Tengasco, Inc. v. United States Department of the Interior et al
Filing
38
ORDER AND REASONS Granting defendants' 28 Motion for Summary Judgment Denying plaintiff's 25 Motion for Summary Judgment;. Signed by Judge Ivan L.R. Lemelle on 7/14/2015. (ijg)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
TENGASCO, INC.
CIVIL ACTION
VERSUS
NO. 14-2184
SARAH JEWELL, Secretary of the
United States Department of the
Interior, ET AL.
SECTION "B"(2)
ORDER AND REASONS
Before
the
Court
are
cross-motions
for
summary
judgment
filed by Plaintiff, Tengasco, Inc. and Defendants, the United
States Department of the Interior, and Bureau of Safety and
Environmental Enforcement.1 The parties have filed responses and
replies.2 The cross-motions, set for submission on August 5,
2015,
are
argument.
before
After
the
Court
careful
on
the
consideration
pleadings,
of
the
without
oral
cross-motions,
responses, replies, competent summary judgment evidence, record,
and applicable law, IT IS ORDERED that Defendants' Motion for
Summary
Judgment
is
GRANTED,
Plaintiff's
Motion
for
Summary
Judgment is DENIED, and Plaintiff's suit is DISMISSED.
I.
FACTUAL AND PROCEDURAL BACKGROUND
Plaintiff, Tengasco, Inc. (“Tengasco”) challenges a civil
penalty
1
2
assessment
levied
by
the
Bureau
of
Safety
and
Rec. Docs. No. 25, 28.
Rec. Docs. No. 30, 33, 34, 35, 37.
1
Environmental Enforcement (“BSEE”), and affirmed by the Interior
Board of Land Appeals of the U.S. Department of the Interior
(“IBLA” or “Department”).3 Tengasco’s claims challenge a federal
agency action and are based upon the Outer Continental Shelf
Lands Act (OCSLA), 43 U.S.C. § 1331, et seq., the Administrative
Procedure Act (APA), 5 U.S.C. § 551, et seq., and the U.S.
Constitution.4
Tengasco is the lessee and facility operator of a lease on
the outer continental shelf in the Gulf of Mexico, namely, the
High Island Block 176 Platform B.5 On February 23, 2011, BSEE
conducted
an
onsite
inspection
of
the
platform
facility
and
determined that certain prior testing records were not available
at the time for review on the platform.6 These included: (1)
testing records from June 9, 2010 to February 23, 2011 for the
surface controlled subsurface safety valves associated with five
wells on the platform; and, (2) testing records from September
1, 2010 to January 25, 2011 for other production safety devices
on the platform.7
During the time period at issue, Tengasco had contracted
with Rhino Offshore, Ltd., to conduct and document the required
3
Rec. Doc. No. 1.
Rec. Doc. No. 1 at 1.
5
Rec. Doc. No. 25-2 at 1; Rec. Doc. No. 28-4 at 6; A.R. 003.
6
Rec. Doc. No. 25-2 at 1.
7
Rec. Doc. No. 25-2 at 2.
4
2
testing.8
Tengasco
contends
that
undisputed
evidence
in
the
administrative record shows that the required testing was in
fact conducted.9 However, by letter dated October 26, 2011, BSEE
informed Tengasco of its intention to impose 22 separate civil
penalties
totaling
$476,000
resulting
from
the
onsite
inspection.10 BSEE divided the 22 proposed civil penalties into 8
different
categories,
each
of
which
was
associated
with
an
Incident of Non-Compliance (“INC”) that the BSEE field inspector
had issued.
Tengasco
responded
by
letter
dated
November
22,
2011,
requesting a meeting to discuss the proposed civil penalties and
asking for additional time to respond due to difficulties in
obtaining
records
from
Rhino
Offshore.11
Tengasco
filed
a
response and made a presentation to BSEE staff.12 Tengasco also
submitted an affidavit of Randy Walker, a former Rhino employee
who worked as an operator-foreman on the platform from June 1,
2010 through December 21, 2010.13 In his affidavit, Mr. Walker
stated that the required safety tests were in fact conducted,
that he was personally present on the platform during the tests,
and
that
he
completed
and
submitted
the
necessary
forms
to
8
Rec. Doc. No. 25-2 at 2.
Rec. Doc. No. 25-3 at 8.
10
Rec. Doc. No. 25-3 at 9.
11
Rec. Doc. No. 25-3 at 9; A.R. 289-334.
12
Rec. Doc. No. 25-3 at 9; A.R. 289-334.
13
Rec. Doc. No. 25-3 at 9; A.R. 354-358: A.R. 302-05.
9
3
document the completion of the tests.14 Attached to the affidavit
were
recompleted
Tengasco
also
testing
records
submitted
for
flight
the
logs
periods
from
at
two
issue.15
helicopter
companies purportedly showing that Rhino inspectors, including
Mr. Walker, made regular trips to the platform during the period
June 2010 to December 2010. On February 1, 2012, BSEE issued a
subpoena to Rhino for all testing records associated with the
safety
devices
in
question
from
June
2010
through
February
2011.16 In response, Rhino submitted several documents, including
a Safety Compliance Inspection Report for the Platform dated
September 13, 2010.17
On July 20, 2012, the BSEE Reviewing Officer issued its
decision, reducing the number of penalties, for a civil penalty
assessment total of $386,000.18 Tengasco appealed BSEE’s decision
to the IBLA, which issued a final decision on June 23, 2014,
affirming BSEE’s order in full.19 Following the IBLA’s affirmance
of the BSEE decision, Tengasco filed this action for judicial
review
against
defendants,
Sarah
Jewell,
in
her
official
14
Rec. Doc. No. 25-3 at 10.
Rec. Doc. No. 25-3 at 9-10.
16
Rec. Doc. No. 1 at 6.
17
Rec. Doc. No. 1 at 6.
18
Rec. Doc. No. 25-3 at 10. Specifically, “BSEE (i) reduced the testing periods allegedly missed in INC No. P-303
from four to three, thereby reducing the INC No. P-303 penalty from $80,000 to $60,000; (ii) reduced the testing
periods allegedly missed in INC No. P-304 from four to three, thereby reducing the INC No. P-304 penalty from
$40,000 to $30,000; (iii) reduced the testing periods allegedly missed in INC No. P-307 from four to three, thereby
reducing the INC No. P-307 penalty from $100,000 to $75,000; and (iv) reduced the testing periods allegedly
missed in INC No. P-308 from four to three, thereby reducing the INC No. P-308 penalty from $140,000 to
$105,000.”
19
Rec. Doc. No. 25-2 at 4; Tengasco, Inc., 184 IBLA 367 (June 23, 2014).
15
4
capacity as Secretary of the U.S. Department of Interior, and
Brian
Salerno,
in
his
official
capacity
as
Director
of
the
BSEE.20
The parties agreed that this case should be resolved by
dispositive
motions,
and
jointly
proposed
a
“Joint
Case
Management Statement,” providing a briefing schedule whereby the
administrative record would be filed, followed by cross-motions
for
summary
judgment,
and
reply
briefs.21
The
Joint
Case
Management Statement was adopted by the Court.22 Briefing is now
complete and the cross-motions for summary judgment are ripe for
decision.23
II.
LAW & ANALYSIS
a. The Outer Continental Shelf Lands Act
The
Outer
Continental
Shelf
Lands
Act
(OCSLA)
governs
federal offshore oil and gas leasing and declares as national
policy that “the outer Continental Shelf is a vital national
resource reserve held by the Federal Government for the public,
20
Rec. Doc. No. 1 at 3.
Rec. Doc. No. 19.
22
Rec. Doc. No. 21.
23
Rec. Doc. No. 19 at 2:
a. Federal Defendants file administrative record February 6, 2015
b. Plaintiff files opening motion for summary judgment March 20, 2015
c. Federal Defendants file a single cross-motion for summary judgment/opposition brief May 1, 2015
d. Plaintiff files reply brief in support of its motion and in opposition to Federal Defendants’ motion June
5, 2015.
e. Federal Defendants file a single reply brief in support of their cross-motion for summary judgment
July 10, 2015.
The Court notes that Tengasco has filed additional pleadings in this matter. Rec. Docs. No. 33, 34.
21
5
which
should
be
made
available
for
expeditious
and
orderly
development, subject to environmental safe-guards, in a manner
which
is
consistent
with
the
maintenance
of
competition
and
other national needs.” 43 U.S.C. § 1332(3). The OCSLA further
provides that, “operations in the outer Continental Shelf should
be conducted in a safe manner by well-trained personnel using
technology, precautions, and techniques sufficient to prevent or
minimize
the
likelihood
of
blowouts,
loss
of
well
control,
fires, spillages....” 43 U.S.C. § 1332(6).
The OCSLA, 43 U.S.C. § 1350 provides:
(b) Civil penalties; hearing
(1) Except as provided in paragraph (2), if any
person fails to comply with any provision of this
subchapter, or any term of a lease, or permit
issued pursuant to this subchapter, or any
regulation or order issued under this subchapter,
after notice of such failure and expiration of
any reasonable period allowed for corrective
action, such person shall be liable for a civil
penalty of not more than $20,000 for each day of
the continuance of such failure. The Secretary
may assess, collect, and compromise any such
penalty. No penalty shall be assessed until the
person charged with a violation has been given an
opportunity for a hearing...
(2) If a failure described in paragraph (1)
constitutes or constituted a threat of serious,
irreparable, or immediate harm or damage to life
(including
fish
and
other
aquatic
life),
property, any mineral deposit or the marine,
coastal or human environment, a civil penalty may
be assessed without regard to the requirement of
expiration of a period allowed for corrective
action.
6
Pursuant
adopted
to
the
safety
installation,
OCSLA,
the
Department
regulations,
inspection,
and
including
testing
of
of
the
rules
safety
Interior
requiring
decisions
on
OCSLA rigs to minimize the potential for catastrophic events on
the rig. 30 C.F.R. § 250.804 (“Production safety-system testing
and
records”).
The
regulations
provide
that
safety
system
devices shall be successfully inspected and tested by the lessee
at
specified
intervals.
30
C.F.R.
§
250.804
(a)(1)-(12).
Additionally, the “lessee shall maintain records for a period of
2
years
for
each
installed...These
history
of
installation,
each
subsurface
records
device,
removal,
shall
and
show
including
inspection,
surface
the
safety
present
dates
and
testing...”.
device
status
and
details
of
30
C.F.R.
§
250.804(b).
b. The Administrative Procedure Act
The Administrative Procedure Act authorizes judicial review
of final agency action. 5 U.S.C. § 704; see id. § 702 (“A person
suffering a legal wrong because of agency action...is entitled
to
judicial
review
thereof.”).24
Per
the
APA,
5
U.S.C.
§
706(2)(a), federal courts are empowered to “hold unlawful and
set aside agency action, findings, and conclusions” if they fail
24
Agency action is final if it is the consummation of the agency’s decision making process and rights or obligations
have been determined. E.g. Center for Auto Safety v. National Highway Traffic Safety Admin., 452 798, 806 (D.C.
Cir. 2006).
7
to
conform
with
any
of
six
specified
standards.
5
U.S.C.
§
706(2); Marsh v. Oregon, 490 U.S. 360, 375, 109 S.Ct. 1851, 104
L.Ed.2d 377 (1989). Under the APA, the administrative record is
reviewed to determine whether the challenged agency action was
arbitrary or capricious, an abuse of discretion, or otherwise
not in accordance with law, contrary to constitutional right, in
excess of statutory jurisdiction, authority or limitation, or
without procedure required by law, or unsupported by substantial
evidence. 5 U.S.C. § 706(2)(A-E).
Ordinarily,
review
of
administrative
decisions
is
to
be
confined to consideration of the decision of the agency...and of
the evidence on which it was based. Marsh, 490 U.S. at 331;
Federal
Power
Commission
v.
Transcontinental
Gas
Pipe
Line
Corp., 423 U.S. 326, 96 S.Ct. 579, 46 L.Ed.2d 533 (1976). The
focal point for judicial review should be the administrative
record already in existence, not some new record made initially
in the reviewing court. Marsh, 490 U.S. at 331. If the decision
of the agency ‘is not sustainable on the administrative record
made,
then
the...decision
must
be
vacated,
and
the
matter
remanded...for further consideration.’ Federal Power Commission,
423 U.S. at 331.
8
c. Summary Judgment Standard of Review over Final Agency
Decisions
Where
the
Court
is
reviewing
the
decision
of
an
administrative agency, a motion for summary judgment stands in a
somewhat
unusual
light,
in
that
the
administrative
record
provides the complete factual predicate for the Court's review.
As
a
result,
judgment
is
the
movant's
similar
to
his
burden
in
ultimate
prevailing
burden
on
on
summary
the
merits:
preponderance of the evidence. See Butts v. Sec’y of Health and
Human
Services,
706
F.2d
107,
108
(2nd
Cir.
1983).
Summary
judgment is an appropriate procedure for resolving a challenge
to a federal agency's administrative decision when review is
based on the administrative record even though the Court does
not apply the standard of review set forth in Fed. R. Civ. P.
56. Tex. Comm. on Nat. Res. v. Van Winkle, 197 F.Supp.2d 586,
595 (N.D. Tex. 2002)(quoting Fund for Animals v. Babbitt, 903
F.Supp.96, 105 (D. D.C.1995)).
When
reviewing
administrative
agency
decisions,
the
function of the district court is to determine whether as a
matter of law, evidence in the administrative record permitted
the agency to make the decision it did, and summary judgment is
an
appropriate
mechanism
for
deciding
the
legal
question
of
whether an agency could reasonably have found the facts as it
did. Id. (quoting Sierra Club v. Dombeck, 161 F.Supp.2d 1052,
9
1064 (D. Ariz. 2001)). Although an agency’s legal conclusions
are reviewed
de novo, the court’s overall review is “highly
deferential to the administrative agency whose final decision is
being reviewed.” Buffalo Marine Services Inc. v. United States,
663 F.3d 750 (5th Cir. 2011).
d. Arguments of the Parties
Tengasco moves the Court for summary judgment vacating the
final decision of the IBLA affirming the decision of the BSEE,
ordering Tengasco to pay $386,000 in civil penalties for alleged
violations of 30 C.F.R. § 250.804(a). The core of Tengasco’s
challenge
before
the
Court
concerns
the
sufficiency
of
the
administrative record to support the civil penalties imposed.
Tengasco
abuse
of
argues
that
discretion,
“the
IBLA’s
decision
and
unsupported
by
is
arbitrary...an
the
administrative
record,” in violation of the OCSLA, the APA and due process.25
Tengasco
argues
that
the
undisputed
evidence
in
the
administrative record shows that the requisite testing was in
fact
conducted,
that
there
is
no
evidence
that
the
safety
devices and other equipment at issue did not work properly or
presented
25
a
threat
of
any
kind,
and
further
that
the
Rec. Doc. No. 1 at 7; Rec. Doc. No. 25-3 at 8.
10
unavailability of testing records onsite at the platform should
not form the basis for the imposed civil penalties.26
Further, Tengasco argues that neither BSEE nor IBLA gave
any reasons for imposing penalties over $3,000.27 Tengasco urges
the court to set aside the IBLA’s decision with directions for
no penalties to be imposed against Tengasco.28
Tengasco
requests
the
Court
vacate
the
IBLA’s
Alternatively,
decision
and
remand the matter for a redetermination and reduction of any
penalties, to no more than $3,000 per penalty and to no more
than four penalties.29
Defendants contend that Plaintiff was properly fined for
failing to conduct required safety testing in accordance with
the OCSLA.30 Plaintiff’s records were reasonably assessed as not
credible,
and
considering
failed
the
to
evidence
document
the
submitted,
required
BSEE
testing.31
factored
in
In
the
severity of the violations and Plaintiff’s compliance history,
and
ultimately
permitted
within
imposed
each
the
minimum
violation
per-violation
category.32
penalty
According
to
Defendants, this conclusion, and the decision to impose civil
26
Rec. Doc. No. 25-3 at 8.
Rec. Doc. No. 25-3 at 6.
28
Rec. Doc. No. 25 at 1.
29
Rec. Doc. No. 25 at 1.
30
Rec. Doc. No. 28-4 at 4.
31
Rec. Doc. No. 28-4 at 4.
32
Rec. Doc. No. 28-4 at 9.
27
11
penalties
in
their
respective
amounts,
is
supported
by
substantial evidence, was neither arbitrary nor capricious, and
must be upheld.33
Thus,
the
issue
before
the
Court
is
whether
the
civil
penalties levied by the BSEE, and affirmed by the Department,
should
be
overturned
for
findings
that
are
arbitrary,
capricious, or unsupported by substantial evidence on the whole
record, or as an abuse of discretion.
The Arbitrariness Standard
As the U.S. Supreme Court observed in Citizens to Preserve
Overton Park, Inc. v. Volpe, when making the factual inquiry
concerning
whether
capricious,”
the
an
agency
reviewing
court
decision
“must
was
“arbitrary
consider
whether
or
the
decision was based on a consideration of the relevant factors
and whether there has been a clear error of judgment.” 401 U.S.
402, 416, 91 S.Ct. 814, 823, 28 L.Ed.2d 136 (1971), overruled on
unrelated grounds by Califano v. Sanders, 430 U.S. 99, 105, 97
S.Ct. 980, 51 L.Ed.2d 192 (1977).
The
U.S.
Supreme
Court
succinctly
reiterated
the
arbitrariness test in National Ass’n v. Defenders of Wildlife:
An agency’s decision will be considered arbitrary only if
it has relied on factors which Congress had not intended it
33
Rec. Doc. No. 28-4 at 4.
12
to consider, entirely failed to consider an important
aspect of the problem, offered an explanation for its
decision that runs counter to the evidence before the
agency, or is so implausible that it could not be ascribed
to a difference in view or the product of agency expertise.
551 U.S. 644, 127 S.Ct. 2518, 2529, 168 L.Ed. 2d 467 (2007).
“Before concluding that a decision was arbitrary and capricious,
a
court
must
overlooked
be
very
something
appreciating
the
Caterpillar,
Inc.,
confident
important
significance
evidence.”
factors
and
(7th
erred
Patterson
Cir.
in
v.
If
the
505
seriously
maker
Omnipoint Corp. v. FCC, 78 F.3d 620,632 (D.C. Cir. 1996).
considers
503,
the
decision
see
agency
F.3d
or
the
1995);
the
70
of
that
articulates
a
rational
relationship between the facts found and the choice made, its
decision is not arbitrary or capricious. State of La., ex rel.
Guste v. Verity, 853 F.2d 322, 327 (5th Cir. 1988). The court’s
inquiry
must
“be
searching
and
careful,”
but
“the
ultimate
standard of review is a narrow one.” Id.
The Court is not to weigh the evidence pro and con, and
agency action is to be upheld, if at all, on the basis of the
record before the agency at the time that it made its decision.
Id. at 327 (citing C.A. White Trucking Co. v. United States, 555
F.2d 1260, 1264 (5th Cir. 1977)).
13
The Substantial Evidence Requirement
The “scope of review” provisions of the APA, 5 U.S.C. §
706(2),
are cumulative. Thus, an agency action which is not
arbitrary or capricious, may in another regard be unsupported by
the
required
substantial
evidence.
However,
the
courts
of
appeals have noted on several occasions that the distinction
between the substantial evidence test, 5 U.S.C. § 706(2)(E), and
the
arbitrary
or
capricious
test,
§
706(2)(A),
is
“largely
semantic.” Aircraft Owners and Pilots Ass’n v. FAA, 600 F.2d
965, 971 n.28 (D.C. Cir. 1979);
Pacific Legal Foundation v.
Dep’t of Transp., 593 F.2d 1338, 1343 n. 35 (D.C. Cir. 1979);
American Public Gas Ass’n v. FPC, 567 F.2d 1016, 1028-29 (D.C.
Cir. 1977); see Assoc. Indus. V. Dep’t of Labor, 487 F.2d 342,
349-50 (2nd Cir. 1973).
However, the distinctive function of paragraph (E) is to
require substantial evidence to be found within the record of
closed-record proceedings to which it exclusively applies. K.
Davis, Administrative Law Treatise § 6:13 512 (2d ed. 1978).
“Substantial evidence is more than a scintilla, less than a
preponderance, and is such relevant evidence as a reasonable
mind might accept as adequate to support a conclusion.” Hames v.
Heckler, 707 F.2d 162, 164 (5th Cir. 1983).
14
The Abuse of Discretion Standard
Some
discretion
is
unreviewable
and
the
courts
may
not
exercise authority over such decisions if the agency is to have
the intended level of discretion. However, “[i]t is rudimentary
administrative law that discretion as to the substance of the
ultimate
decision
does
not
confer
discretion
to
ignore
the
required procedures of decision-making.” Bennett v. Spear, 520
U.S. 154, 172, 117 S.Ct. 1154, 1166, 137 L.Ed. 2d 281 (1997). A
court might find abuse of discretion when the decision is made
“without
rational
explanation,
or
inexplicably
departs
from
established policies.” Diaz-Resendez v. INS, 960 F.2d 493, 495
(5th Cir. 1992).
e. Analysis
1. Whether the Department’s Decision to Impose Civil
Penalties was arbitrary, capricious, unsupported by
substantial evidence or an abuse of discretion.
First,
Tengasco
argues
this
Court
should
set
aside
the
IBLA’s decision with directions for no penalties to be imposed.
In reviewing the Department’s findings, the Court is guided by
certain basic principles. The findings of the Department are
presumed
to
be
supported
by
competent
evidence,
and
if
so
supported are conclusive. Keele Hair & Scalp Specialists, Inc.
v. FTC, 275 F.2d 18, 21 (5th Cir. 1960).
15
The
relevant
departmental
regulation,
30
C.F.R.
§
250.804(b) provides that:
[t]he lessee shall maintain records for a period of 2
years for each subsurface and surface safety device
installed...These records shall be available for
review by a representative of BSEE. The records shall
show the present status and history of each device,
including dates and details of installation, removal,
inspection, testing...
Any violation of the foregoing which “BSEE determines may
constitute, or constituted, a threat of serious, irreparable, or
immediate
harm
or
damage
to
life
(including
fish
and
other
aquatic life), property, any mineral deposit, or the marine,
coastal, or human environment,” may be reviewed for potential
civil
penalties.
30
C.F.R.
§
250.1404(b)(emphasis
added).
If
such a failure described constitutes or constituted a threat of
serious,
irreparable,
or
immediate
harm
or
damage
to
life
(including fish and other aquatic life), property, any mineral
deposit or the marine, coastal or human environment, a civil
penalty may be assessed without regard to the requirement of
expiration of a period allowed for corrective action. 43 U.S.C.
§ 1350 (b)(2).
Tengasco
administrative
contends
there
record
showing
is
undisputed
that
the
evidence
required
in
the
testing
was
conducted. “This includes (i) direct evidence in the form of
both
an
affidavit
and
numerous
reports
by
Rhino’s
operator-
foreman who oversaw the required testing and (ii) corroborative
16
evidence
in
the
form
of
helicopter
manifests
confirming
the
visits to the platform for the times at issue.”34
The Department considered the general travel logs, Walker’s
affidavit,
and
reconstructed
test
concluded
that
“affidavits
and
attesting
to
compliance
with
insufficient
to
constitute
result
statements
the
testing
forms;
from
however,
individuals,
requirements
specific,
are
contemporaneous
verification of testing that owners and operators are required
to maintain and produce upon request within the 2-year time
period
under
30
C.F.R.
§
250.804(b).”35
Specifically,
the
Department affirmed the following BSEE findings:
i.
INC No. P-280 ($40,000) – Tengasco failed to provide
testing records for surface controlled subsurface
safety valves (“SCSSV”) safety devices on four wells
for two testing periods (June 9, 2010 – February 23,
2011) in violation of 30 C.F.R. § 250.804(a)(1)(i).36
ii.
INC No. P-283 ($6,000) – Tengasco failed to provide
testing records for SCSSV safety devices being used as
tubing plugs for a fifth well for two testing periods
(June 9, 2010 – February 23, 2011) in violation of 30
C.F.R. § 250.804(a)(1)(iii).37
iii.
INC No. P-303 ($60,000) – Tengasco failed to provide
testing records for all level safety high (“LSH”)
safety devices for the facility for three testing
34
Rec. Doc. No. 25-3 at 8.
Tengasco, Inc., 184 IBLA 367, 380 2014 WL 4261981 (IBLA, June 23, 2014).
36
Each surface-controlled subsurface safety device installed in a well, including such devices in shut-in and
injection wells, shall be testing in place for proper operation when installed or reinstalled and thereafter at
intervals not exceeding 6 months.
37
Each tubing plug installed in a well shall be inspected for leakage by opening the well to possible flow at intervals
not exceeding 6 months.
35
17
periods (September 1, 2010 – February 23, 2011) in
violation of 30 C.F.R. § 250.804(a)(3)(ii).38
iv.
INC. No. P-304 ($30,000) – Tengasco failed to provide
testing records for all level safety low (“LSL”)
safety devices for the facility for three testing
periods (September 1, 2010 – January 25, 2011) in
violation of 30 C.F.R. § 250.804(a)(3)(ii).39
v.
INC. No. P-307 ($75,000) – Tengasco failed to provide
testing records for all surface safety valve (“SSV”)
safety devices for the facility for three testing
periods (September 1, 2010 – January 25, 2011) in
violation of 30 C.F.R. § 250.804(a)(5).40
vi.
INC. No. P-308 ($105,000) – Tengasco failed to provide
testing records for all flow safety valve (“FSV”)
safety devices for the facility for three testing
periods (September 1, 2010 – January 25, 2011) in
violation of 30 C.F.R. § 250.804(a)(6).41
vii.
INC. No. P-314 ($35,000)- Tengasco failed to provide
testing records for all electronic pressure safety
high (“PSH”) safety devices for the facility for one
testing period (September 1, 2010 – January 25, 2011)
in violation of 30 C.F.R. § 250.804(a)(4)(i); and42
viii.
INC No. P-315 ($35,000) – Tengasco failed to provide
testing records for all electronic pressure safety low
(“PSL”) safety devices for the facility for one
testing period (September 1, 2010 – January 25, 2011)
in violation of 30 C.F.R. § 250.804(a)(4)(i).43
38
All LSH controls must be tested at least once each calendar month, but at no time will more than 6 weeks elapse
between tests.
39
All LSL controls must be tested at least once each calendar month, but at no time will more than 6 weeks elapse
between tests.
40
All SSV's and USV's shall be tested for operation and for leakage at least once each calendar month, but at no
time shall more than 6 weeks elapse between tests.
41
All flowline Flow Safety Valves (FSV) shall be checked for leakage at least once each calendar month, but at no
time shall more than 6 weeks elapse between tests.
42
All PSH must be tested at least once every 3 months, but at no time may more than 120 days elapse between
tests.
43
All PSL must be tested at least once every 3 months, but at no time may more than 120 days elapse between
tests.
18
Affidavit, reconstructed reports and travel logs. Tengasco
submitted a February 2012 Affidavit by Randy Walker, a former
Rhino employee, attesting to reconstructed reports relating to
all device testing at issue, based on his personal knowledge of
the events, “his log books and field notes.”44 Tengasco also
submitted the aforementioned reconstructed reports for June 2010
through February 2011.
actual
safety
and
45
Rhino’s subpoena response provided the
compliance
inspection
report
for
September
2010, and BSEE reduced the penalties for four pertinent INCs
accordingly.46
The
record
additionally
contains
helicopter
manifests and flight logs dated from April 11, 2010 to December
24, 2010.47
In moving for summary judgment, Tengasco bears the burden
of proof in establishing by a preponderance of the evidence that
the required testing was conducted. The regulations provide that
safety system devices shall be successfully inspected and tested
by the lessee at specified periods. 30 C.F.R. § 250.804(a)(1)(12). Additionally, the “lessee shall maintain records for a
period of 2 years for each subsurface and surface safety device
installed...These
history
of
each
records
device,
shall
show
including
the
present
dates
and
status
and
details
of
44
A.R. 354 (Affidavit of Randy Walker).
A.R. 360-465 (Safety and Compliance Inspection Report).
46
A.R. 551-72, 598.
47
A.R. 118-168.
45
19
installation,
removal,
inspection,
testing....”
30
C.F.
R.
§
250.804(b).
Tengasco attempts to distinguish the underlying violations
from those properly subject to civil penalties by arguing that,
at worst, the company violated only the rule at 30 C.F.R. §
250.804(b),
which
requires
the
recordation
and
retention
of
testing. As the IBLA noted, “§§ 250.804(a) and (b) are part of
the same regulation and must be read together. A violation of §
250.804(b) must be analyzed in conjunction with § 250.804(a). A
lessee may be charged a civil penalty for not testing a safety
device
if
it
cannot
show
documentation
to
satisfy
§
250.804(b).”48
First, although Tengasco contends the record evidence is
undisputed,
Tengasco
fails
to
point
to
any
specific
record
documenting the “present status” of each safety device for the
periods at issue, as required by 30 C.F.R. § 250.804(b). The
BSEEE
and
IBLA
concluded
that
because
these
reports
were
prepared by Mr. Walker at a much later date, they failed to
satisfy the “contemporaneous verification of testing” required
by 30 C.F.R. § 250.804(b).49 The travel logs themselves fail to
document
48
49
any
testing.
According
to
Walker,
these
post-hoc
Tengasco, Inc., 184 IBLA at 380. Otherwise, § 250.804(a) would be unenforceable.
A.R. 611 (Reviewing Officer’s Final Decision); Tengasco, Inc., 184 IBLA at 380.
20
reports were based upon his log books and field notes; however,
these items are not contained in the record.50
Moreover, with respect to June, July and August 2010, BSEE
already
possessed
actual
safety
and
compliance
reports
from
prior regulatory interactions. Specifically, BSEE observed that
the
“July
document
2010
report
states
respectfully,
and
they
for
the
were
adjusted
to
pipeline
tested
55
and
PSH
and
PSL
sensor
at
234
and
73
psi,
25
psi,
respectfully.51
However, the “recompleted” documentation for July 2010 shows no
such
adjustment.52
Tengasco
acknowledges
the
discrepancy;
however, responds that this single example only relates to two
of the eight INCS at issue.53
Tengasco
argues
that
the
documents
it
provided
satisfy
BSEE’s standards.54 To support its claim, Tengasco relies on Blue
Dolphin,
ineffective
where
BSEE’s
evidence
“when
predecessor
not
supported
declared
by
affidavits
corroborative
or
50
Tengasco argues that regulations do not impose any such requirement to attach the field notes and logs, and
further, that the BSEE reviewing officer failed to subpoena these documents. However, the regulations impose a
duty upon Tengasco to maintain and produce records for the devices at issue. Although BSEE could have
subpoenaed these documents, BSEE is under no obligation to do so. BSEE exercised its subpoena authority to gain
compliance from an uncooperative party, Rhino Offshores, which is not the case with regard to Mr. Walker.
Tengasco had ample opportunity to obtain and submit this supporting documentation.
51
A.R. 598 (BSEE Reviewing Officer’s Final Decision); Rec. Doc. 37 at 10 (Exhibit A, noting forty-seven (47)
additional inconsistencies between original and reconstructed reports).
52
A.R. 598 (BSEE Reviewing Officer’s Final Decision).
53
A.R. 181. In an e-mail, Norman Ackermann, of Prime 8 Offshore, LLC, Tengasco’s new contractor, informs the
BSEE: “I asked Randy if the numbers changed in his readings and as I understand his reply, there was virtually no
changes in the readings...Oct 2010 BSEE: on the Flowline page the pressures Randy wrote down were in the wrong
’’
columns. Such as found and adjusted too [sic]. On the 10 Williams line the FSV and SDV operation/Auto should be
N/A’s.”
54
Rec. Doc. 23 at 3.
21
contemporaneous
affidavit
that
documentation,
was
accepted
direct
evidence
indirect.”55
or
in
that
case
was
The
an
affidavit supported with copies of the original tally sheet of
the tests.56 BSSE does not have to show that the testing was not
done, instead the burden for providing testing documentation is
on the lessee for the two year period set out in 30 C.F.R. §
250.804(b).57
Here,
though
neither
side
disputes
that
the
helicopter logs provided by Tengasco show Mr. Walker was flown
to the platform on purported dates of testing, they do not rise
to the level of the evidence that was accepted in Blue Dolphin.
The helicopter records do not corroborate whether the tests were
conducted,
or
whether
the
devices
met
safety
standards
required.58 Furthermore the documents reproduced by Mr. Walker
are not contemporaneous or corroborative evidence because they
were drafted much later than the initial tests were conducted.
Tengasco’s
statements
about
the
disparity
in
penalties
assessed in Blue Dolphin compared to the current case are also
incorrect.59
$205,200,
The
before
penalties
being
in
reduced
Blue
to
Dolphin
$61,600
were
by
the
originally
Reviewing
55
Blue Dolphin, 166 IBLA at 135.
Id. at 135 n.1.
57
Id. at 137.
58
Blue Dolphin, 166 IBLA at 137. Without the requirement that documents be kept during the two-year period it
would be virtually impossible for MMS to enforce the testing requirements of 30 CFR 250.804(a) in the absence of
an express admission by the lessee that the testing was not completed. Thus, affidavits and statements from
individuals, which state that the testing was completed, are insufficient to provide documentation of the testing
within the two-year time period provided in the regulations.
59
Rec. Doc. 33 at 2 f.1.
56
22
Officer upon receiving additional tubing inspection reports.60
Blue
Dolphin
remaining
paid
$24,000.
$37,600
in
Therefore,
fines,
and
only
Tengasco’s
claim
appealed
that
the
similar
violations resulted in higher penalties in this case than those
imposed in Blue Dolphin is mistaken.
Additionally, Tengasco claims to be statutorily entitled to
an
opportunity
to
correct
any
violation
and
thus
avoid
the
penalty. Tengasco urges that a violation of a record-keeping
requirement, which does not create a threat of harm, precludes
the
imposition
correct
the
of
a
civil
violation.
As
penalty
absent
discussed,
an
Tengasco
opportunity
to
appears
be
to
operating under the impression that it is being penalized for
failing
to
promptly
provide
the
necessary
records
upon
inspection. The Court notes however, that over the course of
more than a year, BSEE cooperated with Tengasco in its attempts
to submit additional records.61 More importantly, and as further
discussed below, the BSEE’s final order states that INCs were
being issued for violations of 30 C.F.R. § 250.804(a)’s testing
requirements
and
that
the
testing
violations
“subjected
60
Blue Dolphin, 166 IBLA at 133. Reviewing officer examined information Blue Dolphin supplied and revised her
assessment based on the additional documentation of the plug report inspections, but not the affidavits and
statements.
61
See e.g. A.R. 181; 226-28.
23
personnel, environment, and equipment to a threat of serious
and/or immediate injury or damage.”62
Under departmental regulations, BSEE determines whether the
underlying violation is of the type to which a civil penalty
could attach and whether a civil penalty should be assessed in a
particular instance. 30 C.F.R. §§ 250.1400 - 250.1409. When as
here, a determination is left to the discretion of the agency,
the general rule is that the decision should be upheld if there
is a reasonable explanation for the agency’s decision and a
demonstration
that
a
rational
connection
exists
between
its
findings and the choice it makes. State of La., ex rel. Guste v.
Verity, 853 F.2d at 327.
The Court’s role is not to weigh the evidence pro and con;
but
rather,
to
determine
whether
there
exists
a
rational
relationship between the facts and the conclusions made. BSEE,
having
considered
all
of
the
foregoing,
ultimately
concluded
that: (1) the reports at issue were not credible, and (2) those
reports
and
the
travel
logs
both
failed
to
document
the
requisite testing in accordance with 30 C.F.R. § 250.804(b).
Mindful of the narrow scope of review, the Court concludes that,
based on the administrative record, Defendants considered the
relevant
factors,
and
provided
a
rational
explanation
for
concluding that Tengasco’s records failed to evince compliance
62
A.R. 593-96.
24
with
30
C.F.R.
§
250.804(a).
In
sum,
the
Court
concludes
Defendants’ decision to impose civil penalties in this case was
not
arbitrary
or
capricious,
an
abuse
of
discretion,
or
otherwise unsupported by substantial evidence.
2. Whether the Department’s Decision to Impose Civil
Penalties in the Amount of $376,000 was arbitrary,
capricious, unsupported by substantial evidence or
an abuse of discretion.
Second, Tengasco argues in the alternative, that this Court
should vacate the IBLA’s decision and remand the matter for a
redetermination and reduction of any penalties, to no more than
$3,000 per penalty and no more than four penalties.63 BSEE has
the authority to enact civil penalty procedures applicable to
“whenever a lessee, operator or other person engaged in oil,
gas,
sulphur
or
other
minerals
operations
in
the
OCS
has
a
violation.” 30 C.F.R. § 250.1400. The safety system devices that
should be inspected, and the intervals at which they should be
tested, are laid out in statute.64 30 C.F.R. § 250.804. Any lessee
who
fails
to
comply
with
any
provision,
term
of
a
lease,
license, or permit, after notice of such failure and expiration
of any reasonable period allowed for corrective action, will be
liable for a civil penalty.65
63
Rec. Doc. No. 25-3 at 6.
Safety system devices shall be successfully inspected and tested by the lessee at the interval specified below or
more frequently if operating conditions warrant.
65
Secretary may assess, collect, and compromise any such penalty.
64
25
An agency’s selection of penalties to effect its policies
is an act peculiarly within its institutional powers, therefore
the courts review of it is limited. Newell Recycling Co. v. U.S.
E.P.A., 231 F.3d 204, 208 (5th Cir. 2000); see Martex Farms,
S.E. v. U.S. E.P.A., 559 F.3d 29, 33-4 (1st Cir. 2009); see also
Pepperell Associates v. U.S. E.P.A., 246 F.3d 15, 29-30 (1st
Cir.
2001).
The
agency’s
penalty
determination
is
given
significant deference, and will not be overturned unless it is
arbitrary, capricious, an abuse of discretion, or otherwise not
in accordance with law. Newell Recycling Co., 231 F.3d at 208.
Tengasco first challenges the civil penalties imposed on
the
basis
that
both
the
BSEE’s
and
the
IDLA’s
decisions
constituted an abuse of discretion because they failed to give
any reason for the disparate amounts imposed for the penalties,
and the record lacks any explanation for why any penalty above
the $3,000 minimum was levied.
BSEE’s
assessed
decision
follows
Assessment
in
the
Table.66
regards
guidelines
The
agency’s
to
the
shown
amount
in
the
calculations
of
penalties
Civil
and
Penalty
enforcement
codes are laid out in the Civil Penalty Worksheet.67 The Table is
further broken down into three categories A, B, and C, based on
66
67
A.R. 264.
A.R. 258-63.
26
the harm or threat that the violation posed.68 In this case all
violations were in the A category.69 The violations are further
broken down, based on severity, into Enforcement Codes W, C, or
S, which reflect warning, component shut-in, or facility shut-in
respectively.70 One INC was assigned a “W” enforcement code while
the remaining seven were given “C” enforcement codes.71 A “W”
enforcement code is given when the situation poses no immediate
danger to personnel or equipment.72 A “C” enforcement code is
given for a specific piece of equipment or location, when it is
determined to be part of an unsafe situation or it poses an
immediate danger to personnel or other equipment, and it can be
shut-in without affecting the overall safety of the facility.73
BSEE
breaks
down
each
violation
in
the
Civil
Penalty
Worksheet, and lists the number of devices, number of intervals,
and which categories and incidents of noncompliance existed.74
For Category “A” violations with a “W” enforcement code, the
range of penalties is $3,000-35,000 with a starting assessment
point of $10,000.75 One violation was assigned this rating, and
68
A.R. 264.
A.R. 264. (Category A is given for: threat of injury, harm or damage to the marine or coastal environment, threat
of population, or threat of damage to any mineral deposit or property).
70
A.R. 264.
71
A.R. 258.
72
See BSEE National Office Potential Incident of Noncompliance (PINC) List, available at
http://www.bsee.gov/Inspection-and-Enforcement/Enforcement-Programs/Potential-Incident-of-Noncompliance--PINC/
73
Id.
74
A.R. 258-263.
75
A.R. 264.
69
27
was
assessed
the
minimum
amount,
$3,000,
due
in
part
from
mitigating factors such as Tengasco having no “closed and final”
violations and a history of only two INC’s in the prior two
years.76 The remaining seven INC’s were assigned Category “A”
enforcement
code
“C”
violations.77
This
classification
has
a
starting point of $15,000, with the minimum being $5,000 and the
maximum being $35,000.78 From this BSEE once again adjusted all
the
penalties
downward
to
the
minimum
possible
charge
of
$5,000.79 What follows is a breakdown of the revised penalties
assessed against Tengasco:
I.
INC No. P-280 ($40,000) — Four devices at the Category
A, Noncompliance C minimum fine of $5,000 for two
intervals.
II.
INC No. P-283 ($6,000) — Category A, Noncompliance W
minimum fine of $3,000 for two intervals.
III. INC No. P-303 ($60,000) — Four devices at the Category
A, Noncompliance C minimum fine of $5,000 for three
intervals (reduced from four).
IV.
INC. No. P-304 ($30,000) — Two devices at the Category
A, Noncompliance C minimum fine of $5,000 for three
intervals (reduced from four).
V.
INC. No. P-307 ($75,000) — Five devices at the
Category A, Noncompliance C minimum fine of $5,000 for
three intervals (reduced from four).
VI.
INC. No. P-308 ($105,000) — Eighteen devices at the
Category A, Noncompliance C minimum fine of $5,000 for
76
A.R. 212-13, 209.
A.R. 258.
78
A.R. 264.
79
A.R. 598.
77
28
three intervals (reduced from four, and per interval
fine capped at $35,000).
VII. INC. No. P-314 ($35,000) — Eight devices at the
Category A, Noncompliance C minimum fine of $5,000 for
one interval (per interval fine capped at $35,000).
VIII.
INC. No. P-315 ($35,000) — Eight devices at the
Category A, Noncompliance C minimum fine of $5,000 for
one interval (per interval fine capped at $35,000).
While
injury
Tengasco
occurred,
is
BSEE
correct
in
assessed
asserting
seven
of
that
the
no
actual
violations
as
enforcement code “C” which subjects them to the higher mandatory
minimum of $5,000. Only one of the violations was eligible to
receive
a
$3,000
minimum
fine.
After
applying
mitigating
factors, such as Tengasco’s prior record of compliance, BSEE
applied the minimum penalty to all eight charges multiplied by
the testing intervals.80 However, BSEE determined that in seven
instances,
the
threat
personnel
evidence
to
in
the
testing
or
record
violations
constituted
equipment.
BSEE
to
show
both
has
its
an
immediate
provided
reasoning
ample
behind
imposing the penalties and the amounts assessed.
Next,
Tengasco
challenges
BSEE’s
decision
to
assess
penalties based on the number of devices that Tengasco allegedly
80
See BSEE National Office Potential Incident of Noncompliance (PINC) List, available at
http://www.bsee.gov/Inspection-and-Enforcement/Enforcement-Programs/Potential-Incident-of-Noncompliance--PINC/
29
failed to test per period.81 Tengasco claims it should only be
penalized once per testing period, rather than multiple times,
because
“if
failure
to
a
violation
keep
proper
occurred
records
in
of
this
case,
testing
it
the
than
rather
was
the
failure to actually test the devices.”82 As previously discussed,
BSEE
is
keeping,
not
BSEE
penalizing
is
Tengasco
penalizing
for
Tengasco
violations
for
lack
of
of
record-
verifiable
testing.83
The
regulations
laid
out
in
statute
require
periodic
testing for each device. 30 C.F.R. § 250.804. BSEE asserts that
“[t]he plain meaning of the regulation is that each failure to
test each device as required in each time period constitutes a
single, separate violation.”84 When there is a gap left in the
administration of a congressionally created program by Congress,
either
implicitly
administrative
or
explicitly,
agencies
reading
deference
of
the
is
statue.
given
See
to
the
Chevron,
U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467
U.S. 837, 843 (1984). The question for the Court is whether the
agency’s answer is based on a permissible construction of the
statute. Id. In this case BSEE applies the violation to every
device that was not tested, for each time period, assessing a
81
Rec. Doc. 25-3 at 17-8.
Rec. Doc. 25-3 at 17-8.
83
Rec. Doc. 28-5 at 19-20.
84
Tengasco, Inc., 184 IBLA 367, 381 (2014).
82
30
penalty
for
each
one
individually.85
Nothing
in
the
statute
reflects a reading contrary to BSEE’s own interpretation and
implementation of the rules.
Lastly, Tengasco argues the penalty amount should have been
reduced
based
Inspection
on
the
Report.
September
Where
2010
Safety
Congress
has
and
Compliance
entrusted
an
administrative agency with the responsibility of selecting the
means of achieving the statutory policy “the relation of remedy
to policy is peculiarly a matter for administrative competence.”
Butz
v.
Glover
Livestock
Commission
Co.,
411
U.S.
182,
185
(1973); quoting American Power Co. v. SEC, 329 U.S. 90, 112, 67
S.
Ct.
133,
146
(1946).
Tengasco
claims
that
because
the
September 2010 report states that SCSSV testing occurred on June
14, 2010, and the helicopter logs confirm that June 14 was the
“Date of inspection” for the platform, this shows that the tests
were done for that interval.86 The Court has discussed at length
and dismissed this final argument, on the basis that the reports
fail to satisfy the 30 C.F.R. § 250.804(b) testing requirement.
III.
CONCLUSION
In moving for summary judgment, Tengasco has not carried
its
85
86
burden.
For
the
reasons
set
forth
above,
the
court
AR. 258-263.
Rec. Doc. 25-3, at 18.
31
determines that Defendants' decision to impose civil penalties
in the
amount of $386,000.00
for failure to provide testing
records required by law, was not arbitrary, capricious, an abuse
of discretion, or an abuse of due process. The court finds that
based on the above, there remain no genuine issues of material
fact. The court therefore grants Defendants' Motion for Summary
Judgment
and
upholds
the
Defendants'
imposition
of
civil
penalties.
As the court has considered the cross-motions for summary
judgment
in
tandem,
and
granted
Defendants'
summary
judgment
motion, granting Plaintiff's cross-motion for summary judgment,
which was also considered, would be totally inconsistent with
the court's analysis. Accordingly, the court denies Plaintiff's
Motion
for
Summary
Judgment.
Plaintiff's
case
is
dismissed.
Final judgment will issue by separate document as required by
Fed. R. Civ. P. 58.
New Orleans, Louisiana, this 14th day of July, 2015.
____________________________
UNITED STATES DISTRICT JUDGE
32
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?