Cypert v. Broussard Brothers, Inc. et al
Filing
95
ORDER & REASONS that defendant Broussard Brothers, Inc.'s 50 Motion for Summary Judgment is DENIED. Signed by Judge Eldon E. Fallon on 9/26/14. (dno)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
CRAIG H. CYPERT
*
*
*
*
*
VERSUS
BROUSSARD BROTHERS, INC., ET AL.
CIVIL ACTION
No. 13-5049
SECTION “L” (4)
ORDER & REASONS
Before the Court is a Motion for Summary Judgment filed by Defendant Broussard
Brothers, Inc. ("Broussard Brothers”) for its claim against defendant-in-cross-claim, Commercial
Coating Services International, LLC (“CCSI”). (Rec. Doc. 50). The Court has reviewed the
briefs and applicable law and now issues this Order & Reasons.
I.
BACKGROUND
This case arises out of injuries that Plaintiff Craig Cypert allegedly sustained while
working as a pipeline coating technician aboard a vessel, the BB-70. (Rec. Doc. 1 at 2-3).
Cypert claims that he was injured when he stepped on uneven grating in the "jeeping" area on the
barge, causing him to twist his body and hurt his back and legs. (Rec. Doc. 1 at 2-3). Broussard
Brothers, the owner and operator of the BB-70, was selected as a prime contractor for the Kinder
Morgan pipeline project, which involved laying pipeline underneath or along the bottom of Lake
Pontchartrain. Broussard Brothers subcontracted with Defendant CCSI for pipe blasting and
coating services on the portion of the pipe running in Lake Pontchartrain. CCSI employed
Cypert as a pipeline coating technician to work on the pipeline project on the BB-70 in Lake
Pontchartrain. (Rec. Doc. 56 at 2).
Cypert filed suit against Broussard Brothers and CCSI on February 25, 2013. (Rec. Doc.
1). Broussard Brothers filed an Answer to Cypert’s Original and First Amended Complaint and
1
asserted a cross-claim against CCSI, asserting that there was a contract in effect between
Broussard Brothers and CCSI to hold harmless and indemnify Broussard Brothers against claims
like those asserted by Cypert. (Rec. Doc. 37).
II.
SUMMARY OF MOTION AND OPPOSITION
A. Broussard Brother’s Motion for Summary Judgment (Rec. Doc. 50)
Broussard Brothers filed the present Motion for Summary Judgment on April 11, 2014,
but the Court continued the motion after the parties agreed that the Court needed to resolve the
Plaintiff’s seaman status prior to the determination of this motion. (Rec. Doc. 52). On August
25, 2014, the Court denied CCSI’s Motion for Summary Judgment and determined that Cypert
was a seaman. (Rec. Doc. 77).
Broussard Brothers argues that summary judgment is appropriate because the contract
between CCSI and Broussard Brothers requires CCSI to indemnify and defend Broussard
Brothers for Cypert’s claim against Broussard Brothers. Broussard Brothers avers that on May
29, 2012 Donna Ellis with CCSI provided a written Proposal (“Proposal”) to Broussard Brothers
for pipe blasting and coating work in connection with the Kinder Morgan pipeline project. (Rec.
Doc. 50-1 at 5). This Proposal included an attachment entitled “CCSI Commercial Coating
Services International, LLC Standard Terms and Conditions of Sale” (“T&C”). (Rec. Doc. 50-1
at 5). The T&C included an indemnity agreement, which provides:
CCSI agrees to release, defend, indemnify, and hold harmless Customer from and against
any and all claim, damages, losses and expenses directly or indirectly arising out of or
related to bodily injury or death of CCSI’s employees…arising out of, or related to, the
performance or subject matter of this Contract….
(Rec. Doc. 50-1 at 6). In July 2012, Kenneth Choate, Vice President of Broussard Brothers, and
Ron Raphoon, CCSI’s General Manager, exchanged email correspondence, and on July 21,
2
2012, Broussard Brothers claims that Choate accepted the Proposal and told Raphoon and Bryan
Karasek of CCSI that “[a]s a subcontractor, [CCSI] will need to execute a ‘project specific’
service agreement. This agreement addresses the liabilities and obligations taken on by our
company, [Broussard Brothers] and its subcontractors.” (Rec. Doc. 50-1 at 7).
Broussard Brothers claims that following this correspondence, Choate attached an
Agreement (“Broussard Contract”) that required CCSI to indemnify and defend Broussard
Brothers in connection with any claims asserted by CCSI employees related to work on the
project.1 Choate and Raphoon exchanged several amended versions of the Broussard Contract,
and Broussard Brothers contends that the parties agreed on the final edits in August 2012 and
that Choate promised Raphoon a clean copy of the Broussard Contract for his execution. (Rec.
Doc. 50-1 at 8). Broussard Brothers notes that the parties signed the final version of the
Agreement in November 2012. (Rec. Doc. 50-1 at 8). CCSI began work for Broussard Brothers
in August 2012 on the Kinder Morgan pipeline, and Cypert claims he was injured on September
23, 2012. (Rec. Doc. 50-1 at 8-9).
Broussard Brothers argues that Choate accepted CCSI’s Proposal and its T&C when
Broussard Brothers chose CCSI as a subcontractor in July 2012. (Rec. Doc. 50-1 at 13).
Broussard Brothers argues that the Fifth Circuit has “held that notice and acceptance by an
authorized representative of a party triggers the indemnity terms of a proposal, work order, or
quote.” (Rec. Doc. 50-1) (citing Houston Exploration Co. v. Halliburton Energy Servs., Inc.,
359 F.3d 777, 781 (5th Cir. 2004); Employer Reinsurance Corp. v. Tetra Pak, 2002 WL
1
Although Broussard Brothers claims the Broussard Contract contained indemnification
terms that would indemnify Broussard Brothers against CCSI employees’ claims alleging
Broussard Brothers’ negligence, CCSI’s Opposition and Broussard Brothers’ Reply
acknowledges that it does not.
3
32711300 (M.D. La. 2002)).
Moreover, Broussard Brothers asserts that “[t]he intent to
indemnify Broussard Brothers on this job was consistent throughout the work, even though the
formal agreement was not signed until after Cypert’s Accident.”
(Rec. Doc. 50-1 at 15).
Broussard Brothers points to the fact that Choate and Raphoon exchanged correspondence and
versions of the agreement in July 2012, and CCSI’s intent to indemnify endured throughout these
exchanges, culminating in the final agreement that the parties executed on November 28, 2012.
(Rec. Doc. 50-1 at 15).
B. CCSI’s Opposition (Rec. Doc. 78)
CCSI filed an Opposition to the Motion for Summary Judgment, arguing that there is
dispute over material facts. CCSI does not dispute that CCSI sent a proposal to Broussard
Brothers that included an indemnity and defense provision on May 29, 2012. (Rec. Doc. 78 at
3). CCSI argues that when Choate sent Karasek of CCSI an email stating that Broussard
Brothers had chosen CCSI as its subcontractor in the Kinder Morgan project, Choate never
declared that he accepted the terms and conditions of the CCSI proposal. (Rec. Doc. 78 at 3).
Rather, CCSI contends that when Choate stated CCSI would need to execute a “project service”
service agreement, and this constituted a counter-offer as “Broussard [Brothers] required that
CCSI sign the Broussard Contract if CCSI wanted the job.” (Rec. Doc. 78 at 13-14). CCSI
argues that this would signify a counter-offer under both Maritime and Louisiana law. (Rec.
Doc. 78 at 14). CCSI contends that Paragraph 23 of the Broussard Contract further supports this
contention, as it states: “This Agreement supersedes any and all other agreements, either oral or
in writing, between the Parties with respect to the subject matter thereof and contains all of the
covenants and agreements between the Parties with respect to the subject matter….” (Rec. Doc.
78 at 15). CCSI notes that when Choate emailed the final version of the Broussard Contract on
4
November 27, 2012, he stated that “it was this contract ‘that should have been in place prior to
CCSI’s commencement of the work for us on the Kinder Morgan project.’” (Rec. Doc. 78 at
14).
If the Court finds that a contract existed at the time of Cypert’s injury, CCSI maintains
that the Broussard Contract constitutes the only applicable contract. (Rec. Doc. 50 at 11). CCSI
argues that the Broussard Contract indemnity language differs significantly from the CCSI
Proposal, as it only requires CCSI to defend and indemnify Broussard Brothers to the extent that
the acts or omissions of CCSI caused the personal injury to a CCSI employee and does not
provide for indemnification of injuries caused by Broussard Brothers’ own acts of negligence or
by the unseaworthiness of a Broussard Brothers’ vessel. (Rec. Doc. 78 at 5). Accordingly, CCSI
asserts that since Broussard’s negligence allegedly caused Cypert’s injury, CCSI is not required
to indemnify and defend Broussard under the Broussard Contract. (Rec. Doc. 78 at 7). CCSI
emphasizes that Broussard Brothers was mistaken in its Motion for Summary Judgment
memorandum when it represented that both the Proposal and the Broussard Contract contained
the same indemnity language. (Rec. Doc. 78 at 7).
While CCSI maintains that no contract was in place, and Maritime Law therefore applies,
CCSI argues that if the Court finds that the Broussard Contract took effect prior to the injury
then Louisiana Law would apply. (Rec. Doc. 78 at 16). CCSI avers that the parties intended to
enter a written contract, and pursuant to Louisiana Law, when parties agree that a final contract
will be reduced to writing, there is no governing contract until the agreement is reduced to
writing. (Rec. Doc. 78 at 16) (citing La Civ. Cod art. 1947; Rogers v. Brooks, 122 Fed. Appx.
729, 2004 WL 2977453 (5th Cir, 2004)). The absence of a contract at the time of Cypert’s
accident, CCSI contends, signifies that “the parties’ liabilities for Cypert’s injuries were ‘at
5
law.’” (Rec. Doc. 78 at 16). Finally, CCSI argues that even if the Broussard Contract includes
an indemnity provision, LA. R.S. § 7.2780.1 would invalidate such a provision because the
Broussard Contract is a construction contract. (Rec. Doc. 78 at 17).
C. Broussard Brothers’ Reply (Rec. Doc. 87)
Broussard Brothers filed a Reply to CCSI’s Opposition on September 11, 2014. (Rec.
Doc. 87). In response to CCSI’s argument that Broussard Brothers never accepted the CCSI
Proposal, and instead responded with a counter-offer, Broussard Brother asserts that “if the
discussions related to a subcontract were truly a ‘counter-offer’ CCSI would not have performed
and had been paid for the pipe coating services.” (Rec. Doc. 87 at 2). Rather, Broussard
Brothers insists it would have required a subcontract to be in place prior to the initiation of
CCSI’s work.
(Rec. Doc. 87 at 2-3).
Broussard Brothers states that “[t]he electronic
correspondence between Choate and Raphoon…clearly evidences that Broussard Brothers
accepted CCSI’s Proposal for the work on the Lake Pontchatrain project and that the work had
been commenced by CCSI pursuant to the Proposal. (Rec. Doc. 87 at 3).
III.
LAW & ANALYSIS
A.
Standard
Summary judgment is proper "if the pleadings, depositions, answers to interrogatories,
and admissions on file, together with the affidavits, if any, show that there is no genuine issue as
to any material fact and that the moving party is entitled to a judgment as a matter of law."
Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986) (citing Fed. R. Civ. P. 56(c)). "Rule 56(c)
mandates the entry of summary judgment, after adequate time for discovery and upon motion,
against a party who fails to make a showing sufficient to establish the existence of an element
essential to that party's case, and on which the party will bear the burden of proof at trial." Id.
6
When considering a motion for summary judgment, the district court "will review the facts
drawing all inferences most favorable to the party opposing the motion." Reid v. State Farm
Mut. Auto. Ins. Co., 784 F.2d 577, 578 (5th Cir. 1986). The court must find "[a] factual dispute
[to be] 'genuine' if the evidence is such that a reasonable jury could return a verdict for the
nonmoving party [and a] fact [to be] 'material' if it might affect the outcome of the suit under the
governing substantive law." Beck v. Somerset Techs., Inc., 882 F.2d 993, 996 (5th Cir. 1989)
(citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)).
B.
Contract between Broussard Brothers and CCSI
The determination of this motion rests on an analysis of the parties’ contract formation.
While it is not apparent whether Maritime or Louisiana Law applies in the instant case, that
determination has no bearing on the analysis as both apply general contract principles. Under
both Maritime and Louisiana Law, a valid contract requires an offer and an acceptance. See La.
Civ. Code art. 1927; Nat’l Marine, Inc. v. Glencore, Ltd., CIV. A. 95-2682, 1998 WL 118087 at
*3 (E.D. La. Mar. 16, 1998). Under Louisiana Law, “an acceptance not in accordance with the
terms of the offer is deemed to be a counteroffer” (La. Civ. Code art. 1943), and the
determination of the existence of a contract is a finding of fact pursuant to Louisiana Law.
SnoWizard, Inc. v. Robinson, 897 F. Supp. 2d 472, 480 (E.D. La. 2012).
Maritime contracts are subject to the general rules of contract law. Marine Overseas
Servs., Inc. v. Crossocean Shipping Co., 791 F.2d 1227, 1234 (5th Cir. 1986); Otto Candies, Inc.
v. McDermott Int’l Inc., 600 F. Supp. 1334, 1339 (E.D. La. 1985); Fitch Marine Transp., LLC v.
Am. Commercial Lines, LLC, CIV.A.09-4450, 2010 WL 2523062 at *4 (E.D. La. June 14, 2010).
Courts apply federal common law to contracts governed by Maritime Law. Albany Ins. Co. v.
Anh Thi Kieu, 927 F.2d 882, 886 (5th Cir. 1991). As CCSI notes in their Opposition, the courts
7
look to the Restatement (Second) of Contracts when they apply federal common law to maritime
contracts. Marine Overseas Servs., Inc. v. Crossocean Shipping Co., 791 F.2d 1227, 1234 (5th
Cir. 1986); E.N. Bisso & Son Inc. v. World Marine Transport & Salvage Inc., CIV. A. No. 940690, 1996 WL 28520 at *3 (E.D. La. Jan. 23, 1996).
The Second Restatement defines acceptance as follows:
(1) Acceptance of an offer is a manifestation of assent to the terms thereof made by the
offeree in a manner invited or required by the offer.
(2) Acceptance by performance requires that at least part of what the offer requests be
performed or tendered and includes acceptance by a performance which operates as a
return promise.
(3) Acceptance by a promise requires that the offeree complete every act essential to the
making of the promise.
Restatement (Second) of Contracts § 50. A counteroffer is defined as follows:
(1) A counter-offer is an offer made by an offeree to his offeror relating to the same
matter as the original offer and proposing a substituted bargain differing from that
proposed by the original offer.
(2) An offeree's power of acceptance is terminated by his making of a counter-offer,
unless the offeror has manifested a contrary intention or unless the counter-offer
manifests a contrary intention of the offeree.
Offer, Counteroffer
Restatement (Second) of Contracts § 39.
Based on the facts, it is not clear whether Choate’s July 21, 2012 email to CCSI
constituted an acceptance or a counter-offer. (Rec. Doc. 50-2 at 10). The email states that
Broussard Brothers had selected CCSI as its subcontractor, but the language “you will need to
execute a ‘project specific’ service agreement” is ambiguous as to whether that email signified
an acceptance of CCSI’s proposal or whether Choate issued a counter-offer to CCSI with
Broussard Brothers’ own contract terms and conditions. (Rec. Doc. 50-2 at 10). Broussard
Brothers contends that the notion that they rejected the Proposal and asserted a counter-offer is
“unsubstantiated, disputed by Mr. Choate and contrary to the actions of the parties.” (Rec. Doc.
8
87 at 3). But CCSI outlines a compelling argument that the Broussard Contract constituted a
counter-offer as it differed from the CCSI proposal, and Broussard Brothers had stressed that
CCSI’s work was contingent on their acceptance of the Broussard Contract. Indeed, the central
dispute in this motion is over the differing indemnification terms of the two contracts, so it is not
“unsubstantiated” that the Broussard Contract could be determined a counter-offer because it
differed significantly from the original Proposal.
Moreover, Choate acknowledged in a
November 2012 email that the Broussard Contract should have been in place prior to CCSI’s
commencement of work, indicating that it may have been Broussard Brother’s intention to issue
a counteroffer and not accept the Proposal.
Alternatively, Broussard Brothers argues that the email constituted an acceptance and that
“[t]he law is settled that an agreement between the parties constitutes a contract and binds those
parties at once, although they may have agreed that they would thereafter execute a formal
instrument.” (Rec. Doc. 87 at 3). Broussard Brothers cites Newport Ltd v. Sears Roebuck & Co,
a Fifth Circuit case, to support this proposition. In that case, the Fifth Circuit notes that whether
a contract existed upon the execution of a preliminary agreement or did not come to fruition until
the later, formalized agreement depends on the intention of the parties. Newport Ltd v. Sears
Roebuck & Co, 6 F.3d 1058, 1065 (5th Cir. 1993). The Fifth Circuit averred that “[t]he parties'
intent is a question of fact” and ultimately reversed the district court’s decision to grant summary
judgment because there were genuine issues of material fact. Id. Similarly, based upon the
email correspondence; the affidavits; the parties’ course of conduct; and the contracts’
themselves, there is a genuine issue of fact as to Broussard Brothers’ intent and whether the
company accepted the CCSI proposal as a preliminary agreement or responded with a counteroffer. Accordingly, summary judgment is not appropriate at this time.
9
IV.
CONCLUSION
For the foregoing reasons, IT IS ORDERED that Broussard Brother’s Motion for
Summary Judgment (Rec. Doc. 50) is hereby DENIED.
New Orleans, Louisiana, this 26th day of September.
__________________________________
UNITED STATES DISTRICT JUDGE
10
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?