84 Lumber Company v. F.H. Paschen, S.N. Nielsen & Associates, LLC et al
Filing
263
ORDER & REASONS granting 220 Motion for Partial Summary Judgment. Signed by Judge Sarah S. Vance on 5/16/2017. (mmm)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
84 LUMBER COMPANY
VERSUS
CIVIL ACTION
NO. 12-1748
F.H. PASCHEN, S.N. NIELSEN &
ASSOCIATES, LLC, ET AL.
SECTION “R” (5)
ORDER AND REASONS
Defendants F.H. Paschen, S.N. Nielsen & Associates, LLC (“Paschen”),
Continental Casualty Company, Safeco Insurance Company of America, and
Fidelity and Deposit Company of Maryland (collectively, “Defendants”)
move for partial summary judgment on plaintiff 84 Lumber Company’s
Louisiana Public Works Act claims and unjust enrichment claim. 1 For the
following reasons, the Court grants defendants’ motion.
I.
BACKGROUND
This case arises out of two school construction projects in New Orleans,
Louisiana, the Mildred Osborne Project and the South Plaquemines Project.2
On July 26, 2010, Paschen entered into an agreement with the Louisiana
1
2
R. Doc. 220.
R. Doc. 1 at 2-3 ¶ 5.
Department of Education to build a new elementary school at the Mildred
Osborne School in New Orleans (Osborne Project). 3
General Contractor for the project.4
Paschen was the
On September 13, 2010, Paschen
entered into a contract with the Plaquemines Parish School Board to build
the South Plaquemines High School in Buras, Louisiana (South Plaquemines
Project).5 As with the Osborne Project, Paschen was the General Contractor
for the South Plaquemines Project.6 Both projects were subject to the
provisions of the Louisiana Public Works Act (LPWA), La. Rev. Stat. §
38:2241, et seq., and therefore each project required payment bonds before
construction could begin.7 Continental, Safeco, and Fidelity (collectively,
“Sureties”) issued the required bonds. 8
Paschen subcontracted a portion of both projects to J & A Construction
Management Resources Company, Inc. (J & A). 9 On November 19, 2010,
J & A entered into a Master Service Agreement with 84 Lumber Company, in
R. Doc. 214-24 at 1.
Id.
5
R. Doc. 214-7 at 2.
6
Id.
7
R. Doc. 1 at 3 ¶ 6.
8
See R. Doc. 214-25 (Bond for Osborne Project); R. Doc. 214-8
(Bond for South Plaquemines Project).
9
R. Doc. 1 at 3 ¶ 7. See also R. Doc. 214-26 (Osborne Project
Subcontract); R. Doc. 214-9 (South Plaquemines Project Subcontract).
2
3
4
which J & A subcontracted a portion of its work on both projects to 84
Lumber. 10
According to 84 Lumber, in April 2011, Paschen and J & A stopped
paying 84 Lumber for its work on the projects. 11 As a result, on November
29, 2011, 84 Lumber filed sworn statements of claims for money owed on
both projects in compliance with the LPWA. Specifically, 84 Lumber claimed
at least $549,778.16 for the Osborne Project and at least $1,666,921.66 for
the South Plaquemines Project. 12 On December 1, 2011, 84 Lumber, through
its counsel, sent letters by certified mail to Paschen’s attorney Charles F.
Seemann, Jr., detailing the amounts owed, as well as a copy of the sworn
statements. 13 84 Lumber also mailed notice of the sworn statements to the
Sureties. 14
In an attempt to “compromise partially their differences,” Paschen and
84 Lumber entered into two agreements in May 2012, covering both
projects.15
Under the agreements, Paschen agreed to pay 84 Lumber
$1,297,603, and 84 Lumber agreed to indemnify, defend, and hold Paschen
R. Doc. 1 at 3 ¶ 8. See also R. Doc. 214-10 at 1, 6, 12.
R. Doc. 1 at 3-4 ¶ 9. See also R. Doc. 214-11 at 1.
12
R. Doc. 217-27 at 4; R. Doc. 214-13 at 4.
13
R. Doc. 213-13 at 1, 6; R. Doc. 213-29 at 1.
14
R. Doc. 214-14; R. Doc. 214-30.
15
R. Doc. 214-31 (Osborne Project); R. Doc. 214-15 (South
Plaquemines Project).
3
10
11
harmless from any claims, liens, or other expenses that arose from or in
connection with 84 Lumber’s work on the projects. 16 On or about May 17,
2012, 84 Lumber cancelled its November 2011 sworn statements for both
projects and removed them from the mortgage records of Orleans Parish and
Plaquemines Parish, respectively. 17
Less than one month after cancelling both statements, on June 8, 2012,
84 Lumber filed two new sworn statements of claims, one for each project.
84 Lumber claimed $808,520.39 for the Osborne Project, and
$1,042,080.09 for the South Plaquemines Project.18 84 Lumber reflected in
two June 2012 letters mailed to the Plaquemines Parish School Board, and
to the Louisiana Department of Education and the Sureties, respectively, that
84 Lumber had emailed Paschen’s attorney Seemann copies of the sworn
statements. 19
On July 5, 2012, 84 Lumber sued Paschen and the Sureties, alleging
that 84 Lumber was not paid in full for work performed under its Master
Service Agreement with J & A. 20 84 Lumber sued under the LPWA, seeking
R. Doc. 214-31 at 2; R. Doc. 214-15 at 2.
R. Doc. 214-20; R. Doc. 210 at 8.
18
R. Doc. 214-32 at 4 (Osborne Project); R. Doc. 214-21 at 7 (South
Plaquemines Project).
19
R. Doc. 214-22 at 1; R. Doc. R. Doc. 213-32 at 1.
20
R. Doc. 1.
4
16
17
payment on its June 2012 Sworn Statements of Claims from both Paschen
and the Sureties, and brought a claim of unjust enrichment. 21 On February
5, 2013, 84 Lumber amended its complaint to add a breach of contract claim,
as well as a claim for payment for materials and additional work performed
outside of the Master Service Agreement. 22 Paschen answered 84 Lumber’s
complaint and added J & A as a third-party defendant.23
The case was stayed for nearly three years while the parties were to
pursue their claims through arbitration. 24 On January 13, 2016, the case was
reassigned from Judge Helen Berrigan to this Court for all further
proceedings.25 On May 5, 2016, the Court granted 84 Lumber’s motion to
lift the stay and to dismiss J & A’s claims against 84 Lumber for failure to
prosecute. 26
21
22
23
24
1-6.
Id. at 4-6 ¶¶ 13-14, 16, 18.
R. Doc. 28 at 4, 6 ¶¶ 10, 20.
R. Doc. 25.
For a history of the failed arbitration process, see R. Doc. 151 at
R. Doc. 144.
R. Doc. 151. J & A’s claims were also dismissed against Maggie’s
Management, LLC.
5
25
26
With the case reopened, defendants now move for partial summary
judgment on 84 Lumber’s LPWA claims and its unjust enrichment claim. 84
Lumber filed a response, 27 and defendants replied. 28
II.
LEGAL STANDARD
Summary judgment is warranted when “the movant shows that there
is no genuine dispute as to any material fact and the movant is entitled to
judgment as a matter of law.” Fed. R. Civ. P. 56(a); see also Celotex Corp. v.
Catrett, 477 U.S. 317, 322-23 (1986); Little v. Liquid Air Corp., 37 F.3d 1069,
1075 (5th Cir. 1994). When assessing whether a dispute as to any material
fact exists, the Court considers “all of the evidence in the record but refrain[s]
from making credibility determinations or weighing the evidence.” Delta &
Pine Land Co. v. Nationwide Agribusiness Ins. Co., 530 F.3d 395, 398-99
(5th Cir. 2008).
All reasonable inferences are drawn in favor of the
nonmoving party, but “unsupported allegations or affidavits setting forth
‘ultimate or conclusory facts and conclusions of law’ are insufficient to either
support or defeat a motion for summary judgment.” Galindo v. Precision
Am. Corp., 754 F.2d 1212, 1216 (5th Cir. 1985); see also Little, 37 F.3d at
27
28
R. Doc. 222.
R. Doc. 228.
6
1075. “No genuine dispute of fact exists if the record taken as a whole could
not lead a rational trier of fact to find for the non-moving party.” EEOC v.
Simbaki, Ltd., 767 F.3d 475, 481 (5th Cir. 2014).
If the dispositive issue is one on which the moving party will bear the
burden of proof at trial, the moving party “must come forward with evidence
which would entitle it to a directed verdict if the evidence went
uncontroverted at trial.” Int’l Shortstop, Inc. v. Rally’s, Inc., 939 F.2d 1257,
1264-65 (5th Cir. 1991). The nonmoving party can then defeat the motion by
either countering with evidence sufficient to demonstrate the existence of a
genuine dispute of material fact, or “showing that the moving party’s
evidence is so sheer that it may not persuade the reasonable fact-finder to
return a verdict in favor of the moving party.” Id. at 1265.
If the dispositive issue is one on which the nonmoving party will bear
the burden of proof at trial, the moving party may satisfy its burden by
merely pointing out that the evidence in the record is insufficient with
respect to an essential element of the nonmoving party’s claim. See Celotex,
477 U.S. at 325. The burden then shifts to the nonmoving party, who must,
by submitting or referring to evidence, set out specific facts showing that a
genuine issue exists. See id. at 324. The nonmovant may not rest upon the
pleadings, but must identify specific facts that establish a genuine issue for
7
trial. See, e.g., id.; Little, 37 F.3d at 1075 (“Rule 56 mandates the entry of
summary judgment, after adequate time for discovery and upon motion,
against a party who fails to make a showing sufficient to establish the
existence of an element essential to that party’s case, and on which that party
will bear the burden of proof at trial.” (quoting Celotex, 477 U.S. at 322)).
III. DISCUSSION
84 Lumber asserts two claims under the LPWA: 1) recognition and
enforcement of its sworn statement of claims for amounts owed to 84
Lumber; and 2) a payment claim seeking interest, costs, and attorneys’
fees. 29 Defendants argue that the two LPWA claims must be dismissed
because 84 Lumber failed to comply with the statute’s notice requirements.30
As to the unjust enrichment claim, defendants argue that this claim must be
dismissed because 84 Lumber has other legal remedies available. 31
R. Doc. 1 at 4-5 ¶¶ 12-14, 15-16.
R. Doc. 220-1 at 9-14. Defendants also argue, independently of
its notice argument, that 84 Lumber released and waived both of its LPWA
claims against them in the May, 2012 agreements with Paschen. Id. at 15.
Because the Court resolves this motion on the notice argument, it does not
reach defendants’ waiver argument.
31
Id. at 17.
8
29
30
A.
Waiver of Defenses
84 Lumber contends that defendants’ notice and waiver arguments are
affirmative defenses and that defendants failed to plead or preserve them
properly. 32 Thus, according to 84 Lumber, these defenses are not properly
before the Court. The Court rejects this argument. Although defendants’
2013 answer does not specifically mention these defenses, the February 10,
2017 pretrial order, signed by the parties, includes them both. 33 It “‘is a wellsettled rule that a joint pretrial order signed by both parties supersedes all
pleadings and governs the issues . . . to be presented at trial.’” Vanhoy v.
United States, 514 F.3d 447, 450 n.10 (5th Cir. 2008) (quoting McGehee v.
Certainteed Corp., 101 F.3d 1078, 1080 (5th Cir. 1996)). Additionally, after
the trial date was continued, the Court’s March 2, 2017 Scheduling Order
allowed the parties to amend their pleadings.34 Paschen and the Sureties
both filed amended answers that pleaded the notice and waiver defenses. 35
Moreover, there is a good faith exception to waiver of affirmative
defenses when the defense is raised after the pleadings but there is no undue
R. Doc. 222 at 4.
See R. Doc. 210 at 22 (“84 Lumber did not provide proper notice
to Paschen with regard to its LPWA claims.”); Id. at 23 (discussing May 2012
agreements and arguing that the “agreements are binding and enforceable,
and defeat 84 Lumber’s present claims.”).
34
R. Doc. 216 at 2.
35
See R. Doc. 223 at 6; R. Doc. 224 at 6.
9
32
33
prejudice. Kariuki v. Tarango, 709 F.3d 495, 508 (5th Cir. 2013) (“An
affirmative defense is not waived if the defendant ‘raised the issue at a
pragmatically sufficient time, and [the plaintiff] was not prejudiced in its
ability to respond.’”) (quoting Pasco ex rel. Pasco v. Knoblauch, 556 F.3d
572, 577 (5th Cir. 2009) (citation omitted)). 84 Lumber has not even
attempted to show prejudice. Further, it has had ample opportunity to
respond to these defenses, since it signed the pretrial order which included
them, and had the benefit of a continuance to address them. As defendants’
did not waive their affirmative defenses, the Court will proceed to address
them.
B.
Notice Under the LPWA
Under the Louisiana Public Works Act, contracts for projects like the
Osborne Project and the South Plaquemines Project require bonds “for the
payment by the contractor or subcontractor to claimants as defined in R.S.
38:2242.” See La. Rev. Stat. § 38:2241(A)(2). Section 2242(A)(1) defines a
“claimant” as:
any person to whom money is due pursuant to a contract with
the owner or a contractor or subcontractor for doing work,
performing labor, or furnishing materials or supplies for the
construction, alteration, or repair of any public works, or for
transporting and delivering such materials or supplies to the site
of the job by a for-hire carrier, or for furnishing oil, gas,
electricity, or other materials or supplies for use in machines
10
used in the construction, alteration, or repair of any public
works, . . .
Id. § 38:2242(A)(1).
The LPWA provides two avenues of relief for
“claimants” who are owed money for work on public work projects. They can
file an action against the general contractor and the sureties on the project’s
statutory bond, or they can seek “the unexpended fund[s] in the possession
of the public entity with whom the original contract was entered into” by
filing an action against the public authority. Pierce Foundations, Inc. v.
Jaroy Const., Inc., 190 So. 3d 298, 301 (La. 2016) (quoting Wilkin v. Dev
Con Builders, Inc., 561 So. 2d 66, 70 (La. 1990)). Here, 84 Lumber’s LPWA
claims are actions on the projects’ statutory bonds, and 84 Lumber does not
seek money from the contracting public authorities.
Section 2247 governs the notice requirements for actions seeking
payment from a project’s statutory bonds, and states:
Nothing in this Part shall be construed to deprive any claimant,
as defined in this Part and who has complied with the notice and
recordation requirements of R.S. 38:2242(B), of his right of
action on the bond furnished pursuant to this Part, . . .; except
that before any claimant having a direct contractual relationship
with a subcontractor but no contractual relationship with the
contractor shall have a right of action against the contractor or
the surety on the bond furnished by the contractor, he shall in
addition to the notice and recordation required in R.S.
38:2242(B) give written notice to said contractor within fortyfive days from the recordation of the notice of acceptance by the
owner of the work or notice by the owner of default, stating with
substantial accuracy the amount claimed and the name of the
11
party to whom the material was furnished or supplied or for
whom the labor or service was done or performed. Such notice
shall be served by mailing the same by registered or certified
mail, postage prepaid, in an envelope addressed to the contractor
at any place he maintains an office in the state of Louisiana.
La. Rev. Stat. § 38:2247.
If the claimant and the general contractor are in contractual privity,
then the claimant need not file a sworn statement in order to have a right of
action against the general contractor and its surety. Pierce, 190 So. 3d at
304-05. If, as here, the claimant is not in contractual privity with the general
contractor, the claimant will not have a right of action under the LPWA
against the contractor or its sureties unless it satisfies the requirements of
section 2247. In other words, the claimant must provide written notice to
the contractor, stating with substantial accuracy the amount claimed and the
party to whom the labor or material was supplied, by registered or certified
mail, addressed to the contractor at its office in Louisiana.
Compliance with section 2247 is a prerequisite to a right of action, and
failure to comply warrants dismissal. See Interstate Sch. Supply Co. v.
Guitreau’s Const. & Consulting Co., 542 So. 2d 138, 139 n.1 (La. App. 1 Cir.
1989); Electric Supply Co., Inc. v. Great Am. Ins. Co., 973 So. 2d 827, 830
(La. App. 2 Cir. 2007) (“[T]he notice referenced in [section] 2247 is to be
given to the contractor to preserve the right of action against the contractor
12
or the surety.”); See also, e.g., J. Reed Constructors, Inc. v. Roofing Supply
Grp., L.L.C., 135 So. 3d 752, 754-56 (La. App. 1 Cir. 2013). Whether a
claimant has satisfied the notice requirement is a legal question of statutory
interpretation. J. Reed at 756. (citing Livingston Parish Council on Aging v.
Graves, 105 So. 3d 683, 685 (La. 2012)). The Louisiana Supreme Court has
stated that “as a general rule, lien statutes [like the LPWA] are stricti juris
and should thus be strictly construed.” Guichard Drilling Co. v. Alpine
Energy Servs., Inc., 657 So. 2d 1307, 1313 (La. 1995) (italics in original); see
also Wilkin, 561 So. 2d at 71 (noting that the LPWA should be “strictly
construed such that the privileges granted are not extended beyond the
statute[]”). As such, the Court cannot ignore the language of section 2247.
See Interstate Sch. Supply Co., 542 So. 2d at 139 (“[T]he specific language of
[section] 2247 requires compliance with the notice requirements in order to
proceed ‘on the bond.’ The clear language cannot be ignored.”).
Defendants argue that 84 Lumber failed to comply with the LPWA
notice requirements for its June 2012 claims, and point to the lack of
evidence of any communication from 84 Lumber, mailed to Paschen at its
office in Louisiana,36 regarding the June 2012 claims. Further, defendants
At all times relevant to this lawsuit, Paschen maintained an office
in New Orleans, Louisiana at 541 Julia Street, Suite 302. R. Doc. 214-9 at 1;
R. Doc. 214-26 at 1.
13
36
argue that any communications regarding the December 2011 sworn
statements cannot satisfy the notice requirement because 84 Lumber
cancelled those statements in May of 2012.
84 Lumber does not rely on its December 1, 2011 letter to Paschen in
its opposition. Instead, 84 Lumber argues that Paschen had actual notice of
its claims by virtue of 84 Lumber’s filing its complaint, as well as emails sent
to Paschen’s then-attorney Charles Seemann, which 84 Lumber asserts
attached copies of its sworn statements of claims. 37
84 Lumber
acknowledges that its emailed communications may not fully satisfy the
language of section 2247, but argues that all that is required under section
2247 is actual notice. 38
As to 84 Lumber’s assertion that its complaint serves as notice under
section 2247, this argument is foreclosed by the plain language of section
2247. The section states “before any claimant . . . shall have a right of action
. . . he shall . . . give written notice.” La. Rev. Stat. § 38:2247. A complaint
asserting a right of action cannot serve as statutorily required notice if the
notice is required before one has the right of action.
37
38
R. Doc. 222 at 5-6.
Id. at 6.
14
In addition to the complaint, 84 Lumber asserts that two June 2012
emails sent to Charles Seemann satisfy the notice requirements of section
2247. In doing so, 84 Lumber relies on two letters mailed on June 19, and
June 20, 2012, respectively. 39 The June 19 letter was mailed from 84
Lumber’s attorney Beatriz Richmond to the Louisiana Department of
Education and the Sureties, and referred to the Osborne Project, while the
June 20 letter, also mailed from Richmond, referred to the South
Plaquemines Project and was sent to the Plaquemines Parish School Board. 40
The bottom of both letters state, “cc: Charles F. Seemann, Jr. (via e-mail only
w/encl.)”.41 84 Lumber also submits the affidavit of Jo A. Troiani, a legal
secretary with Baker, Donelson, the law firm representing 84 Lumber.42
Troiani attests that she personally emailed copies of the above June 2012
letters to Seemann, each with the sworn statement of claim attached. 43
84 Lumber did not submit copies of the emails to Seemann, 44 and there
is no evidence in the record to indicate that Seemann received the email, or
R. Doc. 214-32; R. Doc. 214-23.
R. Doc. 214-32 at 1; R. Doc. 214-23 at 1.
41
Id.
42
R. Doc. 222-3.
43
R. Doc. 222-3 at 2 ¶¶ 5, 7.
44
Given that 84 Lumber should be in possession of copies of these
emails, 84 Lumber’s failure to submit them is curious.
15
39
40
notified Paschen of its contents.45 The defendants do not concede that
Seemann received the emails, but argue that even if he did, the emails
regarding the June 2012 claims for the Osborne and South Plaquemines
Project do not satisfy section 2247. It is undisputed that any email sent to
Seemann is not a “mailing . . . by registered or certified mail, postage prepaid,
. . . addressed to the contractor at any place he maintains an office in the state
of Louisiana.” La. Rev. Stat. § 38:2247.
84 Lumber cites no case accepting an email as sufficient notice under
section 2247, or any case finding communications sent only to a contractor’s
counsel, and not the contractor itself at its Louisiana office, as sufficient
under section 2247. Acknowledging this, 84 Lumber argues that regardless
of a communication’s deficiencies under the plain language of section 2247,
a claimant complies with section 2247 as long as the general contractor has
“actual notice.” 46 This argument, which is counter to the clear text of section
2247, has not been addressed by The Louisiana Supreme Court. Further, no
Louisiana appellate case has held that actual notice is all that section 2247
requires, regardless of the extent of noncompliance with the text of the
section.
Seemann withdrew as defendants’ attorney in August, 2015,
nearly a year before the case was reopened. R. Doc. 136.
46
R. Doc. 222 at 6.
16
45
But Louisiana appellate cases have addressed similar arguments by
plaintiffs seeking to ignore the clear text of notice provisions in the Public
Works Acts 47 or to interpret the statute in ways that would find loose
compliance as sufficient. For the most part, these cases have rejected these
arguments and found that the clear text cannot be ignored. For example, in
Interstate School Supply, it was undisputed that the claimant complied with
the notice requirements of sections 2242 and 2247 forty-six days after the
public authority’s acceptance of the project. 542 So. 2d at 139. The court
refused to loosely interpret the requirement of compliance within forty-five
days of the authority’s acceptance, and found that the claimant forfeited its
right to proceed on the bond, despite being only one day late. Id.
Louisiana appellate courts have held that failure to provide notice
before filing a sworn statement of claim does not comply with a similar notice
provision in section 2242(F), and this noncompliance defeats a claimant’s
right of action.
For example, in Teche Electric Supply L.L.C. v. M.D.
Descant, Inc., 2 So. 3d 516 (La. App. 3 Cir. 2008), the Louisiana Third Circuit
Court of Appeal found that a claimant’s failure to furnish notice of
nonpayment before filing its lien defeated the claimant’s claim, even though
Both the LPWA and the Public Works Act apply to contracts with
the Louisiana Department of Transportation and Development.
17
47
defendants unquestionably had actual notice two weeks after the lien was
filed. Id. at 522; see also Electric Supply Co., 973 So. 2d at 828-31 (finding
that “clear” language of section 2242(F) requires notice before filing lien).
In a similar vein are several cases dealing with public works contracts
with the Louisiana Department of Transportation and Development, which
are governed by a statute with essentially identical notice requirements.48
For example, in both United Rentals Highway Technologies, Inc. v. St. Paul
Surety, 852 So. 2d 1200 (La. App. 2 Cir. 2003), and Martin Marietta
Materials of Louisiana, Inc. v. U.S. Fidelity and Guarantee Co., 940 So. 2d
152 (La. App. 2 Cir. 2006), the plaintiffs failed to file their sworn statements
in accordance with the statutory provisions. In both cases, the Louisiana
Second Circuit Court of Appeal affirmed the dismissal of their claims, despite
Compare La. Rev. Stat. § 38:2247 (“[H]e shall in addition to the
notice and recordation required in R.S. 38:2242(B) give written notice to
said contractor within forty-five days . . . , stating with substantial accuracy
the amount claimed and the name of the party to whom the material was
furnished or supplied . . . . Such notice shall be served by mailing the same
by registered or certified mail, postage prepaid, in an envelope addressed to
the contractor at any place he maintains an office in the state of Louisiana.”),
with La. Rev. Stat. § 48:256.12 (“[H]e shall in addition to the notice and
recordation required in R.S. 48:256.5(B) give written notice to said
contractor and surety within forty-five days . . . , stating with substantial
accuracy the amount claimed and the name of the party to whom the material
was furnished or supplied . . . . Such notice shall be served by mailing the
same by registered or certified mail, postage prepaid, in envelopes addressed
separately to the contractor and surety at any place each maintains an office
in the state of Louisiana.”
18
48
evidence in both cases that the defendants had actual notice. See Martin
Marietta, 940 So. 2d at 157 (“It is of no moment that in the present case
[defendant] acknowledged receiving a copy of the lien . . . or that [defendant]
admitted in his deposition to receiving a copy of the lien.”); see also id. (“In
United Rentals, both [defendants] had notice, prior to [plaintiff] filing its
statement of claim, that Neosho had failed to pay an invoice for goods and
services provided on the project. . . . Nevertheless, despite this notice, this
court still held that [plaintiff] lost its right of action because it had not
complied with [the notice provisions].”).
84 Lumber cites three older Louisiana appellate court cases in support
of its actual notice argument.
84 Lumber’s reliance on these cases is
misplaced, as none holds that any actual notice alone satisfies section 2247.
In Daigle v. Donald M. Clement Contractor, Inc., 533 So. 2d 1064 (La. App.
4 Cir. 1988), cited by 84 Lumber, the court analyzed the pre-1985Amendment version of section 2247, which allowed claimants to provide
notice by either giving written notice or simply by filing a sworn statement
as provided in section 2242. See 533 So. 2d at 1066 n.1. Further, it was
undisputed in Daigle that the claimant not only complied with section 2247
by mailing a certified letter, but also personally delivered a written invoice to
defendant.
Id. at 1066.
Most importantly, Daigle does not hold that
19
compliance with section 2247 is met whenever there is actual notice, and
does not even mention “actual notice.”
84 Lumber also cites Bob McGaughey Lumber Sales, Inc. v. Lemoine
Co., 590 So. 2d 664 (La. App. 3 Cir. 1991), and Gilchrist Construction Co. v.
Terral Riverservice, Inc., 819 So. 2d 362 (La. App. 3 Cir. 2002).
In
McGaughey, the only issue for the court to resolve was whether notice that
complied with section 2247 in all aspects except that it was mailed through
regular mail, rather than certified or registered mail, defeats one’s claim. The
court held that notice sent through regular mail complies with section 2247
when there is undisputed evidence that the defendant received the mailing.
McGaughey, 590 So. 2d at 667. Therefore, all that McGaughey stands for is
that sending notice through regular mail that otherwise complies with
section 2247 will not defeat one’s claims. See also Gilchrist Const. Co., 819
So. 2d 362, 366-67 (relying on McGaughey to find that notice that otherwise
complies with the statutory notice requirements delivered through regular
mail as opposed to certified or registered mail will not defeat one’s claims
under the Louisiana Department of Transportation and Development Public
Works Act). But neither McGaughey nor Gilchrist says that notice by email
20
to a contractor’s counsel’s email account, or anything about notice that is not
sent to the contractor at its Louisiana office would satisfy the LPWA. 49
The cases 84 Lumber cites are distinguishable from this matter for
another reason as well. In all of them, there was undisputed evidence that
the defendant-contractor had received the notice containing the statutorilyrequired information sent from the plaintiffs. See Daigle, 533 So. 2d at 1066;
McGaughey, 590 So. 2d at 665; Gilchrist, 819 So. 2d at 366-67. Here,
Troiani’s affidavit establishes that she sent the email and its attachment, but
there is no evidence indicating that Seemann received it, or that he brought
it to Paschen.
The Court therefore finds that failure to satisfy the requirements of
section 2247 is not excused by emailing counsel for the contractor. Section
2247 plainly states that claimants shall give written notice, and said notice
shall be mailed to the contractor at its office in Louisiana. Because it is
undisputed that 84 Lumber did not send written notice to Paschen itself, at
McGaughey also states that Daigle “observed that what is
required is actual notice.” 590 So. 2d at 666. This is incorrect, as discussed
above Daigle does not mention actual notice at all and does not hold that
section 2247 solely requires actual notice.
21
49
its office in Louisiana—clear requirements of section 2247—the Court finds
that 84 Lumber has not satisfied section 2247. 50
The Court’s finding that the emails to Seemann are insufficient is
supported by the purpose of the delivery requirements contained in section
2247, which is to “assure actual receipt of written notice of the claim and to
facilitate proof of the claim.” Martin Marietta, 940 So. 2d at 158; see also
McGaughey, 590 So. 2d at 666; cf. Powers Regulator Co. v. Murphy’s
Plumbing Serv., Inc., 311 So. 2d 503, 505 (La. App. 4 Cir. 1975) (claimant
failed to comply with section 2247, despite sending certified mail, because
claimant had actual knowledge that notice was never received).
As
mentioned above, there is no evidence in the record that Seemann or
Paschen received the June 2012 emails. Notably, 84 Lumber’s previous
communications with Seemann were not sent via email, but sent by certified
In addition, the communications that 84 Lumber relies on state
that 84 Lumber is owed $1,850,600.48, but 84 Lumber’s complaint seeks
that amount plus “the full amount of all extra work performed by 84
Lumber,” all apparently under the payment bond. R. Doc. 1 at 6. 84
Lumber’s amended complaint seeks more than $3,200,000 in extra work, so
84 Lumber claims it is owed over $5,000,000. R. Doc. 28 at 4 ¶ 10. 84
Lumber was required to state with substantial accuracy the amount it is
claiming, but a claim for $1,850,600.48 is not substantially accurate if the
claimant actually seeks additional unquantified amounts, or over
$5,000,000.
22
50
mail, and the record contains Seemann’s acknowledged receipts of those
letters. 51
Additionally, this Court, applying Louisiana law sitting in diversity,
must be cautious about adopting “substantive innovation” in state law. See,
e.g., Rhynes v. Branick Mfg. Corp., 629 F.2d 409, 410 (5th Cir. 1980);
Cimino v. Raymark Industries, Inc., 151 F.3d 297, 313-14 (5th Cir. 1998)
(collecting cases); see also Combs v. Int’l Ins. Co., 354 F.3d 568, 577-78 (6th
Cir. 2004) (collecting federal cases that explain that federal courts “must
proceed with caution when making pronouncements about state law”)
(citations omitted). It is not the role of the Court to rewrite or reinterpret
section 2247, that job belongs to the Louisiana Legislature and Louisiana
courts.
Thus, 84 Lumber has failed to comply with the requirements of section
2247.
As compliance with the notice requirements of the LPWA is a
prerequisite to claims on the payment bonds, 84 Lumber’s LPWA claims fail,
and defendants are entitled summary judgment on these claims as a matter
of law. 52
See, e.g., R. Doc. 214-13 at 1, 6; R. Doc. 214-14 at 2, 4.
As mentioned above, because insufficient notice is fatal to 84
Lumber’s LPWA claims, the Court need not address defendants’ argument
that 84 Lumber waived its claims in the May 2012 Defense and Indemnity
Agreements.
23
51
52
C.
Unjust Enrichment
That 84 Lumber did not comply with section 2247 does not affect its
unjust enrichment claim. But the unjust enrichment claim fails for two
different reasons. First, the LPWA provides exclusive remedies to aggrieved
parties in public works projects. See State Through Div. of Admin. v.
McInnis Bros. Const., 701 So. 2d 937, 944 (La. 1997).
Second, under
Louisiana law, unjust enrichment is a quasi-contractual remedy, and one
cannot assert a claim for unjust enrichment if other remedies are available.
See La. Civ. Code art. 2298 (stating that unjust enrichment “shall not be
available if the law provides another remedy”). Therefore, 84 Lumber cannot
bring a claim for unjust enrichment. See, e.g., Bd. of Sup’rs of Louisiana
State Univ. v. Louisiana Agr. Fin. Auth., 984 So. 2d 72, 81 (La. App. 1 Cir.
2008) (noting that availability of LPWA remedies precludes unjust
enrichment claims, and that a claimant is not entitled to assert a claim of
unjust enrichment if the claimant fails to comply with the LPWA).
Defendants are entitled summary judgment as a matter of law on 84
Lumber’s unjust enrichment claim.53
84 Lumber concedes that it cannot bring an unjust enrichment
claim. R. Doc. 222 at 12.
24
53
IV.
CONCLUSION
For the foregoing reasons, the Court GRANTS defendant’s motion for
partial summary judgment.
16th
New Orleans, Louisiana, this _____ day of May, 2017.
_____________________
SARAH S. VANCE
UNITED STATES DISTRICT JUDGE
25
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?