King Company, Limited Partnership v. Catastrophe Cleaning & Restoration Company, Inc.
Filing
41
ORDER AND REASONS denying 18 Motion for Summary Judgment. Signed by Judge Stanwood R. Duval, Jr on 6/24/15. (blg)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
KING COMPANY, LTD. PARTNERSHIP
VERSUS
CIVIL ACTION
NO. 13-6063
CATASTROPHE CLEANING &
RESTORATION CO., INC.
SECTION "K"(3)
ORDER AND REASONS
Before the Court is a Motion for Summary Judgment (Doc. 18) filed by King Company,
Ltd. Partnership ("King") seeking judgment against Catastrophe Cleaning & Restoration Co.,
Inc. ("CATCO"). In essence the case presented concerns work performed for which plaintiff
maintains it has not been properly compensated. Having reviewed the pleadings, memoranda,
exhibits and the relevant law, the Court finds there are material questions of fact precluding
summary judgment.
Standard for Motion for Summary Judgment
Rule 56(a) of the Federal Rules of Civil Procedure provides that summary judgment
should be granted "if the movant shows that there is no genuine dispute as to any material fact
and the movant is entitled to judgment as a matter of law." The party moving for summary
judgment bears the initial responsibility of informing the district court of the basis for its motion,
and identifying those portions of the record "which it believes demonstrate the absence of a
genuine issue of material fact." Stults v. Conoco, 76 F.3d 651 (5th Cir.1996), citing Skotak v.
Tenneco Resins, Inc., 953 F.2d 909, 912-13 (5th Cir.), quoting Celotex Corp. v. Catrett, 477
U.S. 317, 323, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986). When the moving party has
carried its burden under Rule 56, its opponent must do more than simply show that there is some
metaphysical doubt as to the material facts. The nonmoving party must come forward with
"specific facts showing that there is a genuine issue for trial." Matsushita Elec. Industrial Co. v.
Zenith Radio Corp., 475 U.S. 574, 588, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986); Tubacex,
Inc. v. M/V Risan, 45 F.3d 951, 954 (5th Cir.1995).
“A genuine issue of material fact exists ‘if the evidence is such that a reasonable jury
could return a verdict for the nonmoving party.’ ” Pylant v. Hartford Life and Accident
Insurance Company, 497 F.3d 536, 538 (5th Cir. 2007) quoting Anderson v. Liberty Lobby, Inc.,
477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Summary judgment evidence must
be “viewed in the light most favorable to the nonmovant, with all factual inferences made in the
nonmovant’s favor.” Bazan ex rel Bazan v. Hildago County, 246 F.3d 481, 489 (5th Cir. 2001),
citing Anderson v. Liberty Lobby, Inc., 477 U.S. at 255, 106 S.Ct. at 2513.
[C]onclusory statements, speculation, and unsubstantiated assertions cannot
defeat a motion for summary judgment. The Court has no duty to search the
record for material fact issues. Rather, the party opposing the summary judgment
is required to identify specific evidence in the record and to articulate precisely
how this evidence supports his claim.
RSR Corporation v. International Insurance Company, 612 F.3d 851,857 (5th Cir. 2010).
Analysis
This suit arises out of construction work done for CATCO by King and CATCO's
alleged failure to pay for work performed by King on the Ursuline Academy, Alterations &
Additions to the Old Gymnasium project located at 2635 State Street, New Orleans , Louisiana
70118 (the "Project"). At the heart of this dispute is the scope of the agreement between the
2
parties and whether CATCO authorized and agreed to pay for certain work and materials
provided by King. King maintains that there are no questions of fact. King contends that:
(1)
CATCO entered into a time and materials ("T & M") agreement with King to
begin work to complete a project already begun by another contractor in October
of 2012;
(2)
that it invoiced this work with detailed time sheets and work tickets which were
signed and unauthorized by CATCO;
(3)
that a contract signed in December of 2012 was for work already completed;
(4)
that King continued to perform extra work beyond the scope of the December
contract which was allegedly confirmed and acknowledge in email
correspondence on a time and material basis;
(5)
that CATCO has reneged on its promises and that CATCO owes King the
principal amount of $114,066.90, plus reasonable attorney's fees, penalties, and
interest.
CATCO in response contends that the damages King seeks are not valid charges as
allowed under the written contract for a fixed cost for the Project. In essence, CATCO
characterizes the work for which King seeks payment as requiring "change orders" under the
terms of the contract. It characterizes the December contract as requiring the project architect to
authorize any changes to any work, contract specifications and/or plan drawings before any extra
work. Moreover, CATCO relies on the contract language which provides:
"The Subcontractor [King] will not be entitled to any additional compensation for
any extra or changed work unless the Contractor agrees to the additional sum in a
written Change Order signed by the Contractor before the extra, additional or
changed work is begun. If the Subcontractor performs any extra or altered work
3
without a written change order signed by the Contractor before that work is
begun, the Subcontractor waives any right or claim for additional compensation
for that work."
(Doc. 22-2 at page 26 of 49).
Indeed, King avers that the arrangement for all work was on a T&M with daily work
tickets labeled "authorization for Extra Work Not Included in Contract." These tickets were
signed by CATCO'S Senior Project Manager David Belou or CATCO's Superintendant Michael
Smith and that the December contract was for work that had already been performed. In
response, David Belou signed an affidavit attesting that he had "no authority to sign subcontracts and no authority to sign change orders." (Doc. 22-6).
As such, considering that the Court is required to look at the facts in the light most
favorable to the non-movant, clearly, there are innumerable questions of fact at issue.
Accordingly,
IT IS ORDERED that Motion for Summary Judgment (Doc. 18) is DENIED.
New Orleans, Louisiana, this 24th day of June, 2015.
STANWOOD R. DUVAL, JR.
UNITED STATES DISTRICT COURT JUDGE
4
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?