W&W Steel, LLC v. BSC Steel, Inc. et al
Filing
174
MEMORANDUM AND ORDER granting 135 Motion for Partial Summary Judgment of APAC-Kansas, Inc., Judgment shall be entered for APAC-Kansas, Inc. and against W & W Steel, LLC and Liberty Mutual Insurance Company on Count VI of APAC-Kansas, Inc.'s c omplaint in intervention in the amount of $275,756.35 plus prejudgment interest of $155,292.61 along with continuing interest and attorney's fees. ; denying 142 Motion for Partial Summary Judgment of W & W Steel, LLC and Liberty Mut ual Insurance Company; denying 152 APAC-Kansas, Inc.'s Motion for Hearing; denying 159 Motion for Partial Summary Judgment by W & W Steel, LLC and Liberty Mutual Insurance; granting 161 Motion for Summary Judgment of APAC-Kansas, Inc., Judgment shall be entered for APAC-Kansas, Inc. and against BSC Steel, Inc., in the amount of #275,756.35 in principal, plus $155,292.61 in prejudgment interest which continues to accumulate daily, plus costs and attorney's fees; granting [ 163] Motion for Partial Summary Judgment of American Riggers Supply, Inc., Judgment shall be entered for American Riggers Supply, Inc and against BSC Steel, Inc.; W & W Steel, LLC and Liberty Mutual Insurance Company on Count VI of American Riggers Supply, Inc.'s complaint in intervention in the amount of $170,572.00. Signed by District Judge Richard D. Rogers on 2/26/15. (meh)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF KANSAS
APAC-KANSAS, INC.,
Intervenor Plaintiff,
v.
BSC STEEL INC.; W & W STEEL,
LLC; and LIBERTY MUTUAL
INSURANCE CO.;
Intervenor Defendants.
________________________________
Case No. 11-2613-RDR
AMERICAN RIGGERS SUPPLY, INC.,
Intervenor Plaintiff,
v.
BSC STEEL INC.; W & W STEEL,
LLC; and LIBERTY MUTUAL
INSURANCE CO.;
Intervenor Defendants.
MEMORANDUM AND ORDER
This
matter
is
presently
before
the
court
upon
the
following motions for partial summary judgment: (1) APAC-Kansas,
Inc. (APAC) against W & W Steel, LLC (W&W) and Liberty Mutual
Insurance Company (Liberty Mutual) (Doc. # 135); (2) W&W and
Liberty Mutual against APAC (Doc. # 142); (3) W&W and Liberty
Mutual against American Riggers Supply, Inc. (American Riggers)
1
(Doc. # 159); (4) APAC against BSC Steel, Inc. (BSC) (Doc. #
161); and (5)
American Riggers against BSC, W&W and Liberty
Mutual (Doc. # 163).
APAC has also filed a motion for oral
argument on the motion for partial judgment filed against W&W
and
Liberty
partial
summary
judgment filed by W&W and Liberty Mutual against it.1
Having
carefully
Mutual
reviewed
and
the
the
cross-motion
pending
for
motions,
the
court
is
now
prepared to rule.
I.
Factual Background
This case arises out of the construction of the Irwin Army
Community
Hospital
located
on
Fort
Riley,
Kansas.
Balfour-
Walton Joint Venture (BWJV) served as the general contractor on
the project (Project). BWJV contracted a portion of the work to
W&W.
W&W agreed to perform the steel erection of the general
contract work on the project.
W&W then subcontracted some of
its work to Materials Management, Inc. (MMI).
into
a
Mutual,
contract
as
with
surety,
BSC
issued
for
a
the
steel
payment
bond
MMI then entered
erection.
(Payment
Liberty
Bond)
in
connection with the subcontract between BWJV and W&W for sums
1
APAC-Kansas, Inc. seeks oral argument on these motions pursuant to D.Kan. Rule 7.2. Rule 7.2 states that A[t]he
court may set any motion for oral argument ... at the request of a party ...@ The discretion to schedule oral argument lies with the
court. The court does not find oral argument necessary here. The court shall deny APAC-Kansas, Inc.=s request for oral
argument.
2
due on the project in the amount of $12,640,000.
APAC entered into a series of lease agreements with BSC in
which APAC agreed to furnish BSC with certain equipment and
associated
labor.
APAC
furnished
and
supplied
all
of
the
equipment, services and associated labor as required under the
lease
agreements.
APAC
provided
BSC
with
several
invoices
seeking payment for the equipment, services and labor.
The
invoice terms provided in part that finance charges of 1.5% per
month would accrue on all unpaid invoices.
has not made full payment.
BSC admits that it
APAC sought payment from W&W for the
amounts owed by BSC, but W&W has made no payment to APAC.
In
this case, APAC seeks the value of the equipment and services
provided to BSC which amounts to $275,756.35 plus prejudgment
interest
of
$155,292.61
attorney=s fees and costs.
plus
additional
continuing
interest,
APAC seeks to recover these amounts
from the Payment Bond issued by Liberty Mutual.
American Riggers provided material and services to BSC for
use by BSC in performance of BSC=s subcontract with MMI.
BSC
owes American Riggers the principal amount of $170,572.00 for
the material and services.
American Riggers sought payment from
W&W and Liberty Mutual for this amount, but they have made no
payments
to
American
Riggers.
American
Riggers
now
seeks
judgment in the amount of $170,572.00, as well as interest at 10
3
percent under K.S.A. 16-201.
II. Procedural Background
APAC filed a motion for summary judgment on Count VI of its
complaint in intervention.
APAC sought payment from W&W and
Liberty Mutual under the Payment Bond for equipment and services
it provided to BSC.
APAC asserts that payment has not been made
by W&W or Liberty Mutual after they received notice of APAC=s
bond claim.
In response, W&W and Liberty Mutual argued (1) APAC
has no standing to bring claim under the Payment Bond because
APAC is not a proper claimant; (2) APAC is not entitled to
payment under the Payment Bond because it has not shown, as
required by the subcontract between BWJV and W&W, that W&W has
been
paid
by
BWJV
for
the
work
of
APAC;
(3)
W&W
has
been
discharged from any liability to APAC because W&W has satisfied
its responsibilities under the Apay-when-paid@ obligations of its
subcontract with BWJV by paying $163,500.00 to BSC for work
performed by APAC; (4) APAC failed to provide W&W with timely
notice of its claim and W&W has been prejudiced by that failure;
and (5) APAC has failed to show its charges are correct and that
its charges were actually forwarded to W&W.
W&W and Liberty Mutual filed a cross-motion for partial
summary judgment on Count VI of APAC=s complaint in intervention
after it filed a response to APAC=s motion for summary judgment
4
on that claim.
In this motion, W&W and Liberty Mutual raised
one of the arguments raised in their earlier response.
They
contended that APAC is not a proper claimant under the Payment
Bond and, therefore, lacks standing to bring a claim under it.
APAC has also filed a motion for summary judgment against
BSC.
In this motion, APAC seeks summary judgment on the breach
of contract claims asserted in Counts II, III and IV of its
complaint for intervention against BSC.
BSC has indicated to
the court that it does not intend to file a response to APAC=s
motion.
W&W and Liberty Mutual have also filed a motion for partial
summary judgment on American Riggers= claim against them under
the Payment Bond.
They raise the same argument that they raised
concerning the claim made by APAC under the Payment Bond.
They
contend that American Riggers is not a proper claimant under the
Payment Bond and, therefore, lacks standing to bring a claim
under it.
American Riggers has filed a motion for summary judgment
against BSC, W&W Steel and Liberty Mutual.
American Riggers
seeks summary judgment against BSC for payment for the materials
and services that it provided to BSC for the Project.
BSC has
indicated
file
response
to
to
the
court
American
that
Riggers=
it
does
motion.
5
not
intend
American
to
Riggers
a
also
seeks summary judgment against W&W and Liberty Mutual under the
Payment Bond for materials and services provided on the Project.
In response, W&W and Liberty Mutual contend (1) American Riggers
is not a proper claimant under the Payment Bond and, thus, lacks
standing to recover under the Bond; (2) American Riggers is not
entitled to payment under the Payment Bond because it has not
shown, as required by the subcontract between BWJV and W&W, that
W&W has been paid by BWJV for the work of American Riggers; (3)
American Riggers failed to provide W&W with timely notice of its
claim and W&W has been prejudiced by that failure; (4) American
Riggers has failed to show its charges are correct and that its
charges were actually forwarded to W&W; and (5) the amount of
damages owed to American Riggers remains in dispute.
III.
Summary Judgment Standards
Summary
judgment
is
appropriate
if
the
moving
party
demonstrates Athat there is no genuine dispute as to any material
fact@ and that it is Aentitled to judgment as a matter of law.@
Fed.R.Civ.P. 56(a).
the
evidence
and
In applying this standard, the court views
all
reasonable
inferences
light most favorable to the nonmoving party.
therefrom
in
the
City of Herriman
v. Bell, 590 F.3d 1176, 1181 (10th Cir. 2010). AThere is no
genuine issue of material fact unless the evidence, construed in
the light most favorable to the non-moving party, is such that a
6
reasonable jury could return a verdict for the non-moving party.@
Bones v. Honeywell Int=l, Inc., 366 F.3d 869, 875 (10th Cir.
2004)(citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248,
255
(1986)).
A
fact
is
Amaterial@
if,
under
the
applicable
substantive law, it is Aessential to the proper disposition of
the claim.@
Wright ex rel. Trust Co. of Kan. v. Abbott Labs.,
Inc., 259 F.3d 1226, 1231B32 (10th Cir. 2001)(citing Adler v.
WalBMart Stores, Inc., 144 F.3d 664, 670 (10th Cir. 1998)).
An
issue of fact is Agenuine@ if Athere is sufficient evidence on
each side so that a rational trier of fact could resolve the
issue either way.@
Adler, 144 F.3d at 670 (citing Anderson, 477
U.S. at 248).
The
moving
party
initially
must
show
the
absence
of
a
genuine issue of material fact and entitlement to judgment as a
matter of law.
904 (10th
Celotex
Spaulding v. United Transp. Union, 279 F.3d 901,
Cir. 2002), cert. denied, 537 U.S. 816 (2002)(citing
Corp.
v.
Catrett,
477
U.S.
317,
322B23
(1986)).
In
attempting to meet this standard, a movant that does not bear
the ultimate burden of persuasion at trial need not negate the
non-movant=s claim; rather, the movant need simply point out to
the court a lack of evidence for the nonmovant on an essential
element of the nonmovant’s claim.
Adams v. Am. Guar. & Liab.
Ins. Co., 233 F.3d 1242, 1246 (10th
Cir. 2000)(citing Adler, 144
7
F.3d at 671); see also Kannady v. City of Kiowa, 590 F.3d 1161,
1169 (10th Cir. 2010).
Once the movant has met the initial burden of showing the
absence of a genuine issue of material fact, the burden shifts
to the nonmoving party to Aset forth specific facts showing that
there is a genuine issue for trial.@
Anderson, 477 U.S. at 256;
Celotex, 477 U.S. at 324; Spaulding, 279 F.3d at 904 (citing
Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574,
587 (1986)). The nonmoving party may not simply rest upon its
pleadings to satisfy its burden.
Anderson, 477 U.S. at 256;
accord Eck v. Parke, Davis & Co., 256 F.3d 1013, 1017 (10th Cir.
2001). Rather, the nonmoving party must Aset forth specific facts
that would be admissible in evidence in the event of trial from
which a rational trier of fact could find for the nonmovant.@
Mitchell v. City of Moore, Okla., 218 F.3d 1190, 1197B98 (10th
Cir. 2000)(quoting Adler, 144 F.3d at 670B71); see Kannady, 590
F.3d at 1169.
The defendant has the burden of proof on an affirmative
defense,
and
thus
in
moving
for
summary
judgment
on
the
affirmative defense, A[t]he defendant. . .must demonstrate that
no
disputed
material
fact
exists
regarding
the
affirmative
defense asserted.@ Hutchinson v. Pfeil, 105 F.3d 562, 564 (10th
Cir. 1997). Once the defendant makes this initial showing, Athe
8
plaintiff must then demonstrate with specificity the existence
of a disputed material fact.@ Id.
viewed
in
the
light
most
If after the evidence is
favorable
to
the
plaintiff,
the
plaintiff cannot meet this burden, Athe affirmative defense bars
his
claim,
and
the
defendant
is
then
entitled
to
summary
judgment as a matter of law.@ Id.
Finally, summary judgment is not a Adisfavored procedural
shortcut@;
on
the
contrary,
Adesigned
to
secure
the
it
is
just,
an
important
speedy
and
procedure
inexpensive
determination of every action.@ Celotex, 477 U.S. at 327 (quoting
Fed.R.Civ.P. 1). In responding to a motion for summary judgment,
Aa party cannot rest on ignorance of facts, on speculation, or on
suspicion and may not escape summary judgment in the mere hope
that something will turn up at trial.@ Conaway v. Smith, 853 F.2d
789, 794 (10th Cir. 1988). When examining the underlying facts of
the
case,
the
court
is
cognizant
that
it
may
credibility determinations or weigh the evidence.
not
make
Matsushita,
475 U.S. at 587.
IV.
Applicable Law/Analysis
This case is based on diversity jurisdiction.
Thus, the
court applies the substantive law of the forum state, including
its choice-of-law rules.
state=s
choice-of-law
Here, the court must look to the forum
rules
to
9
determine
the
effect
of
a
contractual
choice-of-law
clause.
The
BWJV/W&W
Subcontract,
which is specifically incorporated by reference into the Payment
Bond, states that the Alaws of the State in which the project is
located will be applied in resolving the dispute.@
The project
was located in Kansas and, therefore, Kansas law applies.
With
the
exception
of
the
claims
of
APAC
and
American
Riggers against BSC, the remaining motions involve the claims of
APAC
and
American
Riggers
based
upon
the
Payment
Bond.
As
correctly pointed out by APAC and American Riggers, the court is
not considering any claims under the Miller Act, 40 U.S.C. ' 3131
et seq., which mandates that, when awarding a federal contract
for
construction
of
public
building
or
public
work
of
the
federal government, a contractor must furnish a bond to the
federal
government
in
order
to
ensure
that
payment
of
all
persons supplying labor and material in carrying out the work
provided for in the contract.
40 U.S.C. ' 3131(b)(2).
Here,
BWJV required that W&W execute a Payment Bond for the Project.
It is that common law bond that the court considers here.
AA
surety
bond
is
to
be
construed
in
the
light
of
the
circumstances in which it is given, so as to effectuate its
purpose.@
Local No. 1179 v. Merchants Mut. Bonding Co., 228 Kan.
226, 613 P.2d 944, 946 (1980).
But it is also well established
in Kansas law that Athe obligation of a bond is to be measured by
10
the
bond
itself
enlarged
by
contract.@
(1973).
and
may
not
construction
be
beyond
extended
the
terms
by
implication
of
the
or
executed
In re Smith=s Estate, 211 Kan. 397, 507 P.2d 189, 192
Moreover, A[t]he primary rule for interpreting written
contracts is to ascertain the parties= intent. If the terms of
the contract are clear, the intent of the parties is to be
determined from the language of the contract without applying
rules of construction.@ Osterhaus v. Toth, 291 Kan. 759, 249 P.3d
888, 896 (2011).
But, a bond will be construed favorably to the
bonded, if such construction is consistent with the object for
which the bond was made.
Farmer v. Rutherford, 136 Kan. 298, 15
P.2d 474, 477-78 (1932); State v. Mass. Bonding & Ins. Co., 91
Kan. 74, 136 P. 905, 908 (1913)
A.
Proper Claimants under the Payment Bond
W&W and Liberty Mutual contend in their motions for summary
judgment that American Riggers and APAC are not proper claimants
under
the
Payment
Bond.
Thus,
they
contend
that
APAC
and
American Riggers lack standing to make a claim based upon the
Payment Bond.
The
relevant
portion
of
the
Payment
bond
provides
follows:
NOW THEREFORE, the condition of this obligation
is such that if the Contractor shall make payment to
all claimants for all costs and expenses resulting
11
as
from the performance of this Subcontract and for all
labor, materials, equipment, supplies, services, and
the like, used or reasonably required for use in the
performance of this Subcontract, for all or any part
of which the Contractor and Owner is liable, failing
which such claimants shall have a direct right of
action against the Subcontractor and Surety under this
obligation, subject to the Contractor=s priority, shall
have the right to bring an action against the
Subcontractor
and
Surety
on
behalf
of
unpaid
claimants, then this obligation shall be null and
void, otherwise, it shall remain in full force.
The arguments of W&W and Liberty Mutual have changed during
the course of the debate on the instant motions for summary
judgment. Initially they contended, relying upon the language in
the aforementioned clause Ato whom the Contractor and Owner is
liable,@ that American Riggers and APAC were not proper claimants
under the Payment Bond because they could not establish that the
Contractor
(BWJV)
and
the
Owner
(the
United
States)
were
directly liable to them for their claims.
After APAC and American Riggers pointed out that based upon
that interpretation of the clause no one would qualify as a
claimant because there is no one to whom both BWJV and the
United States could directly be liable, W&W and Liberty Mutual
changed their argument to rewrite the Payment Bond to change
AContractor and Owner@ to AContractor or Owner.@
In support of
this argument, they pointed to a variety of cases where courts
have interpreted Aand@ to mean Aand/or.@
12
The court finds no merit to the arguments offered by W&W
and Liberty Mutual.
The court believes that the appropriate
construction of the phrase Afor all or any part of which the
Contractor and Owner is liable@ is a general reference to the
costs of constructing the project.
under
the
Payment
Bond
only
if
Claimants can seek recovery
they
are
seeking
costs
and
expenses for labor and materials used in the performance of a
subcontract
liable.
for
which
BWJV
and
the
United
States
would
be
See United States ex rel. Wheeling-Pittsburgh Steel
Corp. v. Algernon Blair Inc., 329 F.Supp. 1360, 1364 (D.S.C.
1971)(court construed same clause in a payment bond and found
that
materialman
who
provided
material
to
subcontractor
is
entitled to benefit of the payment bond due to the language
providing for direct action by all claimants).
in harmony with the purpose of the Payment Bond.
This reading is
Moreover, such
an interpretation does not require rewriting the bond language
as suggested by W&W and Liberty Mutual.
Finally, this reading
is consistent with the rule that a bond must be construed in
favor of the claimant and against the surety.
B.
Pay-When-Paid
W&W and Liberty Mutual next contend that even if APAC and
American Riggers are proper claimants, they are not entitled to
summary judgment on their claims because they have not shown
13
that either BWJV or W&W has been paid for their work.
Thus,
they argue that subcontractors APAC and American Riggers can
only recover after they show that an upper-tier contractor has
been paid for the work or supplies sought by them.
The pay-when-paid argument articulated by W&W and Liberty
Mutual is more complicated than either party has acknowledged.
In
MidAmerica
Construction
Management,
Inc.
v.
MasTec
North
America, Inc., 436 F.3d 1257, 1261-62 (10th Cir. 2006), the Tenth
Circuit explained such provisions in construction contracts as
follows:
Construction contracts often contain provisions
referred
to
as
Apay-when-paid@
and
Apay-if-paid@
clauses. See Robert F. Carney & Adam Cizek, Payment
Provisions in Construction Contracts and Construction
Trust
Fund
Statutes:
A
FiftyBState
Survey,
24
Construction Law. 5 (2004). Courts have not uniformly
applied these terms. See id. (ASome courts refer to
both provisions as >pay-when-paid= clauses....@). Still,
the terms Apay-when-paid@ and Apay-if-paid@ refer to
distinct types of contractual clauses:
A typical Apay-when-paid@ clause might
read: AContractor shall pay subcontractor
within seven days of contractor's receipt of
payment from the owner.@ Under such a
provision in a construction subcontract, a
contractor's
obligation
to
pay
the
subcontractor is triggered upon receipt of
payment from the owner. Most courts hold
that this type of clause at least means that
the contractor's obligation to make payment
is suspended for a reasonable amount of time
for the contractor to receive payment from
the
owner.
The
theory
is
that
a
Apay-when-paid@
clause
creates
a
timing
mechanism only. Such a clause does not
14
create
a
condition
precedent
to
the
obligation to ever make payment, and it does
not expressly shift the risk of the owner's
nonpayment to the subcontractor....
A typical Apay-if-paid@ clause might
read: AContractor's receipt of payment from
the owner is a condition precedent to
contractor's obligation to make payment to
the
subcontractor;
the
subcontractor
expressly assumes the risk of the *1262
owner's nonpayment and the subcontract price
includes this risk.@ Under a Apay-if-paid@
provision
in
a
construction
contract,
receipt of payment by the contractor from
the owner is an express condition precedent
to the contractor's obligation to pay the
subcontractor. A Apay-if-paid@ provision in a
construction subcontract is meant to shift
the risk of the owner's nonpayment under the
subcontract from the contractor to the
subcontractor. In many jurisdictions, courts
will enforce a Apay-if-paid@ provision only
if that language is clear and unequivocal.
Judges
generally
will
find
that
a
Apay-if-paid@ provision does not create a
condition precedent, but rather a reasonable
timing provision, where the Apay-if-paid@
provision is ambiguous.
Id. at 5B6 (footnotes omitted).
Two
considered
Kansas
cases,
both
from
this
issue.
In
Shelley
the
federal
Electric,
court,
Inc.
v.
have
U.S.
Fidelity & Guaranty Co., 1992 WL 319654 (D.Kan. Oct. 16, 1992),
Judge Kelly noted that at that time no Kansas case had ever
considered the question of the proper interpretation of Apaidwhen-paid@ contract provisions.
1992 WL 319654 at * 2.
He
examined the construction contract and found it involved a Apaywhen-paid@ clause rather than a Apaid-if-paid@ clause.
15
Id. at *3.
He noted that there was no language indicating the existence of
a condition precedent and no express condition.
Subsequently,
in
Faith
Technologies,
Id.
Inc.
v.
Fidelity
&
Deposit Co. of Md., 2011 WL 251451 (D.Kan. Jan. 26, 2011), Judge
Belot found that the subcontract there contained a Apay-if-paid@
clause.
2011
WL
252451
at
*3.
He
relied
upon
language
contained in the subcontract that provided payment by the owner
to
the
subcontractor
was
a
condition
precedent
subcontractor=s liability for payment to others.
for
the
Id.
In this case, the subcontracts (the contract between W&W
and
MMI
and
the
contract
between
MMI
and
BSC)
provide
pertinent part:
(a) . . . .Contractor shall be obligated to pay
Subcontractor only when Contractor receives payment
from the Owner or General Contractor, as the case may
be, with such payments to be made within ten (10) days
after receipt thereof by Contractor. Contractor shall
not be obligated to make any payments (progress, final
or otherwise) to Subcontractor until the Owner or
General Contractor pays Contractor for the work
performed by the Subcontractor.
(b)
Upon
receipt
of
payment
from
Contractor,
Subcontractor
shall
promptly
pay
each
of
its
subcontractors, materialmen, suppliers and any other
party the amount to which said person is entitled.
Subcontractor shall receive each payment in trust, and
as bailee, for the express use and purpose of paying
for all labor, materials, equipment and services
(including all taxes, fees and assessments thereon)
and other items and things used by subcontractor in
the performance of its work; and title to such
payments or any part thereof shall not vest in
16
in
Subcontractor
until
all
obligations
incurred
by
Subcontractor have been first paid in full and the
work
to
be
done
under
this
Subcontract
is
satisfactorily completed.
Contractor shall have the
right, but not the obligation, at all times to contact
Subcontractor=s
subcontractors,
materialmen
and
suppliers to ensure that the same are being promptly
paid by Subcontractor for labor, materials, equipment
and
services
furnished
for
use
in
performing
Subcontractor=s work.
(c) As an express condition precedent to payment by
Contractor to Subcontractor of any sums due and owing
under this Subcontract, Subcontractor shall provide or
have provided Contractor: (i) A description of work
performed during such preceding payment period, (ii) A
list of all bills for supplies, materials, equipment,
and fixtures incorporated in the work (in detail
reasonably sufficient to allow Contractor to determine
where each item is incorporated) and labor performed
(in detail reasonably sufficient to allow Contractor
to determine where and on what portion of the work the
labor was performed, including, but not limited to,
certified weekly labor payrolls with names, dates,
hours and rates) in connection with the work, together
with copies of the actual bills to be paid; (iii) such
certificates of insurance as required herein; (iv)
lien releases, in forms satisfactory to Contractor,
for Subcontractor and any of its sub-subcontractors,
suppliers, or vendors related to the work for which
payment is requested; and (v) any other information or
documentation as Contractor may reasonably require to
substantiate
Subcontractor=s
request
for
payment.
Subcontractor
understands
and
agrees
that
Subcontractor=s billing must be received by Contractor
no later than the 15th of each month. Failure to
timely submit billing may result in Subcontractor=s
payment being delayed until the following month.
As noted in MidAmerica, many jurisdictions enforce Apay-ifpaid@ provisions only if the language is clear and unequivocal.
These
courts
refuse
to
shift
17
the
risk
of
the
owner=s
nonperformance from the general contractor to the subcontractor
unless the language clearly indicates that the parties intended
to do so.
A review of the language here does not evidence that the
parties intended to shift the risk of the owner=s nonperformance
from the general contractor to the subcontractor with sufficient
clarity to qualify as a condition precedent.
The language of
the subcontracts suggests that the parties agreed to a Apay-whenpaid@ arrangement, not a Apay-if-paid@ arrangement.
The language
contained in paragraphs (a) and (b) could be interpreted only as
timing provisions.
It is not necessarily indicative of the
parties= intent to make the subcontractor=s obligation to pay its
subcontractors dependent upon the subcontractor first being paid
by
the
contractor
or
owner.
This
is
particularly
so
considered in light of the provisions of paragraph (c).
when
There
the parties created a condition precedent for the timely payment
of payments by the contractor to the subcontractor.
sentence
illustrates
that
the
parties
condition precedent if they so desired.
knew
how
to
The first
create
a
That they did not use
such unambiguous language in paragraphs (a) and (b) prevents
this
court
from
construing
that
language
as
a
condition
precedent to the right to payment by APAC and American Riggers.
The language contained here is closer to the language used in
18
the contract in Shelley than that used in the contract in Faith
Technologies.
suggested
by
Therefore,
W&W,
that
there
APAC
are
and
no
requirements,
American
Riggers
had
as
to
establish that (1) W&W had been billed by BSC, through MMI, for
the labor, services and equipment APAC and American Riggers; or
(2) W&W had been paid by BWJV for the work of APAC and American
Riggers for which they make claims.
Accordingly, the court does
not find that the argument of W&W concerning the Apay-when-paid@
provisions of the subcontracts precludes summary judgment for
APAC and American Riggers on Count VI of their complaints in
intervention.
C.
Discharged from Liability Due to Payment
W&W
also
contends
that
it
has
been
discharged
for
any
liability under the Payment Bond for the claims asserted by APAC
because it paid BSC and MMI certain monies that represented work
performed by APAC.
In support of this argument, W&W notes that
in April 2011, BSC, through MMI, submitted certain invoices to
it
for
work
BSC
performed by APAC.
June 2011.
by APAC.
and
MMI
performed
and
this
included
work
W&W paid these amounts to BSC and MMI in
This amount included $163,500.00 for work performed
Accordingly, W&W contends that (1) it discharged its
obligations under the subcontract when it made this payment; and
(2) it had no further liability to APAC for any other monies
19
because it never received any other payments from BWJV that were
withheld from BSC and APAC.
Thus, W&W argues that APAC has no
claim against it under the Payment Bond.
The arguments of W&W are based upon language contained in
the subcontracts.
W&W attempts to piece together various parts
of the subcontracts to support its contentions.
In a nutshell,
W&W contends that it has satisfied its obligations under the
subcontracts because it paid BSC/MMI when it received payment
for the charges that contained the APAC claims.
And, it has no
further obligations to APAC because it has never received any
additional payments from BWJV that involved charges for BSC or
APAC.
In
making
this
argument,
W&W
has
failed
consider the language of the Payment Bond.
the
Payment
obligations
Payment
Bond
of
Bond
the
are
not
conditioned
incorporated
provides
that
are
properly
The obligations of
upon
subcontracts.
claimants
to
the
payment
Rather,
entitled
to
the
sue
directly on the Payment Bond when they have not been paid for
Aall costs and expenses resulting from the performance of this
Subcontract and for all labor, materials, equipment, supplies,
services, and the like, used or reasonably required for use in
the performance of this Subcontract.@
Because APAC was not paid
for the equipment and services it provided to the Project, APAC
20
is covered under the Bond.
Accordingly, the court finds no
merit to the contention raised by W&W.
D.
Notice Requirement
W&W and Liberty Mutual next argue that American Riggers and
APAC did not give timely notice of their claims to W&W.
W&W
indicates that APAC waited almost four months to provide notice
that BSC had not paid for services APAC provided to the Project.
W&W notes that American Riggers did not provide formal notice to
it of BSC=s alleged nonpayment until eight months after American
Riggers first sold BSC material for use in the performance of
the subcontract.
Requirements
as
to
notice
of
loss
are
essentially
contractual, unless the legislature has enacted statutes on the
issue.
loss,
Thus, when a policy makes no reference to notice of
either
expressly
or
by
incorporation
of
a
statutory
provision, there is no specific requirement that such notice be
given, even in the case of the principal=s default on a bond
guaranteeing
payment
for
labor
and
material.
See
Board
of
Public Instruction of Sarasota County v. Fidelity & Cas. Co. Of
N.Y., 184 So.2d 491, 494 (Fla.Dist.Ct.App. 1966); Phoenix Ins.
Co. v. Lester Bros., Inc., 203 Va. 802 127 S.E.2d 432, 436
(1962).
any
Here, W&W and Liberty Mutual have failed to point to
requirement
of
notice
in
the
21
Payment
Bond.
They
have
further
failed
to
show
that
Kansas
or
notice under the circumstances here.
federal
law
requires
As a result, the court
finds no merit to the argument raised by W&W and Liberty Mutual
that either APAC or American Riggers failed to provide to notice
here.
E.
Amount of Damages
In their motions for summary judgment, APAC and American
Riggers
indicated
that
it
provided
BSC
services and repairs for the Project.
owed
the
principal
$155,292.61.
amount
of
certain
materials,
APAC asserts that it is
$275,756.35
plus
interest
of
American Riggers states that BSC owes American
Riggers the principal amount of $170,572 for these materials and
services.
In support of these statements, APAC and American
Riggers rely upon the affidavit of Robert Bartley.
W&W
and
Liberty
Mutual
contend
that
Bartley=s
affidavit
cannot be used to support the statements that BSC has agreed to
the
charges
asserted
by
APAC
and
American
Riggers
because
Bartley last worked for BSC in October 1981 and he is not a
current employee or agent of BSC.
The court finds no merit to
this contention for a number of reasons.
The
uncontroverted
evidence
before
Bartley is an authorized agent of BSC.
the
court
shows
that
Jay D. Patel, an officer
of BSC, has stated in an affidavit that Bartley was authorized
22
to speak on BSC=s behalf.
In addition, APAC has pointed out that
Bartley is currently an officer of BSC, the Secretary, and has
been since at least 2011.
W&W
and
Liberty
Mutual
Accordingly, the challenges made by
to
Bartley=s
declarations
are
without
merit.
Finally, W&W contends that the amount of American Riggers=
damages remains in dispute and must be decided by a finder of
fact.
W&W
contends
that
the
amount
of
damages
claimed
by
American Riggers (1) does not account for the offset of certain
returned items; and (2) fails to consider that it has already
paid BSC for the amount requested by BSC.
The court finds no merit to the arguments raised by W&W
concerning the amount sought by American Riggers.
In fact, the
court is perplexed by the contentions made by W&W.
W&W and
Liberty Mutual have stipulated in the Pretrial Order that BSC
owes American Riggers $170,572.00.
Thus, the argument by W&W
that the amounts owed to American Riggers are in dispute are
contradicted by the stipulation and admission it made in the
Pretrial Order.
Moreover,
W&W
has
failed
to
raise
a
genuine
issue
of
material fact concerning any contention that it is entitled to a
setoff for the return of certain items.
contention
concerning
a
possible
23
setoff,
For support of its
W&W
points
to
an
affidavit of Glenn A. VanEnk, who served as W&W=s Project Manager
for
the
Project.
He
has
stated
in
his
affidavit
that
the
invoices provided by American Riggers fail to provide a setoff
for equipment returned to American Riggers after BSC stopped
work
on
the
project.
However,
as
correctly
pointed
out
by
American Riggers, there is no evidence in the record that any
items were returned to it.
American Riggers has provided an
affidavit of Jennifer Hughes, its Office Manager, in which she
states that no items for which American Riggers seeks payment
were returned to it.
W&W has also argued that it may have already paid MMI and
BSC for some material or services provided by American Riggers.
Thus,
W&W
contends
that
it
would
be
not
liable
to
American
Riggers under the Payment Bond for any amount that it has paid
to MMI and BSC for materials or services provided by American
Riggers.
The court has already considered and rejected this
argument when it was directed at the claim asserted by APAC.
We
must do so again.
In U.S. ex rel. Quality Trust, Inc. v. Cajun Contractors,
Inc.,
486
F.Supp.2d
1255,
1267
(D.Kan.
2007),
Judge
Crow
explained that in order to be successful on a claim under a
Miller Act payment bond, a party must prove that it was not paid
for the equipment it provided, the work it performed or the
24
supplies it furnished to the project.
Although Quality Trust
dealt with a payment bond under the Miller Act, this court is
confident that the elements necessary for success on a common
law payment bond are the same as those for a claim under the
Miller Act, especially when neither party has cited a Kansas
case on the issue.
See Lexicon, Inc. v. Safeco Ins. Co. Of
America, Inc., 436 F.3d 662, 668 n. 3 (6th Cir. 2006).
noted
above,
APAC
and
American
Riggers
have
shown
As
by
the
undisputed facts that each provided equipment, labor or services
to the Project, and each was not paid.
court
has
Liberty
rejected
Mutual,
all
APAC
of
and
the
defenses
American
Accordingly, since the
asserted
Riggers
are
by
W&W
entitled
and
to
summary judgment against W&W and Liberty Mutual on their claims
based upon the Payment Bond.
F.
Claims Against BSC
APAC seeks summary judgment on all its claims against BSC.
APAC asserts causes of action on account and breach of contract
against BSC.
APAC argues that the undisputed facts show that
BSC rented equipment for the Project and that BSC has failed to
pay for that equipment, even though BSC approved APAC=s invoices.
APAC notes that BSC has not asserted any defenses.
As previously noted, BSC has indicated that it does not
intend to respond to APAC=s motion for summary judgment against
25
it.
In
the
pretrial
order,
BSC
has
acknowledged
provided the equipment as set forth in their invoices.
that
APAC
BSC does
not dispute the invoices or the amounts in those invoices.
BSC
asserts no defenses to the claims made by APAC.
Given the admissions of BSC, the court finds that APAC=s
motion for summary judgment must be granted.
Accordingly, the
court shall grant judgment to APAC and against BSC in the amount
of
$275,756.35
in
principal,
plus
prejudgment
interest
of
$155,292.61 which continues to accumulate daily plus its costs
and attorney’=s fees.
IT IS THEREFORE ORDERED that the motion for partial summary
judgment
of
W
&
W
Steel,
LLC
and
Liberty
Mutual
Insurance
Company (Doc. # 142) be hereby denied.
IT IS FURTHER ORDERED that the motion for partial summary
judgment
of
W
&
W
Steel,
LLC
and
Liberty
Mutual
Insurance
Company (Doc. # 159) be hereby denied.
IT IS FURTHER ORDERED that APAC-Kansas, Inc.=s motion for
oral argument (Doc. # 152) be hereby denied.
IT IS FURTHER ORDERED that the motion for partial summary
judgment of APAC-Kansas, Inc. (Doc. # 135) be hereby granted.
Judgment shall be entered for APAC-Kansas, Inc. and against W &
W Steel, LLC and Liberty Mutual Insurance Company on Count VI of
APAC-Kansas, Inc.=s complaint in intervention in the amount of
25
$275,756.35 plus prejudgment interest of $155,292.61 along with
continuing interest and attorney’s fees.
IT IS FURTHER ORDERED that the motion for summary judgment
of APAC-Kansas, Inc. (Doc. # 161) be hereby granted.
Judgment
shall be entered for APAC-Kansas, Inc. and against BSC Steel,
Inc. in the amount of $275,756.35 in principal, plus $155,292.61
in
prejudgment
interest
which
continues
to
accumulate
daily,
plus costs and attorney’s fees.
IT IS FURTHER ORDERED that the motion for partial summary
judgment of American Riggers Supply, Inc. (Doc. # 163) be hereby
granted.
Judgment shall be entered for American Riggers Supply,
Inc. and against BSC Steel, Inc.; W & W Steel, LLC and Liberty
Mutual Insurance Company on Count VI of American Riggers Supply,
Inc.=s complaint in intervention in the amount of $170,572.00.
IT IS SO ORDERED.
Dated this 26th day of February, 2015, at Topeka, Kansas.
s/RICHARD D. ROGERS
Richard D. Rogers
United States District Judge
26
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?