Rain CII Carbon LLC v. ConocoPhillips Company
Filing
97
ORDER AND REASONS denying 90 Motion to Enforce Judgment. Signed by Judge Helen G. Berrigan on 06/24/2013. (kac, )
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
RAIN CII CARBON LLC,
CIVIL ACTION
VERSUS
NO. 09-4169
CONOCOPHILLIPS COMPANY
SECTION “C” (4)
ORDER AND REASONS1
Before the Court is plaintiff’s, RAIN CII CARBON LLC, motion to enforce the Court’s
judgment against defendant CONOCOPHILLIPS COMPANY and its assignee PHILLIPS 66
COMPANY. Rec. Doc. 90. PHILLIPS 66 COMPANY opposes the motion. Rec. Doc. 92.
Having considered the record, the memoranda of counsel and the law, the Court DENIES the
motion for the following reasons.
I. BACKGROUND
ConocoPhillips Company2 (“Phillips”) and Rain CII Carbon LLC (“Rain CII”) entered
into a long-term agreement dated August 23, 2005, for the supply of green anode coke (“coke”).
Rec. Doc. 90-3. Section 4(a) of the agreement contains a complicated formula for calculating the
current market price of the coke over the duration of the agreement. Rec. Doc. 90-3 at 5. Section
4(c) of the agreement permits the parties to re-open price negotiations in the event that either
party reasonably concludes that the price formula does not accurately reflect relevant market
1
Nicholas Roosevelt, a second-year student at Northwestern Law School, assisted in preparing
this Order and Reasons.
2
In May 2012, ConocoPhillips Company assigned substantially all of its refining and marketing
business to Phillips 66 Company. The two entities are collectively referred to as Phillips herein.
See Rec. Doc. 90-3 at 1 (for a description of the contractual relationship between the two
entities).
1
conditions. Rec. Doc. 90-3 at 7. If the parties are unable to re-negotiate the price formula, either
party may declare an impasse and the matter will be submitted to arbitration conducted in
accordance with arbitration provisions included in Section 19 of the agreement. Id. In addition to
addressing dispute resolution procedures, Section 19 states: “[a]ny controversy or claim arising
out of or relating to this Agreement, or the breach thereof, shall be settled by arbitration . . . .”
Rec. Doc. 90-3 at 14. In the case of arbitration regarding the price formula, the parties are each
responsible for proposing a “replacement mechanism” price formula to the arbitrator, who is
then authorized to select the price formula that will most accurately reflect market conditions.
Rec. Doc. 90-3 at 7.
Phillips initiated price formula re-negotiations in 2007. Rec. Doc. 90-3 at 20. Beginning
in 2009, Rain CII began purchasing coke from Phillips, under protest, at the replacement
mechanism price formula advocated by Phillips. Rec. Doc. 90-3 at 24-25. That same year,
Phillips demanded arbitration. Rec. Doc. 90-1 at 4. On March 7, 2011, an arbitrator ruled in
favor of the price formula advocated by Rain CII–the same price formula included in the original
agreement. Rec. Doc. 90-3 at 23. The arbitrator ruled that the original price formula “shall
remain in effect for the balance of the term as stated in the contract.” Id. The ruling also awarded
a money judgment of $17,702,585.33 for, among other damages, the coke purchased by Rain CII
under protest at the price formula advocated by Phillips. Rec. Doc. 90-3 at 24-25. The ruling
stated that the “Award is final and binding with respect to all claims and counterclaims presented
to the arbitrator. All relief not expressly granted herein, is denied.” Rec. Doc. 90-3 at 27.
Following the arbitration ruling, Phillips filed a motion for the Court to vacate the
arbitration award. Rec. Doc. 47. Rain CII filed a cross-motion to confirm the arbitration ruling.
2
Rec. Doc. 59. The Court denied Phillips’ motion and granted Rain CII’s cross-motion,
confirming the arbitration ruling. Rec. Doc. 71. The parties do not dispute that the Court’s order
granting Rain CII’s cross-motion gave the arbitration ruling the same force and effect as a
judgment of the Court. See 9 U.S.C. §13 (2013); see also Rec. Doc. 77-1 at 1; Rec. Doc. 96 at 5.
The Court then granted Phillips’ motion to approve a supersedeas bond, allowing Phillips
to appeal the Court’s judgment without first paying the money judgment to Rain CII. Rec. Doc.
83. The supersedeas bond order did not address Phillips’ obligation to prospectively invoice
Rain CII according to the price formula selected by the arbitrator; however, Phillips’
memorandum in opposition to Rain CII’s current motion contains a declaration by one of its
managers stating that all invoices issued to Rain CII since the date of the arbitration ruling have
been issued according to the price formula selected in the arbitration ruling. Rec. Doc. 92-1.
Rain CII does not address the declaration regarding invoicing in its reply to Phillips’
memorandum in opposition. See Rec. Doc. 96. On April 3, 2012, the Fifth Circuit affirmed the
Court’s order confirming the arbitration ruling. Rec. Doc. 84. On April 6, 2012, the parties
jointly represented to the Court that the money judgment had been satisfied in full. Rec. Doc. 87.
Rain CII now argues that Phillips has failed to satisfy the Court’s judgment by seeking to
initiate a new arbitration proceeding to re-calculate the price formula. Rec. Doc. 90. At issue is
the following language in Section 4(c) of the agreement between Rain CII and Phillips:
“The [arbitrator’s] selected replacement mechanism shall remain in effect for at
least eight quarters, after which either party may reinitiate the [arbitration]
process described in the preceding sentence if the party reasonably concludes that
the replacement mechanism does not accurately reflect changes in relevant market
conditions arising after selection of the replacement mechanism.” Rec. Doc. 90-3
at 7.
3
Rain CII advocates for a construction of the arbitration ruling and of its agreement with
Phillips that makes explicit “that the replacement mechanism [price formula] selected would
remain in effect ‘for the balance of the term of the contract’ or for at least eight quarters ‘as
stated in the contract.’” Rec. Doc. 96 at 4. Rain CII makes the conclusion that the arbitrator’s
selected replacement mechanism price formula did not become final for the purposes of
triggering the eight-quarter clause until the Fifth Circuit affirmed the Court’s judgment;
therefore, Rain CII argues that Phillips is violating the terms of the judgment by seeking
arbitration regarding the price formula on or before April 2, 2014.3 Rec. Doc. 90-1 at 6. Rain
CII’s motion requests an order “prohibiting and nullifying Phillips’ attempt to circumvent the
Court’s Judgment by attempting to invoke the price re-opener provision of the 2005 Contract
prematurely and in violation of the eight-quarter requirement contained in the 2005 Contract.”
Rec. Doc. 90 at 2.
Phillips counters that a new dispute, never before addressed or settled by arbitration or
the Court’s judgment, has arisen over whether the eight-quarter provision ties to the date of the
arbitration ruling or the finally appealed judgment. See Rec. Doc. 92 at 8-12; see also Rec. Doc.
73. Phillips argues that this new dispute should be settled by arbitration pursuant to Section 19 of
the agreement, not by the Court on a Rule 70 motion. Rec. Doc. 92 at 11-12. Phillips also argues
that Rain CII has not provided a sufficient legal argument for this Court to conclude that the
eight-quarter period did not start until the Fifth Circuit affirmed the Court’s judgment. Rec. Doc.
92 at 14-15.
II. LAW AND ANALYSIS
3
In its reply to Phillips’ memorandum in opposition, Rain CII argues that the eight-quarter period
would not conclude until June 30, 2014. Rec. Doc. 96 at 9.
4
A. Judicial Review under the Federal Arbitration Act
The Federal Arbitration Act (“FAA”) provides the means for enforcing arbitral awards,
via a judicial decree confirming, vacating, modifying, or correcting an award. See 9 U.S.C. §§ 913; see also Hall St. Assocs., L.L.C. v. Mattel, Inc., 552 U.S. 576, 578 (2008). The Court’s
review of an arbitral award under the FAA is exceedingly deferential. Brabham v. A.G. Edwards
& Sons , Inc., 376 F.3d 377, 380 (5th Cir. 2004). “The federal courts will defer to the arbitrators’
resolution of the dispute whenever possible.” Anderman/Smith Operating Co. V. Tennessee Gas
Pipeline Co., 918 F.2d 1215, 1218 (5th Cir. 1990). Pursuant to 9 U.S.C. § 13, a court’s judgment
“shall have the same force and effect, in all respects, as, and [is] subject to all the provisions of
law relating to, a judgment in an action; and it may be enforced as if it had been rendered in an
action in the court in which it is entered.”
Rule 70(a) of the Federal Rules of Civil Procedure provides:
If a judgment requires a party to convey land, to deliver a deed or other document,
or to perform any other specific act and the party fails to comply within the time
specific, the court may order the act to be done-at the disobedient party’s
expenseby another person appointed by the court. When done, the act has the same effect
as if done by the party.” Fed.R.Civ.P. 70(a).
Rule 70 “is operative only after a judgment is entered.” De Beers Consol. Mines v. United States,
325 U.S. 212, 218, 65 S.Ct. 1130, 1133 (1945). The Rule may be used to enforce judgments
requiring specific acts. Gilbert v. Johnson, 490 F.2d 827, 829 (5th Cir. 1974) (per curiam) (aff’d
in relevant part on remand, 601 F.2d 761). In Gilbert, a Veterans Administration (“VA”) doctor
that had been fired without a statutorily-mandated board hearing successfully sued to be
reinstated pending a board hearing and to receive compensation for costs associated with his
5
termination. Id. at 828 n. 1. After the VA did not pay the damages and was allegedly confining
the doctor’s work to menial tasks unrelated to his previous employment, the doctor
unsuccessfully moved to enforce the judgment under Rule 70. Id. at 829. On appeal, the Gilbert
court ruled that, “on their face,” the VA appeared to be in violation of the lower court’s
judgment and so reversed and remanded the denial of the doctor’s Rule 70 motion. Id. at 830.
B. Enforcing a Judgment Confirming an Arbitration Ruling
Rain CII asks the Court to use Rule 70 to order Phillips not to take the specific act of
seeking arbitration regarding a reinitiated dispute over the price formula. At the core of the issue
before the Court is the disputed meaning and effect of the eight-quarter provision in Section 4(c)
of the agreement between the parties. In its two memoranda supporting its motion to enforce the
judgment, Rain CII cites no legal authority regarding the use of Rule 70 to enforce an arbitration
ruling confirmed by a court judgment under the FAA, much less the use of the Rule in the
context of an accompanying dispute over the meaning of a contract provision not clearly settled
in that arbitration ruling. Indeed, both parties have cited few legal decisions to support their
arguments, making it necessary not only to review the parties’ arguments, but also to provide
independent reasoning in order to satisfactorily rule on Rain CII’s motion.
The sole legal decision cited to by Rain CII regards prison official defendants that failed
to comply with a court judgment ordering the enactment of an environmental plan. See Morales
Feliciano v. Hernandez Colon, 771 F. Supp. 11, 12 (D.P.R. 1991). In Morales, the court had
previously found the prison officials in contempt for not conforming to a portion of the
environmental plan that required the prison officials to contract for services related to
evaluations and corrective action plans by a certain date. Id. The court ruled that it was
reasonable to use Rule 70 to appoint a special master that would contract on behalf of the prison
6
officials, noting the “public reform” context of the case and that the prison officials had made
clear that they did not otherwise intend to contract for the services. Id. at 13.
The Morales court cited a Fifth Circuit case, Gates v. Collier, to support its holding. Id.
(citing Gates v. Collier, 616 F.2d 1268 (5th Cir. 1980)). In Gates, a state was found liable for
unconstitutional practices at one of its prisons and, after extensive litigation, the lower court
ordered the state treasurer to satisfy a money judgment against it for attorney fees and costs.
Gates, 616 F.2d at 1270. The state argued that, by its own law, it could not be ordered to satisfy
the money judgment, but it was only responsible for satisfying the judgment on a voluntary
basis. Id. The Gates court held that Rule 70 could be properly used to order payment, where the
“the defendants have made it abundantly clear that they intend to resist the judgment until the
bitter end.” Id. at 1271-72.
The Court is not persuaded that either Morales or Gates provide the Court with guidance
on the appropriateness of using Rule 70 to order Phillips not to seek arbitration. To start, neither
case regards enforcement of an arbitration ruling and the case before the Court does not fall
within the public reform context present in both Morales and Gates. Unlike Gates, the motion
before the Court does not regard satisfaction of an express money judgment rendered by a court.
Unlike Morales, Phillips has not previously been found in contempt, and unlike both Morales
and Gates, Phillips has not shown a clear intention to resist the Court’s judgment until the bitter
end. It is true that Phillips appealed the Court’s judgment, but it did so in accordance with the
law and satisfied the money judgment promptly after its appeal to the Fifth Circuit was
unsuccessful. Rec. Doc. 83; Rec. Doc. 87. Furthermore, the parties do not apparently dispute that
Phillips complied with the arbitrator’s selected price formula on all invoices processed after the
arbitration ruling, even while Phillips sought to vacate the ruling and later appeal the Court’s
7
judgment. Rec. Doc. 92-1; Rec. Doc. 96. Perhaps most significantly, Gates and Morales regard
violations of what appear to have been clear court orders, whereas in this case there is a question
of whether the arbitration ruling or the Court’s judgment ever ruled on an interpretation of the
eight-quarter provision that would control the disposition of Rain CII’s motion.
To this point, Phillips argues that the meaning of the eight-quarter provision was never
addressed at any point during the first arbitration process or subsequent FAA confirmation
proceedings. Rec. Doc. 92 at 1-2. Phillips cites to a number of Fifth Circuit decisions supporting
the general conclusion that a court should defer to arbitration proceedings where the parties have
agreed to a broad arbitration provision to resolve disputes. See e.g. Naura Phosphate Royalties,
Inc. v. Drago Daic Interests, Inc., 138 F.3d 160, 165 (5th Cir. 1998). In Naura, the Fifth Circuit
made clear that, when reviewing the enforceability of an arbitration ruling, it would presume that
“when parties include . . . a broad arbitration clause [in their contract], they intend the clause to
reach all aspects of the relationship.” Id. (quoting Valentine Sugars, Inc. v. Donau Corp., 981
F.2d 210, 213 n. 2 (5th Cir. 1993)). Furthermore, the Fifth Circuit has previously reversed a
denied motion to stay pending arbitration where the parties had signed a number of interrelated
agreements, but not all of them plainly included a broad arbitration clause. See Neal v. Hardee’s
Food Sys., Inc., 918 F.2d 34, 37-38 (5th Cir. 1990). The Neal court made clear that it would not
deny arbitration “unless it can be said with positive assurance that an arbitration clause is not
susceptible [to] an interpretation which would cover the dispute at issue.” Id. at 37 (internal
quotation marks omitted).
While Naura dealt primarily with a court’s standard for reviewing the enforceability of
arbitration provisions, not their effect in a court’s judgment, and Neal dealt with the force of
arbitration provisions in the context of interrelated agreements, not an interrelated agreement and
8
judgment, the cases and their predecessors signal a general preference in the Fifth Circuit to
defer to arbitration. Here, the parties have an agreement containing a broad arbitration clause
that would clearly cover the dispute over the eight-quarter provision absent a related prior
arbitration ruling. Naura and Neal therefore support Phillips’ argument that the Court should not
rule on a binding interpretation of the eight-quarter provision without it first being submitted to
an arbiter. They do not, however, fully settle the central issue before the Court–whether the prior
arbitration ruling confirmed by the Court effectively incorporated an interpretation of the eightquarter provision that controls the disposition of Rain CII’s motion.
A recent Fifth Circuit decision provides helpful guidance on this remaining issue. See
Tricon Energy Ltd. v. Vinmar Intern., Ltd., No. 12-20100, 2013 WL 1859079 at *5-*8 (5th Cir.
May 3, 2013) (case may be subject to review or rehearing). In Tricon, the Fifth Circuit affirmed
a lower court confirmation of a breach of contract arbitration ruling that awarded damages and
interest to Tricon Energy. Id. at *1. The arbitration ruling clearly selected a rate at which preand post-award interest on any damages would accrue; however, the lower court rejected Tricon
Energy’s argument that any interest after the lower court’s judgment should accrue at the
arbitration ruling rate, instead of accruing at the statutorily-mandated rate for postjudgment
interest. Id. at *1-*2. The Tricon court concluded that the arbitrator had the authority to set a
postjudgment rate other than the statutory rate, but would have had to expressly include any nonstatutory postjudgment rate in the arbitration ruling in order for it to override the statutory rate.
Id. at *7-*8. The Tricon court then reviewed the arbitration ruling in detail to determine if a nonstatutory rate had been clearly selected–finding it had not been. Id. The court concluded that
mere “boilerplate language” regarding the accrual of interest in the arbitration ruling was
insufficient to show that the arbitration panel intended to award a non-statutory rate. Id. at *8.
9
The Tricon court also rejected the argument that a non-statutory postjudgment rate should have
been awarded, because the awarded party had expressly requested a non-statutory rate in front of
the arbitration panel. Id. The court supported this rejection by pointing to language in the ruling
that stated “‘all claims not expressly granted are hereby denied.’” Id.
Tricon addressed a separate matter pertaining to judgments and applied a heightened legal
standard related to postjudgment interest rates; however, the Court is persuaded that the Tricon
court’s process for reviewing an arbitration ruling provides helpful guidance on how to determine
whether or not a controlling interpretation of the eight-quarter provision was included in the
arbitration provision. Like the awarded party in Tricon, Rain CII can point only to the language
“as stated in the contract” to support its contention that the arbitration ruling expressly included
an interpretation of the eight-quarter provision. Rec. Doc. 90-3 at 23; Rec. Doc. 96 at 3. This
language in the ruling can easily be described as “boilerplate.” Furthermore, even accepting “as
stated in the contract” as a clear implication of the force of the eight-quarter provision, Rain CII
provides nothing to suggest its interpretation of the meaning and effect of the eight-quarter
provision should control. Even less convincing than Tricon Energy’s argument that a nonstatutory rate had been selected merely because it had advocated for the rate during arbitration,
Rain CII cannot even support its argument with evidence that it or Phillips ever addressed the
meaning and effect of the eight-quarter provision in front of either the arbitrator or the Court.
Like the arbitration ruling in Tricon, the arbitration ruling in this case makes clear that relief not
expressly granted is denied. Rec. Doc. 90-3 at 27. Because Rain CII cannot show that the
arbitration ruling contained an interpretation of the eight-quarter provision, Naura and Neal
provide sufficient grounds for the Court to defer judgment on the disputed meaning of the
provision and instead allow the dispute to first be submitted to an arbitrator.
10
The Court is not persuaded that either the arbitration ruling or the Court’s judgment
clearly contained an interpretation of the eight-quarter provision that would, for the purpose of
satisfying the Court’s judgment, prohibit Phillips from once again seeking arbitration over the
price formula. Rain CII cites no relevant legal authority to support its argument and a plain
reading of the arbitration ruling does not indicate that it provided an interpretation of the eightquarter provision that controls Phillips’ ability to seek arbitration. Because the agreement clearly
provides that any claim arising out of or relating to the agreement will be resolved by arbitration
and the force of that provision is supported by the Fifth Circuit, it would be inappropriate to issue
a Rule 70 order that would include a “first pass” interpretation of the disputed eight-quarter
provision in Section 4(c) that has not previously been ruled on by an arbitrator. Rec. Doc. 90-3 at
14, 20. The dispute over the meaning of the eight-quarter provision should therefore be settled by
arbitration, which will clarify whether or not Phillips may reinitiate price formula arbitration. The
parties will have the same rights to seek a court judgment confirming, vacating, modifying, or
correcting the arbitration ruling as they had following the first arbitration proceeding. Rec. Doc.
71 at 4.
Accordingly,
IT IS ORDERED that defendant’s motion is DENIED. (Rec. Doc. 90).
New Orleans, Louisiana, this 24th day of June, 2013.
HELEN G. BERRIGAN
UNITED STATES DISTRICT JUDGE
11
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?