PHILADELPHIA INDEMNITY INSURANCE COMPANY v. WE PEBBLE POINT
Filing
61
ORDER ADOPTING REPORT AND RECOMMENDATIONS for 55 Report and Recommendations; Overruling Philadelphia Insurance's Objection Docket No. 58 and ADOPT the Magistrate Judge's Report and Recommendation Docket No. 55 *** SEE ORDER ***. Signed by Judge Sarah Evans Barker on 11/18/2016.(CKM)
UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF INDIANA
INDIANAPOLIS DIVISION
PHILADELPHIA INDEMNITY
INSURANCE COMPANY,
Plaintiff/Counterclaim Defendant,
vs.
WE PEBBLE POINT, LLC,
Defendant/Counterclaimant.
)
)
)
)
)
)
)
)
)
)
)
)
1:13-cv-01453-SEB-DML
ORDER ADOPTING THE REPORT AND RECOMMENDATION
This cause is before the Court on Plaintiff Philadelphia Indemnity Insurance
Company’s (“Philadelphia Ins.”) Objection [Docket No. 58] to the Magistrate Judge’s
Report and Recommendation (“R&R”) [Docket No. 55]. For the reasons detailed below
we OVERRULE the Objection and ADOPT the R&R.
Background
The facts of this case, which we summarize below, are undisputed by the parties.
Defendant Pebble Point, LLC (“Pebble Point”) owns an apartment complex in
Indianapolis, Indiana. During the relevant time period, Philadelphia Ins. issued Pebble
Point two materially identical insurance policies covering certain losses at that apartment
complex. In December 2012, Pebble Point made a claim against the Policy for damages
to the apartment buildings which it alleged had been caused by an October 2012 storm. It
then made a second, similar claim for a later storm. 1
After investigation, Philadelphia Ins. determined that the majority of losses
claimed by Pebble Point were caused not by the storm, in which case they would have
been covered, but rather by causes such as improper installation or maintenance of
roofing shingles, other constructions defects, and wear and tear, none of which is covered
by the Policy. As a result, Philadelphia Ins. paid Pebble Point $6,288.56—an amount
equal to the damages it found to have been caused by a covered event, minus Pebble
Point’s $10,000 deductible. Pebble Point challenged Philadelphia Ins.’s conclusion,
maintaining that its covered losses ranged in the hundreds of thousands of dollars, and it
demanded that Philadelphia Ins. participate in an appraisal proceeding as outlined in the
Policy.
Philadelphia Ins. declined to initiate the appraisal process, contending that the
parties’ dispute concerned the extent to which the claimed losses were covered by the
Policy, rather than the “amount of loss” claimed. It then brought this suit seeking a
declaratory judgment that it had fully satisfied its obligation under the Policy. Pebble
Point filed a motion to dismiss the Complaint on grounds that it was entitled to enforce
the appraisal provision of the Policy. We granted Pebble Point’s motion September 3,
1
For sake of simplicity, and given that neither our analysis nor our conclusion requires such distinctions,
we refer to the largely identical insurance policies as “the Policy,” to the back-to-back storms as “the
storm,” and to the corresponding claims as “the claim” throughout this Order.
2014, and ordered the parties to proceed to the appraisal process as provided in the
Policy. See Dkt. 29 at 14.
The Policy’s Appraisal Provision provides the following:
If we and you disagree on the value of the property of the amount of
“loss,” either may make written demand for an appraisal of the “loss.”
In this event, each party will select an umpire. If they cannot agree,
either may request that selection be made by a judge of a court having
jurisdiction. The appraisers will state separately the value of the
property and amount of “loss”. If they fail to agree, they will submit
their differences to the umpire. A decision agreed to by any two will
be binding. Each party will:
a. Pay its chosen appraiser; and
b. Bear the other expenses of the appraisal and umpire equally.
If there is an appraisal, we will still retain our right to deny the claim.
Dkt. 40-2 at 37. Pebble Point and Philadelphia Ins. each selected its own appraiser,
Messrs. Lamont (Pebble Point) and Zwolfer (Philadelphia Ins.). Each party also filed a
motion requesting the court to appoint an umpire and provided the court with the
curriculum vitae of various persons the parties represented to be both neutral and
competent. Dkts. 30, 31. On March 11, 2015, the court selected Mr. David J. Balistreri as
the Umpire for the parties’ appraisal. Dkt. 33.
In March 2015, the Umpire requested that the parties’ appraisers provide him with
their estimates of the damages. The Umpire also scheduled the inspection of the
apartment complex for Thursday, May 28, 2015. About one month prior to the
inspection, on April 22, 2015, Pebble Point’s appraiser emailed to the Umpire an
engineering report dated April 15, 2015, which was prepared by Eduard Badiu of CEBB
Engineering & Testing regarding Pebble Point’s claimed losses. 2
As the date of the May 28th inspection approached, weather forecasts did not look
promising, and given that the appraisers and the Umpire did not want to inspect the roofs
at the complex in wet weather, they sought to reschedule the inspection for a date when
adverse weather conditions would not interfere. A number of emails were exchanged
among them to determine a better date; of those emails, however, some went between
only the Umpire and the Philadelphia Ins. Appraiser. Indeed, the Pebble Point Appraiser
discovered that he had been excluded from those communications only in a subsequent
email that had been forwarded to him by the Umpire in which the Umpire informed both
appraisers that he would decide on May 26, 2015 whether the inspection would go
forward as scheduled on May 28, 2015.
In the ten-day period leading up to the scheduled inspection, various emails were
exchanged between the appraisers and the Umpire relating to the scope of information the
Umpire would consider in making his decision. In the first email, dated May 19, 2015,
the Umpire, after describing the information he had received from the appraisers,
requested confirmation of the expected scope of information, including any expected
2
It appears from the record that, at some point, the Umpire was also provided with an engineering report
that Rimkus Consulting Group, Inc. had prepared on behalf of Philadelphia Ins. Apparently, the
appraisers and the Umpire discussed this report at the May 2015 inspection, but none of the parties’
submissions indicates when or how the Umpire received this Rimkus report.
testimony that the appraisers intended to offer at the inspection. This email states in
relevant part:
Do I have all reports/documents you will be submitting for
review? I believe I have adjuster reports (one from each side)
and an engineer report from [Pebble Point’s Appraiser]. Also
– are there any persons other than yourselves who will provide
testimony/opinions regarding this matter? If so please identify
them. I do not accept last minute submission at the site. I hope
to be able to settle this the day of our site visit but have allowed
some time on Friday [May 29th] if additional paperwork is
required.
Dkt. 39-1 at ¶ 5. Pebble Point’s Appraiser responded that his engineer would be attending
the site visit and inspection. Id. at ¶ 6.
On May 26, 2015, the Umpire replied to both appraisers, stating:
If you intend to have your engineer testify to anything on the
date of our site visit please identify him, what his testimony
will regard, and distribute any reports he may have written to
the entire appraisal panel before the end of the day today.
Please be certain [the Philadelphia Ins. Appraiser] and I have a
complete copy to review prior to our site visit.
I assume your engineer is Badiu, has written and will testify
regarding his report (dated 4/15/2015), which has 39 pages in
total. This is the report I have which you sent me earlier.
I will not accept any documents for consideration after today
that have not been previously shared with the entire panel.
Id. at ¶ 7 (emphasis in original).
The Pebble Point Appraiser’s office responded that same day with an email to
both the Umpire and the Philadelphia Ins. Appraiser which included a Drop Box link to a
folder containing his engineer’s previously-submitted, thirty-nine page report as well as
additional photographs taken by the engineer but not included in his original report. Id. at
¶¶ 8–9.
The Umpire responded:
The stuff in the drop box is too much to download, print,
review and make sense of prior to our site visit.
I asked for all this stuff a long time ago and as there is little
time at this late hour I am rejecting its admission.
Id. at ¶ 9.
On the day of the inspection, the Umpire confirmed that in making his decision he
would not consider Pebble Point’s engineering report and that he would not permit
Pebble Point’s engineer to testify regarding his report, stating that its exclusion was due
to its “late submission.” Id. at ¶ 10. Thus, although Mr. Badui was at the site visit with
the appraisers and the Umpire, he was not permitted to provide any input regarding the
inspection.
During the site visit on May 28, 2015, the Pebble Point Appraiser apparently
noticed a social familiarity between the Philadelphia Ins. Appraiser and the Umpire.
According to him, he confronted the two and asked “about full disclosure of the working
relationship between [them]” and, in response, “they each shrugged their shoulders and
walked away.” Id. at ¶ 12. The Umpire and the Philadelphia Ins. Appraiser maintain that,
when confronted, they told the Pebble Point Appraiser that the Umpire “had served as an
engineer on one or two of [the Philadelphia Appraiser’s] prior claims.” Zwolfer Aff. ¶¶
13–14. To date, the full extent of their prior working relationship has not been conveyed
to the court.
The parties also dispute the thoroughness of the inspection itself. It is undisputed
that the appraisers and the Umpire conducted physical inspections of only some of the
twenty-two allegedly damaged roofs and did not inspect the interior portions of any of the
buildings. 3 Pebble Point and its appraiser contend that the Umpire should have inspected
all twenty-two damaged roofs, given that the roofs had varying degrees of damage, faced
different directions, were of different ages, and had different roof coverings. They
contend further that the Umpire “refused” to conduct inspections of the buildings’
interiors despite knowing that Pebble Point was claiming losses to the interior portions of
the common areas and the individual apartments. Philadelphia Ins.’s Appraiser,
meanwhile, maintains that all three men agreed during the site visit that they would
inspect only a “sampling” of the alleged damages to the roofs, and that Pebble Point’s
Appraiser never requested that the Umpire examine any interior damage to the buildings.
On June 8, 2015, the Umpire sent an email to both appraisers containing his
Appraisal Award in which he awarded Pebble Point $37,179.09 for loss replacement
3
The court has been provided with no evidence detailing which, or how many, of the twenty-two roofs
were actually physically inspected.
costs or $29,743.27 for loss in actual cash value, less any applicable deductible or
previous payment on the claim. Dkt. 41-1. Pursuant to the Policy, the Appraisal Award
became binding on June 9, 2015, when the Philadelphia Ins. Appraiser signed the Award,
signifying his agreement. 4 Id.
On June 14, 2015, the Pebble Point Appraiser emailed the Umpire (with a copy to
the Philadelphia Ins. Appraiser), with the following request:
So that I may provide an explanation to my client, can you
please advise me as to why you chose not to allow my client[’]s
engineering report to be submitted as well as why you did not
allow my client[’]s expert to testify at the appraisal hearing[?]
Dkt. 41-4 at 1. The Umpire responded:
I set the award based on the testimony of both appraisers, all
reports submitted, and my visual examination of the site.
You did not provide ample notification for the other side to
have their own expert present even though I asked for
notification ten days prior to our inspection. I did, however,
consider his report.
Id. 5
4
Pursuant to the Policy, the Award becomes binding when any two members of the three-member panel
agree on its terms.
5
The court has not been informed of any prior deadlines set by the Umpire during the appraisal process
related to the disclosure of expert testimony which were not satisfied by Pebble Point. Presumably, the
Umpire is referring to the same-day deadline set by him in his May 19, 2015 email, which, contrary to his
subsequent email, was met by Pebble Point.
On June 29, 2015, Pebble Point filed a Motion to Set Aside the Appraisal Award,
contending that the Appraisal Award was “tainted with collusion and partiality.” Dkt. 391 at ¶ 11. On August 7, 2015, pursuant to 28 U.S.C. § 636(b)(1)(B) we designated
Magistrate Judge Debra McVicker Lynch of our court to issue a proposed report and
recommendation regarding Pebble Point’s motion to set aside. Dkt. 45. On January 28,
2016, Magistrate Judge Lynch issued her R&R recommending that the Award bet set
aside due to a tainted appraisal process and that the parties’ insurance dispute be litigated
in this court. Dkt. 55. On February 12, 2016, Philadelphia Ins., pursuant to Federal Rule
of Civil Procedure 72, filed its Objection to the Magistrate Judge’s R&R, contending that
the evidence did not support her conclusions. Dkt. 58.
Legal Standard
A district court reviewing a magistrate judge’s decision on non-dispositive issues
may modify or set aside that decision if it is clearly erroneous or contrary to law. See 28
U.S.C. § 636(b)(1)(A); Fed. R. Civ. P. 72(a). Rule 72(a) provides, in pertinent part, that
the district judge in the case must “modify or set aside any part of the order that is clearly
erroneous or is contrary to law.” Fed. R. Civ. P. 72(a). A finding is clearly erroneous
when “the reviewing court on the entire evidence is left with the definite and firm
conviction that a mistake has been committed.” Anderson v. City of Bessemer, 470 U.S.
564, 573 (1983); see also Weeks v. Samsung Heavy Indus. Co. Ltd., 126 F.3d 926, 943
(7th Cir. 1997).
With respect to dispositive matters, Rule 72(b) requires a party who disagrees with
a magistrate judge’s report and recommendation on a dispositive motion to file “specific
written objections to the proposed findings and recommendations.” Fed. R. Civ. P.
72(b)(2); see also 28 U.S.C. § 636(b)(1); Johnson v. Zema Sys. Corp., 170 F.3d 734, 739
(7th Cir. 1999); Goffman v. Gross, 59 F.3d 668, 671 (7th Cir. 1995). The district court
then determines, de novo, “any part of the magistrate judge’s disposition that has been
properly objected to.” Fed. R. Civ. P. 72(b)(3); see also 28 U.S.C. § 636(b)(1); Remy Inc.
v. Tecnomatic, S.P.A., 2013 WL 1311095, at *1 (S.D. Ind. Mar. 26, 2013).
Analysis
Philadelphia Insurance’s Objection to the Magistrate Judge’s Report &
Recommendation is narrow. For the most part, it does not dispute the factual sequence of
events leading up to and occurring during and after the inspection and appraisal process,
nor does it dispute any fact relating to the subsequent issuance of the Appraisal Award
that Pebble Point now seeks to set aside. 6 In addition, both parties agree that the case
relied upon by the Magistrate Judge in reaching her conclusion, Atlas Construction Co.
v. Indiana Insurance Co., 309 N.E.2d 810 (Ind. Ct. App. 1974), is controlling in this
matter.
In interposing its objection to the R&R, Philadelphia Ins. argues simply that the
evidence relied upon by the Magistrate Judge was insufficient to support her finding of
6
We note also that Philadelphia Ins. has not raised an objection to the Magistrate Judge’s
recommendation that this case be litigated in this Court as opposed to remanded for a new appraisal
process. Accordingly, we hereby ADOPT that portion of the R&R.
fraud, mistake, or misfeasance, which is required to set aside an award. We are
unpersuaded by this argument.
Under Atlas and its progeny, an appraisal award may be set aside upon a showing
of fraud, collusion, misfeasance, bias, or some similar exceptional circumstance of
manifest injustice. See e.g., Atlas, 309 N.E.2d at 812 (“The Courts of Indiana will not
hesitate to set aside an appraisal award if it is tainted with fraud, collusion, or
partiality….”); Jupiter Aluminum Corp. v. Home Ins. Co., 225 F.3d 868, 875 (7th Cir.
2000) (“[U]nder Indiana law, an appraisal award is binding unless it can be shown that
the appraisal is infected with unfairness or injustice.”); FDL, Inc. v. Cincinnati Ins. Co.,
135 F.3d 503, 505 (7th Cir. 1998) (“Exceptional circumstances [for setting aside an
appraisal award] include manifest injustice, fraud, collusion, misfeasance or the like.”).
As explained in her well-reasoned R&R, Magistrate Judge Lynch concluded that
the evidence in this case supported a finding of bias and partiality on the part of
Philadelphia Ins. such that it tainted the appraisal process and warranted setting aside the
Award. We agree with the Magistrate Judge’s conclusion based in particular on the
following salient factual findings:
• Previously Undisclosed relationship: It remains undisputed that the Umpire who
was proposed to the court by Philadelphia Ins. as a neutral and competent candidate
for the Appraisal Panel had a prior working relationship with the Philadelphia Ins.
Appraiser who was also assigned to the Panel. This relationship was not disclosed
to the court nor to Pebble Point and its appraiser until, and only after, the Pebble
Point Appraiser perceived a familiarity between the two during the site visit and
inspection on May 28, 2015.
• Ex Parte Emails: Certain emails regarding the scheduling of the site visit and
inspection were exchanged between only the Philadelphia Ins. Appraiser and the
Umpire and were not disclosed to the Pebble Point Appraiser until three days prior
to the May 28, 2015 inspection.
• Exclusion of Pebble Point Expert Report & Testimony: Despite the need for
engineering expertise regarding the causation of the claimed losses in this case (as
Philadelphia Ins. itself stressed before this court), the Umpire refused to admit
Pebble Point’s engineering report or to allow its engineer, who was in attendance at
the site visit, to offer any input or testimony regarding the damage to the buildings.
When pushed for an explanation by Pebble Point’s Appraiser after the Award had
been issued, the Umpire stated that he had rejected its admission because it was
“late.” However, it appears from the record that the Umpire was originally provided
the report more than one month prior to the site visit and inspection. Then, ten days
prior to the site visit, the Umpire acknowledged that he had received the report and
inquired as to whether the parties anticipated presenting testimony or opinions
regarding the claim. When Pebble Point responded that it planned to present its
engineer’s testimony, the Umpire set a same-day deadline for Pebble Point to
provide the entire Panel with copies of his report and expected testimony, signaling
once again that he was already in possession of Mr. Badui’s 39-page report, dated
April 15, 2015. Pebble Point’s Appraiser complied with the same-day deadline set
by the Umpire by providing the Philadelphia Ins. Appraiser and the Umpire with a
Drop Box link to a folder containing the 39-page engineering report along with
additional photos of the damaged buildings. Nonetheless, the Umpire rejected its
admission, stating that the materials were “too much” for him to review prior to the
site visit which was set to occur ten days later, even though he had previously
acknowledged having possession of the very same report for approximately one
month.
• Insufficiency of Site Inspection: It is undisputed that the Umpire, although having
full knowledge of the scope and details of Pebble Point’s claimed losses, declined
to inspect all of the allegedly damaged roofs and any of the buildings’ interiors
during the site visit.
• Awarded Amount: The awarded amount of $37,179.09, less the $10,000
deductible and $6,288,56 already paid on the claim, was significantly less than the
$562,000 in losses claimed by Pebble Point.
While no single fact necessarily establishes the existence of fraud, collusion, or
bias in this case, we find that the cumulative effect of all the evidence before us is
sufficient to prove misfeasance, partiality, and arbitrariness in the appraisal process and
thus warrants setting aside the Appraisal Award. Accordingly, we OVERRULE
Philadelphia Insurance’s Objection [Docket No. 58] and ADOPT the Magistrate Judge’s
Report and Recommendation [Docket No. 55].
IT IS SO ORDERED.
Date: 11/18/2016
Distribution:
Patrick C. McGinnis
MERLIN LAW GROUP
pmcginnis@merlinlawgroup.com
Phillip N. Sanov
MERLIN LAW GROUP, P.A.
psanov@merlinlawgroup.com
Eric S. Pavlack
PAVLACK LAW LLC
eric@pavlacklawfirm.com
Colin E. Flora
PAVLACK LAW, LLC
Colin@PavlackLawFirm.com
John Patrick Schomaker
SMITH ROLFES & SKAVDAHL CO, L.P.A.
pschomaker@smithrolfes.com
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?