Landis Construction Co., LLC v. Torus Specialty Ins. Co. et al
Filing
30
ORDER & REASONS denying 16 , 17 & 19 Motions for Judgment on the Pleadings. Signed by Judge Martin L.C. Feldman on 7/13/2016. (caa)
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
LANDIS CONSTRUCTION, LLC
CIVIL ACTION
V.
NO. 16-1619
TORUS SPECIALTY INS. COMPANY,
ALTERRA EXCESS & SURPLUS LINES
INS. COMPANY, AND STARR SURPLUS
LINES INS. COMPANY
SECTION "F"
ORDER AND REASONS
Before the Court are three motions, all of which seek the
same relief. The defendants, StarStone Specialty Insurance Company
(f/k/a Torus Specialty Insurance Company), Starr Surplus Lines
Insurance Company, and Evanston Insurance Company (f/k/a Alterra
Excess & Surplus Insurance Company) move for judgment on the
pleadings to dismiss the plaintiff, Landis Construction’s, socalled “Delay Claim” and associated claim for statutory penalties.
For the reasons that follow, the motions are DENIED.
Background
This
is
an
insurance
dispute
between
a
builder,
Landis
Construction, and the insurers of the building project’s owner.
1501 Canal Apartments, LLC is the owner of its namesake
building on Canal Street in New Orleans. 1501 Canal hired Landis
Construction as a general contractor to perform renovations on the
building. The contract required the owner, 1501 Canal, to purchase
and maintain property insurance to protect the interests of the
1
builder, Landis Construction. 1501 Canal was also required to name
Landis as an “Additional Insured” on the policy.
In
compliance
with
its
obligations
under
the
building
contract, 1501 Canal obtained builder’s risk insurance. Three
different
insurance
companies
issued
policies
that
covered
a
portion of the total coverage amount (the policy limit). StarStone
issued a policy covering 37.5% of the policy limit; Starr issued
a policy covering 37.5% of the policy limit; and Evanston issued
a policy covering the remaining 25% of the policy limit. The
insurers agreed that Starstone’s would be the lead policy.
The total limit under the three policies was $22,955,000.
That amount was divided into sublimits for certain categories of
risks. For “physical damage,” the sublimit was $17,549,514. The
sublimit
for
“physical
damage
to
Existing
Property”
was
$5,050,486. Finally, the sublimit for “Delay in Completion-Soft
Costs” was $355,000. Central to these motions is a disagreement
over the sublimit category in which Landis’ claims fall.
In January of 2014, during the final stages of the renovation
project, a pressure relief valve attached to a water boiler on the
roof of the building released. Water flowed from the roof and
flooded the elevator machine room and electrical rooms below.
Landis was required to repair the water damage, and it incurred
costs in doing so. After consulting with its subcontractor in
February of 2014, Landis learned that the cost of replacing the
2
bus ducts in the building would be $333,056. This did not include
the cost of demolition and removal of the damaged bus ducts or
Landis’ lost profits and overhead expenses. In June of 2014, the
defendant insurers issued a $308,014 payment to Landis to cover
repair
costs.
By
July
of
2014,
however,
Landis
had
incurred
expenses totaling $443,092.48. It asked the defendants for an
additional partial payment of $138,048.48 to cover the difference
between the amount paid and the actual cost of the repairs.
Landis completed performance under the building contract in
September of 2014. The owner, 1501 Canal, was obligated under the
contract to pay Landis the balance owed for the costs incurred to
repair the water damage. In lieu of payment, however, 1501 Canal
subrogated and assigned to Landis its insurance claims against the
defendants. 1 Landis contends that the net loss it sustained as a
result of the water damage is $875,144.21 plus $5,925 for “Claims
Preparation Costs.” After subtracting the $308,014 already paid,
Landis submits that the defendants owe $573,055.21 to satisfy the
claim. This amount includes charges for Landis’ profits, overhead,
and costs during the period in which repairs were made.
After months of back and forth with the insurance adjuster,
the defendants agreed to pay a portion of the outstanding balance.
1
Landis also maintains that it was subrogated to 1501 Canal’s
insurance claims by operation of law because it had completed
performance without receiving reimbursement.
3
On September 9, 2015, the defendants’ accountant recommended an
additional $22,000 payment for “physical damage” and a payment of
$193,037 for “Soft Costs” related to Landis’ “Delay Claim.” On
October 7, 2015, the defendants submitted proof of loss forms to
Landis showing an agreed payment of $193,037. Landis executed the
forms and returned them on October 12, 2015.
Over 30 days later, on November 13, 2015, Landis received
payment of $72,388.94 from Starr. On November 18, 2015, Landis
received payment of $48,259.30 from Evanston. Finally, on January
8, 2016, Landis received payment of $72,388.94 from StarStone. 2
The defendants have yet to tender the remaining $22,000 payment
for
“physical
damage”
because
Landis
refused
to
execute
a
“Policyholders Release” in exchange. Landis seeks reimbursement
for the balance of the costs it incurred to repair the water
damage. 3
The defendants move for dismissal of Landis’ claims for lost
profits and overhead costs, which make up a substantial portion of
2
In addition to the balance of its insurance claim, Landis seeks
penalties for the untimeliness of the defendants’ payments.
3
The exact amount that Landis seeks is unapparent to the Court.
In its amended complaint, Landis claims that it was owed
$573,055.21 before the defendants made the final payment of
$193,037. The difference between the two is 380,018.21. However,
later in its amended complaint, Landis claims that it is owed “at
least $199,773.42 not including penalties and attorneys’ fees.”
Compare paragraphs 31 and 53 of the amended complaint.
4
the unpaid balance. According to the defendants, that portion is
a “Delay Claim” governed by the “Delay in Completion” endorsement
attached
to
the
insurance
policy.
The
Delay
in
Completion
endorsement provides: “For the purpose of this endorsement only,
the Named Insured, if different from that shown on the policy
declarations,
shall
be
as
shown
on
the
declarations
of
this
endorsement. There shall be no Additional Insureds hereunder.”
Directly below, the “Named Insureds” are listed. 1501 Canal is
listed, but Landis is not. 4 Simply put, because Landis is not a
“Named Insured,” the defendants contend the Delay in Completion
endorsement explicitly precludes Landis from recovering its lost
profits and overhead costs.
Landis
responds
that
it
has
fallen
into
a
well-placed
semantics trap. According to Landis, sometime during the monthslong dealings with the insurance adjuster, the adjuster began
referring to Landis’ claim for lost profits and overhead as the
“Delay Claim.” Unwittingly, and perhaps ineptly, Landis acquiesced
to the technical designation. It too began calling its claim a
“Delay Claim.” Indeed, Landis repeatedly distinguished between its
“Delay Claim” and its “Physical Damage Claim” throughout its
original complaint.
4
Landis is listed in the policy as an “Additional Insured” – one
who is specifically excluded by the Delay in Completion
endorsement.
5
After the defendants filed their motions for judgment on the
pleadings,
however,
Landis
realized
the
technical
meaning
of
“Delay Claim” and sought leave to amend and correct its complaint.
Landis’ motion to amend was unopposed, and the Court granted it on
June 27, 2016. In its amended complaint, Landis submits that the
policy clearly includes its claim for lost profits and overhead in
the “physical damages” category, not in the Delay in Completion
endorsement. 5
As a result, Landis urges that the “Delay Claim” which the
defendants seek to dismiss is misidentified as such. It contends
that its claim for lost profits and overhead are included under
the coverage terms of the policy for physical damage, and are not
subject
to
the
Landis
contends
Delay
that
in
Completion
the
motions
endorsement.
to
dismiss
Accordingly,
are
moot.
Alternatively, Landis submits that it is subrogated to the rights
of 1501 Canal, who is a “Named Insured,” and thus, its claim for
lost profits and overhead is valid even if it constitutes a “Delay
Claim” under the Delay in Completion endorsement.
I.
5
For example, the policy includes coverage for the “Total Contract
Value,” which includes “all wages, expenses, materials, supplies,
equipment, change orders plus if declared, contractor’s profit and
overhead, existing structures (when coverage is included by
endorsement) and such other charges, all whether provided by the
owner, contractors or others, which will become a part of or will
be expended on the project. . . .” (emphasis added).
6
Federal Rule of Civil Procedure 12(c) permits a party to move
for judgment after both the complaint and answer have been filed.
See Fed. R. Civ. P. 12(c). “A motion brought pursuant to [Rule
12(c)] is designed to dispose of cases where the material facts
are not in dispute and a judgment on the merits can be rendered by
looking to the substance of the pleadings and any judicially
noticed facts.” Great Plains Trust Co. v. Morgan Stanley Dean
Witter & Co., 313 F.3d 305, 312 (5th Cir. 2002)(quoting Hebert
Abstract Co. v. Touchstone Props. Ltd., 914 F.2d 74, 76 (5th Cir.
1990)).
In considering a Rule 12(c), motion, the Court “accepts ‘all
well-pleaded
facts
as
true,
viewing
favorable to the plaintiff.’”
them
in
the
light
most
See Martin K. Eby Constr. Co. v.
Dall. Area Rapid Transit, 369 F.3d 464 (5th Cir. 2004) (quoting
Jones v. Greninger, 188 F.3d 322, 324 (5th Cir. 1999)). Documents
attached
to
a
motion
to
dismiss
are
considered
part
of
the
pleadings if they are referred to in the plaintiff’s complaint and
are central to the claim.
Causey v. Sewell Cadillac-Chevrolet,
Inc., 394 F.3d 285, 288 (5th Cir. 2004) (citing Collins v. Morgan
Stanley
Dean
Witter,
224
F.3d
496,
498-99
(5th
Cir.
2000)).
Accordingly, the Court considers the insurance policy in resolving
these motions.
II.
7
The
defendants’
pleadings
is
that
sole
basis
Landis’
for
“Delay
partial
Claim”
judgment
and
its
on
the
associated
statutory penalty claim must be dismissed because Landis has no
rights under the Delay in Completion endorsement. Since Landis has
amended the complaint, however, there no longer exists a “Delay
Claim.” Thus, accepting the well-pleaded facts in Landis’ amended
complaint as true, the defendants’ motions are obviously moot.
Even
assuming
Completion
that
Landis
endorsement,
has
no
Landis
rights
now
under
asserts
the
rights
Delay
under
in
a
different provision of the policy that does not exclusively apply
to “Named Insureds.” To the contrary, Landis now relies on language
that explicitly includes coverage for the type of damages it seeks.
The
defendants
have
yet
to
address
or
contest
such
rights.
Accordingly, the defendants’ motions for partial judgment on the
pleadings are DENIED. 6
New Orleans, Louisiana, July 13, 2016
______________________________
MARTIN L. C. FELDMAN
UNITED STATES DISTRICT JUDGE
6
The defendants filed a last-minute joint reply brief asking the
Court to resolve the “Delay Claim” issue because, in its opposition
brief, Landis claims it has reserved an alternative theory of
recovery under the Delay in Completion endorsement based on its
subrogated rights to the Named Insured (1501 Canal). Yet the
defendants attempt to raise a new issue not presented in their
initial motions: the scope of Landis’ subrogation rights. That
issue is not currently before the Court, and the Court does not
address it here.
8
Disclaimer: Justia Dockets & Filings provides public litigation records from the federal appellate and district courts. These filings and docket sheets should not be considered findings of fact or liability, nor do they necessarily reflect the view of Justia.
Why Is My Information Online?