Reine et al v. State Farm Insurance Company et al
Filing
33
AMENDED ORDER AND REASONS granting 27 MOTION for Summary Judgment. 32 Order on Motion to Dismiss Case is VACATED. Signed by Judge Helen G. Berrigan on 2/23/2015.(kac)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
STEVE REINE AND JULIE REINE
CIVIL ACTION NO. 13-cv-5641
VERSUS
SECTION “C”
STATE FARM INSURANCE
COMPANY, et al
HON. HELEN BERRIGAN
Amended Order and Reasons
Before the Court is a Motion to Dismiss and/or Alternatively for Summary Judgment
submitted by defendant, the Federal Emergency Management Agency (“FEMA”). Rec. Doc. 27.
Plaintiff has not opposed the motion. Having considered the record, the law, and the memoranda
of counsel, the Court GRANTS FEMA’s motion.
I.
Factual background
This dispute arises out of defendants’ refusal to make payments on a home insurance
policy for damage that plaintiffs allege they suffered from Hurricane Isaac’s storm surge.
Plaintiffs own property in LaPlace, Louisiana (“the residence”). Rec. Doc. 1, ¶4 at 2. They
maintained flood insurance coverage under a Standard Flood Insurance Policy (“SFIP”) issued
1
by FEMA through the National Flood Insurance Program and effective from June 23, 2013
through June 23, 2013. Rec. Doc. 27-2, ¶4-5 at 2. According to plaintiffs, on August 29, 2012,
the residence sustained damage from Hurricane Isaac’s storm surge. Rec. Doc. 1, §8 at 3. Per
declarations and documents provided by FEMA, on September 4, 2012, an independent adjuster
inspected the property and issued a final report. The report recommended a payment of
$116,944.18 for damage to the building and contents loss. Rec. Doc. 27-7 at 4. On September 10,
2012 an advance payment of $5,000 was issued. Rec. Doc. 27-8. On October 30, 2012, plaintiffs
submitted a signed proof of loss for $105,629.29 with a statement for replacement cost coverage
for $11,314.89. Rec. Doc. 27-10. On November 9, 2012, FEMA issued a final building payment
and final contents payment for the amount sworn to in the proof of loss. Rec. Docs. 11, 12. On
that date, FEMA also issued a denial of additional amounts that plaintiffs had claimed for
property damage which FEMA found could not have been caused by the three inches of water
that entered the home. Rec. Doc. 27-13.
On November 27, 2012, plaintiffs submitted a new estimate of damages by Michaelson
and Messinger Insurance Specialists, LLC for $390,203.16 (“November estimate”). Rec. Doc.
27-14. However, FEMA alleges that plaintiffs never submitted an additional proof of loss to
substantiate the amount claimed in the November estimate. Rec. Doc. 27-2, ¶17 at 5. On August
28, 2013, plaintiffs filed suit against FEMA and State Farm Insurance Company (“State Farm”),
alleging breach of contract, bad faith claims adjusting, negligent claims adjusting, and intentional
infliction of emotional distress due to defendants’ refusal to make further payments for the
damages claimed in the November estimate. Rec. Doc. 1.
2
II.
Standard of review
FEMA has filed this motion as a motion to dismiss or, in the alternative, as a motion for
summary judgment. Because FEMA has introduced into the record evidence that goes beyond
plaiintiffs’ pleadings, including a sworn declaration and numerous documents to support its
motion, the Court finds that the motion is more appropriately evaluated as a motion for summary
judgment.
Summary judgment is proper when the record indicates that there is not a “genuine issue
as to any material fact and that the moving party is entitled to judgment as a matter of law.” Fed.
R. Civ. P. 56. A genuine issue of fact exists if the evidence is such that a reasonable jury could
return a verdict for the non-moving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248
(1996).
A party seeking summary judgment “bears the initial responsibility of informing the
district court of the basis for its motion, and identifying those portions of ‘[discovery], together
with the affidavits, if any,’ which it believes demonstrate the absence of a genuine issue of
material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). Once the initial burden is met,
the nonmoving party must “designate specific facts showing there is a genuine issue for trial”
using evidence cognizable under Rule 56. Id. at 324. “[U]nsubstantiated assertions” and
“conclusory allegations” will not defeat a properly supported motion for summary judgment.
Hopper v. Frank, 16 F.3d 92, 97 (5th Cir. 1994); Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871,
871-73 (1990). “If the evidence is merely colorable, or is not significantly probative,” summary
judgment is appropriate. Anderson, 477 U.S. at 249-50 (internal citations omitted). “Only
disputes over facts that might affect the outcome of the suit under the governing law will
properly preclude the entry of summary judgment.” Id. at 248.
3
When reviewing a motion for summary judgment, a court must view the evidence and
inferences drawn therefrom in the light most favorable to the non-moving party. Daniels v. City
of Arlington, Texas, 246 F.3d 500, 502 (5th Cir. 2001). Summary judgment does not allow a
court to resolve credibility issues or weigh evidence. Int’l Shortstop, Inc. v. Rally’s, Inc., 939
F.2d 1257, 1263 (5th Cir. 1991).
III.
Law and Analysis
a. Plaintiffs’ breach of contract claim
FEMA claims it is entitled to summary judgment on plaintiffs’ breach of contract claim
because plaintiffs failed to submit a proof of loss in support of the November estimate. Plaintiffs
were covered under a Standard Flood Insurance Policy (“SFIP”) issued by FEMA. Rec. Doc. 272, ¶4 at 2. Federal regulations require as a precondition to recovery that the insured submit a
proof of loss to their insurer within 60 days. The proof of loss must be signed and sworn and
must include, inter alia, the date and time of loss, specifications of damaged buildings and
detailed repair estimates, and an inventory of damaged personal property. 44 C.F.R. § Pt. 61,
App. A(1)(VII)(J)(4). Although normally the insured must submit proof of loss within 60 days,
the Acting Federal Insurance Administrator extended this deadline for claims related to
Hurricane Isaac, giving plaintiffs approximately 240 days to submit the proof of loss. Rec. Doc.
27-16. The Fifth Circuit Court of Appeals has held that “the provisions of an insurance policy
issued pursuant to a federal program must be strictly construed and enforced” and that the failure
to provide proof of loss “relieves the federal insurer’s obligation to pay what otherwise might be
a valid claim.” Gowland v. Aetna, 143 F.3d 951, 954 (5th Cir. 1998). Because plaintiffs have not
adduced any evidence that they did in fact timely submit a proof of loss, the Court finds that
4
FEMA is entitled to summary judgment on plaintiff’s breach of contract claim. Accordingly,
plaintiffs’ breach of contract claim is DISMISSED WITH PREJUDICE.
Accordingly,
IT IS ORDERED that FEMA’s Motion for Summary Judgment (Rec. Doc. 27) is
GRANTED.
IT IS FURTHER ORDERED that judgment be entered in favor of defendant and against
plaintiff, dismissing the case with prejudice.
IT IS FURTHER ORDERED that the Court’s previous Order and Reasons (Rec. Doc.
32) is VACATED in its entirety.
New Orleans, Louisiana, this 23rd day of February 2015.
________________________________
HELEN G. BERRIGAN
UNITED STATES DISTRICT JUDGE
5
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?