. at 173 ¶¶ 467–68. Judge Herndon ruled
that Apex was “jointly and severally liable for taking such action as may be necessary to
Page 8 of 19
abate the hydrocarbon contamination at the [Hartford Village Site] and all associated
conditions that present or may present an imminent and substantial endangerment to
health or society.” Id. (emphasis added). In finding Apex jointly liable under RCRA,
Judge Herndon noted that the principles governing joint and several liability were the
same under government enforcement provisions of other federal environmental laws like
CERCLA. Id. at 174 ¶ 470.
Based on these findings, Judge Herndon issued an injunction ordering Apex to
“investigate the conditions relevant to the potential migration of groundwater
contamination from beneath the Hartford Refinery to beneath the Village of Hartford[.]”
Order and Terms of Injunction Pursuant to Fed. R. Civ. P. 65(d), United States v. Apex Oil
Company, Inc., No. 05-cv-242-DRH (S.D. Ill. July 28, 2008), ECF No. 199-2 at 2 [hereinafter
Herndon Order]. Judge Herndon further ordered that Apex take:
“such other action as may be necessary to abate the hydrocarbon contamination at
the [Hartford Village Site] and all associated conditions that present or may present
an imminent and substantial endangerment to health or the environment,
pursuant to the terms of any further order of the Court.”
Herndon Order at 2 (emphasis added).
Lastly, Judge Herndon ordered Apex to “coordinate and cooperate with the
parties to the [2004 AOC] in performing activities required under this injunction.” Id.
The Herndon Order was followed in 2010 by a Unilateral Administrative Order
issued by the U.S. EPA (“2010 UAO”) in which the U.S. EPA ordered certain cleanup
work under the authority granted to it by the Herndon Order and 2004 AOC. Hartford
Area Hydrocarbon Site Unilateral Administrative Order, RCRA-05-2010-0020, Filing #1 (2010)
Page 9 of 19
(Doc. 219). The 2010 UAO ordered work to be completed solely within the Hartford
Village Site but noted that “[n]othing in this Order in any way alters, limits, or otherwise
affects the Respondents’ continuing obligations under the 2004 AOC and the [Herndon
Injunction].” Id. at 14–15. In a letter sent to Apex and other parties with the order, the
EPA noted that the parties were jointly liable for the cleanup work and that the work
would require “continuous cooperation amongst all Respondents[.]” Id. at 3. As in the
2004 UAO, the United States retained authority to take any actions “necessary to protect
public health or the environment or minimize an actual or threatened release…on at, or
from the Site, including but not limited to the right to bring enforcement actions under
RCRA and any other applicable statute or regulation.” Id. at 39.
Separate from the federal actions, the IEPA sued Apex and Premcor in 2013 under
the Illinois Environmental Protection Act in the Circuit Court of Madison County, Illinois,
for contamination at the Hartford Refinery (“Madison County Proceeding”). That state
action culminated in the Apex Consent Order (Doc. 143-1). In the Apex Consent Order,
IEPA released Apex from “any and all liability. . .arising under any Environmental Laws
relating to each Release of Substances, threatened Release of Substances, and resulting
conditions existing at, under, from, on or upon the Refinery” (Id. at 14). Environmental
Laws as defined in the Apex Consent Order includes “any federal, state or local
law…relating to the protection of the environment[,]” a broad yet vague definition that
might appear to encompass CERCLA (Doc. 143-1 at 6). The Apex Consent Order further
states that it intends to be a good faith settlement pursuant to the Illinois Joint Tortfeasor
Contribution Act, and that all claims that could have been brought against Apex by third
Page 10 of 19
parties in the Madison County Proceeding. Id. at 16. This release was qualified with
certain reservations, including the statement that “[t]his Consent Order does not resolve,
settle or in any way alter any liability imposed upon Apex by the [Herndon Order] or by
the [2010 UAO]” (Id. at 15–16).
The Apex Consent Order was approved by a September 6, 2016 order of the Circuit
Court of Madison County, Illinois (“State Court Order”) (Doc. 143-2). The Madison
County Circuit Court noted that if approved, the Apex Consent Order would “extinguish
Apex’s liability for contribution for sums ultimately paid by other parties,” citing
specifically to the Illinois Environmental Protection Act (Id. at 2). In its order, the Madison
County Circuit Court addressed concerns raised by Premcor that the Apex Consent
Order would give Apex a free pass on liability imposed in the Herndon Order and
U.S. EPA Order, stating that “this agreement and order does not let Apex ‘off the hook’
financially for the federal orders” (Id. at 5). After reviewing pleadings presented by the
parties to the Apex Consent Order and hearing arguments as to the intended scope and
meaning of the Apex Consent Order, the Illinois Circuit Court concluded that it “does
not affect any liabilities of any parties created by the [U.S. EPA Order]” and that it “does
not impair or impinge upon matters addressed and resolved by the [Herndon Order]”
(Id.). The court dismissed Premcor’s motion for summary judgment for contribution
costs, noting that as the Apex Consent Order did not affect the Herndon Order or
2010 UAO, any dispute over those orders “would be filed in Federal court where the
orders were entered” (Id. at 6).
Page 11 of 19
Premcor also settled with the state, agreeing to a consent order with the IEPA in
2018 (“Premcor Consent Order”). The parties to that order indicated that “this Consent
Order shall in no way preclude or otherwise impair Premcor’s ability to pursue CERCLA
claim(s) against the Refinery Defendants[,]” with “Refinery Defendants” defined as
including Apex (Doc. 132 at 5, 18). The Premcor Consent Order further states that it does
not prejudice Premcor’s rights under the Herndon Order and that it is “intended to, and
shall serve, as of the Effective Date, as protection from contribution actions or claims as
provided by Section 113(f)(2) of CERCLA” (Doc. 132 at 40).
Premcor commenced this action in 2017 under Section 113(f) of CERCLA, seeking
contribution for costs incurred in completing the remediation work ordered by the IEPA
pursuant to the Premcor Consent Order. As discussed, Apex seeks to be dismissed from
the action under the CERCLA Settlement Bar.
LEGAL STANDARD
Motions for reconsideration are only appropriate where the court has
misunderstood a party, made a decision outside of the issues presented by the parties,
made an error of apprehension, where a significant change in the law has occurred, or
where significant new facts have been discovered. Broaddus v. Shields, 665 F.3d 846, 860
(7th Cir. 2011) (citing Bank of Waunakee v. Rochester Cheese Sales, Inc., 906 F.2d 1185, 1191
(7th Cir. 1990)).
Page 12 of 19
DISCUSSION
I.
Motion to Reconsider
a)
Applicable Law
The CERCLA Settlement Bar, 42 U.S.C. § 9613(f)(2), provides that a “person who
has resolved its liability to the United States or to a State in an administrative or judicially
approved settlement shall not be liable for claims for contribution regarding matters
addressed in the settlement” (emphasis added). The Seventh Circuit has clarified that
determination of the matters addressed in the settlement requires a factual inquiry into
“the reasonable expectations of the signatories” which involves consideration of factors
such as the “particular location, time frame, hazardous substances, and clean-up costs
covered by the agreement” though this should not be treated as an exhaustive list of
considerations. Akzo Coatings v. Aigner Corp., 30 F.3d 761, 766 (7th Cir. 1994). In
considering location, the Court should pay attention to words describing movement of
waste from or to the site, which can imply leaching or transportation of waste extending
liability beyond any explicit demarcated area discussed in the settlement. See Rumpke of
Indiana v. Cummins Engine Co., 107 F.3d 1235, 1238 (7th Cir. 1997). In reading the scope of
an order prescribing remediation work, the court should look to the more general
response goal, rather than the immediate tasks to be performed. See, e.g., Allied Corp. v.
Frola, 1993 U.S. Dist. LEXIS 13343 at *21 (D.N.J.).
When in doubt, Courts should not construe settlements broadly, but rather should
“require settling parties to be more explicit when they intend to bar contribution[.]” Akzo
Coatings, 30 F.3d at 768. Certain courts have held that a settlement must make clear in
Page 13 of 19
unambiguous language that it intends to resolve parties’ potential CERCLA liability.
W.R. Grace & Co.-Conn. v. Zotos Intern., Inc., 559 F.3d 85, 91 (2d Cir. 2009) (text of consent
order which made no reference to CERCLA "establishes that the DEC settled only its state
law claims"). Where a settlement could be construed to grant immunity only through
broad, “limited and ambiguous language[,]” courts have been reluctant to extend the
CERCLA Settlement Bar to prevent suit by third parties. See, e.g., Litgo N.J., Inc. v. Martin,
2010 U.S. Dist. LEXIS 57390 at *89 (D.N.J.) (finding that language on fully resolving
liability was standard form language and refusing to read in release of CERCLA liability);
Cf. DMJ Assocs., LLC v. Capasso, 2015 U.S. Dist. LEXIS 177460 at *87 (E.D.N.Y.) (discussing
settlement where state regulator explicitly stated that party had resolved CERCLA
liability for purposes of the CERCLA Settlement Bar).
b)
Discussion
Apex’s Motion for Reconsideration does not indicate that they disagree with this
Court’s conclusion that all matters addressed by the Herndon Order and 2010 UAO are
carved out of the matters addressed by the Apex Consent Order. Rather, Apex argues
that those federal orders were confined to the Hartford Village Site and did not touch on
the Hartford Refinery at all. Thus, all liability connected with the territory within the
Hartford Refinery was within the matters addressed by the Apex Consent Order and is
subject to the CERCLA Settlement bar, Apex contends.
This argument is incorrect and stems from an oversimplification of the federal
orders. The true scope of those federal orders is best seen in the Herndon Findings. While
the immediate effect of the Herndon Order was to require Apex to participate in certain
Page 14 of 19
remediation activities within the Hartford Village Site, the Herndon Findings make clear
that these activities were viewed as only an initial step. More broadly, Herndon found
Apex to be liable for the pollution at both Hartford Refinery and the Hartford Village
Site, cataloging how a long history of spills and poor environmental practices created the
extensive plume of hydrocarbon waste extending from beneath the Hartford Refinery to
the Hartford Village Site. Remediation at the Hartford Village Site was the first priority
because that territory was inhabited, and the hydrocarbon vapors presented a serious
and imminent risk to public health. However, Herndon describes the Active LNAPL
System, implemented in the Hartford Village Site, as only the beginning of remediation
activities. That system, which will be operative for as long as 25 years, will allow
groundwater remediation to begin. This subsequent groundwater remediation will
necessitate treatment of the portion of the plume under the Hartford Refinery—
otherwise, as Herndon notes, the flow of groundwater will simply continue to move more
contamination to the Hartford Village Site. Because the waste under the refinery is
inextricably linked to the waste under the Hartford Village Site in a shifting, irregular
plume that defies the clean boundaries that polluters such as Apex might seek to impose
upon it, Judge Herndon correctly noted that the waste under the Hartford Refinery was
an ”imminent and substantial endangerment” to Hartford Village Site. Herndon Findings
at 173 ¶¶ 467–68. Based on this language, it seems clear to this Court that when Herndon
found Apex liable for abating “the hydrocarbon contamination at the [Hartford Village
Site] and all associated conditions that present or may present an imminent and substantial
endangerment to health or society[,]” (emphasis added) the associated conditions are the
Page 15 of 19
rest of the hydrocarbon plume, including the contamination beneath Hartford Refinery.1
See Herndon Order at 2.
With this in mind, the Court must then determine what to make of the language
in the Apex Consent Order purporting to release Apex from any and all liability arising
from Hartford Refinery and how to reconcile this with the carve-out of federal liability.
While a Court should first attempt to interpret a settlement or consent order based on the
plain language of the document, where the language is ambiguous the court will look to
extrinsic evidence to assess the intent of the parties and determine their reasonable
expectations. See Alliance to End Repression v. City of Chicago, 742 F.2d 1007, 1021–22 (7th
Cir. 1984) (“consent decrees are construed according to precepts of contract
construction”); 17A C.J.S. Contracts § 386 (noting ambiguity permits use of extrinsic
evidence of intent). Here, the interplay between the broad release language and the carveout of federal liability creates ambiguity as to the precise extent of the release.
The language in the Premcor Consent Order explicitly foreseeing a CERCLA
contribution claim by Premcor against Apex for costs arising from that order provides
some insight into the intent of the IEPA, for it appears that it was not under the
impression that it had given Apex complete protection from liability for all matters
arising from the contamination at the Hartford Refinery. Indeed, the release language of
the Premcor Consent Order is more specific throughout, explicitly mentioning CERCLA
The Court notes that Apex has in the past expressed sentiments that are in line with this interpretation,
having argued in its appeal from the Herndon Order that it “purports to require Apex to abate any
conditions beneath the Refinery that may contribute to oil contamination beneath the Village of Hartford.”
Doc. 224-1 at 50.
1
Page 16 of 19
in a number of places and clarifying both that the order will act as a settlement bar under
CERCLA and that it will create a cause of action for contribution against defendants that
include Apex. The Apex Consent Order, on the other hand, never mentions CERCLA and
discusses claims from third parties and settlement in the context of the Illinois
Environmental Protection Act and Illinois Joint Tortfeasors Act. Taken together with the
Premcor Consent Order, the broad and ambiguous release of the Apex Consent Order
looks more like vague boilerplate language, not indicative of an intent by both parties to
grant the far-reaching protection that Apex now seeks. As the Seventh Circuit held in
Akzo Coating, 30 F.3d at 768, the Court will “require settling parties to be more explicit
when they intend to bar contribution[.]”
In Apex’s motion, it repeatedly equates its consent order to that of Premcor,
arguing that the Court’s January decision would mean that “both Premcor and Apex
would not have obtained any protection from any federal claim related to the Refinery
Site” (Doc. 219 at 15–16). Premcor and Apex have different liabilities under the federal
orders, and their consent orders are worded differently in a manner that reflects the
reasonable expectations of the signatories to those agreements.
First, the Herndon Order and Findings apply only to Apex, while Premcor is only
subject to the 2004 AOC and 2010 UAO. Because Premcor voluntarily entered into the
2004 AOC, it was not subject to the federal proceeding resulting in the Herndon Order
and Findings, which established that Apex was liable for the entirety of the plume of
contamination arising under the Hartford Refinery and spreading under the Hartford
Village Site. Rather, Premcor’s federal liability solely stems from the two EPA
Page 17 of 19
administrative orders, which are more limited in scope and deal exclusively with specific
remediation work to be completed in the Hartford Village Site. Because Premcor’s federal
liability appears more confined to the Hartford Village Site, it would likely be on firmer
ground in seeking a settlement bar based on the Premcor Consent Order. The language
of that order reflects this reasonable expectation, as the order states that it is “intended
to, and shall serve, as of the Effective Date, as protection from contribution actions or
claims as provided by Section 113(f)(2) of CERCLA[.]”
On the other hand, because Apex is subject to federal liability for the Hartford
Refinery Site under the Herndon Order & Findings, any consent order that carved out
Apex’s federal liability would leave Apex vulnerable to suit under that federal order.
With this liability in mind, it does not seem that the reasonable expectations of the
signatories to the Apex Consent Order could encompass protection under the CERCLA
Settlement Bar, as envisioned by Akzo Coatings. Apex might be inclined to argue that a
state consent order could at least protect Apex from contribution for remediation work
ordered by the state, as opposed to the federal government, but the Court is not sure that
a state consent order could have even this effect. The work ordered by the U.S. EPA and
IEPA is all part of the same general response goal for remediating the totality of the
hydrocarbon plume for which Apex is liable. To allow a state settlement to bar suit for
contribution for work towards that goal ordered by the state but not the federal
government would create a perverse outcome where Apex’s liability was contingent on
which administrative body happened to order certain remediation work, where Apex’s
overall liability for remediating the contamination as a whole had already been
Page 18 of 19
established in federal court. It is the view of this Court that such an outcome would
amount to a misuse of the CERCLA Settlement Bar.
But the Court need not reach such a holding in this action. Based on its extensive
review of the past federal and state proceedings, the factual record describing the scope
of hydrocarbon contamination and remediation efforts in the Hartford Village Site and
Hartford Refinery, and the Apex and Premcor Consent Orders, the Court concludes that
it was not the intent of the IEPA to grant Apex protection under the CERCLA Settlement
Bar and that the Apex Consent Order did not accomplish this. Rather, the Apex Consent
Order is best read as completely resolving Apex’s liability to the State of Illinois but
barring suits for contribution solely under the Illinois laws involved in the Madison
County Proceeding, not CERCLA.
CONCLUSION
For the reasons set forth above, the Court DENIES Apex’s Motion for
Reconsideration (Doc. 219).
IT IS SO ORDERED.
DATED: March 13, 2020
____________________________
NANCY J. ROSENSTENGEL
Chief U.S. District Judge
Page 19 of 19