VT Milcom, Inc v. Walbridge-Dotster et al
Filing
71
MEMORANDUM OPINION & ORDER granting 54 Motion to Amend Complaint. Signed by Chief Judge Thomas B. Russell on 11/8/2011. cc:counsel (KJA)
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF KENTUCKY
PADUCAH DIVISION
CASE NO. 5:08-CV-202
THE UNITED STATES FOR THE USE AND
BENEFIT OF VT Milcom, INC.,
PLAINTIFF
v.
WALBRIDGE-DOSTER, A JOINT
VENTURE, TRAVELERS CASUALTY AND
SURETY COMPANY OF AMERICA,
FEDERAL INSURANCE COMPANY, and
SAFECO INSURANCE COMPANY OF
AMERICA
DEFENDANTS
MEMORANDUM OPINION AND ORDER
This matter is before the Court upon Plaintiff VT Milcom’s Motion for Leave to File
Amended Complaint (DN 54). The Defendants have responded (DN 61). Plaintiff has replied
(DN 62). For the following reasons, Plaintiff’s motion (DN 54) is GRANTED.
BACKGROUND
This breach of contract case involves a federal government construction project. In 2005,
the U.S. Army Corps of Engineers (COE) entered into a contract with Defendant WalbridgeDoster (W-D) for the construction of the Division Headquarters Command and Control Facility
in Fort Campbell, Kentucky. W-D, the general contractor, entered into a sub-contract with VT
Milcom (Milcom) that required Milcom to install electrical and communications systems. For
various reasons, there were several changes in the plan and project schedules. For example,
hidden building foundations, sewer lines, and manholes were uncovered on the project site.
Additionally, active communications lines were uncovered and needed to be re-routed. As a
result, Milcom alleges that W-D has refused to pay Milcom all sums due under the subcontract
or for the additional labor, service, and material expenses it incurred due to the various changes.
In April 2009, after Milcom filed its original complaint, W-D informed Milcom that its
claims related to the actions or inactions of the COE and therefore invoked the prime contract
disputes procedure outlined in the prime contract between W-D and the COE. W-D maintains
that Milcom’s claims arise from the site of the COE, the design of the COE, and the changes in
scope ordered by the COE; therefore, Milcom’s claims, if proven, should be paid for by the
COE. The dispute procedure outlined in the prime contract is derived from the Federal Contract
Disputes Act and requires the submission of a written, formal, documented claim that W-D can
certify to the COE.
Shortly after this action commenced, the parties submitted a Consent Motion to Stay (DN
24) so that Milcom’s claims could be presented by W-D to the COE. For various reasons
disputed by the parties, Milcom’s claims were not presented to the COE. W-D filed a motion to
lift the stay (DN 44) in April 2011 so that this litigation could proceed. Citing confusion over
the claims asserted against W-D, Milcom filed this Motion for Leave to File Amended
Complaint.
STANDARD
Federal Rule of Civil Procedure 15(a)(2) provides that “a party may amend its pleading
only with the opposing party’s written consent or the court’s leave.” The rule directs that the
“court should freely give leave when justice so requires.” Fed. R. Civ. P. 15(a)(2). This rule
gives effect to the principle that, as far as possible, cases should be determined on their merits
and not on technicalities. Cooper v. Am. Employers’ Ins. Co., 296 F.2d 303, 306 (6th Cir. 1961).
Denial of leave to amend may be appropriate “where there is undue delay, bad faith or dilatory
motive on the part of the movant, repeated failure to cure deficiencies by amendments previously
allowed, undue prejudice to the opposing party by virtue of allowance of the amendment, futility
of the amendment, etc.” Miller v. Champion Enters., Inc., 346 F.3d 660, 690 (6th Cir. 2003)
(citations and quotation omitted).
DISCUSSION
Plaintiff Milcom seeks leave of this Court to file an amended complaint to clarify the
factual basis for its claims. W-D opposes Milcom’s motion because (1) it is futile, (2) it will
substantially prejudice W-D, and (3) its justifications for the amendment are illusory. Generally,
W-D contends that Milcom is attempting to shift the responsibility for its claims from the COE
to W-D by re-characterizing its claims generally as “additional labor, services, and materials it
provided in compliance with WD’s directives.”
1. Futility of the Amended Complaint
W-D asserts that Milcom’s amended complaint is futile because it merely restates the same
allegations pled in the original complaint with added language shifting its focus to W-D. “An
amendment is futile when it ‘merely restates the same facts using different language, or
reasserts a claim previously determined.’” Bower v. Jones, 978 F.2d 1004, 1008 (7th Cir.
1992)(quoting Wakeen v. Hoffman House, Inc., 724 F.2d 1238, 1244 (7th Cir. 1983)).
However, the amended complaint does not merely restate the same facts– it clarifies the basis on
which Milcom’s claims against W-D are premised. Milcom asserts that recent communications
between counsel made it clear that W-D misconstrued Milcom’s original complaint. The
amended complaint clarifies that Milcom’s claims against W-D are based on the actions of W-D
and breach of the contract between Milcom and W-D. Accordingly, Milcom’s amended
complaint is not futile.
2. Prejudice to W-D
W-D next asserts that allowing Milcom to file its amended complaint will substantially
prejudice W-D. To support this contention, W-D points to the time and resources devoted to
assisting Milcom in presenting its claims to the COE. However, the extent of the assistance
given by W-D is highly contested by the parties. W-D alleges that, although it cooperated with
Milcom and expressed its willingness to present a certified claim to the COE, Milcom failed to
provide the data necessary to permit W-D to submit Milcom’s claims. Milcom alleges that WD refused to submit a certified claim to the COE, a jurisdictional prerequisite to invoking the
Federal Contract Dispute process. Milcom further alleges that its claim was incomplete because
W-D refused to provide the Prime Contract Record—which would make the claim complete—
unless Milcom first agreed to release W-D and its bonding company from all claims it had
against them. Nevertheless, because the events that occurred during the two-year stay are
distinct from the progression of this litigation, the Court finds this argument unavailing.
W-D also asserts that it will be prejudiced because the amended complaint asserts a new
theory of liability based on evidence that was available to Milcom at the time the original
complaint was filed. However, the Court does not agree that the amended complaint asserts a
new theory of liability. In fact, the two complaints are strikingly similar. Like the original
complaint, the amended complaint asserts a breach of contract claim against the same
defendant. Despite W-D’s assertion otherwise, the original complaint did not seek to hold the
COE responsible for Milcom’s increased expenses or for the sums due under the subcontract
between W-D and Milcom. That the parties attempted to find an alternate resolution of
Milcom’s claims does not change the nature of the claims asserted in the original complaint.
Furthermore, W-D will not be prejudiced by any delay in filing an amended complaint as
this action is not at a late stage in the litigation. Although W-D points to the fact that this
litigation is over two and a half years old, it was stayed for two years. “Delay alone however,
without any specifically resulting prejudice, or any obvious design by dilatoriness to harass the
opponent, should not suffice as reason for denial.” Moore v. City of Paducah, 790 F.2d 557,
562 (6th Cir. 1986). Accordingly, W-D has not shown that it will be prejudiced by the amended
complaint.
3. Justifications for Amended Complaint
As justification for its amended complaint, Milcom asserts that it will help clarify the nature
of its claims to opposing counsel, and will help narrow the scope of discovery. W-D argues that
these justifications are illusory and do nothing to clarify or narrow the scope of discovery. As
discussed above, the Court finds that the complaint does help to clarify the nature of its claims
to opposing counsel. Despite the fact that this action was filed against W-D and not against the
COE, and that the Complaint alleged breach of the subcontract between W-D and Milcom, W-D
insists that the original complaint did not assert claims against it. The amended complaint
clarifies that the claims are against W-D, for the actions of W-D and based on the contract
between Milcom and W-D. Accordingly, this clarification will likely help to focus the parties’
future discovery efforts on the actions or inactions of the actual parties to this litigation.
CONCLUSION
For the foregoing reasons, Plaintiff’s Motion for Leave to Amend Complaint (DN 54) is
GRANTED.
November 8, 2011
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?