Parkcrest Builders, LLC v. Housing Authority of New Orleans
Filing
207
ORDER AND REASONS. It is ORDERED that Liberty's 67 Motion for Judgment on the Pleadings and 170 Motion for Judgment on the Pleadings and Motion to Dismiss are GRANTED in part and DENIED in part. It is FURTHER ORDERED that Liberty' ;s motion to dismiss HANO's fraud claim is GRANTED. It is FURTHER ORDERED that Libert's motion to dismiss HANO's breach of contract claim is DENIED. It is FURTHER ORDERED that Liberty's liability is capped at the penal sum of the bond. Signed by Judge Carl Barbier. (Reference: 15-1533)(gec)
UNITED STATES DISTRICT COURT
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
PARKCREST BUILDERS, LLC
CIVIL ACTION
VERSUS
NO: 15-1533
c/w 16-14118
16-15849
THE HOUSING AUTHORITY OF NEW
ORLEANS
SECTION: "J"(4)
ORDER AND REASONS
Before the Court is a Motion for Judgment on the Pleadings
(Rec. Doc. 67) filed by Intervenor Liberty Mutual Insurance Company
(“Liberty”), an opposition thereto (Rec. Doc. 70) filed by the
Housing Authority of New Orleans (“HANO”), and a reply (Rec. Doc.
75) filed by Liberty.
Also before the Court is a Motion for
Judgment on the Pleadings and Motion to Dismiss (Rec. Doc. 170)
filed by Liberty, an opposition thereto (Rec. Doc. 189) filed by
HANO, and a reply (Rec. Doc. 194) filed by Liberty.
Having
considered the motion and legal memoranda, the record, and the
applicable law, the Court finds that the motion should be GRANTED
in part and DENIED in part.
FACTS AND PROCEDURAL BACKGROUND
This case arises out of disputes that occurred during the
construction of affordable housing units in New Orleans.
1
Liberty
alleges that on March 4, 2013, HANO entered into a contract with
Parkcrest
Builders,
LLC
(“Parkcrest”)
whereby
Parkcrest
would
serve as the contractor for the construction of the Florida Avenue:
New Affordable Housing Units (the “Project”).
(Rec. Doc. 32 at
3.) Liberty alleges that because the project fell within the ambit
of the Louisiana Public Works Act, Parkcrest was obligated to
obtain a statutory performance and payment bond, and that it sought
the bond from Liberty.
Id.
Liberty avers that it issued a
payment and performance bond naming Parkcrest as principal and
HANO as obligee in connection with the project and that the bond’s
penal sum was $11,288,000.00.
Liberty
alleges
that
(Rec. Doc. 67-1 at 4.)
the
relationship
between
HANO
and
Parkcrest deteriorated during the course of the project, and on
April 10, 2015, HANO terminated Parkcrest.
On May 8, 2015,
Parkcrest brought this suit against HANO, alleging that the delays
in the project were caused by HANO and that HANO breached the
contract by terminating Parkcrest “for convenience.”
1.)
(Rec. Doc.
HANO filed a counterclaim against Parkcrest, alleging that
delays in the project were attributable solely to Parkcrest. (Rec.
Doc. 22)
In its counterclaim, HANO seeks damages for the delays
and also asserts claims that allegedly arose after Parkcrest was
terminated from the project. Id. at 15.
2
After terminating Parkcrest, HANO called upon Liberty to
perform its obligations as surety for Parkcrest.
On or about June
9, 2015, HANO and Liberty entered into a Takeover Agreement to
complete the project. Liberty and HANO dispute the factual details
leading up to the Takeover Agreement, the interpretation of the
Takeover Agreement, and the details surrounding implementation of
the Takeover Agreement.
These disagreements create the basis for
the instant motion.
Once the Takeover Agreement was executed, Liberty retained
Parkcrest as its completion contractor.
(See Rec. Doc. 32 at 6.)
Liberty alleges that HANO began violating the Takeover Agreement’s
terms shortly thereafter by failing to make required payments,
reducing the amounts approved for payment, failing to timely
respond to change order proposals submitted by Parkcrest, and
failing
to
timely
issue
punch
performance of the project.
lists
Id. at 6-8.
and
grant
substantial
Liberty alleges that it
was working to complete items on a punch list that HANO had
purposefully withheld when HANO terminated it from the project on
June 29, 2016.
Id. at 8-9.
Liberty then intervened in this lawsuit to allege breach of
the Takeover Agreement, bad faith breach of contract, and wrongful
termination claims.
(Rec. Doc. 32.)
counterclaim against Liberty.
In response, HANO filed a
(Rec. Doc. 37 at 17.)
3
HANO alleges
that Liberty acted as a de-facto contractor and is therefore liable
in amounts in excess of the penal sum of the bond.
Id.
HANO
further alleges that Liberty breached the terms of the Takeover
Agreement in bad faith and that it induced HANO to sign the
Takeover
Agreement
through
fraudulent
misrepresentation.
Id.
HANO alleges that it is due stipulated damages and general damages
arising out of Liberty’s failure to perform.
Id.
On December 19, 2016, Liberty filed an initial motion for
judgment on the pleadings (Rec. Doc. 67) on HANO’s counterclaim.
Thereafter, HANO moved to file a first supplemental and amended
counterclaim (“first amended counterclaim”) which the Magistrate
Judge granted.
second
(See Rec. Doc. 79.)
supplemental
and
amended
HANO then moved to file a
counterclaim
(“second
amended
counterclaim”), which the Magistrate Judge also granted.
Rec. Doc. 124.)
(See
Liberty responded by filing a second motion for
judgment on the pleadings, this time also requesting dismissal of
HANO’s fraud claim for failure to state a claim under Federal Rule
of Civil Procedure 12(b)(6).
amended
counterclaim
amended counterclaims.
(Rec. Doc. 170).
incorporates
the
original
HANO’s second
and
the
first
Accordingly, the Court will analyze the
instant motion for judgment on the pleadings and motion to dismiss
by referring to the briefing for both motions filed by Liberty and
the original, first amended, and second amended counterclaim.
4
See
Johnson v. Moog, Inc., No. 10-67, 2011 WL 719600, at *1 n.1 (E.D.
Tex. Feb. 22, 2011).
PARTIES’ ARGUMENTS
Liberty argues that HANO’s fraud claim should be dismissed
because Liberty was under no obligation to disclose that its
representative for completing the construction was also providing
Liberty with litigation services.
Liberty also argues that HANO’s
breach of contract claim should be dismissed to the extent that
HANO alleges that Liberty breached the contract by using Parkcrest
as the completion contractor.
More specifically, Liberty argues
that the terms of the Takeover Agreement explicitly permitted
Liberty to use Parkcrest as the completion contractor.
Finally,
Liberty argues that its liability is capped at the penal sum of
its bond because the Takeover Agreement specifically states that
Liberty would not be liable in excess of that amount.
In opposition, HANO argues that its fraud claim should not be
dismissed
because
Liberty
withheld
the
true
nature
of
the
construction representative’s and Parkcrest’s role in the project,
and that HANO would not have entered into the Takeover Agreement
had it known the entire truth.
HANO also argues that its breach
of contract claim states a clear cause of action.
HANO further
contends that Liberty is liable in excess of the penal sum of the
5
bond because it acted as a de-facto contractor on the project and
therefore lost the benefit of its liability cap.
LEGAL STANDARD
Rule 12(c) provides that “[a]fter the pleadings are closed—
but early enough not to delay trial—a party may move for judgment
on the pleadings.” Fed. R. Civ. P. 12(c). A motion brought pursuant
to Rule 12(c) “is designed to dispose of cases where the material
facts are not in dispute and a judgment on the merits can be
rendered by looking to the substance of the pleadings and any
judicially
noticed
facts.”
Hebert
Abstract
Co.
v.
Touchstone
Props., Ltd., 914 F.2d 74, 76 (5th Cir. 1990).
Courts evaluate a motion under Rule 12(c) for judgment on the
pleadings using the same standard as a motion to dismiss under
Rule 12(b)(6) for failure to state a claim. Doe v. MySpace, Inc.,
528 F.3d 413, 418 (5th Cir. 2008) (citing Johnson v. Johnson, 385
F.3d 503, 529 (5th Cir. 2004)). To survive a Rule 12(b)(6) motion
to dismiss, the plaintiff must plead enough facts to “state a claim
to relief that is plausible on its face.” Ashcroft v. Iqbal, 556
U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S.
544, 570 (2007)). A claim is facially plausible when the plaintiff
pleads facts that allow the court to “draw the reasonable inference
that the defendant is liable for the misconduct alleged.” Id. A
court must accept all well-pleaded facts as true and must draw all
6
reasonable inferences in favor of the plaintiff. Lormand v. U.S.
Unwired, Inc., 565 F.3d 228, 232 (5th Cir. 2009); Baker v. Putnal,
75 F.3d 190, 196 (5th Cir. 1996). The court is not, however, bound
to accept as true legal conclusions couched as factual allegations.
Iqbal,
556
U.S.
at
678.
“[C]onclusory
allegations
or
legal
conclusions masquerading as factual conclusions will not suffice
to prevent a motion to dismiss.” Taylor v. Books A Million, Inc.,
296 F.3d 376, 378 (5th Cir. 2002).
DISCUSSION
I.
Fraud
HANO’s fraud claim revolves around three misrepresentations
allegedly made by Liberty during negotiations of the Takeover
Agreement.
Neither party disputes that the Takeover Agreement
contained the following provision: “[I]t is the Surety’s right, at
its sole discretion, to choose the completion contractor under
this agreement.”
(See Rec. Doc. 67-1 at 5; Rec. Doc. 80 at 3.)
Thus, HANO acknowledges that the plain terms of the Takeover
Agreement permitted Liberty to use Parkcrest as its completion
contractor.
However,
HANO
asserts
that
the
three
alleged
misrepresentations made by Liberty induced HANO to agree to parts
of the Takeover Agreement to which it would not have otherwise
consented.
7
The first alleged misrepresentation made by Liberty is how it
characterized its decision to use Parkcrest as its completion
contractor under the Takeover Agreement.
HANO alleges that a
Liberty representative told HANO’s project manager that Liberty
intended to use Parkcrest as the completion contractor in order to
use
Parkcrest’s
quickly.
subcontractors
and
finish
the
project
more
HANO also alleges that a Liberty representative told
HANO that Liberty had done a thorough search of Parkcrest’s work
throughout the country and found it to be satisfactory.
alleges
that
neither
statement
was
true
and
that
HANO
these
misrepresentations masked the depth of the relationship between
Liberty and Parkcrest.
The second alleged misrepresentation is very similar to the
first.
HANO alleges that the real reason Liberty wanted Parkcrest
to be the completion contractor is that Liberty and Parkcrest had
engaged in a “dual defense agreement.”
As stated above, Parkcrest
had already filed suit against HANO prior to the execution of the
Takeover Agreement.
HANO alleges that Liberty and Parkcrest had
entered into a mutual agreement to defend Parkcrest’s performance
on the project.
HANO further alleges that Liberty never mentioned
the existence of this agreement to HANO in the period leading up
to the execution of the Takeover Agreement.
8
HANO alleges that it
would not have agreed to allow Parkcrest to serve as completion
contractor if it had known.
Finally,
HANO
alleges
that
Liberty
intentionally
misrepresented to HANO the nature of Liberty’s relationship with
a company called Meridian Consulting Group, LLC (“Meridian”). HANO
states that it only consented to the use of Parkcrest as completion
contractor
because
Liberty
agreed
to
“continually
maintain
a
representative on the project” to provide full-time oversight and
management.
The representative was to serve as a liaison between
HANO and Parkcrest should any more disputes arise. Liberty told
HANO that it chose Meridian to play this supervisory role of
construction consultant.
But HANO alleges that Liberty did not
disclose to HANO the true nature of the relationship between
Liberty and Meridian.
HANO alleges that Meridian has provided,
and continues to provide, Liberty with litigation support and
management services.
HANO alleges that if it had known the full
extent of Meridian’s participation, it would not have agreed to
allow Meridian serve as the representative.
Liberty’s
failure
to
disclose
Meridian’s
HANO argues that
full
participation
amounts to fraud.
Under Louisiana law, “[f]raud is a misrepresentation or a
suppression of the truth made with the intention either to obtain
an
unjust
advantage
for
one
party
9
or
to
cause
a
loss
or
inconvenience to the other.”
La. Civ. Code art. 1953.
A fraud
claim against a party to a contract must contain three basic
elements: “(1) a misrepresentation, suppression, or omission of
true information; (2) the intent to obtain an unjust advantage or
to cause damage or inconvenience to another; and (3) the error
induced
by
a
fraudulent
act
must
relate
to
a
circumstance
substantially influencing the victim's consent to (a cause of) the
contract.”
Shelton v. Standard/700 Assocs., 2001-0587, p. 5 (La.
10/16/01), 798 So. 2d 60, 64.
9(b)
also
requires
that
Federal Rule of Civil Procedure
fraud
allegations
“state
with
particularity the circumstances constituting fraud or mistake.”
Fed. R. Civ. P. 9(b).
All
three
misrepresentations
alleged
failure to disclose the entire truth.
from silence or inaction.”
by
HANO
involve
a
“Fraud may also result
La. Civ. Code art. 1953.
However,
when fraud is alleged to have been perpetrated by silence or
suppression of the truth, “there must exist a duty to speak or to
disclose information.”
McCarthy v. Evolution Petroleum Corp.,
2014-2607, p. 10 (La. 10/14/15), 180 So. 3d 252, 258.
Generally,
no duty to speak or disclose exists but it “may arise where there
exists a fiduciary relationship between the parties.”
Becnel v.
Grodner, 2007-1041, p. 4 (La. App. 4 Cir. 4/2/08); 982 So. 2d 891,
894.
The
Louisiana
Supreme
Court
10
has
described
a
fiduciary
relationship as “one that exists when confidence is reposed on one
side and there is resulting superiority and influence on the
other.”
Plaquemines Par. Comm'n Council v. Delta Dev. Co., 502
So. 2d 1034, 1040 (La. 1987).
fiduciary
relationship
.
.
“The defining characteristic of a
.
is
the
special
relationship
of
confidence or trust imposed by one in another who undertakes to
act primarily for the benefit of the principal in a particular
endeavor.”
Scheffler v. Adams & Reese, LLP, 2006-1774, p. 7 (La.
2/22/07); 950 So. 2d 641, 648.
HANO does not allege that a fiduciary relationship existed
between
itself
and
Liberty,
nor
do
counterclaim lead to such a conclusion.
the
allegations
in
the
In fact, the allegations
suggest that the relationship between HANO and Liberty was that of
two parties to a business transaction.
Liberty’s role as surety
did not create a fiduciary relationship.
See Nat'l Union Fire
Ins. Co. of Pittsburgh, Pa. v. Turtur, 892 F.2d 199, 207 (2d Cir.
1989) (“[I]n general, a surety does not owe a fiduciary duty to
its principal.”)
HANO
the
Meridian.
depth
Thus, Liberty was not obligated to disclose to
of
its
relationship
with
either
Parkcrest
or
HANO acknowledges that Liberty disclosed Meridian’s
role as construction consultant.
It was not necessary for Liberty
to also disclose that Meridian would serve a dual role as its
consulting
expert
and
that
it
11
would
be
providing
litigation
support.
See Wilson v. Mobil Oil Corp., 940 F. Supp. 944, 955
(E.D. La. 1996) (“[A]bsent a duty to disclose, silence with respect
to the details of a business transaction does not constitute
fraud.”)
As to HANO’s allegations that Liberty made intentionally
false statements about Parkcrest in order to induce HANO to execute
the Takeover Agreement, this is inadequately pled.
conclusory
allegation
that
Liberty’s
statement
HANO makes a
that
it
had
investigated Parkcrest’s work throughout the nation was false, but
provides no detail to support this accusation.
Additionally,
HANO’s allegation that Liberty committed a misrepresentation by
telling HANO that it chose Parkcrest as the completion contractor
in order to use Parkcrest’s subcontractors falls well short of
fraud.
Even if Liberty had other reasons for choosing Parkcrest,
it is entirely plausible that Liberty was at least partially
enticed by the opportunity to use subcontractors who were familiar
with the work site.
conclusion.
use
of
HANO’s pleading does not require a contrary
Moreover, HANO has failed to explain how Liberty’s
Parkcrest
as
completion
contractor
and
Meridian
as
construction consultant was meant to obtain an unjust advantage
for Liberty or to cause damage or inconvenience to HANO.
See La.
Civ. Code art. 1953. Accordingly, HANO’s fraud claim is dismissed.
12
II.
Breach of the Takeover Agreement
Contracts in Louisiana must be performed in good faith.
Civ. Cod. art. 1983.
La.
“An obligor in bad faith is liable for all
the damages, foreseeable or not, that are a direct consequence of
his failure to perform.”
La. Civ. Code art. 1997.
Bad faith
implies “the conscious doing of a wrong for dishonest or morally
questionable motives.”
Sartisky v. Louisiana Endowment for the
Humanities, No. 14-1125, 2014 WL 5040817, at *2 (E.D. La. Sept.
26, 2014) (quoting MKR Servs., LLC v. Dean Hart Constr., LLC,
44,456, p. 6 (La. App. 2 Cir. 7/8/09), 16 So. 3d 562, 566).
HANO alleges that Liberty breached the Takeover Agreement in
multiple
ways.
The
original
counterclaim
makes
the
general
allegation that Liberty, in bad faith, failed to arrange for
completion of the project diligently and expeditiously.
Doc. 37 at 18.)
(Rec.
The first amended counterclaim fleshes out the
breach of contract claim by providing more specific allegations.
First, HANO argues that Liberty and Parkcrest worked in tandem to
increase the amount that would be payable to Parkcrest.
HANO
alleges
that
Liberty
failed
to
continually
Second,
maintain
a
representative on the project during the course of the work.
Finally, HANO alleges that Liberty failed to provide adequate
oversight and management as agreed in the Takeover Agreement,
13
failed to complete the project according to the contract, and
failed to achieve substantial completion.
Liberty does not argue that the entire breach of contract
claim should be dismissed; rather, it contends that any allegation
that Liberty violated the Completion Agreement when it retained
Parkcrest
as
the
completion
contractor
should
be
dismissed.
However, HANO’s breach of contract claims, as stated in both the
original, first amended, and second amended counterclaim, includes
no allegation that Liberty violated the Takeover Agreement in that
manner.
the
In fact, HANO expressly acknowledges that it entered into
Takeover
Agreement
knowing
that
Liberty
Parkcrest as the completion contractor.
intended
to
use
(See Rec. Doc. 70 at 1-
2.) Accordingly, further analysis of Liberty’s motion for judgment
on the breach of contract claim is unnecessary and Liberty’s motion
is denied.
III. Extent of Liberty’s liability
The final issue is whether Liberty is liable for damages in
excess of the penal sum of its bond resulting from the allegations
that it breached the Takeover Agreement.
As described above,
Liberty issued a payment and performance bond naming Parkcrest as
principal
and
$11,288,000.00.
HANO
as
obligee.
The
bond’s
penal
sum
is
Liberty argues that its liability is capped at
the sum of the penal bond.
HANO contends that Liberty functioned
14
as a de-facto contractor on the project and is therefore liable
for amounts exceeding the penal sum of the bond for its alleged
breach of the Takeover Agreement.
Louisiana’s Public Works Act requires that the successful
bidder to whom a public works contract has been awarded “shall
furnish good and solvent bond in an amount not less than one-half
of the amount of the contract, for the faithful performance of his
duties.”
La. Stat. Ann. § 38:2216(A)(1).
The issuance of the
bond results in the surety becoming bound “to pay up to the amount
of the bond in the event of nonfulfillment or nonperformance of
the contractor's obligations for the public works contract.” Scott
v. Red River Waterway Comm'n, 41,009, p. 6 (La. App. 2 Cir.
4/12/06), 926 So. 2d 830, 835.
Because Liberty issued a bond on
a public works project with the penal sum of $11,288,000.00, this
is the extent of its obligation as surety.
The
Takeover
Agreement
includes
the
following
provision:
“The liability of Surety under this Agreement is strictly limited
to the penal sum of the Bond.
In no event will Surety be required
to expend more than the penal sum of its Bond.” 1
at 3.)
facto
(Rec. Doc. 23-5
Nevertheless, HANO alleges that Liberty served as a decontractor
on
the
project
1
after
signing
the
Takeover
The Takeover Agreement was filed by HANO as an exhibit to the counterclaim it
filed against Parkcrest. HANO’s counterclaim against Liberty incorporates by
reference its counterclaim against Parkcrest.
15
Agreement.
In
support
of
this
position,
HANO
alleges
that
paperwork submitted by Liberty to HANO after execution of the
Takeover Agreement was sent and signed by “Contractor: Liberty
Mutual.”
In Louisiana, a surety who steps into the shoes of the
contractor and takes an active role in the completion of the
project loses the benefit of its liability being capped at the
penal sum.
Klein v. J.D. & J.M. Collins, 106 So. 120, 122 (1925).
In Klein v. J.D. & J.M. Collins, the Louisiana Supreme Court
addressed a scenario where a contractor agreed to build a duplex
apartment complex.
Id. at 121.
The plaintiff alleged that when
the contractor on the project could no longer afford to pay its
laborers, the surety on the bond agreed to undertake completion of
the building.
Id.
The court concluded that if the surety had
“left it to the owner to complete the work upon the default of the
contractors, unquestionably the company could not be held liable
for more than the amount for which it had bound itself as surety
. . . .”
Id. at 122.
But if the surety agreed to complete the
project upon the contractor’s failure to do so, then it “put itself
in the place of the contractors from the moment of the new
undertaking, and became liable for the costs of completing the
building, without reference [to] the amount for which it had signed
as surety.”
Id.
16
Liberty acknowledges that a surety can become bound in excess
of the penal sum of the bond when it assumes the role of contractor,
but argues that such a scenario could not exist here because the
Takeover Agreement expressly states that Liberty’s liability is
limited to the penal sum of the bond.
The Court agrees.
The
Louisiana Public Works Act “does not specifically detail how the
surety
may
situation.”
act
to
remedy
a
contractor's
Scott, 926 So. 2d at 836.
default
in
a
given
When HANO terminated
Parkcrest from the project, it called upon Liberty to perform its
duty as surety.
At that time, both parties entered into the
Takeover Agreement whereby Liberty agreed to oversee the Project’s
completion.
As described in Klein, Liberty’s decision to oversee
completion could have exposed it to liability in excess of the
penal sum of the bond.
It is for this reason that “takeover
agreements are often carefully negotiated by sureties to preserve
the
protection
of
the
Construction Law § 12:22.
bond
amount.”
4A
Bruner
&
O'Connor
The Takeover Agreement between HANO and
Liberty included a clause expressly limiting Liberty’s obligation
to the penal sum of the bond.
This is one mechanism a surety may
employ to prevent becoming liable in excess of the penal sum of
the bond.
See Int’l Fid. Ins. Co. v. County of Rockland, 98 F.
Supp. 2d 400, 429 (S.D.N.Y. 2000) (“To avoid liability in excess
of the bond amount, . . . the surety must include a clause in the
17
takeover agreement which limits the surety's liability in the
course of performance to the original bond penalty.”) (quoting
Bruce C. King, Takeover and Completion of Bonded Contracts by the
Survey,
FALL
1997,
at
22-23);
Allegheny
Cas.
Co.
v.
Archer-
W./Demaria Joint Venture III, No. 8:13-CV-128-SCB-TGW, 2014 WL
4162787, at *11 (M.D. Fla. Aug. 21, 2014) (holding that “even if
a
performing
surety's
liability
can
exceed
the
penal
sum,
a
performing surety can limit its liability by expressly so providing
in a contract with the benefitted obligee”).
Moreover, “the
meaning and intent of the parties to a written instrument should
be determined within the four corners of the document, and its
terms cannot be explained or contradicted by extrinsic evidence.”
Scott, 926 So. 2d at 834.
The terms of the Takeover Agreement are
clear, and the Court need not look beyond them to determine that
HANO and Liberty agreed that Liberty would not be liable for
damages in excess of the penal bond.
CONCLUSION
Accordingly,
IT IS ORDERED that Liberty’s Motion for Judgment on the
Pleadings (Rec. Doc. 67) and Motion for Judgment on the Pleadings
and Motion to Dismiss (Rec. Doc. 170) are GRANTED in part and
DENIED in part.
18
IT IS FURTHER ORDERED that Liberty’s motion to dismiss HANO’s
fraud claim is GRANTED.
IT IS FURTHER ORDERED that Liberty’s motion to dismiss HANO’s
breach of contract claim is DENIED.
IT IS FURTHER ORDERED that Liberty’s liability is capped at
the penal sum of the bond.
New Orleans, Louisiana this 5th day of June, 2017.
__________________________
CARL J. BARBIER
UNITED STATES DISTRICT JUDGE
19
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?