Western Building Group, LLC v. Travelers Casualty and Surety Company of America et al
Filing
17
ORDER granting 7 Motion to Stay Case and Compel Arbitration; granting 12 Motion for Leave to File Sur-reply; denying 14 Motion for Oral Argument. The parties shall file a joint status report, not less than once every six months, regarding the progress of the arbitration. Signed by Magistrate Judge James P. O'Hara on 1/18/2017. (ah)
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF KANSAS
UNTIED STATES OF AMERICA,
For the Use and Benefit of
WESTERN BUILDING GROUP, LLC,
Plaintiff,
v.
TRAVELERS CASUALTY AND SURETY
COMPANY OF AMERICA, et al.,
Defendants.
)
)
)
)
)
)
)
)
)
)
)
)
Case No. 16-1407-JTM
ORDER
This construction dispute is brought under the Miller Act1 by a subcontractor on a
federal project against the prime contractor and its surety. Defendants have filed a motion
to stay this action and compel arbitration, in accordance with an arbitration provision in the
subcontract (ECF No. 7). Plaintiff does not oppose arbitration, but asks the court to
“prohibit the arbitrator from issuing a stay of the arbitration proceedings” while the prime
contractor resolves pass-through claims with the United States Army Corps of Engineers
1
40 U.S.C. § 270a et seq. The Miller Act “requires a Government contractor to post
a surety bond ‘for the protection of all persons supplying labor and material in the
prosecution of the work provided for’ in the contract. The Act further provides that any
person who has so furnished labor or material and who has not been paid in full within 90
days after the last labor was performed or material supplied may bring suit on the payment
bond for the unpaid balance.” F. D. Rich Co. v. U. S. ex rel. Indus. Lumber Co., 417 U.S.
116, 118 (1974) (quoting 40 U.S.C. § 270b(a)).
O:\ORDERS\16-1407-JTM-7.wpd
-1-
(“COE”), the owner of the project.2 Because plaintiff does not oppose the motion to compel
arbitration and stay this case, the motion is granted. The court denies plaintiff’s unsupported
request for the court to set procedural limits on the arbitration.
The facts are few and undisputed. Defendant Archer Western Aviation Partners
(“AWAP”), a joint venture, was awarded a federal contract to construct three airplane
hangers at McConnell Air Force Base in Wichita, Kansas. As required by the Miller Act,3
AWAP executed a payment bond, covering the contract, with defendant Travelers Casualty
and Surety Company of America (“Travelers”). AWAP then entered a subcontract with
plaintiff whereby plaintiff agreed to perform insulated-metal and roof-panel work on the
project. The subcontract contains an arbitration provision, which states in pertinent part:
Any controversy or claim of Contractor against Subcontractor or Subcontractor
against Contractor or its surety shall, at the option of Contractor or
Contractor’s surety and at any time, be resolved by arbitration pursuant to rules
determined by Contractor. The Contractor and Subcontractor agree to equally
split the administrative costs, fees, and other similar expenses charged by the
arbitrator or arbitration agency. Subcontractor irrevocably submits to the
jurisdiction of the federal, state, or United States territory courts located in the
state or United States territory of the Project for the purpose of proceedings
with respect to the arbitration.4
On November 7, 2016, plaintiff filed this lawsuit. Plaintiff’s complaint asserts three
causes of action, all arising from plaintiff’s contention that it is owed money for work it
2
ECF No. 10 at 5.
3
See 40 U.S.C. § 3131(b)(2).
4
Subcontract, ECF No. 8-2, at ¶ 11.2.
O:\ORDERS\16-1407-JTM-7.wpd
-2-
performed under the subcontract. The first cause of action is brought under the Miler Act,
and the remaining causes of action are brought under state law for breach of contract and
quantum merit. On December 13, 2016, defendants jointly filed the instant motion to compel
arbitration and stay the case.
“Under the Federal Arbitration Act (‘FAA’),5 agreements to arbitrate are ‘valid,
irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the
revocation of any contract.’”6 Thus, federal policy favors arbitration agreements and requires
the court to “rigorously enforce” them.7 On a motion to compel arbitration under the FAA,
the court should compel arbitration if it finds (1) a valid arbitration agreement exists between
the parties, and (2) the dispute before it falls within the scope of the agreement.8 In this case,
the parties agree that both conditions are present.9 Accordingly, the court grants defendants’
5
9 U.S.C. §§ 1–3.
6
In re Cox Enters., Inc. Set-top Cable Television Box Antitrust Litig., 790 F.3d 1112,
1116 (10th Cir. 2015) (quoting 9 U.S.C. § 2), cert. denied sub nom. Cox Commc’ns, Inc. v.
Healy, 136 S. Ct. 801 (2016).
7
Shearson/Am. Express, Inc. v. McMahon, 482 U.S. 220, 226 (1987); see also In re
Cox, 790 F.3d at 1116 (quoting Hill v. Ricoh Ams. Corp., 603 F.3d 766, 777 (10th Cir.
2010)).
8
9 U.S.C. §§ 2–3.
9
See ECF No. 10 at 2 (“[Plaintiff] recognizes that under the Subcontract, AWAP and
the surety, Defendant Travelers . . . has the option to require arbitration. . . . [Plaintiff] has
no objection to arbitration of its claims against the Defendants in an expeditious manner.”).
O:\ORDERS\16-1407-JTM-7.wpd
-3-
motion to compel arbitration. As required by the FAA, the court stays this action pending
the arbitration.10
Plaintiff asks the court to place restrictions on the arbitration.11 Plaintiff expresses
concern that “Defendants intend . . . to stay the arbitration proceeding until [AWAP] can
litigate its pass-through claims against the Corps of Engineers.”12 According to plaintiff,
such an arbitration stay would delay resolution of plaintiff’s Miller Act claims in violation
of the Tenth Circuit’s opinion in Fanderlik-Locke Co. v. U.S. ex rel. Morgan, 285 F.2d 939,
942 (10th Cir. 1960).13 Plaintiff asserts the court must “give effect” to the parties’
subcontract agreement that “the arbitrator would be limited to applying the law of the state
of Kansas and decisions of the District of Kansas and the Tenth Circuit construing the Miller
Act.”14 Specifically, plaintiff asks the court to “prohibit the arbitrator from issuing a stay of
10
See 9 U.S.C. § 3.
11
The court grants plaintiff’s motion for leave to file a sur-reply in support of
plaintiff’s request that the court set parameters on the arbitration (ECF No. 12). The court
has considered plaintiff’s sur-reply in deciding this matter. The court finds the parties’
positions on plaintiff’s request clearly set forth in the multiplicitous briefs addressing the
issue (ECF Nos. 10, 11, 12, 13, 14, 15, and 16) and therefore denies plaintiff’s motion to
further address the issue in oral argument (ECF No. 14).
12
ECF No. 10 at 3.
13
Plaintiff sets forth a detailed substantive argument that the “paid when and if paid”
clause of the subcontract did not waive plaintiff’s Miller Act rights and cannot operate to stay
plaintiff’s Miller Act claim.
14
Id. at 4.
O:\ORDERS\16-1407-JTM-7.wpd
-4-
the arbitration proceedings contrary to the established law of this jurisdiction”15 and to
prohibit defendants from asking the arbitrator to stay plaintiff’s Miller Act claims.16
The court respectfully declines plaintiff’s request. First, plaintiff has cited no case,
and the court knows of none, in which a court has compelled arbitration and placed
restrictions of this type on the arbitration proceeding. Binding precedent suggests that the
court has no such authority. The Supreme Court has directed that “‘procedural questions
which grow out of the dispute and bear on its final disposition’ are presumptively not for the
judge, but for an arbitrator, to decide.”17 And the Tenth Circuit has directed that “‘arbitration
is a matter of contract’ in which courts have a limited role. In that limited role, courts do not
have authority to decide questions explicitly addressed by the arbitration agreement.”18 “In
this circuit, the arbitration panel is entitled to extreme deference in setting the bounds of its
15
Id. at 5.
16
Id. at 15.
17
Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84 (2002) (emphasis in
original) (quoting John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543, 557 (1964) (holding
that an arbitrator should decide whether steps that were prerequisites to arbitration were
completed)); see also Green Tree Fin. Corp. v. Bazzle, 539 U.S. 444, 452–53 (2003) (ruling
that question which “concerns contract interpretation and arbitration procedures” is for
arbitrator, not court, to decide); Local 7 United Food and Commercial Workers Intern. Union
v. Albertson’s Inc., 963 F.2d 382, at *3 (10th Cir. 1992) (unpublished table decision)
(holding that under broad arbitration clause, whether a party could impose unilateral time
limits for the selection of arbitrators was a question for arbitrator, not court, to decide).
18
Shell Oil Co. v. CO2 Comm., Inc., 589 F.3d 1105, 1108 (10th Cir. 2009) (quoting
Howsam, 537 U.S. at 83).
O:\ORDERS\16-1407-JTM-7.wpd
-5-
authority to decide an issue submitted to arbitration.”19 Thus, although plaintiff may well be
correct that under Fanderlik-Locke the arbitration of plaintiff’s Miller Act claim cannot be
stayed pending a resolution of AWAP’s pass-though claims against the COE, the question
is for the arbitrator to decide, not for this court to dictate.
Second, plaintiff’s request presupposes a potential future development—i.e., that
defendants will move the arbitrator to stay the arbitration—which may or may not come to
fruition. The court may not issue advisory opinions about speculative future events.20 If and
when defendants make such a motion, plaintiff may assert their substantive arguments that
Fanderlik-Locke prohibits such a stay, and the arbitrator will rule under the applicable law.
Plaintiff has not cited a case suggesting that the court may anticipate and decide an issue
which only hypothetically may arise during arbitration.
In summary, plaintiff recognizes that its claims are subject to arbitration under the
19
Hungry Horse LLC v. E Light Elec. Servs., Inc., 569 F. App’x 566, 573 (10th Cir.
2014).
20
See, e.g., Camreta v. Greene, 563 U.S. 692, 717 (2011) (“The ‘judicial Power is one
to render dispositive judgments,’ not advisory opinions.”) (quoting Plaut v. Spendthrift Farm,
Inc., 514 U.S. 211, 219 (1995)); Rio Grande Silvery Minnow v. Bureau of Reclamation, 601
F.3d 1096, 1112 (10th Cir. 2010) (holding that speculative concerns about possible future
action cannot support a claim for declaratory relief because “such relief would amount to an
advisory opinion regarding the scope of [defendant’s] discretion and such an opinion would
clearly be improper”).
O:\ORDERS\16-1407-JTM-7.wpd
-6-
subcontract and that this federal lawsuit should be stayed pending such arbitration.21 Plaintiff
has not persuaded the court that the court has authority to place parameters on the mandated
arbitration.
IT IS THEREFORE ORDERED that defendants’ motion to compel arbitration and
stay proceedings is granted, and all proceedings in this matter shall be STAYED pending
arbitration of the claims presently asserted by plaintiff.
IT IS FURTHER ORDERED that this court shall retain jurisdiction to review, modify,
or vacate any arbitration awards, should any party choose to seek such action as permitted
by the FAA, and shall retain jurisdiction to dismiss this lawsuit if plaintiff fails to initiate
arbitration within 30 days of the entry of this order.
IT IS FURTHER ORDERED that the parties shall file a joint status report, not less
than once every six months (to begin six months from the date of this order), regarding the
progress of the arbitration.
Dated January 18, 2017, at Kansas City, Kansas.
s/ James P. O’Hara
James P. O’Hara
U.S. Magistrate Judge
21
See U.S. ex rel. Humbarger v. Law Co., No. 01-4156-SAC, 2002 WL 436772, at *4
(D. Kan. Feb. 20, 2002) (“The court finds that this agreement between the contractor and
subcontractor to arbitrate their dispute will be upheld even though Miller Act jurisdiction
exists, and that this suit brought in federal court under the Act should be stayed pending such
arbitration. The Miller Act does not prohibit arbitration before resort to the courts where, as
here, the subcontractor and contractor have previously agreed to arbitrate disputes.”).
O:\ORDERS\16-1407-JTM-7.wpd
-7-
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?