United States of America v. Essex Electric Company LLC et al
Filing
21
OPINION AND ORDER DENYING 18 MOTION to Dismiss for Lack of Jurisdiction by Counter Claimant Essex Electric Company LLC. Signed by Judge Theresa L Springmann on 7/7/2014. (lhc)
UNITED STATES DISTRICT COURT
NORTHERN DISTRICT OF INDIANA
FORT WAYNE DIVISION
UNITED STATES, FOR THE USE
AND BENEFIT OF JR. BROOKS
CONSTRUCTION, INC.,
Plaintiff,
v.
ESSEX ELECTRIC COMPANY, LLC
and JAMES SMITH,
Defendants.
)
)
)
)
)
)
)
)
)
)
)
)
CAUSE NO.: 1:13-cv-00025-TLS
OPINION AND ORDER
This matter is before the Court on the Defendants’, Essex Electric Company, LLC
(“Essex”) and James Smith, Motion to Dismiss for Lack of Subject Matter Jurisdiction [ECF No.
18] filed on June 14, 2013. The Plaintiff, Jr. Brooks Construction, Inc., filed Plaintiff’s Response
to Motion to Dismiss Complaint for Lack of Subject Matter Jurisdiction [ECF No. 19] on July 5,
2013. The Motion is ripe for ruling.
BACKGROUND
The Plaintiff filed a Complaint against the Defendants for failure to pay for labor and
materials supplied as a subcontractor pursuant to the Miller Act, 40 U.S.C. § 3133. On June 8,
2011, Defendant Essex contracted with the Department of Veteran Affairs (“VA”) on a federal
project known as the Marion VA Salt Dome Project (“Project”). The Plaintiff alleges that Essex
then obtained a Miller Act bond in the amount of $354,555. The plaintiff alleges that Defendant
Smith agreed to be bound jointly and severally with Essex on the bond. In early December 2011
the Plaintiff entered a contract to work as a subcontractor on the Project. On January 25, 2012,
the government issued a “Stop Work Order” to the Plaintiff. The Plaintiff had not completed its
work on the Project at that time, but ceased work on the 25th. Exactly one year later, on January
25, 2013, the Plaintiff filed a Complaint [ECF No. 1] against the Defendants for failure to pay
$16,000 under one invoice and $40,908.61 under another for labor and materials provided for the
Project. In total the Plaintiff has claimed $56,908.61 in unpaid invoices. The Plaintiff has further
claimed the Defendants owe an additional $51,343.88 for concrete forms the Plaintiff rented for
the Project. The Plaintiff alleges that the Defendants used the forms after the Plaintiff had been
removed from the Project while the Plaintiff continued to pay rent. The Plaintiff also alleges that
the Defendants assumed the rental costs going forward at some point in the fall of 2012.
The Defendants filed their Answer and Counterclaim [ECF No. 9] with the Court on
March 15, 2013. Three months later, on June 14, they filed the instant Motion to Dismiss. The
Defendants argue, based on 28 U.S.C. § 1332(a), that the amount in controversy here is less than
the $75,000 minimum necessary for diversity subject matter jurisdiction. The Defendants argue
that the Plaintiffs can only recover the value of the two unpaid invoices under the Miller Act.
The unpaid invoices are for $16,000 and $40,908.61, for a total of $56,908.61. According to the
Defendants, the concrete form rentals do not constitute “materials” as covered by bond
protection under the Miller Act because they were not physically incorporated into or consumed
in the project. See Rowley v. Mid-Continent Cas., Inc., 2004 WL 614500 (E.D. La. 2004).
Therefore, the Plaintiff’s claim for an additional $51,343.88 for concrete form rental cannot be
part of this action. As such, the Defendants contend the amount in controversy is below the
$75,000 minimum for diversity jurisdiction.
2
In the alternative, the Defendants claim that the Plaintiff cannot recover damages for the
rental value of the concrete forms because they failed to mitigate their damages. Consistent with
contract law, a bond payment claimant is required to make reasonable efforts to mitigate its
damages. See United States ex rel. Apex Roofing & Insulation v. Union Indem. Ins. Co., 865 F.2d
1226 (11th Cir. 1989). The Defendants argue that even if the Plaintiff could recover rental costs
under the Miller Act, they cannot here because they let the concrete forms sit idle for nearly 10
months after being removed from the Project. The Defendants argue that if the rent was
recoverable under the Miller Act, the Plaintiff would have had to use reasonable efforts to
mitigate damages rather than allowing them to accrue.
The Plaintiff argues that the Miller Act is “remedial legislation that should be read
charitably to subcontractors.” See United States ex rel. S & G Excavating, Inc. v. Seaboard Sur.
Co., 236 F.3d 883, 886 (7th Cir. 2001). Congress intended the Miller Act to protect
subcontractors who supply labor and materials to general contractors for public works. Id. The
Plaintiff alleges that the Defendants assumed the cost of the rented concrete forms in the fall of
2012. The Plaintiff argues that the Defendants would not have done so if they had not been using
the concrete forms after the Plaintiff had been ordered off the job. The Plaintiff argues that the
Defendants used the concrete forms after the Plaintiff was ordered off the job and after the
Defendants assumed the rental costs, presumably because the Defendants continued to need and
use the forms for completion of the Project. Therefore, the concrete forms should be considered
as materials supplied for the Project under the Miller Act.
Additionally, the Plaintiff argues that the timing of the Motion to Dismiss was
inappropriate. Federal Rule of Civil Procedure 12(b) provides that “A motion asserting any of
these defenses must be made before pleading if a responsive pleading is allowed.” The Plaintiff
3
argues the Motion to Dismiss is improper because it was filed nearly three full months after the
Defendants filed their Answer.
ANALYSIS
A. Timing of the Motion to Dismiss
The Plaintiff argues the Defendants waived the lack of subject matter jurisdiction defense
because they did not timely file the instant Motion to Dismiss, making it improper now. A
motion to dismiss for lack of subject matter jurisdiction must be made before the responsive
pleading, if a pleading is allowed. Fed. R. Civ. P. 12(b). Defenses listed in Federal Rule of Civil
Procedure 12(b)(2)–(5) are waived if the moving party fails to properly make a motion, to
include it in the responsive pleading, or to amend the responsive pleading pursuant to Rule
15(a)(1). Fed. R. Civ. P. 12(h)(1)(B). However, the defense of lack of subject matter jurisdiction
is listed in Rule 12(b)(1) and cannot be waived even if the moving party fails to timely file its
motion. The Court may determine that it lacks subject matter jurisdiction and dismiss the case at
any time. Fed. R. Civ. P. 12(h)(3). It is well-settled law that defendants may object to subject
matter jurisdiction regardless of when the motion is filed; the objecting party may raise the
motion even after they had previously acknowledged the court had jurisdiction. See, e.g.,
Henderson ex rel. Henderson v. Shinseki, 131 S. Ct. 1197, 1202 (2011). In this case the
Defendants filed their Answer on March 15, 2013. The Defendants filed this Motion to Dismiss
three months later on June 14, 2013. Although Rule 12(b) indicates that Rule 12(b) motions
should be filed before an answer, a motion to dismiss for lack of subject matter jurisdiction may
be raised at any time. Therefore, the Court finds that the Defendants’ delay in filing a motion to
4
dismiss for lack of subject matter jurisdiction does not preclude them from raising the defense
here.
B. Subject Matter Jurisdiction
The Miller Act allows subcontractors who furnish labor or materials to a general
contractor for the construction, alteration, or repair of a public building of the United States to
sue for the unpaid amount or balance due under the contract. See, e.g., United States ex rel.
Hussman Corp. v. Fidelity & Dep. Co. of Md., 999 F. Supp. 734, 741 (D.N.J. 1998). Actions
under the Miller Act are brought in the name of the United States for the use of the person suing.
Id. Courts are to liberally construe the Miller Act to effectuate Congress’s intent to protect
subcontractors providing material and labor to public works projects. Id. (citations omitted). The
four elements of a prima facie case for a bond payment claim under the Miller Act are: “(1) the
materials were supplied in prosecution of the work provided for in the contract; (2) the
materialman has not been paid; (3) the materialman had a good faith belief that the materials
were intended for the specified work; and (4) the jurisdictional requirements were met.” Id. The
Defendants argue that the Plaintiff has failed to meet the jurisdictional requirement of a prima
facie Miller Act case because the amount in controversy is less than $75,000. The Defendants
argue that because the amount in controversy is less than $75,000 the Court lacks subject matter
jurisdiction pursuant to 28 U.S.C. 1332(a). As a result, the Plaintiff could not have satisfied the
jurisdictional element of a prima facie Miller Act Case. However, the case the Defendants cite to
specifically discusses the jurisdictional element of a prima facie Miller Act case in terms of the
Miller Act’s one year statute of limitations. Id. The subject matter jurisdiction requirements laid
out in 28 U.S.C. § 1332(a) are not discussed in that court’s reference to the jurisdictional element
5
of a prima facie Miller Act claim. Other courts have discussed the elements of a prima facie
Miller Act case and have also discussed the jurisdictional element in terms of the statute of
limitations. For instance, the Ninth Circuit has consistently discussed the jurisdictional element
in terms of timely notice and filing under the Miller Act. See United States ex rel. Martin Steel
Constructors, Inc. v. Avanti Constructors, Inc., 750 F.2d 759, 761 (9th Cir. 1984); see also
United States ex rel. Balzer Pac. Equip. Co. v. Fid. and Deposit Co. of Md., 895 F.2d 546, 551
(9th Cir. 1990) (holding the movant satisfied the jurisdictional element by bringing suit within
the one year statute of limitations).
Other Circuit Courts have discussed the Miller Act’s one-year statute of limitations
without mentioning the prima facie elements of a Miller Act Case. The Circuit Courts that have
addressed the one-year statute of limitations in the Miller Act have uniformly regarded the
requirement as a jurisdictional limitation on the rights conferred in the Act. See United States ex
rel. Harvey Gulf Int’l Marine, Inc. v. Md. Cas. Co., 573 F.2d 245, 247 (5th Cir. 1978) (citing
United States ex rel. Celanese Coatings Co. v. Gullard, 504 F.2d 466 (9th Cir. 1974); United
States ex rel. Gen. Dynamics Corp. v. Home Indem. Co., 489 F.2d 1004 (7th Cir. 1973); United
States ex rel. Statham Instruments, Inc. v. W. Cas. & Sur. Co., 359 F.2d 521 (6th Cir. 1966);
United States ex rel. Soda v. Montgomery, 253 F.2d 509 (3d Cir. 1958)). To the extent that the
word “jurisdictional” is used in those cases, the court refers to the conditional nature of the right
to sue under the Miller Act, not to the subject matter jurisdiction of the court itself. United States
ex rel. Tex. Bitulithic Co. v. Fid. and Deposit Co. of Md., 813 F.2d 697, 699 (5th Cir. 1987).
The Plaintiff argues that this Court has subject matter jurisdiction pursuant to the
provisions of the Miller Act, 40 U.S.C. § 3133(b)(3)(B). (Complaint 1, ECF No. 1). The Miller
Act provides that “A civil action brought under this subsection must be brought in the United
6
States District Court for any district in which the contract was to be performed and executed,
regardless of the amount in controversy.” 40 U.S.C. § 3133(b)(3)(B). Federal Courts have
unanimously interpreted the language “must be brought in the United States District Court” to
grant exclusive federal subject matter jurisdiction. United States ex rel. Owens-Corning
Fiberglass Corp. v. Brandt Const. Co., 826 F.2d 643, 646 (7th Cir. 1987); see also Koppers Co.
v. Continental Cas. Co., 337 F.2d 499, 506 (8th Cir. 1964) (holding there is no doubt the statute
places exclusive jurisdiction over Miller Act bond suits in federal court); Blanchard v. Terry &
Wright, Inc., 331 F.2d 467, 469 (6th Cir. 1964) (Miller Act expressly confers exclusive federal
jurisdiction); United States ex rel. Brown Minneapolis Tank Co. v. Kinley Const. Co., 816 F.
Supp. 2d 1139, 1145 (D.N.M. 2011) (same).
The latter portion of 40 U.S.C. § 3133(b)(3)(B) provides that Miller Act cases should be
brought in the appropriate district court “regardless of the amount in controversy.” Consistent
with the clear language of the Act, federal courts have interpreted the statute to grant exclusive
federal subject matter jurisdiction regardless of the amount in controversy. The Supreme Court
interpreted the Heard Act, the statutory predecessor to the Miller Act enacted in 1894 at ch. 280,
28 Stat. 278, as granting federal jurisdiction without regard to the amount in controversy. U.S.
Fid. & Guar. Co. v. Hendry Corp., 391 F.2d 13, 18 (5th Cir. 1968) (citing U.S. Fid. & Guar. Co.
v. United States, 204 U.S. 349, 356 (1907)). The Court in U.S. Fidelity & Guaranty Co. v. United
States said interpreting the original Heard Act gave reason to believe that Congress intended all
suits under the Act to be brought in district courts “without regard to the amount in dispute.” 204
U.S. at 358. Congress strengthened that position in 1905 when they amended the Heard Act by
adding language that allowed subcontractors to bring suit in the district court in the district where
the contract was to be performed “irrespective of the amount in controversy in such suit, and not
7
elsewhere.” Id. (italics in original). Over time, through the different adaptations of the Miller
Act, federal courts have continued to hold that they have exclusive subject matter jurisdiction
over Miller Act cases regardless of the amount in controversy. See Hendry Corp., 391 F.2d at 20;
Fanderlik-Locke Co. v. United States ex rel. Morgan, 285 F.2d 939, 943 (10th Cir. 1960); see
also Kinley Const. Co., 816 F. Supp. 2d at 1147 (holding 2002 change to Miller Act does not
reduce precedential value of previous case law on Miller Act).
The Court finds that it has subject matter jurisdiction pursuant to the Miller Act, 40
U.S.C. § 3133(b)(3). As established above, the federal district court where the contract was to be
performed and executed has exclusive subject matter jurisdiction regardless of the amount in
controversy. For the forgoing reasons, the Court declines to address the parties’ arguments about
whether the rented concrete forms constitute “materials” protectable under the Miller Act and
sufficient to establish the amount in controversy for diversity subject matter jurisdiction because
the Court’s subject matter jurisdiction is established on other grounds.
CONCLUSION
For the foregoing reasons, the Court DENIES the Defendants’ Motion to Dismiss for
Lack of Subject Matter Jurisdiction [ECF 18].
SO ORDERED on July 7, 2014.
s/ Theresa L. Springmann___________
THERESA L. SPRINGMANN
UNITED STATES DISTRICT COURT
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?